TIME SCHEDULE

KEGIATAN : PEMBANGUNAN SARANA VENUE TERBANG LAYANG


PEKERJAAN : Pembangunan Sarana Venue Terbang Layang LANUD Timika di Kabupatern Mimika (MYC)
NOMOR KONTRAK / TANGGAL KONTRAK : 050 / 6137 . M
LOKASI : KABUPATEN MIMIKA
TAHUN ANGGARAN : 2020-2021

MASA KERJA 210 HARI KALENDER


Bulan Ke - 1 Bulan Ke - 2 Bulan Ke - 3 Bulan Ke - 4
Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 5 Minggu 6 Minggu 7 Minggu 8 Minggu 9 Minggu 10 Minggu 11 Minggu 12 Minggu 13 Minggu 14 Minggu 15 Minggu 16
No Uraian Pekerjaan Bobot (%)
29-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Jan-21 5-Apr-21 12-Apr-21
S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D
3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21

0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.02 0.02
I. SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI 0.26
0.26

3.01 3.01 3.01 3.01 3.01 3.01 4.01 5.01 6.51 6.51
II. PEKERJAAN LANDASAN PRECISSION 72.14
0.11 0.002

0.47 0.47 0.47 0.47 0.47


III. PEKERJAAN PENIMBUNAN AREA WASIT 2.33
0.01

1.46
IV. PEKERJAAN PENIMBUNAN APRON 8.74
0.01

V. PEKERJAAN PENIMBUNAN AREA PENONTON 2.33

0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72
VI. PEKERJAAN PEMBUATAN JALAN AKSES KE LOKASI 8.58
0.13

VII. PEKERJAAN PEMBUATAN GEDUNG PASI 5.61


0.10
JUMLAH NILAI PEKERJAAN 100
KEMAJUAN PEKERJAAN RENCANA (%) 0.01 0.72 0.72 0.72 0.72 0.72 3.73 3.73 3.73 3.73 4.20 4.20 5.20 5.48 6.99 7.98
KEMAJUAN PEKERJAAN RENCANA KUMULATIF (%) - 0.01 0.73 1.46 2.18 2.90 3.63 7.36 11.09 14.82 18.55 22.74 26.94 32.13 37.61 44.61 52.59
KEMAJUAN PEKERJAAN REALISASI (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.37 0.25
KEMAJUAN PEKERJAAN REALISASI KUMULATIF (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.37 0.62
DEVIASI (±) 0.01 0.73 1.46 2.18 2.90 3.63 7.36 11.09 14.82 18.55 22.74 26.94 32.13 37.61 44.24 51.97
ME SCHEDULE

MASA KERJA 210 HARI KALENDER


Bulan Ke - 5 Bulan Ke - 6 Bulan Ke - 7 Bulan ke - 8
Minggu 17 Minggu 18 Minggu 19 Minggu 20 Minggu 21 Minggu 22 Minggu 23 Minggu 24 Minggu 25 Minggu 26 Minggu 27 Minggu 28 Minggu 29 Minggu 30
19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21 5-Jul-21 12-Jul-21 19-Jul-21
S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D
25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21 11-Jul-21 18-Jul-21 27-Jul-21
100...
0.02 0.02 0.02 0.02 0.01 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004
100.00
90

6.51 6.51 6.51 6.51 90.000.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.10 80
23.58 7.99 17.52 5.35
80.00
70

70.00
1.62 60

60.00
1.46 1.46 1.46 1.46 1.46 50
5.94 50.00
40
40.00 0.58 0.58 0.58 0.58
2.00 30
30.00

20
20.00
3.61 0.91
10
10.00
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.20 0.20 0.20 0.20 0.20 0.20 0.20
0.27 0.56 0.12 0.00 -

8.78 8.78 8.78 8.78 2.77 1.89 1.89 1.29 1.29 0.71 0.71 0.71 0.71 0.31
61.37 70.16 78.94 87.73 90.50 92.39 94.28 95.57 96.86 97.57 98.28 98.98 99.69 100.00
27.46 8.55 17.64 15.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
28.08 36.62 54.27 70.09 70.09 70.09 70.09 70.09 70.09 70.09 70.09 70.09 70.09 70.09
33.29 33.53 24.67 17.64 20.41 22.30 24.19 25.48 26.77 27.48 28.19 28.90 29.61 29.91
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN SARANA VENUE TERBANG LAYANG


