BENGKEL ME Rp 1,921,814,448.70
A PEKERJAAN TANAH DAN PONDASI BATU BELAH, ROOLAG Rp 109,453,904.82
B PEKERJAAN STRUKTUR Rp 672,635,996.15
C PEKERJAAN DINDING DAN PLESTERAN Rp 586,109,704.54
D PEKERJAAN PELAPIS LANTAI DAN DINDING Rp 104,684,560.72
E PEKERJAAN PLAFOND Rp 41,757,412.24
F PEKERJAAN PENGECATAN Rp 27,910,945.84
G PEKERJAAN RANGKA BESI DAN PENUTUP ATAP Rp 213,852,254.84
H PEKERJAAN PINTU JENDELA Rp 60,763,849.40
I PEKERJAAN SANITASI Rp 7,352,160.16
J PEKERJAAN LISTRIK Rp 63,339,600.00
K PEKERJAAN AIR BERSIH Rp 1,132,000.00
L PEKERJAAN AIR KOTOR DAN AIR BEKAS Rp 30,583,140.00
M PEKERJAAN EXHAUST FAN Rp 2,238,920.00
Sembilan Puluh Delapan Milyar Enam Ratus Enam Puluh Dua Juta Tujuh Ratus Sembilan Belas Ribu Rupiah
RENCANA ANGGARAN BIAYA
PEKERJAAN LANSEKAP
1 Pekerjaan urugan tanah subur 159.95 m3 Rp 200,000.00 Rp 31,990,000.00
2 Pekerjaan penanaman rumput gajah mini 3,199.00 m2 Rp 75,000.00 Rp 239,925,000.00
3 Pekerjaan pengadaan dan penanaman pohon ketapang 50.00 unit Rp 2,500,000.00 Rp 125,000,000.00
4 Pekerjaan pengadaan dan penanaman pohon ketapang kencana 7.00 unit Rp 2,500,000.00 Rp 17,500,000.00
5 Pekerjaan pengadaan dan penanaman pohon cemara pinus 140.00 unit Rp 1,000,000.00 Rp 140,000,000.00
6 Pekerjaan pengadaan dan penanaman tanaman perdu andong merah 20.00 m Rp 200,000.00 Rp 4,000,000.00
7 Pekerjaan pengadaan dan penanaman tanaman perdu bunga lolipop golden 10.00 m Rp 250,000.00 Rp 2,500,000.00
8 Pekerjaan pengadaan dan penanaman tanaman perdu heliconia catalea 17.00 m Rp 300,000.00 Rp 5,100,000.00
PEKERJAAN HYDRANT
PERALATAN UTAMA
1 Pompa Diesel Fire Pump ( DFP )
Kap : 500 USGPM. 1.00 unit Rp 724,490,000.00 Rp 724,490,000.00
Head : 80 M
Jenis : Centrifugal End Suction Pump
Speed : 2900 RPM.
Lokasi : Ruang Pompa
Complete with :
- Panel Control Diesel 12V NFPA20 Standard
- base Plate Coupling & Guard
- Accessories : - Gauges
- Battery : 1 Sets
- Fuel Tank
- Radiator, Muffler, Flexible pipe
h. Flexible Joint
Diameter : 4" 2.00 bh Rp 2,004,000.00 Rp 4,008,000.00
: 2 1/2" 1.00 bh Rp 1,390,000.00 Rp 1,390,000.00
i. Pressure Gauge 1.00 bh Rp 602,000.00 Rp 602,000.00
k. Automatic Air Vent : 250 mm 1.00 bh Rp 9,205,000.00 Rp 9,205,000.00
l. Safety Valve lengkap dengan Flow meter 1.00 bh Rp 24,248,000.00 Rp 24,248,000.00
m. Air release valve 1.00 bh Rp 24,000,000.00 Rp 24,000,000.00
n. presure switch 1.00 bh Rp 4,300,000.00 Rp 4,300,000.00
o. Pressure Tank 1000 Liter 1.00 bh Rp 8,050,000.00 Rp 8,050,000.00
p. Pondasi Pompa 3.00 ls Rp 2,300,000.00 Rp 6,900,000.00
q. Ijin Depnaker 1.00 ls Rp 5,000,000.00 Rp 5,000,000.00
PEKERJAAN CCTV
PERALATAN UTAMA
Pengadaan dan pemasangan lengkap peralatan
instalasi kabel, dudukan dan penggantung, training dan
tes commissioning
PERALATAN UTAMA
NVR SE Unit, 2U Rackmount, Supports up to 16 channels, 1.00 unit Rp 31,940,000.00 Rp 31,940,000.00
Intel Core i7 Processor, 8GB RAM, Removable HD's, 400W Power Supply,
DVD-RW, 2x 1Gb Ethernet, 6 each SATA Drive Bays with 1 each 1TB SATA Drives,
Windows 7 OS, Includes 3 year advanced parts replacement
Assesories:
Wall Mount Bracket 1.00 unit Rp 1,231,200.00 Rp 1,231,200.00
Wall Mount Bracket with access hole (new) 1.00 unit Rp 1,981,800.00 Rp 1,981,800.00
220mm Extension pole for HDZCM1 1.00 unit Rp 683,100.00 Rp 683,100.00
1.5NPT Adapter 1.00 unit Rp 774,900.00 Rp 774,900.00
Wall Mount Bracket 1.00 unit Rp 1,876,500.00 Rp 1,876,500.00
Pendant Mount Bracket 1.00 unit Rp 1,309,500.00 Rp 1,309,500.00
Instalasi dengan kabel UTP cat-6, lengkap dengan peralatan instalasi kabel 1,518.00 m Rp 38,000.00 Rp 57,684,000.00
galian tanah 1,518.00 m Rp 30,000.00 Rp 45,540,000.00
Switch hub. 4 port 16.00 bh Rp 420,000.00 Rp 6,720,000.00
Pekerjaan Ducting Radiator dan knalpot genset 2 unit 1.00 lot Rp 52,000,000.00 Rp 52,000,000.00
Pentanahan Body Genset dengan BC 50 mm2 2.00 titik Rp 5,000,000.00 Rp 10,000,000.00
Pentanahan Netral Genset dengan BC 50 mm2 2.00 titik Rp 5,000,000.00 Rp 10,000,000.00
Tangki solar bulanan / BBM Kap.6.000 liter 2.00 unit Rp 75,000,000.00 Rp 150,000,000.00
Pemipaan Elektrik & Manual Pump Solar 2.00 unit Rp 2,150,000.00 Rp 4,300,000.00
Perijinan ke Instansi terkait 1.00 lot Rp 5,500,000.00 Rp 5,500,000.00
Fuel Electric Pump c/w Panel Control 2.00 unit Rp 6,500,000.00 Rp 13,000,000.00
Pekerjaan Ducting Radiator System, 2 unit genset 1.00 lot Rp 32,500,000.00 Rp 32,500,000.00
Material & Peralatan Bantu 1.00 ls Rp 15,000,000.00 Rp 15,000,000.00
Solar test 10,000.00 Liter Rp 14,000.00 Rp 140,000,000.00
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
2 Pekerjaan Panel
Panel LVMDP 1.00 unit Rp 280,000,000.00 Rp 280,000,000.00
Panel COS 500A 1.00 unit Rp 35,000,000.00 Rp 35,000,000.00
Panel Terminal existing 1.00 unit Rp 32,000,000.00 Rp 32,000,000.00
Panel Rumah dinas existing 1.00 unit Rp 13,500,000.00 Rp 13,500,000.00
Panel STP/IPAL 1.00 unit Rp 8,200,000.00 Rp 8,200,000.00
Panel Runway 1.00 unit Rp 17,200,000.00 Rp 17,200,000.00
Panel Bangunan PKP Existing 1.00 unit Rp 6,300,000.00 Rp 6,300,000.00
Panel Gudang alat berat Existing 1.00 unit Rp 4,300,000.00 Rp 4,300,000.00
1 set lampu PJU solar cell (2 lengan): 1.00 unit Rp 145,274,000.00 Rp 145,274,000.00
Lampu led 2x60 watt
SOLAR PANEL MONO/POLY-CRYSTALLINE 2X200WP 24V
CXN CONTROLLER 10A AUTOMATIC ON-OFF
BATTERY TYPE MF 2X150AH 24V (SERI)
BOX BATTERY CHARGER SOLLAR CELL
TIANG OCTAGONAL 7M + SOLLAR CELL SUPPORT
INSTALASI MATERIALS : CONECTOR,CABLES,CABLEGLAND,CABLE TIES
COUPLE FEMALE/MALE ETC
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
10,241.68
PAVING
urugan pasir 493.68 0.10 49.37
49.37
-
sirtu 493.68 0.25 123.42
123.42
paving
75.00 1.60 120.00
18.00 1.20 21.60
21.50 1.50 32.25
2.75 2.30 6.32
9.00 1.50 13.50
30.00 10.00 300.00
493.68
perkerasan beton
1,235.00 0.20 247.00
247.00
wiremesh m6 34,76 kg/ lbr 1 lbr = 2,1*5,4 3.07 1,235.00 3,785.59
PERKERASAN TANAH
perkerasan tanah
8,745.00 0.10 874.50
874.50
DRAINASE
SAL U-20 21.00 21.00
74.00 74.00
75.00 75.00
117.00 117.00
75.00 75.00
362.00
PAGAR
LANSEKAP
GEDUNG ADMINISTRASI
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 0.60 m3 Rp 14,990,788.55 Rp 8,994,473.13
2 Footplat
- Beton K250 4.03 m3 Rp 17,361,638.90 Rp 70,002,128.06
- Pembesian 498.14 kg Rp 40,265.29 Rp 20,057,910.82
- Bekesting 8.16 m2 Rp 407,897.78 Rp 3,328,445.91
3 Sloof SL 1
- Beton K250 4.62 m3 Rp 17,361,638.90 Rp 80,210,771.73
- Pembesian 486.19 kg Rp 40,265.29 Rp 19,576,531.26
- Bekesting 46.20 m2 Rp 436,608.68 Rp 20,171,321.14
4 Sloof SL 2
- Beton K250 0.50 m3 Rp 17,361,638.90 Rp 8,698,181.09
- Pembesian 66.80 kg Rp 40,265.29 Rp 2,689,560.07
- Bekesting 10.02 m2 Rp 436,608.68 Rp 4,374,819.00
5 Ringbalk RB1
- Beton K250 0.50 m3 Rp 17,361,638.90 Rp 8,698,181.09
- Pembesian 66.80 kg Rp 40,265.29 Rp 2,689,560.07
- Bekesting 9.18 m2 Rp 977,188.97 Rp 8,975,480.72
6 Balok B1
- Beton K250 4.08 m3 Rp 17,361,638.90 Rp 70,835,486.73
- Pembesian 429.28 kg Rp 40,265.29 Rp 17,285,082.14
- Bekesting 54.40 m2 Rp 977,188.97 Rp 53,159,080.15
7 Kolom K1
- Beton K250 1.97 m3 Rp 17,361,638.90 Rp 34,167,705.36
- Pembesian 503.42 kg Rp 40,265.29 Rp 20,270,511.53
- Bekesting 39.36 m2 Rp 959,962.43 Rp 37,784,121.37
8 Kolom KP
- Beton K250 1.01 m3 Rp 17,361,638.90 Rp 17,617,723.08
- Pembesian 158.05 kg Rp 40,265.29 Rp 6,363,847.98
- Bekesting 27.06 m2 Rp 959,962.43 Rp 25,976,583.45
9 Meja beton pantry
- Beton K175 0.11 m3 Rp 16,436,533.70 Rp 1,808,018.71
- Pembesian 5.64 kg Rp 40,265.29 Rp 227,096.22
- Bekesting 1.10 m2 Rp 1,278,972.43 Rp 1,406,869.68
10 Tritiran / topi2 (atas bouvent)
- Beton K175 0.62 m3 Rp 16,436,533.70 Rp 10,138,053.99
- Pembesian 38.90 kg Rp 40,265.29 Rp 1,566,480.70
- Bekesting 7.71 m2 Rp 1,278,972.43 Rp 9,860,877.46
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum dan rangka hollow 89.90 m2 Rp 411,862.15 Rp 37,024,347.97
2 Pekerjaan pemasangan plafond kalsiboard dan rangka hollow 6.11 m2 Rp 307,998.30 Rp 1,880,329.63
2 Pekerjaan pemasangan plafond sprandel 59.65 m2 Rp 589,664.91 Rp 35,172,038.02
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 505.96 m2 Rp 72,574.75 Rp 36,720,180.46
2 Pekerjaan pengecatan plafond 96.00 m2 Rp 72,666.40 Rp 6,975,974.08
PEKERJAAN SANITASI
1 Pekerjaan pemasangan closet duduk / monoblok 3.00 unit Rp 4,040,721.71 Rp 12,122,165.12
2 Pekerjaan pemasangan shower spray 3.00 unit Rp 512,359.96 Rp 1,537,079.88
3 Pekerjaan pemasangan toilet paper holder 3.00 unit Rp 483,379.96 Rp 1,450,139.88
4 Pekerjaan pemasangan kran air 3.00 unit Rp 161,523.71 Rp 484,571.13
5 Pekerjaan pemasangan floor drain 3.00 unit Rp 116,014.19 Rp 348,042.56
6 Pekerjaan pemasangan tempat sabun 3.00 unit Rp 333,879.96 Rp 1,001,639.88
7 Pekerjaan pemasangan bak cuci stainless steel 1.00 unit Rp 1,704,280.68 Rp 1,704,280.68
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP ke PP GD. Administrasi 40.00 m Rp 160,800.00 Rp 6,432,000.00
(NYY 4 x 10 mm2)
2 PP. GD. Administrasi 1.00 unit Rp 13,000,000.00 Rp 13,000,000.00
Pekerjaan Grounding panel 1.00 ls Rp 2,500,000.00 Rp 2,500,000.00
Pekerjaan penerangan dan kontak-kontak
1 RM led 2x10 watt 4.00 bh Rp 1,772,600.00 Rp 7,090,400.00
2 Downlight 4", + lampu bolam led 10 watt, e27 16.00 bh Rp 682,800.00 Rp 10,924,800.00
3 Downlight 4", + lampu bolam led 5 watt + tutup acliric, E27 3.00 bh Rp 399,200.00 Rp 1,197,600.00
4 Downlight outbow 4", + lampu bolam led 10 watt + E27 3.00 bh Rp 863,800.00 Rp 2,591,400.00
5 saklar tunggal 3.00 bh Rp 56,000.00 Rp 168,000.00
6 saklar ganda 7.00 bh Rp 70,000.00 Rp 490,000.00
7 Stop kontak umum dinding, 200 watt 10.00 bh Rp 80,000.00 Rp 800,000.00
8 Stop kontak komputer, 400 watt (lantai) 8.00 bh Rp 380,000.00 Rp 3,040,000.00
9 Stop kontak proyektor, 100 watt, plafon 1.00 bh Rp 80,000.00 Rp 80,000.00
