1 2
KETERANGAN GAMBAR
1. PENGGALIAN SEPTICTANK MESS INDO
• PROGRESS : 100%
• KENDALA : PEGAWAI SUBKON LIBUR
• ACTION : DILANJUTKAN BESOK
• TARGET :
• SISA PEKERJAAN : PENGECORAN SEPTICTANK
3 3. DENAH PEKERJAAN
2 JANUARI 2021
POWER HOUSE
PAGI SIANG SORE MALAM
1 2
KETERANGAN GAMBAR
1. PEMASANGAN AIR DISCHARGE
• PROGRESS : 80%
• KENDALA :
• ACTION :
• TARGET :-
• SISA PEKERJAAN :-
KETERANGAN GAMBAR
1. PEMASANGAN PREFAB KANTIN CUNGKO
• PROGRESS : 90%
• KENDALA : HUJAN SETENGAH HARI
• ACTION :
• TARGET : 31/12/2020
• SISA PEKERJAAN :
3
2 JANUARI 2021
GUDANG HANDAK
PAGI SIANG SORE MALAM
1 2
KETERANGAN GAMBAR
1. PEMBUATAN TANGGUL HANDAK
• PROGRESS : 45%
• KENDALA : TANAH LEMBEK
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : PEMBUATAN JALUR AIR
1 2
KETERANGAN GAMBAR
1. PEMASANGAN PREFAB LAB INDO
• PROGRESS : 0%
• KENDALA : MENUNGGU SELSAI PEMASANGAN DI KANTIN CUNGKO
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : MENUNGGU PREFAB
1 2
KETERANGAN GAMBAR
1. PEMASANGAN BEKISTING
• PROGRESS : 100%
• KENDALA : PEGAWAI SUBCON LIBUR
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : PEKERJAAN PENGECORAN
KETERANGAN GAMBAR
1. CLEARING GUDANG CORESHED
• PROGRESS : 100%
• KENDALA :-
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : PEMADATAN AREA
2
2 JANUARI 2021
WORKSHOP INDO
PAGI SIANG SORE MALAM
KETERANGAN GAMBAR
1. WORKSHOP
• PROGRESS : 0%
• KENDALA :-
• ACTION :-
• TARGET :-
• SISA PEKERJAAN : PENGECORAN SLAB
2
2 JANUARI 2021
TANGKI BBM
PAGI SIANG SORE MALAM
KETERANGAN GAMBAR
1. WORKSHOP
• PROGRESS : 0%
• KENDALA : MENUNGGU MATERIAL DAN DESIGN
• ACTION :
• TARGET :
• SISA PEKERJAAN : PENGECORAN SLAB
2
2 JANUARI 2021
AKSES JALAN UTAMA
PAGI SIANG SORE MALAM
1 2
KETERANGAN GAMBAR
1. CLEARING JALAN AKSES MENUJU PIT
• PROGRESS : 100%
• KENDALA :-
• ACTION :-
• TARGET :
• SISA PEKERJAAN : PENGHAMPARAN LIMESTONE
2. PEMADATAN MATERIAL
• PROGRESS : 30%
• KENDALA : KEKURANGAN MATERIAL LIMESTONE
• ACTION :-
• TARGET :
• SISA PEKERJAAN : PELEBARAN JALAN