PEKERJAAN : Pembangunan Sarana Venue Terbang Layang LANUD Timika di Kabupatern Mimika (MYC)
NOMOR KONTRAK / TANGGAL KONTRAK : 050 / 6137 . M
LOKASI : KABUPATEN MIMIKA
TAHUN ANGGARAN : 2020-2021

MASA KERJA 210 HARI KALENDER


Bulan Ke - 1 Bulan Ke - 2 Bulan Ke - 3 Bulan Ke - 4
Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 5 Minggu 6 Minggu 7 Minggu 8 Minggu 9 Minggu 10 Minggu 11 Minggu 12 Minggu 13 Minggu 14 Minggu 15 Minggu 16
No Uraian Pekerjaan Bobot (%)
29-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Jan-21 5-Apr-21 12-Apr-21
S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D
3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21

0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.02 0.02
I. SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI 0.26
0.26

3.01 3.01 3.01 3.01 3.01 3.01 4.01 5.01 6.51 6.51
II. PEKERJAAN LANDASAN PRECISSION 72.14
0.11 0.002

0.47 0.47 0.47 0.47 0.47


III. PEKERJAAN PENIMBUNAN AREA WASIT 2.33
0.01

1.46
IV. PEKERJAAN PENIMBUNAN APRON 8.74
0.01

V. PEKERJAAN PENIMBUNAN AREA PENONTON 2.33

0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72
VI. PEKERJAAN PEMBUATAN JALAN AKSES KE LOKASI 8.58
0.13

VII. PEKERJAAN PEMBUATAN GEDUNG PASI 5.61


0.10
JUMLAH NILAI PEKERJAAN 100
KEMAJUAN PEKERJAAN RENCANA (%) 0.01 0.72 0.72 0.72 0.72 0.72 3.73 3.73 3.73 3.73 4.20 4.20 5.20 5.48 6.99 7.98
KEMAJUAN PEKERJAAN RENCANA KUMULATIF (%) - 0.01 0.73 1.46 2.18 2.90 3.63 7.36 11.09 14.82 18.55 22.74 26.94 32.13 37.61 44.61 52.59
KEMAJUAN PEKERJAAN REALISASI (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.37 0.25
KEMAJUAN PEKERJAAN REALISASI KUMULATIF (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.37 0.62
DEVIASI (±) 0.01 0.73 1.46 2.18 2.90 3.63 7.36 11.09 14.82 18.55 22.74 26.94 32.13 37.61 44.24 51.97
ME SCHEDULE

MASA KERJA 210 HARI KALENDER


Bulan Ke - 5 Bulan Ke - 6 Bulan Ke - 7 Bulan ke - 8
Minggu 17 Minggu 18 Minggu 19 Minggu 20 Minggu 21 Minggu 22 Minggu 23 Minggu 24 Minggu 25 Minggu 26 Minggu 27 Minggu 28 Minggu 29 Minggu 30
19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21 5-Jul-21 12-Jul-21 19-Jul-21
S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D
25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21 11-Jul-21 18-Jul-21 27-Jul-21
100...
0.02 0.02 0.02 0.02 0.01 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004
100.00
90

6.51 6.51 6.51 6.51 90.000.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.10 80
23.58 7.99 17.52 5.35
80.00
70

70.00
0.28 60

60.00
1.46 1.46 1.46 1.46 1.46 50
0.57 50.00
40
40.00 0.58 0.58 0.58 0.58
0.57 30
30.00

20
20.00
3.61 0.91
10
10.00
0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.20 0.20 0.20 0.20 0.20 0.20 0.20
0.27 0.56 0.12 0.08 -

8.78 8.78 8.78 8.78 2.77 1.89 1.89 1.29 1.29 0.71 0.71 0.71 0.71 0.31
61.37 70.16 78.94 87.73 90.50 92.39 94.28 95.57 96.86 97.57 98.28 98.98 99.69 100.00
27.46 8.55 17.64 7.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
28.08 36.62 54.27 62.02 62.02 62.02 62.02 62.02 62.02 62.02 62.02 62.02 62.02 62.02
33.29 33.53 24.67 25.70 28.47 30.37 32.26 33.55 34.84 35.55 36.25 36.96 37.67 37.98
DAFTAR PERSONIL