10 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 26.00 titik Rp 420,000.00 Rp 10,920,000.00
11 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 19.00 titik Rp 550,000.00 Rp 10,450,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH FOOTPLAT 12 1.0 1.0 1.1 13.20
PAS BATU 16.7 0.8 1.7 22.71
ROOLAG 14 0.9 0.25 3.15
39.06
ROOLAG
PONDASI BATU 14 0.36 5.04
FOOTPLAT
PEMBESIAN
dia 13 - 150 7 12 2.35 1.04 205.30
dia 13 - 150 7 12 2.35 1.04 205.30
4D13 4 12 1.04 1.35 67.39
dia 8 -150 6 12 0.7 0.4 20.16
498.14
SLOOF SL1
SLOOF SL2
RB 1
B1
K1
KP
PEMBESIAN
4d10 4 11 0.62 4.1 111.85
DIA. 8-200 21 11 0.5 0.4 46.20
158.05
MEJA BETON
TOPI2
PEKERJAAN DINDING
252.98
PEKERJAAN LANTAI
PEKERJAAN PLAFOND
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding 505.96
plafond 96.00
GEDUNG OPERASIONAL
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 0.60 m3 Rp 14,990,788.55 Rp 8,994,473.13
2 Footplat
- Beton K250 4.03 m3 Rp 17,361,638.90 Rp 70,002,128.06
- Pembesian 498.14 kg Rp 40,265.29 Rp 20,057,910.82
- Bekesting 8.16 m2 Rp 407,897.78 Rp 3,328,445.91
3 Sloof SL 1
- Beton K250 4.62 m3 Rp 17,361,638.90 Rp 80,210,771.73
- Pembesian 486.19 kg Rp 40,265.29 Rp 19,576,531.26
- Bekesting 46.20 m2 Rp 436,608.68 Rp 20,171,321.14
4 Sloof SL 2
- Beton K250 0.42 m3 Rp 17,361,638.90 Rp 7,213,760.96
- Pembesian 55.89 kg Rp 40,265.29 Rp 2,250,346.32
- Bekesting 8.31 m2 Rp 436,608.68 Rp 3,628,218.15
5 Ringbalk RB1
- Beton K250 0.42 m3 Rp 17,361,638.90 Rp 7,213,760.96
- Pembesian 55.89 kg Rp 40,265.29 Rp 2,250,346.32
- Bekesting 7.62 m2 Rp 977,188.97 Rp 7,443,737.00
6 Balok B1
- Beton K250 4.08 m3 Rp 17,361,638.90 Rp 70,835,486.73
- Pembesian 429.28 kg Rp 40,265.29 Rp 17,285,082.14
- Bekesting 54.40 m2 Rp 977,188.97 Rp 53,159,080.15
7 Kolom K1
- Beton K250 1.97 m3 Rp 17,361,638.90 Rp 34,167,705.36
- Pembesian 503.42 kg Rp 40,265.29 Rp 20,270,511.53
- Bekesting 39.36 m2 Rp 959,962.43 Rp 37,784,121.37
8 Kolom KP
- Beton K250 0.83 m3 Rp 17,361,638.90 Rp 14,414,500.70
- Pembesian 129.31 kg Rp 40,265.29 Rp 5,206,784.71
- Bekesting 22.14 m2 Rp 959,962.43 Rp 21,253,568.27
9 Meja beton pantry
- Beton K175 0.11 m3 Rp 16,436,533.70 Rp 1,808,018.71
- Pembesian 5.64 kg Rp 40,265.29 Rp 227,096.22
- Bekesting 1.10 m2 Rp 1,278,972.43 Rp 1,406,869.68
10 Tritiran / topi2 (atas bouvent)
- Beton K175 0.62 m3 Rp 16,436,533.70 Rp 10,138,053.99
- Pembesian 38.90 kg Rp 40,265.29 Rp 1,566,480.70
- Bekesting 7.71 m2 Rp 1,278,972.43 Rp 9,860,877.46
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum dan rangka hollow 89.90 m2 Rp 411,862.15 Rp 37,024,347.97
2 Pekerjaan pemasangan plafond kalsiboard dan rangka hollow 6.11 m2 Rp 307,998.30 Rp 1,880,329.63
2 Pekerjaan pemasangan plafond sprandel 59.65 m2 Rp 589,664.91 Rp 35,172,038.02
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 505.96 m2 Rp 72,574.75 Rp 36,720,180.46
2 Pekerjaan pengecatan plafond 96.00 m2 Rp 72,666.40 Rp 6,975,974.08
PEKERJAAN SANITASI
1 Pekerjaan pemasangan closet duduk / monoblok 2.00 unit Rp 4,040,721.71 Rp 8,081,443.41
2 Pekerjaan pemasangan shower spray 2.00 unit Rp 512,359.96 Rp 1,024,719.92
3 Pekerjaan pemasangan toilet paper holder 2.00 unit Rp 483,379.96 Rp 966,759.92
4 Pekerjaan pemasangan kran air 2.00 unit Rp 161,523.71 Rp 323,047.42
5 Pekerjaan pemasangan floor drain 2.00 unit Rp 116,014.19 Rp 232,028.37
6 Pekerjaan pemasangan tempat sabun 2.00 unit Rp 333,879.96 Rp 667,759.92
7 Pekerjaan pemasangan bak cuci stainless steel 1.00 unit Rp 1,704,280.68 Rp 1,704,280.68
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP ke PP GD. Operasional 53.00 m Rp 160,800.00 Rp 8,522,400.00
(NYY 3 x 10 mm2)
2 PP. GD. Operasional 1.00 unit Rp 7,000,000.00 Rp 7,000,000.00
3 Pekerjaan Grounding panel 1.00 ls Rp 2,500,000.00 Rp 2,500,000.00
Pekerjaan penerangan dan kontak-kontak
1 RM led 2x10 watt 6.00 bh Rp 1,772,600.00 Rp 10,635,600.00
2 Downlight 4", + lampu bolam led 10 watt 13.00 bh Rp 682,800.00 Rp 8,876,400.00
3 Downlight 4", + lampu bolam led 5 watt + tutup acliric 2.00 bh Rp 399,200.00 Rp 798,400.00
4 Downlight outbow 4", + lampu bolam led 10 watt + E27 4.00 bh Rp 863,800.00 Rp 3,455,200.00
5 saklar tunggal 4.00 bh Rp 56,000.00 Rp 224,000.00
6 saklar ganda 7.00 bh Rp 70,000.00 Rp 490,000.00
7 Stop kontak umum dinding, 200 watt 9.00 bh Rp 80,000.00 Rp 720,000.00
8 Stop kontak komputer, 400 watt (lantai) 10.00 bh Rp 380,000.00 Rp 3,800,000.00
9 Stop kontak proyektor, 100 watt, plafon 1.00 bh Rp 80,000.00 Rp 80,000.00
10 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 25.00 titik Rp 420,000.00 Rp 10,500,000.00
11 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 20.00 titik Rp 550,000.00 Rp 11,000,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH FOOTPLAT 12 1.0 1.0 1.1 13.20
PAS BATU 13.9 0.8 1.7 18.84
ROOLAG 14 0.9 0.25 3.15
35.19
ROOLAG
-
PONDASI BATU 14 0.36 5.04
FOOTPLAT
PEMBESIAN
dia 13 - 150 7 12 2.35 1.04 205.30
dia 13 - 150 7 12 2.35 1.04 205.30
4D13 4 12 1.04 1.35 67.39
dia 8 -150 6 12 0.7 0.4 20.16
498.14
SLOOF SL1
SLOOF SL2
RB 1
B1
K1
KP
MEJA BETON
TOPI2
PEKERJAAN DINDING
220.99
PEKERJAAN LANTAI
KERAMIK DINDING
KM 2 5.70 2 22.80
MEJA DAN DINDING PANTRY 1.55 0.50 0.78
0.50 0.65 0.33
2.20 0.1 0.22
2.85 2 5.70
29.82
PEKERJAAN PLAFOND
KALSI
KA 2 1.50 1.35 4.05
4.05
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding 441.97
plafond 96.00
GEDUNG KEAMANAN
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 0.40 m3 Rp 14,990,788.55 Rp 5,996,315.42
2 Footplat
- Beton K250 2.69 m3 Rp 17,361,638.90 Rp 46,668,085.37
- Pembesian 332.10 kg Rp 40,265.29 Rp 13,371,940.54
- Bekesting 5.44 m2 Rp 407,897.78 Rp 2,218,963.94
3 Sloof SL 1
- Beton K250 2.76 m3 Rp 17,361,638.90 Rp 47,918,123.37
- Pembesian 292.43 kg Rp 40,265.29 Rp 11,774,729.38
- Bekesting 27.60 m2 Rp 436,608.68 Rp 12,050,399.64
4 Sloof SL 2
- Beton K250 0.50 m3 Rp 17,361,638.90 Rp 8,594,011.26
- Pembesian 66.30 kg Rp 40,265.29 Rp 2,669,588.49
- Bekesting 9.90 m2 Rp 436,608.68 Rp 4,322,425.96
5 Balok B1 elv +3.17
- Beton K250 0.26 m3 Rp 17,361,638.90 Rp 4,427,217.92
- Pembesian 35.18 kg Rp 40,265.29 Rp 1,416,532.77
- Bekesting 4.68 m2 Rp 977,188.97 Rp 4,568,358.45
6 Balok B1 elv +3.82
- Beton K250 1.62 m3 Rp 17,361,638.90 Rp 28,125,855.02
- Pembesian 211.86 kg Rp 40,265.29 Rp 8,530,603.57
- Bekesting 29.70 m2 Rp 977,188.97 Rp 29,022,512.51
7 Kolom K1
- Beton K250 1.28 m3 Rp 17,361,638.90 Rp 22,222,897.80
- Pembesian 326.72 kg Rp 40,265.29 Rp 13,155,474.36
- Bekesting 25.60 m2 Rp 959,962.43 Rp 24,575,038.29
8 Kolom K2
- Beton K250 0.90 m3 Rp 17,361,638.90 Rp 15,625,475.01
- Pembesian 141.20 kg Rp 40,265.29 Rp 5,685,458.44
- Bekesting 24.00 m2 Rp 959,962.43 Rp 23,039,098.40
9 Tritiran / topi2 (atas jendela)
- Beton K175 0.59 m3 Rp 16,436,533.70 Rp 9,644,957.98
- Pembesian 37.04 kg Rp 40,265.29 Rp 1,491,587.27
- Bekesting 7.34 m2 Rp 1,278,972.43 Rp 9,381,262.80
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum t = 9 mm dan rangka hollow 44.00 m2 Rp 411,862.15 Rp 18,121,934.60
2 Pekerjaan pemasangan plafond kalsiboard dan rangka hollow 12.00 m2 Rp 307,998.30 Rp 3,695,979.62
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 292.64 m2 Rp 72,574.75 Rp 21,237,925.72
2 Pekerjaan pengecatan plafond 56.00 m2 Rp 72,666.40 Rp 4,069,318.21
PEKERJAAN SANITASI
1 Pekerjaan pemasangan closet duduk / monoblok 1.00 unit Rp 4,040,721.71 Rp 4,040,721.71
2 Pekerjaan pemasangan shower spray 1.00 unit Rp 512,359.96 Rp 512,359.96
3 Pekerjaan pemasangan toilet paper holder 1.00 unit Rp 483,379.96 Rp 483,379.96
4 Pekerjaan pemasangan kran air 1.00 unit Rp 161,523.71 Rp 161,523.71
5 Pekerjaan pemasangan floor drain 1.00 unit Rp 116,014.19 Rp 116,014.19
6 Pekerjaan pemasangan tempat sabun 1.00 unit Rp 333,879.96 Rp 333,879.96
7 Pekerjaan pemasangan bak cuci stainless steel 1.00 unit Rp 1,704,280.68 Rp 1,704,280.68
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP MCB box rumah dinas 40.00 m Rp 160,800.00 Rp 6,432,000.00
(NYY 3 x 10 mm2)
2 MCB BOX 1.00 unit Rp 2,400,000.00 Rp 2,400,000.00
Pekerjaan penerangan dan kontak-kontak
1 Downlight 4", + lampu bolam led 10 watt 17.00 bh Rp 682,800.00 Rp 11,607,600.00
2 Downlight 4", + lampu bolam led 5 watt + tutup acliric 1.00 bh Rp 399,200.00 Rp 399,200.00
3 Lampu dinding led 10 watt 2.00 bh Rp 1,413,200.00 Rp 2,826,400.00
4 saklar tuggal 1.00 bh Rp 56,000.00 Rp 56,000.00
5 saklar ganda 5.00 bh Rp 70,000.00 Rp 350,000.00
6 Stop kontok umum dinding, 200 watt 6.00 bh Rp 80,000.00 Rp 480,000.00
7 Stop kontok umum lantai, 200 watt 1.00 bh Rp 370,000.00 Rp 370,000.00
8 Stop kontok komputer dinding, 400 watt 1.00 bh Rp 80,000.00 Rp 80,000.00
9 Stop kontok komputer lantai,400 watt 1.00 bh Rp 420,000.00 Rp 420,000.00
10 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 20.00 titik Rp 420,000.00 Rp 8,400,000.00
11 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 9.00 titik Rp 550,000.00 Rp 4,950,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH FOOTPLAT 8 1.0 1.0 1.95 15.60
PAS BATU 13.0 0.8 1.8 18.72
ROOLAG 2 0.3 0.3 0.18
34.32
FOOTPLAT
PEMBESIAN
dia 13 - 150 7 8 2.35 1.04 136.86
dia 13 - 150 7 8 2.35 1.04 136.86
4D13 4 8 1.04 1.35 44.93
dia 8 -150 6 8 0.7 0.4 13.44
332.10
SLOOF SL1
SLOOF SL2
B1 elv 3.17
K1
K2
KP 10 0.15 0.15 4 0.90
0.90
PEMBESIAN
4d10 4 10 0.62 4 99.20
DIA. 8-200 21 10 0.5 0.4 42.00
141.20
PLAT
LISPLANK BETON
TOPI2
PEKERJAAN DINDING
146.32
PEKERJAAN LANTAI
PEKERJAAN PLAFOND
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding 292.64
plafond 56.00
RENCANA ANGGARAN BIAYA
BENGKEL ME
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 0.60 m3 Rp 14,990,788.55 Rp 8,994,473.13
2 Footplat P1
- Beton K250 4.03 m3 Rp 17,361,638.90 Rp 70,002,128.06
- Pembesian 471.62 kg Rp 40,265.29 Rp 18,990,075.42
- Bekesting 8.16 m2 Rp 407,897.78 Rp 3,328,445.91
4 Sloof SL 1
