Anda di halaman 1dari 10

2 JANUARI 2020

KOMPLEK MESS INDO


PAGI SIANG SORE MALAM

CERAH CERAH CERAH CERAH

1 2

KETERANGAN GAMBAR
1. PENGGALIAN SEPTICTANK MESS INDO
• PROGRESS : 100%
• KENDALA : PEGAWAI SUBKON LIBUR
• ACTION : DILANJUTKAN BESOK
• TARGET :
• SISA PEKERJAAN : PENGECORAN SEPTICTANK

2. CLEARING AREA MESS BLOK 4


• PROGRESS : 60%
• KENDALA : HOSE BOCOR
• ACTION : MAINTENANCE
• TARGET :
• SISA PEKERJAAN : LEVELING

3 3. DENAH PEKERJAAN
2 JANUARI 2021
POWER HOUSE
PAGI SIANG SORE MALAM

CERAH CERAH CERAH CERAH

1 2

KETERANGAN GAMBAR
1. PEMASANGAN AIR DISCHARGE
• PROGRESS : 80%
• KENDALA :
• ACTION :
• TARGET :-
• SISA PEKERJAAN :-

2. PENGECORAN JALUR KABEL


• PROGRESS : 90%
• KENDALA :-
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : PENGECORAN LANTAI BETON
3
3. DENAH LOKASI PEKERJAAN
2 JANUARI 2021
KOMPLEK MESS CUNGKO
PAGI SIANG SORE MALAM

CERAH CERAH CERAH CERAH

KETERANGAN GAMBAR
1. PEMASANGAN PREFAB KANTIN CUNGKO
• PROGRESS : 90%
• KENDALA : HUJAN SETENGAH HARI
• ACTION :
• TARGET : 31/12/2020
• SISA PEKERJAAN :

2. DENAH LOKASI PEKERJAAN

3
2 JANUARI 2021
GUDANG HANDAK
PAGI SIANG SORE MALAM

CERAH CERAH CERAH CERAH

1 2

KETERANGAN GAMBAR
1. PEMBUATAN TANGGUL HANDAK
• PROGRESS : 45%
• KENDALA : TANAH LEMBEK
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : PEMBUATAN JALUR AIR

2. JALAN AKSES HANDAK


• PROGRESS : 50%
• KENDALA : HUJAN MEMBUAT TANAH MENJADI LEMBEK
• ACTION :-
• TARGET :-
• SISA PEKERJAAN :-

3 3. DENAH LOKASI PEKERJAAN


2 JANUARI 2021
LABORATORIUM INDO
PAGI SIANG SORE MALAM
CERAH CERAH CERAH CERAH

1 2

KETERANGAN GAMBAR
1. PEMASANGAN PREFAB LAB INDO
• PROGRESS : 0%
• KENDALA : MENUNGGU SELSAI PEMASANGAN DI KANTIN CUNGKO
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : MENUNGGU PREFAB

2. TOILET LAB INDO


• PROGRESS : 100%
• KENDALA :-
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : INSTALASI BANGUNAN

3 3. DENAH LOKASI PEKERJAAN


2 JANUARI 2021
KOMPLEK PERKANTORAN
PAGI SIANG SORE MALAM
CERAH CERAH CERAH CERAH

1 2

KETERANGAN GAMBAR
1. PEMASANGAN BEKISTING
• PROGRESS : 100%
• KENDALA : PEGAWAI SUBCON LIBUR
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : PEKERJAAN PENGECORAN

2. JALAN AKSES PERKANTORAN


• PROGRESS : 100%
• KENDALA :
• ACTION :
• TARGET :
• SISA PEKERJAAN :-

3 3. DENAH LOKASI PEKERJAAN


2 JANUARI 2021
GUDANG CORESHED
PAGI SIANG SORE MALAM

CERAH CERAH CERAH CERAH

KETERANGAN GAMBAR
1. CLEARING GUDANG CORESHED
• PROGRESS : 100%
• KENDALA :-
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : PEMADATAN AREA

2. DENAH LOKASI PEKERJAAN

2
2 JANUARI 2021
WORKSHOP INDO
PAGI SIANG SORE MALAM

CERAH CERAH CERAH CERAH

KETERANGAN GAMBAR
1. WORKSHOP
• PROGRESS : 0%
• KENDALA :-
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : PENGECORAN SLAB

2. DENAH LOKASI PEKERJAAN

2
2 JANUARI 2021
TANGKI BBM
PAGI SIANG SORE MALAM

CERAH CERAH CERAH CERAH

KETERANGAN GAMBAR
1. WORKSHOP
• PROGRESS : 0%
• KENDALA : MENUNGGU MATERIAL DAN DESIGN
• ACTION :
• TARGET :
• SISA PEKERJAAN : PENGECORAN SLAB

2. DENAH LOKASI PEKERJAAN

2
2 JANUARI 2021
AKSES JALAN UTAMA
PAGI SIANG SORE MALAM

CERAH CERAH CERAH CERAH

1 2

KETERANGAN GAMBAR
1. CLEARING JALAN AKSES MENUJU PIT
• PROGRESS : 100%
• KENDALA :-
• ACTION :-
• TARGET :
• SISA PEKERJAAN : PENGHAMPARAN LIMESTONE

2. PEMADATAN MATERIAL
• PROGRESS : 30%
• KENDALA : KEKURANGAN MATERIAL LIMESTONE
• ACTION :-
• TARGET :
• SISA PEKERJAAN : PELEBARAN JALAN

3 3. DENAH LOKASI PEKERJAAN