Pekerjaan : Pembangunan Sarana Venue Terbang Layang LANUD di


Kabupaten Mimika
Kontraktor Pelaksana : PT. Mandava Putra Utama - PT. Pilar Delta Cakra (KSO)

No. JENIS ALAT PERIODE PEMAKAIAN SATUAN VOLUME


1 Operator Excavator 80-140 HP 30 Hari orang 2
2 Operator Motor Grader > 100hp 40 Hari orang 1
3 Operator Vibrator Roller 5-8 Ton 40 Hari orang 1
5 Sopir Dump Truck (6 Roda) 40 Hari orang 30
6 Sopir Dump Truck (10 Roda) 40 Hari orang 20
Operator Asphalt Distributor/Aspahalt Sprayer
7 3 Hari orang 1
850 Liter
8 Operator Asphalt Finisher 10 Ton 3 Hari orang 1
9 Operator Pneumatic Tire Roller 8-10 Ton 3 Hari orang 1
10 OperatorTandem Roller 6-8 Ton 3 Hari orang 1
11 Operator Tire Roller 8-10 T 3 Hari orang 1
DAFTAR ALAT

Pekerjaan : Pembangunan Sarana Venue Terbang Layang LANUD di


Kabupaten Mimika
Kontraktor Pelaksana : PT. Mandava Putra Utama - PT. Pilar Delta Cakra (KSO)

No. JENIS ALAT PERIODE PEMAKAIAN SATUAN VOLUME


1 Excavator 80-140 HP 30 Hari orang 2
2 Motor Grader > 100hp 40 Hari orang 1
3 Vibrator Roller 5-8 Ton 40 Hari orang 1
5 Dump Truck (6 Roda) 40 Hari orang 30
6 Dump Truck (10 Roda) 40 Hari orang 20

7 Asphalt Distributor/Aspahalt Sprayer 850 Liter 3 Hari orang 1

8 Asphalt Finisher 10 Ton 3 Hari orang 1


9 Pneumatic Tire Roller 8-10 Ton 3 Hari orang 1
10 Tandem Roller 6-8 Ton 3 Hari orang 1
11 Tire Roller 8-10 T 3 Hari orang 1
K3 (KESEHATAN DAN KESELAMATAN KERJA)

Pekerjaan : Pembangunan Sarana Venue Terbang Layang LANUD di


Kabupaten Mimika
Kontraktor Pelaksana : PT. Mandava Putra Utama - PT. Pilar Delta Cakra (KSO)

No. JENIS ALAT SATUAN VOLUME


1 Sepatu Safety Pcs 15
2 Helm Safety Pcs 15
3 Rompi Pcs 15
5 Sarung Tangan Pcs 24
6 Police Line m' 1000

Lampiran:
1. Sepatu Safety

2. Helm Safety

3. Rompi
4. Sarung Tangan

5. Police Line
BOBOT PEKERJAAN

KEGIATAN : PEMBANGUNAN SARANA VENUE TERBANG LAYANG


Pembangunan Sarana Venue Terbang Layang Lanud Timika di Kabupatern Mimika
PEKERJAAN : (MYC)
LOKASI : KOMPLEKS BANDAR UDARA MOZES KILANGIN - KABUPATEN MIMIKA
TAHUN ANGGARA : 2020

Harga satuan
No. Jenis barang/jasa Satuan Volume Bobot (%) Total (Rp.)
(Rp.)
I SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI
1 Penyiapan RKK
a. Kartu Identitas Pekerja (KIP) Bh 20.00 6,500.00 0.001 143,000.00
2 Sosialisasi dan Promosi K3
a. Papan informasi K3 Set 2.00 435,000.00 0.004 957,000.00
3 Alat Pelindung Kerja
a. Restricted Area (Pembatas Area) Ls 1.00 265,000.00 0.001 291,500.00
4 Material Pelindung Diri
a. Safety Shoes (sepatu keselamatan) Set 20.00 220,000.00 0.020 4,840,000.00
b. Safety Helmet (topi pelindung) Bh 20.00 75,000.00 0.007 1,650,000.00
c. Safety Vest (rompi keselamatan) Bh 20.00 45,000.00 0.004 990,000.00
d. Safety gloves (sarung tangan) Set 20.00 8,000.00 0.001 176,000.00
e. Face Shield (pelindung muka/helm las) Bh 5.00 125,000.00 0.003 687,500.00
f. Goggles, Spectacles (pelindung mata) Bh 20.00 45,000.00 0.004 990,000.00
5 Asuransi dan Perijinan
a. BPJS Ketenagakerjaan dan Kesehatan Kerja Ls 1.00 3,000,000.00 0.013 3,300,000.00
6 Personil K3
a. Ahli K3 Konstruksi OB 7.00 6,400,000.00 0.200 49,280,000.00
7 Fasilitas Sarana Kesehatan
a. Kotak P3K Bh 1.00 200,000.00 0.001 220,000.00