- Beton K250 3.60 m3 Rp 17,361,638.90 Rp 62,501,900.05
- Pembesian 380.19 kg Rp 40,265.29 Rp 15,308,410.91
- Bekesting 36.00 m2 Rp 436,608.68 Rp 15,717,912.57
5 Sloof SL 2
- Beton K250 0.90 m3 Rp 17,361,638.90 Rp 15,625,475.01
- Pembesian 118.74 kg Rp 40,265.29 Rp 4,781,100.10
- Bekesting 18.00 m2 Rp 436,608.68 Rp 7,858,956.29
6 Kolom K1
- Beton K250 1.92 m3 Rp 17,361,638.90 Rp 33,334,346.69
- Pembesian 490.08 kg Rp 40,265.29 Rp 19,733,211.55
- Bekesting 38.40 m2 Rp 959,962.43 Rp 36,862,557.44
7 Kolom K2
- Beton K250 0.36 m3 Rp 17,361,638.90 Rp 6,250,190.01
- Pembesian 73.76 kg Rp 40,265.29 Rp 2,969,967.52
- Bekesting 9.60 m2 Rp 959,962.43 Rp 9,215,639.36
7 Kolom KP
- Beton K250 1.08 m3 Rp 17,361,638.90 Rp 18,750,570.02
- Pembesian 169.44 kg Rp 40,265.29 Rp 6,822,550.12
- Bekesting 28.80 m2 Rp 959,962.43 Rp 27,646,918.08
8 Balok B1
- Beton K250 2.16 m3 Rp 17,361,638.90 Rp 37,501,140.03
- Pembesian 281.70 kg Rp 40,265.29 Rp 11,342,731.17
- Bekesting 39.60 m2 Rp 977,188.97 Rp 38,696,683.34
9 Pelat lantai beton t = 12 cm
- Rabat beton 9.10 m3 Rp 14,990,788.55 Rp 136,420,972.89
- Wiremesh M10 645.68 kg Rp 84,081.70 Rp 54,289,537.11
11 Tritisan / topi2 (atas jendela)
- Beton K175 0.28 m3 Rp 16,436,533.70 Rp 4,539,770.61
- Pembesian 18.25 kg Rp 40,265.29 Rp 734,680.42
- Bekesting 3.45 m2 Rp 1,278,972.43 Rp 4,415,652.33
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum t = 9 mm dan rangka hollow 7.50 m2 Rp 411,862.15 Rp 3,088,966.13
2 Pekerjaan pemasangan plafond kalsiboard dan rangka hollow 3.00 m2 Rp 307,998.30 Rp 923,994.90
2 Pekerjaan pemasangan plafond sprandel 64.01 m2 Rp 589,664.91 Rp 37,744,451.21
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 374.07 m2 Rp 72,574.75 Rp 27,147,948.67
2 Pekerjaan pengecatan plafond 10.50 m2 Rp 72,666.40 Rp 762,997.16
PEKERJAAN SANITASI
1 Pekerjaan pemasangan closet duduk / monoblok 1.00 unit Rp 4,040,721.71 Rp 4,040,721.71
2 Pekerjaan pemasangan shower spray 1.00 unit Rp 512,359.96 Rp 512,359.96
3 Pekerjaan pemasangan toilet paper holder 1.00 unit Rp 483,379.96 Rp 483,379.96
4 Pekerjaan pemasangan kran air 1.00 unit Rp 161,523.71 Rp 161,523.71
5 Pekerjaan pemasangan floor drain 1.00 unit Rp 116,014.19 Rp 116,014.19
6 Pekerjaan pemasangan tempat sabun 1.00 unit Rp 333,879.96 Rp 333,879.96
7 Pekerjaan pemasangan bak cuci 1.00 unit Rp 1,704,280.68 Rp 1,704,280.68
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP ke PP BG. Bengkel 25.00 m Rp 76,800.00 Rp 1,920,000.00
(NYY 3 x 6 mm2)
2 PP. Bangunan bengkel 1.00 unit Rp 17,000,000.00 Rp 17,000,000.00
3 Pekerjaan Grounding panel 1.00 ls Rp 2,500,000.00 Rp 2,500,000.00
Pekerjaan penerangan dan kontak-kontak
1 RM led 2x16 watt 9.00 bh Rp 2,581,200.00 Rp 23,230,800.00
2 Downlight 6", + lampu bolam led 10 watt 2.00 bh Rp 682,800.00 Rp 1,365,600.00
3 Downlight 5", + lampu bolam led 4 watt + tutup acliric 1.00 bh Rp 399,200.00 Rp 399,200.00
4 Lampu baret led 10 watt 5.00 bh Rp 1,013,200.00 Rp 5,066,000.00
5 saklar tunggal 3.00 bh Rp 56,000.00 Rp 168,000.00
6 saklar ganda 2.00 bh Rp 70,000.00 Rp 140,000.00
7 Stop kontok umum dinding 200 watt 5.00 bh Rp 80,000.00 Rp 400,000.00
8 Stop kontok umum dinding 400 watt 2.00 bh Rp 80,000.00 Rp 160,000.00
9 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 17.00 titik Rp 420,000.00 Rp 7,140,000.00
10 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 7.00 titik Rp 550,000.00 Rp 3,850,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH P1 12 1.0 1.0 1.25 15.00
P2 4 0.8 0.8 1.62 4.15
PAS BATU 11.5 0.8 1.62 14.90
ROOLAG 4 1.0 0.3 1.20
35.25
PONDASI BATU
AANSTAMPING PAS BATU 11.5 0.8 0.2 1.84
P2 4 0.8 0.8 0.2 0.51
2.35
ROOLAG
PONDASI BATU 4.0 0.11 0.44
FOOTPLAT
SLOOF SL1
SLOOF SL2
B1
K1
4 12 0.2 4 38.40
K2
4 4 0.2 4 9.60
KP
4 12 0.2 4 28.80
PLAT LANTAI
645.68
TOPI2
PEKERJAAN DINDING
187.03
PEKERJAAN LANTAI
PEKERJAAN PLAFOND
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding 374.07
plafond 10.50
RENCANA ANGGARAN BIAYA
GUDANG KARGO
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 1.00 m3 Rp 14,990,788.55 Rp 14,990,788.55
2 Footplat P1
- Beton K250 6.72 m3 Rp 17,361,638.90 Rp 116,670,213.43
- Pembesian 802.24 kg Rp 40,265.29 Rp 32,302,423.34
- Bekesting 13.60 m2 Rp 407,897.78 Rp 5,547,409.84
3 Sloof SL 1
- Beton K250 6.36 m3 Rp 17,361,638.90 Rp 110,420,023.43
- Pembesian 668.03 kg Rp 40,265.29 Rp 26,898,370.94
- Bekesting 63.60 m2 Rp 436,608.68 Rp 27,768,312.21
4 Sloof SL 2
- Beton K250 0.17 m3 Rp 17,361,638.90 Rp 3,020,925.17
- Pembesian 24.64 kg Rp 40,265.29 Rp 992,297.72
- Bekesting 3.48 m2 Rp 40,265.29 Rp 140,123.20
5 Kolom K1
- Beton K250 3.84 m3 Rp 17,361,638.90 Rp 66,668,693.39
- Pembesian 983.52 kg Rp 40,265.29 Rp 39,601,714.46
- Bekesting 76.80 m2 Rp 959,962.43 Rp 73,725,114.88
6 Kolom KP
- Beton K250 1.30 m3 Rp 17,361,638.90 Rp 22,500,684.02
- Pembesian 222.05 kg Rp 40,265.29 Rp 8,940,826.31
- Bekesting 34.56 m2 Rp 959,962.43 Rp 33,176,301.69
7 Ringbalk
- Beton K250 3.35 m3 Rp 17,361,638.90 Rp 58,230,936.88
- Pembesian 435.84 kg Rp 40,265.29 Rp 17,549,383.47
- Bekesting 61.49 m2 Rp 977,188.97 Rp 60,087,349.97
8 Plat atap tritisan
- Beton K175 11.02 m3 Rp 16,436,533.70 Rp 181,089,510.07
- Pembesian 186.72 kg Rp 40,265.29 Rp 7,518,334.27
- Bekesting 44.07 m2 Rp 977,188.97 Rp 43,064,718.05
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum t = 9 mm dan rangka hollow 135.80 m2 Rp 411,862.15 Rp 55,930,879.97
2 Pekerjaan pemasangan plafond kalsiboard dan rangka hollow 4.20 m2 Rp 307,998.30 Rp 1,293,592.87
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 568.03 m2 Rp 72,574.75 Rp 41,224,662.80
2 Pekerjaan pengecatan plafond 140.00 m2 Rp 72,666.40 Rp 10,173,295.53
PEKERJAAN SANITASI
1 Pekerjaan pemasangan closet duduk / monoblok 2.00 unit Rp 4,040,721.71 Rp 8,081,443.41
2 Pekerjaan pemasangan shower spray 2.00 unit Rp 512,359.96 Rp 1,024,719.92
3 Pekerjaan pemasangan toilet paper holder 2.00 unit Rp 483,379.96 Rp 966,759.92
4 Pekerjaan pemasangan kran air 2.00 unit Rp 161,523.71 Rp 323,047.42
5 Pekerjaan pemasangan floor drain 2.00 unit Rp 116,014.19 Rp 232,028.37
6 Pekerjaan pemasangan tempat sabun 2.00 unit Rp 333,879.96 Rp 667,759.92
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP ke PP GD. Administrasi 150.00 m Rp 474,000.00 Rp 71,100,000.00
(NYY 4 x 25 mm2)
2 PP. Bang.kargo 1.00 unit Rp 17,000,000.00 Rp 17,000,000.00
3 Pekerjaan Grounding panel 1.00 ls Rp 2,500,000.00 Rp 2,500,000.00
Pekerjaan penerangan dan kontak-kontak
1 RM led 2x10 watt 26.00 bh Rp 1,772,600.00 Rp 46,087,600.00
2 Downlight 4", + lampu bolam led 10 watt 4.00 bh Rp 682,800.00 Rp 2,731,200.00
3 Downlight 4", + lampu bolam led 5 watt + tutup acliric 2.00 bh Rp 399,200.00 Rp 798,400.00
4 Lampu dinding led 10 watt 8.00 bh Rp 1,413,200.00 Rp 11,305,600.00
5 saklar tunggal 4.00 bh Rp 56,000.00 Rp 224,000.00
6 saklar ganda 8.00 bh Rp 70,000.00 Rp 560,000.00
7 Stop kontok umum dinding, 200 Watt 12.00 bh Rp 80,000.00 Rp 960,000.00
8 Stop kontok komputer lantai, 400 Watt 2.00 bh Rp 420,000.00 Rp 840,000.00
9 Stop konta X-Ray 1000 Watt, lantai 1.00 bh Rp 900,000.00 Rp 900,000.00
10 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 40.00 titik Rp 420,000.00 Rp 16,800,000.00
11 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 15.00 titik Rp 550,000.00 Rp 8,250,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH FT 1 20 1.0 1.0 1.95 39.00
PAS BATU 71.6 0.8 1.6 91.65
130.65
FOOTPLAT
SLOOF SL1
SLOOF SL2
RB
K1
PEMBESIAN
8 d13 8 20 1.04 4.8 798.72
DIA. 8-150 33 20 0.7 0.4 184.80
983.52
KP
PEMBESIAN
4d10 4 12 0.62 4.8 142.85
DIA. 8-200 33 12 0.5 0.4 79.20
222.05
PLAT
TOPI 1 14.20 1.95 0.25 6.92
2 4.20 1.95 0.25 4.10
11.02
PEKERJAAN DINDING
PEKERJAAN LANTAI
PEKERJAAN PLAFOND
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding 568.03
plafond 140.00
RENCANA ANGGARAN BIAYA
PEKERJAAN TANAH
1 Pekerjaan galian tanah 148.59 m3 Rp 155,541.87 Rp 23,112,199.78
2 Pekerjaan urugan pasir bawah bak 4.31 m3 Rp 10,960,418.16 Rp 47,206,521.02
PEKERJAAN STRUKTUR
1 Rabat beton bawah bak 4.31 m3 Rp 14,990,788.55 Rp 64,565,326.30
2 Plat lantai
- Beton K250 21.54 m3 Rp 17,361,638.90 Rp 373,882,893.79
- Pembesian 3,230.25 kg Rp 40,265.29 Rp 130,066,941.31
- Bekesting 43.07 m2 Rp 1,278,972.43 Rp 55,085,342.70
3 Plat dinding
- Beton K250 33.44 m3 Rp 17,361,638.90 Rp 580,505,928.58
- Pembesian 5,015.42 kg Rp 40,265.29 Rp 201,947,272.26
- Bekesting 79.00 m2 Rp 1,278,972.43 Rp 101,038,822.23
4 Plat atap
- Beton K250 3.12 m3 Rp 17,361,638.90 Rp 54,142,270.92
- Pembesian 623.70 kg Rp 40,265.29 Rp 25,113,459.11
- Bekesting 4.42 m2 Rp 1,278,972.43 Rp 5,649,860.72
5 Kolom KP Lt.1
- Beton K250 1.24 m3 Rp 17,361,638.90 Rp 21,445,964.46
- Pembesian 251.06 kg Rp 40,265.29 Rp 10,109,163.86
- Bekesting 32.94 m2 Rp 959,962.43 Rp 31,621,162.55
6 Kolom KP Lt.2
- Beton K250 0.24 m3 Rp 17,361,638.90 Rp 4,101,687.19
- Pembesian 56.73 kg Rp 40,265.29 Rp 2,284,169.17
- Bekesting 6.30 m2 Rp 959,962.43 Rp 6,047,763.33
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH 14.6 2.95 3.45 148.59
148.59
KP LT.1
PEMBESIAN
TUMPUAN 4d10 4 18 0.62 1.925 85.93
LAPANGAN 4d10 4 18 0.62 1.925 85.93
TUMPUAN DIA. 8-150 11 18 0.5 0.4 39.60
LAPANGAN DIA. 8-150 11 18 0.5 0.4 39.60
251.06
KP LT.2
PEMBESIAN
TUMPUAN 4d10 4 7 0.62 1.15 19.96
LAPANGAN 4d10 4 7 0.62 1.15 19.96
TUMPUAN DIA. 8-150 6 7 0.5 0.4 8.40
LAPANGAN DIA. 8-150 6 7 0.5 0.4 8.40
56.73
RUMAH DINAS
PEKERJAAN TANAH
1 Pekerjaan galian tanah pondasi dan footplat 21.63 m3 Rp 155,541.87 Rp 3,363,592.94
2 Pekerjaan urugan tanah kembali 7.08 m3 Rp 94,267.80 Rp 667,730.25
3 Pekerjaan urugan pasir bawah footplat 1.70 m3 Rp 10,960,418.16 Rp 18,632,710.87
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 0.85 m3 Rp 14,990,788.55 Rp 12,742,170.27
2 Footplat P1
- Beton K250 5.41 m3 Rp 17,361,638.90 Rp 93,857,019.91
- Pembesian 122.81 kg Rp 40,265.29 Rp 4,944,899.29
- Bekesting 7.65 m2 Rp 407,897.78 Rp 3,120,418.04
5 Sloof SL 1
- Beton K250 2.29 m3 Rp 17,361,638.90 Rp 39,766,833.91
- Pembesian 322.89 kg Rp 40,265.29 Rp 13,001,371.06
- Bekesting 30.54 m2 Rp 436,608.68 Rp 13,334,029.17
7 Ringbalk RB1
- Beton K250 1.53 m3 Rp 17,361,638.90 Rp 26,511,222.61
- Pembesian 199.61 kg Rp 40,265.29 Rp 8,037,434.34
- Bekesting 27.99 m2 Rp 977,188.97 Rp 27,356,405.31
8 Kolom K1
- Beton K250 1.87 m3 Rp 17,361,638.90 Rp 32,540,051.72
- Pembesian 414.03 kg Rp 40,265.29 Rp 16,671,100.94
- Bekesting 49.98 m2 Rp 959,962.43 Rp 47,978,922.42
10 Atap pelat beton t =10 cm
- Beton K250 0.72 m3 Rp 17,361,638.90 Rp 12,573,298.89
- Pembesian 97.76 kg Rp 40,265.29 Rp 3,936,398.82
- Bekesting 7.24 m2 Rp 1,278,972.43 Rp 9,262,318.36
11 Lisplank beton
- Beton K175 0.26 m3 Rp 16,436,533.70 Rp 4,193,781.57
- Pembesian 13.32 kg Rp 40,265.29 Rp 536,333.61
- Bekesting 2.55 m2 Rp 1,278,972.43 Rp 3,263,298.16
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
12 Meja beton
- Beton K175 0.13 m3 Rp 16,436,533.70 Rp 2,140,036.69
- Pembesian 6.34 kg Rp 40,265.29 Rp 255,120.85
- Bekesting 1.30 m2 Rp 1,278,972.43 Rp 1,665,222.11
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum t = 9 mm dan rangka hollow 31.94 m2 Rp 411,862.15 Rp 13,154,877.07
2 Pekerjaan pemasangan plafond kalsiboard dan rangka hollow 11.74 m2 Rp 307,998.30 Rp 3,615,900.06
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 279.67 m2 Rp 72,574.75 Rp 20,297,240.87
2 Pekerjaan pengecatan plafond 43.68 m2 Rp 72,666.40 Rp 3,174,068.21
3 Pekerjaan pengecatan waterproofing 7.24 m2 Rp 150,000.00 Rp 1,086,300.00
PEKERJAAN SANITASI
1 Pekerjaan pemasangan closet duduk / monoblok 1.00 unit Rp 4,040,721.71 Rp 4,040,721.71
2 Pekerjaan pemasangan shower spray 1.00 unit Rp 512,359.96 Rp 512,359.96
3 Pekerjaan pemasangan toilet paper holder 1.00 unit Rp 483,379.96 Rp 483,379.96
4 Pekerjaan pemasangan kran air 1.00 unit Rp 161,523.71 Rp 161,523.71
5 Pekerjaan pemasangan floor drain 1.00 unit Rp 116,014.19 Rp 116,014.19
6 Pekerjaan pemasangan tempat sabun 1.00 unit Rp 333,879.96 Rp 333,879.96
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari SDP rumah dinas ke MCB box rumah dinas 60.00 m Rp 76,800.00 Rp 4,608,000.00
(NYY 3 x 6 mm2)
2 MCB BOX 1.00 unit Rp 2,400,000.00 Rp 2,400,000.00
Pekerjaan penerangan dan kontak-kontak
1 Downlight 4", + lampu bolam led 10 watt 10.00 bh Rp 682,800.00 Rp 6,828,000.00
2 Downlight 4", + lampu bolam led 5 watt + tutup acliric 1.00 bh Rp 399,200.00 Rp 399,200.00
3 Lampu GL pilar globe 18 watt + tiang galvanis 2" tinggi 1,5 meter 1.00 bh Rp 3,254,200.00 Rp 3,254,200.00
4 Lampu dinding led 10 watt 2.00 bh Rp 1,413,200.00 Rp 2,826,400.00
5 Lampu SL led 10 watt + fitting outbow E27 2.00 bh Rp 457,000.00 Rp 914,000.00
6 saklar ganda 6.00 bh Rp 70,000.00 Rp 420,000.00
7 Stop kontok umum 200 watt, dinding 10.00 bh Rp 80,000.00 Rp 800,000.00
8 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 16.00 titik Rp 420,000.00 Rp 6,720,000.00
9 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 10.00 titik Rp 550,000.00 Rp 5,500,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH FOOTPLAT P1 17 1.0 1.0 1.25 21.25
ROOLAG 12.5 0.1 0.3 0.38
21.63
FOOTPLAT
SLOOF SL1
RB 1
RB 50.9 0.15 0.2 1.53
LISPLANK BETON
MEJA BETON
PEKERJAAN DINDING
139.84
PEKERJAAN LANTAI
PEKERJAAN PLAFOND
GYPSUM
K.TIDUR 2 3.00 2.50 15.00
R. KELURGA 4.20 3.00 12.60
PANTRY 2.00 2.17 4.34
31.94
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding 279.67
plafond 43.68
POS JAGA
PEKERJAAN TANAH
1 Pekerjaan galian tanah pondasi dan footplat 1.85 m3 Rp 155,541.87 Rp 287,791.34
2 Pekerjaan urugan tanah kembali 0.62 m3 Rp 94,267.80 Rp 58,139.67
3 Pekerjaan urugan pasir bawah footplat 0.45 m3 Rp 10,960,418.16 Rp 4,891,086.60
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 0.11 m3 Rp 14,990,788.55 Rp 1,619,005.16
2 Footplat P1
- Beton K250 0.64 m3 Rp 17,361,638.90 Rp 11,133,150.95
- Pembesian 159.39 kg Rp 40,265.29 Rp 6,417,884.00
- Bekesting 2.70 m2 Rp 407,897.78 Rp 1,101,324.01
3 Sloof SL 1
- Beton K250 0.45 m3 Rp 17,361,638.90 Rp 7,812,737.51
- Pembesian 77.86 kg Rp 40,265.29 Rp 3,134,942.45
- Bekesting 6.00 m2 Rp 436,608.68 Rp 2,619,652.10
4 Ringbalk RB1
- Beton K250 0.45 m3 Rp 17,361,638.90 Rp 7,812,737.51
- Pembesian 77.86 kg Rp 40,265.29 Rp 3,134,942.45
- Bekesting 8.25 m2 Rp 977,188.97 Rp 8,061,809.03
5 Kolom K1
- Beton K250 0.47 m3 Rp 17,361,638.90 Rp 8,086,183.32
- Pembesian 104.03 kg Rp 40,265.29 Rp 4,188,717.21
- Bekesting 12.42 m2 Rp 959,962.43 Rp 11,922,733.42
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum t = 9 mm dan rangka hollow 6.00 m2 Rp 411,862.15 Rp 2,471,172.90
2 Pekerjaan pemasangan plafond kalsiboard dan rangka hollow 13.36 m2 Rp 307,998.30 Rp 4,113,625.31
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 86.84 m2 Rp 72,574.75 Rp 6,302,115.28
2 Pekerjaan pengecatan plafond 19.36 m2 Rp 72,666.40 Rp 1,406,530.77
PEKERJAAN SANITASI
1 Pekerjaan pemasangan closet jongkok 1.00 unit Rp 2,111,392.50 Rp 2,111,392.50
2 Pekerjaan pemasangan bak mandi 1.00 unit Rp 3,786,736.10 Rp 3,786,736.10
3 Pekerjaan pemasangan kran air 2.00 unit Rp 161,523.71 Rp 323,047.42
4 Pekerjaan pemasangan floor drain 1.00 unit Rp 116,014.19 Rp 116,014.19
5 Pekerjaan pemasangan tempat sabun 1.00 unit Rp 333,879.96 Rp 333,879.96
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP rumah dinas ke MCB BOX POS JAGA 01 84.00 m Rp 76,800.00 Rp 6,451,200.00
(NYY 3 x 6 mm2)
2 kabel dari POS TIKETING ke MCB BOX POS TIKETING 02 182.00 m Rp 76,800.00 Rp 13,977,600.00
(NYY 3 x 6 mm2)
3 MCB BOX POS JAGA 01 1.00 unit Rp 2,400,000.00 Rp 2,400,000.00
4 MCB BOX POS JAGA 02 1.00 unit Rp 2,400,000.00 Rp 2,400,000.00
Pekerjaan penerangan dan kontak-kontak
1 Downlight 4", + lampu bolam led 10 watt 4.00 bh Rp 682,800.00 Rp 2,731,200.00
2 Downlight 4", + lampu bolam led 5 watt + tutup acliric 2.00 bh Rp 399,200.00 Rp 798,400.00
3 saklar ganda 2.00 bh Rp 70,000.00 Rp 140,000.00
4 Stop kontok umum 6.00 bh Rp 80,000.00 Rp 480,000.00
5 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 6.00 titik Rp 420,000.00 Rp 2,520,000.00
6 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 6.00 titik Rp 550,000.00 Rp 3,300,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH FOOTPLAT P1 6 0.6 0.6 0.75 1.62
FOOTPLAT
PEMBESIAN
dia 12 - 150 5 6 2.35 0.89 62.75
dia 12 - 150 5 6 2.35 0.89 62.75
4D12 4 6 0.89 1.25 26.70
dia 8 -150 6 6 0.5 0.4 7.20
159.39
SLOOF SL1
RB 1
K1
PEMBESIAN
4d12 4 3 0.89 3.3 35.24
4d12 4 3 0.89 3.8 40.58
DIA. 8-150 22 3 0.5 0.4 13.20
DIA. 8-150 25 3 0.5 0.4 15.00
104.03
PEKERJAAN DINDING
PEKERJAAN LANTAI
PEKERJAAN PLAFOND
GYPSUM
POS JAGA 3.00 2.00 6.00
6.00
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding 86.84
plafond 19.36
RENCANA ANGGARAN BIAYA
POS TICKETING
PEKERJAAN TANAH
1 Pekerjaan galian tanah pondasi dan footplat 1.28 m3 Rp 155,541.87 Rp 199,342.46
2 Pekerjaan urugan tanah kembali 0.36 m3 Rp 94,267.80 Rp 33,936.41
3 Pekerjaan urugan pasir bawah footplat 0.32 m3 Rp 10,960,418.16 Rp 3,551,175.48
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 0.07 m3 Rp 14,990,788.55 Rp 1,079,336.78
2 Footplat P1
- Beton K250 0.43 m3 Rp 17,361,638.90 Rp 7,422,100.63
- Pembesian 72.44 kg Rp 40,265.29 Rp 2,916,817.35
- Bekesting 1.80 m2 Rp 407,897.78 Rp 734,216.01
3 Sloof SL 1
- Beton K250 0.25 m3 Rp 17,361,638.90 Rp 4,375,133.00
- Pembesian 45.24 kg Rp 40,265.29 Rp 1,821,649.87
- Bekesting 3.36 m2 Rp 436,608.68 Rp 1,467,005.17
4 Ringbalk RB1
- Beton K250 0.25 m3 Rp 17,361,638.90 Rp 4,375,133.00
- Pembesian 45.24 kg Rp 40,265.29 Rp 1,821,649.87
- Bekesting 4.62 m2 Rp 977,188.97 Rp 4,514,613.06
5 Kolom K1
- Beton K250 0.49 m3 Rp 17,361,638.90 Rp 8,508,071.14
- Pembesian 109.07 kg Rp 40,265.29 Rp 4,391,847.53
- Bekesting 13.07 m2 Rp 959,962.43 Rp 12,544,789.08
6 Topi-topi (tritisan)
- Beton K250 0.37 m3 Rp 17,361,638.90 Rp 6,441,168.03
- Pembesian 19.44 kg Rp 40,265.29 Rp 782,757.17
- Bekesting 3.71 m2 Rp 1,278,972.43 Rp 4,744,987.73
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum t = 9 mm dan rangka hollow 3.60 m2 Rp 411,862.15 Rp 1,482,703.74
2 Pekerjaan pemasangan plafond kalsiboard dan rangka hollow 7.40 m2 Rp 307,998.30 Rp 2,279,187.43
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 47.58 m2 Rp 72,574.75 Rp 3,453,251.63
2 Pekerjaan pengecatan plafond 11.00 m2 Rp 72,666.40 Rp 799,330.36
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP rumah dinas ke MCB BOX POS TIKETING 01 130.00 m Rp 124,800.00 Rp 16,224,000.00
(NYY 3 x 10 mm2)
2 kabel dari POS TIKETING ke MCB BOX POS TIKETING 02 40.00 m Rp 55,200.00 Rp 2,208,000.00
(NYY 3 x 4 mm2)
3 MCB BOX POS TIKETING 01 1.00 unit Rp 3,200,000.00 Rp 3,200,000.00
4 MCB BOX POS TIKETING 02 1.00 unit Rp 2,400,000.00 Rp 2,400,000.00
Pekerjaan penerangan dan kontak-kontak
1 Downlight 4", + lampu bolam led 10 watt 4.00 bh Rp 682,800.00 Rp 2,731,200.00
2 saklar ganda 2.00 bh Rp 70,000.00 Rp 140,000.00
3 Stop kontok umum 8.00 bh Rp 80,000.00 Rp 640,000.00
4 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 4.00 titik Rp 420,000.00 Rp 1,680,000.00
5 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 8.00 titik Rp 550,000.00 Rp 4,400,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH FOOTPLAT P1 4 0.6 0.6 0.75 1.08
FOOTPLAT
PEMBESIAN
dia 12 - 150 5 4 1.40 0.89 24.92
dia 12 - 150 5 4 1.40 0.89 24.92
4D12 4 4 0.89 1.25 17.80
dia 8 -150 6 4 0.5 0.4 4.80
72.44
SLOOF SL1
RB 1
K1
PEMBESIAN
4d12 4 3 0.89 3.48 37.17
4d12 4 3 0.89 3.98 42.51
DIA. 8-150 23 3 0.5 0.4 13.80
DIA. 8-150 26 3 0.5 0.4 15.60
109.07
TOPI2
PEKERJAAN DINDING
PEKERJAAN LANTAI
PEKERJAAN PLAFOND
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding #REF!