II PEKERJAAN LANDASAN PRECISSION


A PEKERJAAN PERSIAPAN
1 Mobilisasi ls 1.00 27,633,500.00 0.123 30,396,850.00
2 Manajemen dan Keselamatan Lalu Lintas ls 1.00 7,100,000.00 0.032 7,810,000.00
3 Pembersihan area dan pembuangan sampah m² 47,300.00 1,557.68 0.328 81,045,830.25
4 Pek. pengukuran dan pemasangan bowplank ls 47,300.00 1,311.75 0.276 68,250,352.50
5 Papan nama proyek ls 1.00 505,593.76 0.002 556,153.13

B PEKERJAAN TANAH DAN PASIR


1 Timbunan sirtu m³ 40,252.30 291,777.75 52.315 12,919,198,078.96
2 Timbunan tanah, tebal 15 cm m³ 7,095.00 262,597.50 8.299 2,049,442,188.75
3 Penanaman rumput manila (joysia matrella merr) m² 10,000.00 92,020.50 4.099 1,012,225,500.00
4 Penanaman rumput gajah lokal - (axonapus compresus) m² 21,500.00 56,611.50 5.422 1,338,861,975.00

C PEKERJAAN BETON
1 Pengecoran Beton Precision Landing Pad m³ 24.39 2,097,317.10 0.228 56,268,920.48
2 Galian Tanah m³ 40.65 95,245.88 0.017 4,258,919.30

III PEKERJAAN PENIMBUNAN AREA WASIT


A PEKERJAAN PERSIAPAN
1 Pembersihan area dan pembuangan sampah m² 1,875.00 1,489.95 0.01 3,073,021.88

B PEKERJAAN TANAH DAN PASIR


1 Timbunan sirtu m³ 1,031.25 291,777.75 1.34 330,985,385.16

C PEKERJAAN PENGADAAN TENDA MEMBRAN


1 Pondasi Tenda m³ 1.01 1,878,466.62 0.01 2,086,976.41
2 Pemasangan Angkur Pondasi Titik 60.00 30,800.70 0.01 2,032,846.20
3 Pemasangan dan Pengadaan Tenda Membran m² 128.00 1,626,900.00 0.93 229,067,520.00

IV PEKERJAAN PENIMBUNAN APRON


A PEKERJAAN PERSIAPAN
1 Pembersihan area dan pembuangan sampah m² 7,500.00 1,557.68 0.05204 12,850,818.75

B PEKERJAAN TANAH DAN PASIR


1 Timbunan sirtu m³ 4,125.00 291,777.75 5.36116 1,323,941,540.63
2 Timbunan tanah, tebal 15 cm m³ 1,125.00 262,597.50 1.31591 324,964,406.25
3 Penanaman rumput gajah lokal (axonapus compresus) m² 7,500.00 56,611.50 1.89125 467,044,875.00

V PEKERJAAN PENIMBUNAN AREA PENONTON


A PEKERJAAN PERSIAPAN
1 Pembersihan area dan pembuangan sampah m² 2,500.00 1,489.95 0.02 4,097,362.50

B PEKERJAAN TANAH DAN PASIR


1 Timbunan sirtu m³ 1,375.00 291,777.75 1.79 441,313,846.88

C PEKERJAAN PENGADAAN TENDA MEMBRAN


1 Pondasi Tenda m³ 1.82 1,914,941.70 0.02 3,833,713.28
2 Pemasangan Angkur Pondasi Titik 60.00 30,800.70 0.01 2,032,846.20
3 Pemasangan dan Pengadaan Tenda Membran m² 256.00 1,626,900.00 1.86 458,135,040.00