plafond 11.00
RENCANA ANGGARAN BIAYA
PEKERJAAN TANAH
1 Pekerjaan galian tanah pondasi dan footplat 10.77 m3 Rp 155,541.87 Rp 1,675,372.59
2 Pekerjaan urugan tanah kembali 3.59 m3 Rp 94,267.80 Rp 338,459.11
PEKERJAAN STRUKTUR
1 Pekerjaan pemasangan cerucuk bawah pondasi 108.00 m Rp 57,780.28 Rp 6,240,270.27
volume tidak mengingat disesuaikan hingga tanah keras
2 Rabat beton bawah footplat 0.58 m3 Rp 14,990,788.55 Rp 8,634,694.21
3 Footplat P1
- Beton K250 1.10 m3 Rp 17,361,638.90 Rp 19,063,079.52
- Pembesian 234.86 kg Rp 40,265.29 Rp 9,456,866.22
- Bekesting 6.96 m2 Rp 407,897.78 Rp 2,838,968.57
4 Ringbalk RB1 pada elv. +4.00, +8.00 dan +10.00
- Beton K250 1.68 m3 Rp 17,361,638.90 Rp 29,167,553.36
- Pembesian 280.71 kg Rp 40,265.29 Rp 11,302,747.74
- Bekesting 21.60 m2 Rp 977,188.97 Rp 21,107,281.82
5 Kolom K1
- Beton K250 4.32 m3 Rp 17,361,638.90 Rp 75,002,280.06
- Pembesian 316.62 kg Rp 40,265.29 Rp 12,748,956.03
- Bekesting 57.60 m2 Rp 959,962.43 Rp 55,293,836.16
6 Plat lantai tandon
- Beton K250 0.80 m3 Rp 17,361,638.90 Rp 13,889,311.12
- Pembesian 152.05 kg Rp 40,265.29 Rp 6,122,256.26
- Bekesting 4.00 m2 Rp 1,278,972.43 Rp 5,115,889.73
7 Plat penutup tandon
- Beton K250 0.48 m3 Rp 17,361,638.90 Rp 8,333,586.67
- Pembesian 62.61 kg Rp 40,265.29 Rp 2,520,929.05
- Bekesting 4.00 m2 Rp 1,278,972.43 Rp 5,115,889.73
8 Dinding beton tandon
- Beton K250 2.03 m3 Rp 17,361,638.90 Rp 35,209,403.70
- Pembesian 511.06 kg Rp 40,265.29 Rp 20,577,816.19
- Bekesting 17.80 m2 Rp 1,278,972.43 Rp 22,765,709.31
PEKERJAAN LAIN-LAIN
1 Pekerjaan tangga besi (pipa besi dia 2") 12.00 m Rp 500,000.00 Rp 6,000,000.00
2 Pekerjaan bukaan manhole 1.00 unit Rp 1,500,000.00 Rp 1,500,000.00
3 Pekerjaan pemasangan pipa besi dia.2" (supplay dari sumur bor dan pompa) 30.00 m Rp 352,763.50 Rp 10,582,905.07
4 Pekerjaan pengecatan waterproof pada tandon 48.00 m2 Rp 150,000.00 Rp 7,200,000.00
5 Pekerjaan pengecatan kolom dan balok 84.00 m2 Rp 72,574.75 Rp 6,096,278.78
PEKERJAAN TANAH
1 Pekerjaan galian tanah pondasi dan footplat 6.93 m3 Rp 155,541.87 Rp 1,077,905.16
2 Pekerjaan urugan tanah kembali 2.31 m3 Rp 94,267.80 Rp 217,758.62
3 Pekerjaan urugan pasir 0.40 m3 Rp 10,960,418.16 Rp 4,384,167.26
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 0.20 m3 Rp 14,990,788.55 Rp 2,998,157.71
2 Footplat P2
- Beton K250 1.45 m3 Rp 17,361,638.90 Rp 25,243,822.97
- Pembesian 161.44 kg Rp 40,265.29 Rp 6,500,427.83
- Bekesting 1.44 m2 Rp 407,897.78 Rp 587,372.81
4 Sloof S1
- Beton K250 0.38 m3 Rp 17,361,638.90 Rp 6,510,614.59
- Pembesian 57.74 kg Rp 40,265.29 Rp 2,324,804.89
- Bekesting 5.00 m2 Rp 436,608.68 Rp 2,183,043.41
4 Ringbalk RB1
- Beton K250 0.64 m3 Rp 17,361,638.90 Rp 11,068,044.80
- Pembesian 95.54 kg Rp 40,265.29 Rp 3,846,832.72
- Bekesting 11.05 m2 Rp 977,188.97 Rp 10,797,938.15
5 Kolom K1
- Beton K250 0.34 m3 Rp 17,361,638.90 Rp 5,859,553.13
- Pembesian 74.98 kg Rp 40,265.29 Rp 3,019,091.17
- Bekesting 9.00 m2 Rp 959,962.43 Rp 8,639,661.90
6 Plat atap
- Beton K250 1.78 m3 Rp 17,361,638.90 Rp 30,925,419.30
- Pembesian 343.11 kg Rp 40,265.29 Rp 13,815,341.88
- Bekesting 17.81 m2 Rp 1,278,972.43 Rp 22,781,696.47
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 52.44 m2 Rp 72,574.75 Rp 3,805,819.75
2 Pekerjaan pengecatan waterproof 35.63 m2 Rp 150,000.00 Rp 5,343,750.00
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP rumah dinas ke SDP RUANG POMPA 20.00 m Rp 1,676,400.00 Rp 33,528,000.00
(NYY 4 x 16 mm2)
2 kabel dari SDP RUANG POMPA ke MCB BOX R. POMPA 6.00 m Rp 55,200.00 Rp 331,200.00
(NYY 3 x 4 mm2)
3 SDP RUANG POMPA 1.00 unit Rp 2,400,000.00 Rp 2,400,000.00
4 MCB BOX RUANG POMPA 1.00 unit Rp 8,400,000.00 Rp 8,400,000.00
Pekerjaan penerangan dan kontak-kontak
1 Lampu TL Led 1x16 watt 3.00 bh Rp 823,400.00 Rp 2,470,200.00
wall exhaust fan 200 cfm 3.00 bh Rp 1,457,000.00 Rp 4,371,000.00
saklar tuggal 1.00 bh Rp 56,000.00 Rp 56,000.00
2 saklar ganda 1.00 bh Rp 70,000.00 Rp 70,000.00
3 Stop kontok umum 2.00 bh Rp 80,000.00 Rp 160,000.00
4 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 6.00 titik Rp 420,000.00 Rp 2,520,000.00
5 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 2.00 titik Rp 550,000.00 Rp 1,100,000.00
PEKERJAAN GWT
PEKERJAAN TANAH
1 Pekerjaan galian tanah 157.30 m3 Rp 155,541.87 Rp 24,466,736.15
2 Pekerjaan urugan pasir bawah plat 3.03 m3 Rp 10,960,418.16 Rp 33,155,264.93
PEKERJAAN STRUKTUR
1 Rabat beton bawah plat 3.03 m3 Rp 14,990,788.55 Rp 45,347,135.38
2 Plat lantai
- Beton K250 7.56 m3 Rp 17,361,638.90 Rp 131,297,394.21
- Pembesian 1,592.64 kg Rp 40,265.29 Rp 64,128,105.69
3 Dinding beton
- Beton K250 25.00 m3 Rp 17,361,638.90 Rp 434,040,972.59
- Pembesian 5,286.05 kg Rp 40,265.29 Rp 212,844,236.51
- Bekesting 100.00 m2 Rp 1,278,972.43 Rp 127,897,243.33
4 Plat penutup
- Beton K250 7.56 m3 Rp 17,361,638.90 Rp 131,297,394.21
- Pembesian 1,309.50 kg Rp 40,265.29 Rp 52,727,553.57
- Bekesting 30.25 m2 Rp 1,278,972.43 Rp 38,688,916.11
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
TOWER AIR
PEKERJAAN TANAH
GALIAN TANAH FOOTPLAT P1 4 1.2 1.2 1.87 10.77
10.77
FOOTPLAT
CERUCUK 9 4 3 108.00
PEMBESIAN
dia 13 - 150 5 4 2.62 1.04 54.50
dia 13 - 150 5 4 2.62 1.04 54.50
8D16 8 4 1.58 1.95 98.59
dia 10-150 10 4 1.1 0.62 27.28
234.86
K1
PEMBESIAN
4d12 4 4 0.89 12.1 172.30
TUMPUAN DIA. 8-150 41 4 1.1 0.4 72.16
LAPANGAN DIA. 8-150 41 4 1.1 0.4 72.16
316.62
DINDING
PENGECATAN waterproof
RUMAH POMPA
PEKERJAAN TANAH
GALIAN TANAH FOOTPLAT P1 4 1.0 1.0 1.35 5.40
ROOLLAG 17.0 0.3 0.3 1.53
6.93
FOOTPLAT
PEMBESIAN
dia 13 - 150 7 4 2.40 1.04 69.89
dia 13 - 150 7 4 2.40 1.04 69.89
4 D12 4 4 0.89 1.1 15.66
dia 8 150 5 4 0.5 0.6 6.00
161.44
SLOOF
RB
K1
PEMBESIAN
4d12 4 5 0.89 3.1 55.18
TUMPUAN DIA. 8-150 11 5 0.5 0.4 11.00
LAPANGAN DIA. 8-150 11 4 0.5 0.4 8.80
74.98
PLAT ATAP
PEKERJAAN DINDING
PEKERJAAN LANTAI
dinding 52.44
water proof 2 4.75 3.75 35.63
GWT
PEKERJAAN TANAH
GALIAN TANAH 5.5 5.5 5.2 157.30
157.30
PLAT LANTAI
DINDING
PLAT PENUTUP
PEKERJAAN TANAH
1 Pekerjaan galian tanah 15.46 m3 Rp 155,541.87 Rp 2,404,055.14
2 Pekerjaan urugan pasir bawah bak 0.64 m3 Rp 10,960,418.16 Rp 7,058,509.30
PEKERJAAN STRUKTUR
1 Rabat beton bawah bak 0.64 m3 Rp 16,436,533.70 Rp 10,585,127.70
2 Plat lantai
- Beton K250 1.29 m3 Rp 17,892,031.77 Rp 23,044,936.91
- Pembesian 290.72 kg Rp 407,897.78 Rp 118,584,043.36
3 Plat dinding
- Beton K250 3.76 m3 Rp 17,892,031.77 Rp 67,274,039.44
- Pembesian 858.26 kg Rp 407,897.78 Rp 350,080,719.30
- Bekesting 18.80 m2 Rp 1,278,972.43 Rp 24,044,681.75
4 Plat penutup
- Beton K250 1.18 m3 Rp 17,892,031.77 Rp 21,032,083.34
- Pembesian 322.95 kg Rp 407,897.78 Rp 131,731,404.69
- Bekesting 5.88 m2 Rp 1,278,972.43 Rp 7,517,160.48
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
GWT
GALIAN TANAH 2.8 2.3 2.4 15.46
15.46
URUGAN PASIR 2.8 2.3 0.1 0.64
0.64
DINDING
plester
dinding dalam 2 2.8 2 11.20
2 1.9 2 7.60
plat bwh 1 2.8 2.3 6.44
plat atas 2 2.8 2.3 12.88
dikurangi manhole 2 0.75 0.75 (1.13)
37.00
RENCANA ANGGARAN BIAYA
BANGUNAN GENSET
PEKERJAAN STRUKTUR
1 Rabat beton bawah footplat 0.50 m3 Rp 14,990,788.55 Rp 7,495,394.28
2 Footplat P1
- Beton K250 3.36 m3 Rp 17,361,638.90 Rp 58,335,106.72
- Pembesian 415.12 kg Rp 40,265.29 Rp 16,714,925.68
- Bekesting 6.80 m2 Rp 407,897.78 Rp 2,773,704.92
4 Sloof SL 1
- Beton K250 2.88 m3 Rp 17,361,638.90 Rp 50,001,520.04
- Pembesian 450.04 kg Rp 40,265.29 Rp 18,121,118.33
- Bekesting 28.80 m2 Rp 436,608.68 Rp 12,574,330.06
5 Sloof SL 2
- Beton K250 1.63 m3 Rp 17,361,638.90 Rp 28,282,109.77
- Pembesian 328.65 kg Rp 40,265.29 Rp 13,233,234.69
- Bekesting 21.72 m2 Rp 436,608.68 Rp 9,483,140.59
6 Kolom K1
- Beton K250 1.72 m3 Rp 17,361,638.90 Rp 29,862,018.91
- Pembesian 209.24 kg Rp 40,265.29 Rp 8,425,108.52
- Bekesting 34.40 m2 Rp 959,962.43 Rp 33,022,707.71
7 Kolom K2
- Beton K250 1.26 m3 Rp 17,361,638.90 Rp 21,836,601.33
- Pembesian 295.96 kg Rp 40,265.29 Rp 11,917,043.00
- Bekesting 33.54 m2 Rp 959,962.43 Rp 32,197,140.01
8 Ringbalk RB1
- Beton K250 1.75 m3 Rp 17,361,638.90 Rp 30,313,421.53
- Pembesian 228.04 kg Rp 40,265.29 Rp 9,181,934.84
- Bekesting 32.01 m2 Rp 977,188.97 Rp 31,279,819.04
9 Ringbalk RB2
- Beton K250 2.40 m3 Rp 17,361,638.90 Rp 41,667,933.37
- Pembesian 273.06 kg Rp 40,265.29 Rp 10,994,645.82
- Bekesting 30.00 m2 Rp 977,188.97 Rp 29,315,669.20
10 Plat atap elv + 2.95
- Beton K175 1.27 m3 Rp 17,361,638.90 Rp 22,000,668.82
- Pembesian 146.44 kg Rp 40,265.29 Rp 5,896,609.60
- Bekesting 10.56 m2 Rp 1,278,972.43 Rp 13,505,948.90
11 Plat atap elv + 4.00
- Beton K175 7.16 m3 Rp 17,361,638.90 Rp 124,341,279.97
- Pembesian 761.66 kg Rp 40,265.29 Rp 30,668,361.38
- Bekesting 59.68 m2 Rp 1,278,972.43 Rp 76,331,632.76
12 Dudukan genset
- Beton K250 0.66 m3 Rp 17,361,638.90 Rp 11,458,681.68
- Pembesian 46.87 kg Rp 40,265.29 Rp 1,887,314.50
- Bekesting 3.30 m2 Rp 1,278,972.43 Rp 4,220,609.03
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum t = 9 mm dan rangka hollow 28.20 m2 Rp 411,862.15 Rp 11,614,512.63
2 Pekerjaan perapihan pada plafond beton ekspose 59.40 m2 Rp 526,738.70 Rp 31,288,278.64
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 315.63 m2 Rp 72,574.75 Rp 22,907,028.79
2 Pekerjaan pengecatan plafond 87.60 m2 Rp 72,666.40 Rp 6,365,576.35
3 Pekerjaan pengecatan waterproofing 70.24 m2 Rp 125,000.00 Rp 8,780,250.00
PEKERJAAN SANITASI
1 Pekerjaan pemasangan closet duduk / monoblok 1.00 unit Rp 4,040,721.71 Rp 4,040,721.71
2 Pekerjaan pemasangan shower spray 1.00 unit Rp 512,359.96 Rp 512,359.96
3 Pekerjaan pemasangan toilet paper holder 1.00 unit Rp 483,379.96 Rp 483,379.96
4 Pekerjaan pemasangan kran air 1.00 unit Rp 161,523.71 Rp 161,523.71
5 Pekerjaan pemasangan floor drain 1.00 unit Rp 116,014.19 Rp 116,014.19
6 Pekerjaan pemasangan tempat sabun 1.00 unit Rp 333,879.96 Rp 333,879.96
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP ke MCB BOX Ruang genset 25.00 m Rp 55,200.00 Rp 1,380,000.00
(NYY 3 x 4 mm2)
2 MCB BOX ruang genset 1.00 unit Rp 240,000.00 Rp 240,000.00
Pekerjaan penerangan dan kontak-kontak
1 TL led 1x16 watt 7.00 bh Rp 823,400.00 Rp 5,763,800.00
2 Downlight 4", + lampu bolam led 10 watt 2.00 bh Rp 682,800.00 Rp 1,365,600.00
3 Downlight 4", + lampu bolam led 5 watt + tutup acliric 2.00 bh Rp 399,200.00 Rp 798,400.00
4 saklar tuggal 3.00 bh Rp 56,000.00 Rp 168,000.00
5 saklar ganda 2.00 bh Rp 70,000.00 Rp 140,000.00
6 Stop kontok umum dinding 200 W 4.00 bh Rp 80,000.00 Rp 320,000.00
7 Instalasi kabel penerangan NYM 3x2,5 m2 dalam counduit 11.00 titik Rp 420,000.00 Rp 4,620,000.00
8 Instalasi kabel stop kontak NYM 3x2,5 m2 dalam counduit 4.00 titik Rp 550,000.00 Rp 2,200,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH FOOTPLAT P1 13 1.0 1.0 1.35 17.55
PAS BATU 61.6 0.8 1.7 83.78
101.33
PONDASI BATU
AANSTAMPING 61.6 0.8 0.2 9.86
PONDASI BATU 61.6 0.5 0.7 21.56
SLOOF SL1
SLOOF 48.0 0.20 0.3 2.88
SLOOF SL2
SLOOF 36.2 0.15 0.3 1.63
K1
KOLOM K1 10 0.20 0.20 4.3 1.72
1.72
K2
KOLOM K1 13 0.15 0.15 4.3 1.26
1.26
DUDUKAN GENSET
157.82
PEKERJAAN PLAFOND
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding 315.63
plafond 87.60
PEKERJAAN TANAH
1 Pekerjaan galian tanah footplat 21.13 m3 Rp 155,541.87 Rp 3,285,878.00
2 Pekerjaan urugan tanah kembali dan dipadatkan 2.21 m3 Rp 188,535.60 Rp 417,292.13
3 Pekerjaan urugan pasir bawah pondasi 1.10 m3 Rp 10,960,418.16 Rp 12,056,459.98
PEKERJAAN STRUKTUR
1 Pondasi Pilecap dan tiang pancang P1
- Rabat beton bawah pondasi 0.66 m3 Rp 14,990,788.55 Rp 9,953,883.60
- Beton Pilecap 5.98 m3 Rp 17,361,638.90 Rp 103,753,154.09
- Pembesian 1,229.18 kg Rp 40,265.29 Rp 49,493,123.65
- Tiang pancang 3.82 m3 Rp 4,750,000.00 Rp 18,121,725.00
volume tidak mengikat, asumsi kedalaman 3 m
2 Footplat P2
- Rabat beton bawah pondasi 0.55 m3 Rp 14,990,788.55 Rp 8,244,933.70
- Beton K250 3.52 m3 Rp 17,361,638.90 Rp 61,031,803.28
- Pembesian 446.55 kg Rp 40,265.29 Rp 17,980,350.89
- Bekesting 5.41 m2 Rp 407,897.78 Rp 2,207,542.80
3 Sloof SL 1
- Beton K250 2.76 m3 Rp 17,361,638.90 Rp 47,918,123.37
- Pembesian 452.64 kg Rp 40,265.29 Rp 18,225,663.12
- Bekesting 18.40 m2 Rp 436,608.68 Rp 8,033,599.76
4 Sloof SL 2
- Beton K250 1.73 m3 Rp 17,361,638.90 Rp 30,079,039.40
- Pembesian 169.66 kg Rp 40,265.29 Rp 6,831,408.49
- Bekesting 23.10 m2 Rp 436,608.68 Rp 10,085,660.57
5 Ringbalk RB1
- Beton K250 1.01 m3 Rp 17,361,638.90 Rp 17,448,447.10
- Pembesian 131.98 kg Rp 40,265.29 Rp 5,314,212.50
- Bekesting 18.43 m2 Rp 977,188.97 Rp 18,004,706.83
6 Balok B1 lantai 2
- Beton K250 2.21 m3 Rp 17,361,638.90 Rp 38,334,498.70
- Pembesian 248.43 kg Rp 40,265.29 Rp 10,003,298.37
- Bekesting 20.24 m2 Rp 977,188.97 Rp 19,778,304.82
7 Balok B2 lantai 2
- Beton K250 0.43 m3 Rp 17,361,638.90 Rp 7,500,228.01
- Pembesian 58.12 kg Rp 40,265.29 Rp 2,340,057.38
- Bekesting 5.76 m2 Rp 977,188.97 Rp 5,628,608.49
8 Balok B1 lantai 3
- Beton K250 2.21 m3 Rp 17,361,638.90 Rp 38,334,498.70
- Pembesian 248.43 kg Rp 40,265.29 Rp 10,003,298.37
- Bekesting 20.24 m2 Rp 977,188.97 Rp 19,778,304.82
9 Balok B2 lantai 3
- Beton K250 0.43 m3 Rp 17,361,638.90 Rp 7,500,228.01
- Pembesian 58.12 kg Rp 40,265.29 Rp 2,340,057.38
- Bekesting 5.76 m2 Rp 977,188.97 Rp 5,628,608.49
10 Balok B1 lantai 4
- Beton K250 2.21 m3 Rp 17,361,638.90 Rp 38,334,498.70
- Pembesian 248.43 kg Rp 40,265.29 Rp 10,003,298.37
- Bekesting 20.24 m2 Rp 977,188.97 Rp 19,778,304.82
11 Balok B2 lantai 4
- Beton K250 0.43 m3 Rp 17,361,638.90 Rp 7,500,228.01
- Pembesian 58.12 kg Rp 40,265.29 Rp 2,340,057.38
- Bekesting 5.76 m2 Rp 977,188.97 Rp 5,628,608.49
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
12 Balok B1 lantai 5
- Beton K250 2.21 m3 Rp 17,361,638.90 Rp 38,334,498.70
- Pembesian 248.43 kg Rp 40,265.29 Rp 10,003,298.37
- Bekesting 20.24 m2 Rp 977,188.97 Rp 19,778,304.82
13 Balok B2 lantai 5
- Beton K250 2.15 m3 Rp 17,361,638.90 Rp 37,334,468.30
- Pembesian 266.80 kg Rp 40,265.29 Rp 10,742,939.47
- Bekesting 28.67 m2 Rp 977,188.97 Rp 28,017,962.24
14 Balok B1 atap
- Beton K250 2.21 m3 Rp 17,361,638.90 Rp 38,334,498.70
- Pembesian 248.43 kg Rp 40,265.29 Rp 10,003,298.37
- Bekesting 20.24 m2 Rp 977,188.97 Rp 19,778,304.82
15 Kolom K1 lantai 1
- Beton K250 3.88 m3 Rp 17,361,638.90 Rp 67,363,158.95
- Pembesian 230.48 kg Rp 40,265.29 Rp 9,280,166.04
- Bekesting 31.04 m2 Rp 959,962.43 Rp 29,797,233.93
16 Kolom K2 lantai 1
- Beton K250 1.10 m3 Rp 17,361,638.90 Rp 19,016,203.09
- Pembesian 59.05 kg Rp 40,265.29 Rp 2,377,600.74
- Bekesting 29.21 m2 Rp 959,962.43 Rp 28,038,582.75
17 Kolom K1 lantai 2
- Beton K250 3.00 m3 Rp 17,361,638.90 Rp 52,084,916.71
- Pembesian 223.41 kg Rp 40,265.29 Rp 8,995,570.99
- Bekesting 24.00 m2 Rp 959,962.43 Rp 23,039,098.40
18 Kolom KP lantai 2
- Beton K250 0.20 m3 Rp 17,361,638.90 Rp 3,515,731.88
- Pembesian 11.99 kg Rp 40,265.29 Rp 482,732.47
- Bekesting 5.40 m2 Rp 959,962.43 Rp 5,183,797.14
20 Kolom K1 lantai 3
- Beton K250 3.00 m3 Rp 17,361,638.90 Rp 52,084,916.71
- Pembesian 223.41 kg Rp 40,265.29 Rp 8,995,570.99
- Bekesting 24.00 m2 Rp 959,962.43 Rp 23,039,098.40
21 Kolom KP lantai 3
- Beton K250 0.14 m3 Rp 17,361,638.90 Rp 2,343,821.25
- Pembesian 9.46 kg Rp 40,265.29 Rp 380,877.40
- Bekesting 3.60 m2 Rp 959,962.43 Rp 3,455,864.76
22 Kolom K1 lantai 4
- Beton K250 3.00 m3 Rp 17,361,638.90 Rp 52,084,916.71
- Pembesian 223.41 kg Rp 40,265.29 Rp 8,995,570.99
- Bekesting 24.00 m2 Rp 959,962.43 Rp 23,039,098.40
23 Kolom KP lantai 4
- Beton K250 0.34 m3 Rp 17,361,638.90 Rp 5,859,553.13
- Pembesian 17.05 kg Rp 40,265.29 Rp 686,442.60
- Bekesting 9.00 m2 Rp 959,962.43 Rp 8,639,661.90
24 Kolom K1 lantai 5
- Beton K250 3.12 m3 Rp 17,361,638.90 Rp 54,168,313.38
- Pembesian 223.41 kg Rp 40,265.29 Rp 8,995,570.99
- Bekesting 24.96 m2 Rp 959,962.43 Rp 23,960,662.34
25 Plat lantai 2
- Beton K250 1.60 m3 Rp 17,361,638.90 Rp 27,709,175.69
- Pembesian 91.95 kg Rp 40,265.29 Rp 3,702,232.02
- Bekesting 13.30 m2 Rp 1,278,972.43 Rp 17,010,333.36
26 Plat lantai 3
- Beton K250 1.60 m3 Rp 17,361,638.90 Rp 27,709,175.69
- Pembesian 91.95 kg Rp 40,265.29 Rp 3,702,232.02
- Bekesting 13.30 m2 Rp 1,278,972.43 Rp 17,010,333.36
27 Plat lantai 4
- Beton K250 1.60 m3 Rp 17,361,638.90 Rp 27,709,175.69
- Pembesian 91.95 kg Rp 40,265.29 Rp 3,702,232.02
- Bekesting 13.30 m2 Rp 1,278,972.43 Rp 17,010,333.36
28 Plat lantai 5
- Beton K250 5.86 m3 Rp 17,361,638.90 Rp 101,753,093.29
- Pembesian 315.95 kg Rp 40,265.29 Rp 12,721,897.76
- Bekesting 48.84 m2 Rp 1,278,972.43 Rp 62,465,013.64
29 Plat atap beton
- Beton K250 3.61 m3 Rp 17,361,638.90 Rp 62,689,405.75
- Pembesian 193.44 kg Rp 40,265.29 Rp 7,788,917.00
- Bekesting 30.09 m2 Rp 1,278,972.43 Rp 38,484,280.52
30 Tangga menara
- Beton K250 10.68 m3 Rp 17,361,638.90 Rp 185,387,580.21
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
PEKERJAAN PLAFOND
1 Pekerjaan pemasangan plafond gypsum dan rangka hollow 48.00 m2 Rp 411,862.15 Rp 19,769,383.20
2 Pekerjaan pemasangan plafond kalsiboard dan rangka hollow 7.00 m2 Rp 307,998.30 Rp 2,155,988.11
2 Pekerjaan pemasangan perapihan pelat beton 50.52 m2 Rp 526,738.70 Rp 26,610,839.00
PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan dinding weathershield 669.26 m2 Rp 72,574.75 Rp 48,571,433.50
2 Pekerjaan pengecatan plafond 55.00 m2 Rp 72,666.40 Rp 3,996,651.82
3 Pekerjaan pengecatan waterproof 21.00 m2 Rp 125,000.00 Rp 2,625,000.00
PEKERJAAN SANITASI
1 Pekerjaan pemasangan closet duduk / monoblok 2.00 unit Rp 4,040,721.71 Rp 8,081,443.41
2 Pekerjaan pemasangan shower spray 2.00 unit Rp 512,359.96 Rp 1,024,719.92
3 Pekerjaan pemasangan toilet paper holder 2.00 unit Rp 483,379.96 Rp 966,759.92
4 Pekerjaan pemasangan kran air 2.00 unit Rp 161,523.71 Rp 323,047.42
5 Pekerjaan pemasangan floor drain 2.00 unit Rp 116,014.19 Rp 232,028.37
6 Pekerjaan pemasangan tempat sabun 2.00 unit Rp 333,879.96 Rp 667,759.92
PEKERJAAN LISTRIK
Pekerjaan kabel feeder
1 kabel dari LVMDP ke PP Menara Air Nav. 40.00 m Rp 160,800.00 Rp 6,432,000.00
(NYY 3 x 10 mm2)
1 kabel dari PP Menara air nav. Ke MCB box bangunan menera air nav. 16.00 m Rp 76,800.00 Rp 1,228,800.00
(NYY 3 x 6 mm2)
PP. Menara air nav. 1.00 unit Rp 13,000,000.00 Rp 13,000,000.00
PP. bangunan Menara air nav. 1.00 unit Rp 3,000,000.00 Rp 3,000,000.00
Pekerjaan Grounding panel 1.00 unit Rp 2,500,000.00 Rp 2,500,000.00
URAIAN PEKERJAAN JML / UNIT PANJANG LEBAR LUAS TINGGI VOLUME SATUAN
PEKERJAAN TANAH
GALIAN TANAH P1 4 2.0 0.83 1 6.64
P2 11 1.0 1.0 1.25 13.75
ROOLAG 30.64 0.2 0.12 0.74
21.13
P1
PEMBESIAN
13 d19 13 4 5.30 2.23 614.59
13 d19 13 4 5.30 2.23 614.59
1,229.18
PEMBESIAN
8 d19 8 8 3.60 2.23 513.79
DIA 10-150 21 8 1.4 2.23 529.37
1,043.16
P2
PEMBESIAN
dia 13 - 150 7 11 2.35 1.04 188.19
dia 13 - 150 7 11 2.35 1.04 188.19
4D12 4 11 0.89 1.32 51.69
dia 8 -150 6 11 0.7 0.4 18.48
446.55
SLOOF SL1
SLOOF SL2
RB 1
B1 LT.2
B1 LT.3
B1 LT.4
B1 LT.5
B1 ATAP
K2 LT.1
K1 LT.2
KP LT.2
K1 LT.3
KP LT.3
K1 LT.4
KP LT.4
K1 LT.5
PLAT LT.2
PLAT LT.4
PEKERJAAN DINDING
334.63
PEKERJAAN LANTAI
KERAMIK 40X40 POLISHED ATC LUAS TOTAL BANG 5.00 6.00 30.00
DIKURANGI KM 1.50 2.00 (3.00)
MENARA LT.1 5.00 4.20 21.00
LT.2 5.00 4.20 21.00
LT.3 5.00 4.20 21.00
LT.4 5.00 4.20 21.00
DIKURANGI KM 2.00 2.00 (4.00)
LT.5 5.00 4.20 21.00
TRAP TANGGA 64 1.00 0.2 12.80
140.80
PEKERJAAN PLAFOND
PEKERJAAN ATAP
PEKERJAAN PENGECATAN
dinding 669.26
plafond 55.00
BANGUNAN KEAMANAN
Pemasangan 1 unit pintu type P1 Rp 7,784,403.11
Pemasangan 1 unit pintu type P2 Rp 4,171,618.99
Pemasangan 1 unit pintu type P3 Rp 4,267,589.20
Pemasangan 1 unit jendela type J1 Rp 3,994,290.50
Pemasangan 1 unit jendela type J2 Rp 5,424,365.40
Pemasangan 1 unit jendela type J3 Rp 5,005,232.20