VI PEKERJAAN PEMBUATAN JALAN AKSES KE LOKASI


A PEKERJAAN PERSIAPAN
1 Pembersihan area dan pembuangan sampah m² 4,620.00 1,557.68 0.03 7,916,104.35
2 Pembuatan Pintu Akses Masuk Bandara ls 1.00 25,000,000.00 0.11 27,500,000.00

B PEKERJAAN TANAH DAN PASIR


1 Timbunan sirtu m³ 3,465.00 291,777.75 4.50 1,112,110,894.13

C PEKERJAAN PERKERASAN BERBUTIR


1 Lapis Pondasi Agregat Kelas A m³ 411.84 114,335.99 0.21 51,796,949.15
2 Lapis Pondasi Agregat Kelas B m³ 544.50 709,452.72 1.72 424,926,709.47

D PEKERJAAN ARSITEKTURAL LAPANGAN


1 Lapis Resap Pengikat - Aspal Cair m² 1,980.00 11,583.69 0.10 25,229,271.24
2 Laston Lapis Aus (AC-WC) m³ 379.50 621,198.64 1.05 259,319,372.37

E PEKERJAAN BETON
1 Pemasangan Box Culvert 1,5x1,5x1 m' 20.00 8,239,471.62 0.73 181,268,375.62

VII PEKERJAAN PEMBUATAN GEDUNG PASI


A PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Lapangan m² 474.46 12,147.30 0.02567 6,339,748.75
2 Pek. Pengukuran dan Pasang Bowplank m' 85.01 29,456.12 0.01115 2,754,471.47
3 Pek. Pembangunan Direksi Keets m² 20.00 527,697.76 0.04701 11,609,350.82
4 Pek. Gudang Tempat Bahan dan Alat m² 16.00 527,697.76 0.03761 9,287,480.66

B PEKERJAAN TANAH DAN PASIR


1 Pek. Galian Tanah m³ 181.93 88,908.75 0.07205 17,792,685.78
2 Pek. Urugan Kembali Tanah Pondasi m³ 54.58 28,987.88 0.00705 1,740,374.04
3 Pek. Urugan Pasir Alas Pondasi m³ 5.37 436,614.75 0.01044 2,579,083.33
4 Pas. Batu Kosong m³ 16.28 1,091,334.02 0.07914 19,543,609.54
5 Pas. Pondasi Batu Kali 14 m³ 34.90 1,768,286.85 0.27489 67,884,532.17
6 Pek. Urugan Sirtu Dibawah Lantai Bangunan m³ 122.77 291,777.75 0.15956 39,403,709.80
7 Pek. Urugan Pasir Alas Lantai Bangunan m³ 13.02 417,631.50 0.02422 5,981,318.34
8 Pek. Urugan Sirtu Untuk Leveling m³ 217.88 268,169.00 0.26026 64,271,527.89

C PEKERJAAN BETON
1 Pek. Cor Lantai Kerja Beton Tumbuk 135 t. 5 cm m³ 1.80 1,534,232.70 0.01230 3,037,780.75
2 Pek. Pondasi Poer Plat m³ 9.00 4,628,065.78 0.18553 45,817,851.18
3 Pek. Kolom Pedestal m³ 2.40 5,215,029.68 0.05575 13,767,678.36
4 Pek. Sloof Beton 15/20, Camp 1 2 3 m³ 9.36 5,415,436.47 0.22578 55,757,333.86
5 Pek. Kolom Praktis Beton 11/11, Camp 1 2 3 m³ 81.40 111,027.75 0.04026 9,941,424.79
6 Pek. Kolom Beton 30/30, Camp. 1 2 3 m³ 11.13 4,837,210.47 0.23981 59,221,967.74
7 Pek. Ringbalk Beton 15/20, Camp. 1 2 3 m³ 5.70 5,849,151.80 0.14851 36,674,181.82
8 Pek. Plat Lantai (Dalam Bangunan) Tebal 10 Cm m³ 16.82 1,766,714.65 0.13237 32,687,754.47
9 Pek. Canopy Beton m³ 0.90 6,407,293.84 0.02569 6,343,220.90
10 Pek. Canopy/List Pintu dan Jendela m³ 3.20 5,718,940.31 0.08152 20,130,669.90
11 Pek. Cor Beton Drop Off Area m³ 35.94 1,902,294.90 0.30454 75,205,326.58

D PEKERJAAN DINDING DAN PLESTERAN


1 Pas. Dinding Batu Tela 1 3 (h40 cm) m² 121.16 168,783.75 0.09109 22,494,822.67
2 Pas. Dinding Batu Tela 1 5 m² 187.95 99,620.63 0.08340 20,596,066.24
3 Pek. Plesteran Dinding 13 (h40 cm) m² 121.16 120,757.83 0.06517 16,094,120.63
4 Pek. Plesteran Dinding 15 m² 187.95 113,275.43 0.09483 23,419,128.86
5 Pek. Plesteran Beton 13 (Kolom Expose) m² 63.91 94,326.89 0.02685 6,631,274.90
6 Pek. Acian Dinding m² 618.23 46,409.49 0.12780 31,560,912.90

E PEKERJAAN KERAMIK DAN BATU ALAM


1 Pas. Keramik Lantai Dalam 60/60 m² 164.13 411,120.80 0.30057 74,224,983.05
2 Pas. Keramik Teras dan Keliling m² 70.50 449,890.18 0.14128 34,888,983.27
3 Pas. Keramik Lantai Km/WC 25/25 m² 8.62 179,488.94 0.00689 1,701,914.09
4 Pas. Dinding Keramik Km/WC 25/50 m² 26.90 161,956.00 0.01941 4,792,278.04
5 Pek. Plint Keramik Ukuran (10 x 60) cm m' 95.00 38,420.23 0.01626 4,014,913.81

F PEKERJAAN PINTU DAN JENDELA


1 Pek. Kusen Pintu, Jendela m³ 1.79 9,453,996.75 0.07538 18,614,919.60
2 Pek. Pintu Utama Bh 1.00 7,177,500.00 0.03197 7,895,250.00
3 Pek. Daun Pintu m² 18.90 833,522.25 0.07017 17,328,927.58
4 Pek. Daun Pintu KM lapis Formika, (Lebar 70 cm) m² 3.60 969,006.59 0.01554 3,837,266.09
5 Pek. Daun Jendela m² 8.65 750,756.60 0.02893 7,143,449.05
6 Pas. Jendela Kaca Riben 5 mm Kayu Besi m² 32.75 691,626.13 0.10089 24,915,831.24
7 Pek. Lubang Angin Bh 6.00 56,310.90 0.00150 371,651.96
8 Alat Bantu dan Anker Ls 1.00 800,000.00 0.00356 880,000.00

G PEKERJAAN KUNCI DAN ALAT GANTUNGAN


1 Pas. Kunci Tanam Pintu 2 Slaag (1 bh per pintu) Bh 6.00 445,524.75 0.01191 2,940,463.35
2 Pas. Kunci Tanam Selinder (1 bh per pintu) Bh 3.00 230,807.78 0.00308 761,665.66
3 Pas. Engsel Pintu ( 3 bh per pintu) Bh 19.00 61,169.63 0.00518 1,278,445.16
4 Pas. Engsel Jendela (2 bh per jendela) Bh 52.00 45,813.08 0.01061 2,620,507.89
5 Pas. Hak Angin Jendela (2 bh per jendela) Bh 26.00 49,972.73 0.00579 1,429,219.94
6 Pas. Grendel Pintu (1 bh per pintu) Bh 8.00 64,830.15 0.00231 570,505.32
7 Pas. Grendel Jendela (1 bh per jendela) Bh 26.00 60,906.45 0.00705 1,741,924.47

H PEKERJAAN PENUTUP ATAP


1 Kuda-kuda kayu besi uk. 6 x 12 cm M³ 2.13 7,025,478.90 0.06666 16,460,697.06
2 Gording kayu kelas I uk. 6 x 12 cm M³ 1.76 6,055,056.00 0.04747 11,722,588.42
3 Kaso 5/5 M³ 395.77 59,247.29 0.10445 25,793,131.05
4 Reng 2/3 M³ 395.77 56,225.37 0.09912 24,477,544.85
5 Pas. Atap Genteng Metal Warna M² 395.77 235,989.93 0.41602 102,737,508.06
6 Talang jurai dalam M' 10.70 221,177.39 0.01054 2,603,257.82
7 Lisplank kayu besi uk. 2.5 x 25 cm M' 71.94 98,679.57 0.03162 7,808,909.09
8 Cat lisplank M² 21.58 76,399.62 0.00734 1,813,574.18
9 Pas. Nok / Bumbungan Genteng Metal Bh 29.54 361,191.60 0.04753 11,736,559.85
10 Alat Bantu & Perancah Ls 1.00 1,400,000.00 0.00624 1,540,000.00