Pemasangan 1 unit jendela type BV1 Rp 974,089.30
BENGKEL ME
Pemasangan 1 unit pintu type P1 Rp 14,538,450.00
Pemasangan 1 unit pintu type P2 Rp 4,171,618.99
Pemasangan 1 unit pintu type P3 Rp 4,267,589.20
Pemasangan 1 unit pintu type P2A Rp 4,274,593.15
Pemasangan 1 unit pintu type P4 Rp 6,762,143.15
Pemasangan 1 unit jendela type J1 Rp 4,418,290.50
Pemasangan 1 unit jendela type BV1 Rp 974,089.30
Rp 14,538,450.00
GUDANG KARGO
Pemasangan 1 unit pintu type P1 Rp 15,782,200.00
Pemasangan 1 unit pintu type P2 Rp 4,992,676.47
Pemasangan 1 unit pintu type P3 Rp 4,358,218.15
Pemasangan 1 unit jendela type J1 Rp 3,508,362.05
Pemasangan 1 unit jendela type BV1 Rp 2,387,480.25
Pemasangan 1 unit jendela type BV2 Rp 974,089.30
Kode Uraian pekerjaan Harga satuan
RUMAH DINAS
Pemasangan 1 unit pintu type PJ1 Rp 10,850,729.90
Pemasangan 1 unit pintu type PJ2 Rp 5,752,670.15
Pemasangan 1 unit pintu type P1 Rp 4,230,093.15
Pemasangan 1 unit pintu type P2 Rp 3,951,593.15
Pemasangan 1 unit jendela type J1 Rp 2,025,363.10
Pemasangan 1 unit jendela type J2 Rp 3,434,726.20
Pemasangan 1 unit jendela type BV1 Rp 944,279.80
POS JAGA
Pemasangan 1 unit pintu type P1 Rp 9,131,978.83
Pemasangan 1 unit pintu type P2 Rp 3,424,389.20
Pemasangan 1 unit jendela type J1 Rp 4,177,824.50
Pemasangan 1 unit jendela type BV1 Rp 944,279.80
POS TICKETING
Pemasangan 1 unit pintu type P1 Rp 3,903,944.03
Pemasangan 1 unit jendela type J1 Rp 2,585,895.25
Pemasangan 1 unit jendela type J2 Rp 3,150,589.31
RUMAH GENSET
Pemasangan 1 unit pintu type PU Rp 12,706,116.50
Pemasangan 1 unit pintu type PJ Rp 6,561,596.27
Pemasangan 1 unit pintu type P1 Rp 6,446,923.35
Pemasangan 1 unit pintu type P2 Rp 4,468,093.15
Pemasangan 1 unit jendela type BV1 Rp 2,700,000.00
Pemasangan 1 unit jendela type BV2 Rp 866,597.20
Tenaga
Pekerja 0.300 Oh x Rp 136,620.00 = Rp 40,986.00
Tukang batu 0.000 Oh x Rp 204,930.00 = Rp -
Kepala tukang 0.000 Oh x Rp 265,650.00 = Rp -
Mandor 0.010 Oh x Rp 273,240.00 = Rp 2,732.40
Jumlah (II) = Rp 43,718.40
Jumlah (I)+(II) = Rp 9,530,798.40
Overhead & profit (15%) = Rp 1,429,619.76
Harga satuan pekerjaan = Rp 10,960,418.16
Tenaga
Pekerja 0.300 Oh x Rp 136,620.00 = Rp 40,986.00
Tukang batu 0.000 Oh x Rp 204,930.00 = Rp -
Kepala tukang 0.000 Oh x Rp 265,650.00 = Rp -
Mandor 0.010 Oh x Rp 273,240.00 = Rp 2,732.40
Jumlah (II) = Rp 43,718.40
Jumlah (I)+(II) = Rp 1,125,578.40
Overhead & profit (15%) = Rp 168,836.76
Harga satuan pekerjaan = Rp 1,294,415.16
Tenaga
Pekerja 0.250 Oh x Rp 136,620.00 = Rp 34,155.00
Tukang batu 0.000 Oh x Rp 204,930.00 = Rp -
Kepala tukang 0.000 Oh x Rp 265,650.00 = Rp -
Mandor 0.025 Oh x Rp 273,240.00 = Rp 6,831.00
Jumlah (II) = Rp 40,986.00
Jumlah (I)+(II) = Rp 1,372,506.00
Overhead & profit (15%) = Rp 205,875.90
Harga satuan pekerjaan = Rp 1,578,381.90
Tenaga
Pekerja 1.500 Oh x Rp 136,620.00 = Rp 204,930.00
Tukang batu 0.750 Oh x Rp 204,930.00 = Rp 153,697.50
Kepala tukang 0.075 Oh x Rp 265,650.00 = Rp 19,923.75
Mandor 0.075 Oh x Rp 273,240.00 = Rp 20,493.00
Jumlah (II) = Rp 399,044.25
Jumlah (I)+(II) = Rp 10,512,049.61
Overhead & profit (15%) = Rp 1,576,807.44
Harga satuan pekerjaan Rp 12,088,857.05
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
Tenaga
Pekerja 1.500 Oh x Rp 136,620.00 = Rp 204,930.00
Tukang batu 0.750 Oh x Rp 204,930.00 = Rp 153,697.50
Kepala tukang 0.075 Oh x Rp 265,650.00 = Rp 19,923.75
Mandor 0.075 Oh x Rp 273,240.00 = Rp 20,493.00
Jumlah (II) = Rp 399,044.25
Jumlah (I)+(II) = Rp 10,010,357.84
Overhead & profit (15%) = Rp 1,501,553.68
Harga satuan pekerjaan Rp 11,511,911.52
Tenaga
Pekerja 1.500 Oh x Rp 136,620.00 = Rp 204,930.00
Tukang batu 0.750 Oh x Rp 204,930.00 = Rp 153,697.50
Kepala tukang 0.075 Oh x Rp 265,650.00 = Rp 19,923.75
Mandor 0.075 Oh x Rp 273,240.00 = Rp 20,493.00
Jumlah (II) = Rp 399,044.25
Jumlah (I)+(II) = Rp 9,661,208.33
Overhead & profit (15%) = Rp 1,449,181.25
Harga satuan pekerjaan Rp 11,110,389.58
Tenaga
Pekerja 0.780 Oh x Rp 136,620.00 = Rp 106,563.60
Tukang batu 0.390 Oh x Rp 204,930.00 = Rp 79,922.70
Kepala tukang 0.039 Oh x Rp 265,650.00 = Rp 10,360.35
Mandor 0.039 Oh x Rp 273,240.00 = Rp 10,656.36
Jumlah (II) = Rp 207,503.01
Jumlah (I)+(II) = Rp 5,869,791.81
Overhead & profit (15%) = Rp 880,468.77
Harga satuan pekerjaan Rp 6,750,260.58
A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 Mpa (K100) slump (3-6)cm , w/c = 0,87
Bahan
Semen portland 230.000 Kg x Rp 19,958.93 = Rp 4,590,553.90
Pasir beton 893.000 kg x Rp 5,647.07 = Rp 5,042,834.79
koral beton 1,027.000 kg x Rp 3,082.22 = Rp 3,165,442.22
Air 200.000 ltr x Rp 50.00 = Rp 10,000.00
Jumlah (I) = Rp 12,808,830.91
Tenaga
Pekerja 1.200 Oh x Rp 136,620.00 = Rp 163,944.00
Tukang batu 0.200 Oh x Rp 204,930.00 = Rp 40,986.00
Kepala tukang 0.020 Oh x Rp 265,650.00 = Rp 5,313.00
Mandor 0.060 Oh x Rp 273,240.00 = Rp 16,394.40
Jumlah (II) = Rp 226,637.40
Jumlah (I)+(II) = Rp 13,035,468.31
Overhead & profit (15%) = Rp 1,955,320.25
Harga satuan pekerjaan Rp 14,990,788.55
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
A.4.1.1.5 Membuat 1 m3 beton mutu f'c = 14,5 Mpa (K-175) slump (12±2)cm , w/c = 0,66
Bahan
Semen portland 326.00 Kg x Rp 19,958.93 = Rp 6,506,611.18
Pasir beton 760.00 kg x Rp 5,647.07 = Rp 4,291,774.29
Kerikil (maks 30 mm) 1,029.00 kg x Rp 3,082.22 = Rp 3,171,606.67
Air 215.00 ltr x Rp 50.00 = Rp 10,750.00
Jumlah (I) = Rp 13,980,742.13
Tenaga
Pekerja 1.650 Oh x Rp 136,620.00 = Rp 225,423.00
Tukang batu 0.275 Oh x Rp 204,930.00 = Rp 56,355.75
Kepala tukang 0.028 Oh x Rp 265,650.00 = Rp 7,438.20
Mandor 0.083 Oh x Rp 273,240.00 = Rp 22,678.92
Jumlah (II) = Rp 311,895.87
Jumlah (I)+(II) = Rp 14,292,638.00
Overhead & profit (15%) = Rp 2,143,895.70
Harga satuan pekerjaan Rp 16,436,533.70
A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K-225) , slump (12±2 ) cm, w/c = 0,58
Bahan
Semen portland 371.00 Kg x Rp 19,958.93 = Rp 7,404,763.03
Pasir beton 698.00 m3 x Rp 5,647.07 = Rp 3,941,655.86
Koral beton 1,047.00 m3 x Rp 3,082.22 = Rp 3,227,086.67
Air 215.00 ltr x Rp 50.00 = Rp 10,750.00
Jumlah (I) = Rp 14,584,255.55
Tenaga
Pekerja 1.650 Oh x Rp 136,620.00 = Rp 225,423.00
Tukang batu 0.275 Oh x Rp 204,930.00 = Rp 56,355.75
Kepala tukang 0.028 Oh x Rp 265,650.00 = Rp 7,438.20
Mandor 0.083 Oh x Rp 273,240.00 = Rp 22,678.92
Jumlah (II) = Rp 311,895.87
Jumlah (I)+(II) = Rp 14,896,151.42
Overhead & profit (15%) = Rp 2,234,422.71
Harga satuan pekerjaan Rp 17,130,574.14
A.4.1.1.8 Membuat 1 m3 beton mutu f'c = 21,7 Mpa (K-250) , slump (12±2 ) cm, w/c = 0,56
Bahan
Semen portland 384.00 Kg x Rp 19,958.93 = Rp 7,664,229.12
Pasir beton 692.00 kg x Rp 5,647.07 = Rp 3,907,773.43
Koral beton 1,039.00 kg x Rp 3,082.22 = Rp 3,202,428.89
Air 215.00 ltr x Rp 50.00 = Rp 10,750.00
Jumlah (I) = Rp 14,785,181.44
Tenaga
Pekerja 1.650 Oh x Rp 136,620.00 = Rp 225,423.00
Tukang batu 0.275 Oh x Rp 204,930.00 = Rp 56,355.75
Kepala tukang 0.028 Oh x Rp 265,650.00 = Rp 7,438.20
Mandor 0.083 Oh x Rp 273,240.00 = Rp 22,678.92
Jumlah (II) = Rp 311,895.87
Jumlah (I)+(II) = Rp 15,097,077.31
Overhead & profit (15%) = Rp 2,264,561.60
Harga satuan pekerjaan Rp 17,361,638.90
A.4.1.1.10 Membuat 1 m3 beton mutu f'c = 26,4 Mpa (K-300), slump (12±2 ) cm, w/c = 0,52
Bahan
Semen portland 413.00 Kg x Rp 19,958.93 = Rp 8,243,038.09
Pasir beton 681.00 kg x Rp 5,647.07 = Rp 3,845,655.64
Koral beton 1,021.00 kg x Rp 3,082.22 = Rp 3,146,948.89
Air 215.00 ltr x Rp 50.00 = Rp 10,750.00
Jumlah (I) = Rp 15,246,392.62
Tenaga
Pekerja 1.650 Oh x Rp 136,620.00 = Rp 225,423.00
Tukang batu 0.275 Oh x Rp 204,930.00 = Rp 56,355.75
Kepala tukang 0.028 Oh x Rp 265,650.00 = Rp 7,438.20
Mandor 0.083 Oh x Rp 273,240.00 = Rp 22,678.92
Jumlah (II) = Rp 311,895.87
Jumlah (I)+(II) = Rp 15,558,288.49
Overhead & profit (15%) = Rp 2,333,743.27
Harga satuan pekerjaan Rp 17,892,031.77
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
Tenaga
Pekerja 0.007 Oh x Rp 136,620.00 = Rp 956.34
Tukang batu 0.007 Oh x Rp 204,930.00 = Rp 1,434.51
Kepala tukang 0.001 Oh x Rp 265,650.00 = Rp 185.95
Mandor 0.000 Oh x Rp 273,240.00 = Rp 109.30
Jumlah (II) = Rp 2,686.10
Jumlah (I)+(II) = Rp 40,250.99
Overhead & profit (15%) = Rp 6,037.65
Harga satuan pekerjaan Rp 46,288.63
Tenaga
Pekerja 0.007 Oh x Rp 136,620.00 = Rp 956.34
Tukang batu 0.007 Oh x Rp 204,930.00 = Rp 1,434.51
Kepala tukang 0.001 Oh x Rp 265,650.00 = Rp 185.95
Mandor 0.000 Oh x Rp 273,240.00 = Rp 109.30
Jumlah (II) = Rp 2,686.10
Jumlah (I)+(II) = Rp 35,013.29
Overhead & profit (15%) = Rp 5,251.99
Harga satuan pekerjaan Rp 40,265.29
Tenaga
Pekerja 0.003 Oh x Rp 136,620.00 = Rp 341.55
Tukang batu 0.003 Oh x Rp 204,930.00 = Rp 512.33
Kepala tukang 0.003 Oh x Rp 265,650.00 = Rp 664.13
Mandor 0.000 Oh x Rp 273,240.00 = Rp 27.32
Jumlah (II) = Rp 1,545.32
Jumlah (I)+(II) = Rp 73,114.52
Overhead & profit (15%) = Rp 10,967.18
Harga satuan pekerjaan Rp 84,081.70
Tenaga
Pekerja 0.520 Oh x Rp 136,620.00 = Rp 71,042.40
Tukang kayu 0.260 Oh x Rp 204,930.00 = Rp 53,281.80
Kepala tukang 0.026 Oh x Rp 265,650.00 = Rp 6,906.90
Mandor 0.003 Oh x Rp 273,240.00 = Rp 710.42
Jumlah (II) = Rp 131,941.52
Jumlah (I)+(II) = Rp 354,693.72
Overhead & profit (15%) = Rp 53,204.06
Harga satuan pekerjaan Rp 407,897.78
Tenaga
Pekerja 0.520 Oh x Rp 136,620.00 = Rp 71,042.40
Tukang kayu 0.260 Oh x Rp 204,930.00 = Rp 53,281.80
Kepala tukang 0.026 Oh x Rp 265,650.00 = Rp 6,906.90
Mandor 0.003 Oh x Rp 273,240.00 = Rp 710.42
Jumlah (II) = Rp 131,941.52
Jumlah (I)+(II) = Rp 379,659.72
Overhead & profit (15%) = Rp 56,948.96
Harga satuan pekerjaan Rp 436,608.68
Tenaga
Pekerja 0.660 Oh x Rp 136,620.00 = Rp 90,169.20
Tukang kayu 0.330 Oh x Rp 204,930.00 = Rp 67,626.90
Kepala tukang 0.033 Oh x Rp 265,650.00 = Rp 8,766.45
Mandor 0.003 Oh x Rp 273,240.00 = Rp 901.69
Jumlah (II) = Rp 167,464.24