I PEKERJAAN PLAFOND
1 Pek. Plafond Gipsum 9 mm (Luar-Dalam) m² 260.13 195,099.10 0.22606 55,826,242.34
2 Pek. List Plafon Gypsum (Luar-Dalam) m' 190.00 59,980.27 0.05076 12,535,876.85
3 Alat Bantu dan Perancah Ls 1.00 1,400,000.00 0.00624 1,540,000.00

J PEKERJAAN SANITASI
1 Pas. Kloset Duduk Putih, ex. Toto Bh 3.00 2,677,771.80 0.03578 8,836,646.94
2 Pek. Bak Air Fiber Glass Bh 3.00 893,830.54 0.01194 2,949,640.79
3 Pas. Kran Air 1/2 Bh 10.00 44,301.15 0.00197 487,312.65
4 Pas. Floor Drain Bh 6.00 140,307.75 0.00375 926,031.15
5 Instalasi Pipa Air Bersih PVC Dia. 2 Type AW m' 40.00 156,660.90 0.02791 6,893,079.60
6 Instalasi Pipa Air Kotor PVC Dia. 4 Type AW m' 20.00 91,479.47 0.00815 2,012,548.23
7 Pas. Washtafel Bh 2.00 1,055,281.19 0.00940 2,321,618.63
8 Pek. Septic Tank + Peresapan Unit 1.00 7,775,172.68 0.03463 8,552,689.95

K PEKERJAAN INSTALASI LISTRIK & LAMPU ELECTRIKAL


1 Panel Box MCB 18 Grup Unit 1.00 4,000,000.00 0.01782 4,400,000.00
2 Pengetanahan Panel Listrik BC. 16 mm2 Unit 1.00 5,000,000.00 0.02227 5,500,000.00
3 Pas. 1 Titik Penerangan Lampu Ttk 45.00 299,717.55 0.06008 14,836,018.73
4 Pas. Ttk Lampu Philips SL 23 Watt Ttk 45.00 155,000.00 0.03107 7,672,500.00
5 Pek. Instalasi Stop Kontak AC/ Khusus Ttk 8.00 449,583.75 0.01602 3,956,337.00
6 Pek. Saklar Tunggal Ex Broco Bh 12.00 255,000.00 0.01363 3,366,000.00
7 Pek. Saklar Ganda Ex Broco Bh 8.00 265,000.00 0.00944 2,332,000.00
8 Pek. Stop Kontak Ex Broco Bh 16.00 232,000.00 0.01653 4,083,200.00
9 Pek. Stop Kontak AC Clipsal Bh 8.00 388,000.00 0.01383 3,414,400.00
10 AC 2 PK Unit 6.00 9,000.00 0.00024 59,400.00
11 Exhaust Fan Unit 4.00 1,800,000.00 0.03207 7,920,000.00

L PEKERJAAN PENGECATAN
1 Pek. Cat Dinding m² 304.44 55,514.25 0.07528 18,590,834.10
2 Pek. Cat Plafon m² 395.77 30,632.25 0.05400 13,335,658.14
3 Pek. Cat Kilap Kusen m² 37.52 39,025.77 0.00652 1,610,671.46
4 Pek. Cat Kilap Pintu, Jendela m² 12.00 52,665.77 0.00282 695,188.12

M PEKERJAAN LAIN-LAIN
1 Pas. Saluran Keliling Bangunan m' 65.11 217,493.10 0.06308 15,577,073.32

N PEKERJAAN AKHIR
1 Pek. Pembersihan Akhir Ls 1.00 1,500,000.00 0.00668 1,650,000.00
2 Pek. Photo Dokumentasi Ls 1.00 1,400,000.00 0.00624 1,540,000.00
3 Pek. Laporan-laporan Ls 1.00 1,900,000.00 0.00846 2,090,000.00
4 Pek. Shop Drawing & Asbuilt Drawing Ls 1.00 4,500,000.00 0.02004 4,950,000.00