Jumlah (I)+(II) = Rp 834,749.94
Overhead & profit (15%) = Rp 125,212.49
Harga satuan pekerjaan Rp 959,962.43
Tenaga
Pekerja 0.660 Oh x Rp 136,620.00 = Rp 90,169.20
Tukang kayu 0.330 Oh x Rp 204,930.00 = Rp 67,626.90
Kepala tukang 0.033 Oh x Rp 265,650.00 = Rp 8,766.45
Mandor 0.003 Oh x Rp 273,240.00 = Rp 901.69
Jumlah (II) = Rp 167,464.24
Jumlah (I)+(II) = Rp 849,729.54
Overhead & profit (15%) = Rp 127,459.43
Harga satuan pekerjaan Rp 977,188.97
Tenaga
Pekerja 0.660 Oh x Rp 136,620.00 = Rp 90,169.20
Tukang kayu 0.330 Oh x Rp 204,930.00 = Rp 67,626.90
Kepala tukang 0.033 Oh x Rp 265,650.00 = Rp 8,766.45
Mandor 0.003 Oh x Rp 273,240.00 = Rp 901.69
Jumlah (II) = Rp 167,464.24
Jumlah (I)+(II) = Rp 1,112,149.94
Overhead & profit (15%) = Rp 166,822.49
Harga satuan pekerjaan Rp 1,278,972.43
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
Tenaga
Pekerja 0.660 Oh x Rp 136,620.00 = Rp 90,169.20
Tukang kayu 0.330 Oh x Rp 204,930.00 = Rp 67,626.90
Kepala tukang 0.033 Oh x Rp 265,650.00 = Rp 8,766.45
Mandor 0.003 Oh x Rp 273,240.00 = Rp 901.69
Jumlah (II) = Rp 167,464.24
Jumlah (I)+(II) = Rp 1,112,149.94
Overhead & profit (15%) = Rp 166,822.49
Harga satuan pekerjaan Rp 1,278,972.43
Tenaga
Pekerja 0.660 Oh x Rp 136,620.00 = Rp 90,169.20
Tukang kayu 0.330 Oh x Rp 204,930.00 = Rp 67,626.90
Kepala tukang 0.033 Oh x Rp 265,650.00 = Rp 8,766.45
Mandor 0.006 Oh x Rp 273,240.00 = Rp 1,639.44
Jumlah (II) = Rp 168,201.99
Jumlah (I)+(II) = Rp 781,949.49
Overhead & profit (15%) = Rp 117,292.42
Harga satuan pekerjaan Rp 899,241.91
Tenaga
Pekerja 0.060 Oh x Rp 136,620.00 = Rp 8,197.20
Tukang batu 0.060 Oh x Rp 204,930.00 = Rp 12,295.80
Kepala tukang 0.006 Oh x Rp 265,650.00 = Rp 1,593.90
Mandor 0.003 Oh x Rp 273,240.00 = Rp 819.72
Jumlah (II) = Rp 22,906.62
Jumlah (I)+(II) = Rp 45,201.97
Overhead & profit (15%) = Rp 6,780.30
Harga satuan pekerjaan Rp 51,982.26
Tenaga
Pekerja 0.060 Oh x Rp 136,620.00 = Rp 8,197.20
Tukang batu 0.060 Oh x Rp 204,930.00 = Rp 12,295.80
Kepala tukang 0.006 Oh x Rp 265,650.00 = Rp 1,593.90
Mandor 0.003 Oh x Rp 273,240.00 = Rp 819.72
Jumlah (II) = Rp 22,906.62
Jumlah (I)+(II) = Rp 54,668.08
Overhead & profit (15%) = Rp 8,200.21
Harga satuan pekerjaan Rp 62,868.30
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
Tenaga
Pekerja 0.650 Oh x Rp 136,620.00 = Rp 88,803.00
Tukang batu 0.200 Oh x Rp 204,930.00 = Rp 40,986.00
Kepala tukang 0.020 Oh x Rp 265,650.00 = Rp 5,313.00
Mandor 0.030 Oh x Rp 273,240.00 = Rp 8,197.20
Jumlah (II) = Rp 143,299.20
Jumlah (I)+(II) = Rp 1,936,482.84
Overhead & profit (15%) = Rp 290,472.43
Harga satuan pekerjaan Rp 2,226,955.27
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
Tenaga
Pekerja 0.650 Oh x Rp 136,620.00 = Rp 88,803.00
Tukang batu 0.200 Oh x Rp 204,930.00 = Rp 40,986.00
Kepala tukang 0.020 Oh x Rp 265,650.00 = Rp 5,313.00
Mandor 0.030 Oh x Rp 273,240.00 = Rp 8,197.20
Jumlah (II) = Rp 143,299.20
Jumlah (I)+(II) = Rp 1,824,557.49
Overhead & profit (15%) = Rp 273,683.62
Harga satuan pekerjaan Rp 2,098,241.12
Tenaga
Pekerja 0.650 Oh x Rp 136,620.00 = Rp 88,803.00
Tukang batu 0.200 Oh x Rp 204,930.00 = Rp 40,986.00
Kepala tukang 0.020 Oh x Rp 265,650.00 = Rp 5,313.00
Mandor 0.030 Oh x Rp 273,240.00 = Rp 8,197.20
Jumlah (II) = Rp 143,299.20
Jumlah (I)+(II) = Rp 1,808,889.25
Overhead & profit (15%) = Rp 271,333.39
Harga satuan pekerjaan Rp 2,080,222.63
Tenaga
Pekerja 0.300 Oh x Rp 136,620.00 = Rp 40,986.00
Tukang batu 0.150 Oh x Rp 204,930.00 = Rp 30,739.50
Kepala tukang 0.015 Oh x Rp 265,650.00 = Rp 3,984.75
Mandor 0.015 Oh x Rp 273,240.00 = Rp 4,098.60
Jumlah (II) = Rp 79,808.85
Jumlah (I)+(II) = Rp 1,165,538.58
Overhead & profit (15%) = Rp 174,830.79
Harga satuan pekerjaan Rp 1,340,369.37
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
Tenaga
Pekerja 0.300 Oh x Rp 136,620.00 = Rp 40,986.00
Tukang batu 0.150 Oh x Rp 204,930.00 = Rp 30,739.50
Kepala tukang 0.015 Oh x Rp 265,650.00 = Rp 3,984.75
Mandor 0.015 Oh x Rp 273,240.00 = Rp 4,098.60
Jumlah (II) = Rp 79,808.85
Jumlah (I)+(II) = Rp 441,986.95
Overhead & profit (15%) = Rp 66,298.04
Harga satuan pekerjaan Rp 508,284.99
Tenaga
Pekerja 0.300 Oh x Rp 136,620.00 = Rp 40,986.00
Tukang batu 0.150 Oh x Rp 204,930.00 = Rp 30,739.50
Kepala tukang 0.015 Oh x Rp 265,650.00 = Rp 3,984.75
Mandor 0.015 Oh x Rp 273,240.00 = Rp 4,098.60
Jumlah (II) = Rp 79,808.85
Jumlah (I)+(II) = Rp 416,845.19
Overhead & profit (15%) = Rp 62,526.78
Harga satuan pekerjaan Rp 479,371.97
Tenaga
Pekerja 0.300 Oh x Rp 136,620.00 = Rp 40,986.00
Tukang batu 0.150 Oh x Rp 204,930.00 = Rp 30,739.50
Kepala tukang 0.015 Oh x Rp 265,650.00 = Rp 3,984.75
Mandor 0.015 Oh x Rp 273,240.00 = Rp 4,098.60
Jumlah (II) = Rp 79,808.85
Jumlah (I)+(II) = Rp 339,961.23
Overhead & profit (15%) = Rp 50,994.18
Harga satuan pekerjaan Rp 390,955.41
Tenaga
Pekerja 0.300 Oh x Rp 136,620.00 = Rp 40,986.00
Tukang batu 0.100 Oh x Rp 204,930.00 = Rp 20,493.00
Kepala tukang 0.010 Oh x Rp 265,650.00 = Rp 2,656.50
Mandor 0.015 Oh x Rp 273,240.00 = Rp 4,098.60
Jumlah (II) = Rp 68,234.10
Jumlah (I)+(II) = Rp 201,892.08
Overhead & profit (15%) = Rp 30,283.81
Harga satuan pekerjaan Rp 232,175.89
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
Pemasangan 1 m2 finishing siar pas batu kali
Bahan
Semen portland 6.340 kg x Rp 19,958.93 = Rp 126,539.62
Pasir pasang 0.012 m3 x Rp 7,905,900.00 = Rp 94,870.80
Jumlah (I) = Rp 221,410.42
Tenaga
Pekerja 0.300 Oh x Rp 136,620.00 = Rp 40,986.00
Tukang batu 0.150 Oh x Rp 204,930.00 = Rp 30,739.50
Kepala tukang 0.015 Oh x Rp 265,650.00 = Rp 3,984.75
Mandor 0.015 Oh x Rp 273,240.00 = Rp 4,098.60
Jumlah (II) = Rp 79,808.85
Jumlah (I)+(II) = Rp 301,219.27
Overhead & profit (15%) = Rp 45,182.89
Harga satuan pekerjaan = Rp 346,402.16
Pemasangan 1 m2 Acian
Bahan
Semen portland 3.250 kg x Rp 19,958.93 = Rp 64,866.52
Jumlah (I) = Rp 64,866.52
Tenaga
Pekerja 0.200 Oh x Rp 136,620.00 = Rp 27,324.00
Tukang batu 0.100 Oh x Rp 204,930.00 = Rp 20,493.00
Kepala tukang 0.010 Oh x Rp 265,650.00 = Rp 2,656.50
Mandor 0.010 Oh x Rp 273,240.00 = Rp 2,732.40
Jumlah (II) = Rp 53,205.90
Jumlah (I)+(II) = Rp 118,072.42
Overhead & profit (15%) = Rp 17,710.86
Harga satuan pekerjaan = Rp 135,783.29
Tenaga
Pekerja 0.240 Oh x Rp 136,620.00 = Rp 32,788.80
Tukang batu 0.120 Oh x Rp 204,930.00 = Rp 24,591.60
Kepala tukang 0.012 Oh x Rp 265,650.00 = Rp 3,187.80
Mandor 0.012 Oh x Rp 273,240.00 = Rp 3,278.88
Jumlah (II) = Rp 63,847.08
Jumlah (I)+(II) = Rp 1,072,659.09
Overhead & profit (15%) = Rp 160,898.86
Harga satuan pekerjaan = Rp 1,233,557.96
Tenaga
Pekerja 0.240 Oh x Rp 136,620.00 = Rp 32,788.80
Tukang batu 0.120 Oh x Rp 204,930.00 = Rp 24,591.60
Kepala tukang 0.012 Oh x Rp 265,650.00 = Rp 3,187.80
Mandor 0.012 Oh x Rp 273,240.00 = Rp 3,278.88
Jumlah (II) = Rp 63,847.08
Jumlah (I)+(II) = Rp 1,056,909.09
Overhead & profit (15%) = Rp 158,536.36
Harga satuan pekerjaan = Rp 1,215,445.46
Tenaga
Pekerja 0.240 Oh x Rp 136,620.00 = Rp 32,788.80
Tukang batu 0.120 Oh x Rp 204,930.00 = Rp 24,591.60
Kepala tukang 0.012 Oh x Rp 265,650.00 = Rp 3,187.80
Mandor 0.012 Oh x Rp 273,240.00 = Rp 3,278.88
Jumlah (II) = Rp 63,847.08
Jumlah (I)+(II) = Rp 1,045,873.59
Overhead & profit (15%) = Rp 156,881.04
Harga satuan pekerjaan = Rp 1,202,754.63
Tenaga
Pekerja 0.240 Oh x Rp 136,620.00 = Rp 32,788.80
Tukang batu 0.120 Oh x Rp 204,930.00 = Rp 24,591.60
Kepala tukang 0.012 Oh x Rp 265,650.00 = Rp 3,187.80
Mandor 0.012 Oh x Rp 273,240.00 = Rp 3,278.88
Jumlah (II) = Rp 63,847.08
Jumlah (I)+(II) = Rp 1,041,159.09
Overhead & profit (15%) = Rp 156,173.86
Harga satuan pekerjaan = Rp 1,197,332.96
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
Tenaga
Pekerja 0.620 Oh x Rp 136,620.00 = Rp 84,704.40
Tukang batu 0.350 Oh x Rp 204,930.00 = Rp 71,725.50
Kepala tukang 0.035 Oh x Rp 265,650.00 = Rp 9,297.75
Mandor 0.030 Oh x Rp 273,240.00 = Rp 8,197.20
Jumlah (II) = Rp 173,924.85
Jumlah (I)+(II) = Rp 1,134,641.77
Overhead & profit (15%) = Rp 170,196.27
Harga satuan pekerjaan = Rp 1,304,838.04
Tenaga
Pekerja 0.620 Oh x Rp 136,620.00 = Rp 84,704.40
Tukang batu 0.350 Oh x Rp 204,930.00 = Rp 71,725.50
Kepala tukang 0.035 Oh x Rp 265,650.00 = Rp 9,297.75
Mandor 0.030 Oh x Rp 273,240.00 = Rp 8,197.20
Jumlah (II) = Rp 173,924.85
Jumlah (I)+(II) = Rp 1,134,242.59
Overhead & profit (15%) = Rp 170,136.39
Harga satuan pekerjaan = Rp 1,304,378.98
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
A.4.6.1.2 Pembuatan dan pemasangan 1 m3 kusen pintu dan jendela, kayu kelas II
Bahan
balok kayu 1.200 m3 x Rp 4,993,200.00 = Rp 5,991,840.00
paku 10 cm 1.250 kg x Rp 52,706.00 = Rp 65,882.50
lem kayu 1.000 kg x Rp 20,250.00 = Rp 20,250.00
Jumlah (I) = Rp 6,077,972.50
Tenaga
Pekerja 6.000 Oh x Rp 136,620.00 = Rp 819,720.00
Tukang 18.000 Oh x Rp 204,930.00 = Rp 3,688,740.00
Kepala tukang 1.800 Oh x Rp 265,650.00 = Rp 478,170.00
Mandor 0.300 Oh x Rp 273,240.00 = Rp 81,972.00
Jumlah (II) = Rp 5,068,602.00
Jumlah (I)+(II) = Rp 11,146,574.50
Overhead & profit (15%) = Rp 1,671,986.18
Harga satuan pekerjaan = Rp 12,818,560.68
Tenaga
Pekerja 0.015 Oh x Rp 136,620.00 = Rp 2,049.30
Tukang batu 0.150 Oh x Rp 204,930.00 = Rp 30,739.50
Kepala tukang 0.015 Oh x Rp 265,650.00 = Rp 3,984.75
Mandor 0.001 Oh x Rp 273,240.00 = Rp 204.93
Jumlah (II) = Rp 36,978.48
Jumlah (I)+(II) = Rp 1,028,683.48
Overhead & profit (15%) = Rp 154,302.52
Harga satuan pekerjaan = Rp 1,182,986.00
Tenaga
Pekerja 0.015 Oh x Rp 136,620.00 = Rp 2,049.30
Tukang batu 0.150 Oh x Rp 204,930.00 = Rp 30,739.50
Kepala tukang 0.015 Oh x Rp 265,650.00 = Rp 3,984.75
Mandor 0.001 Oh x Rp 273,240.00 = Rp 204.93
Jumlah (II) = Rp 36,978.48
Jumlah (I)+(II) = Rp 1,111,183.48
Overhead & profit (15%) = Rp 166,677.52
Harga satuan pekerjaan = Rp 1,277,861.00
Tenaga
Pekerja 0.015 Oh x Rp 136,620.00 = Rp 2,049.30
Tukang batu 0.150 Oh x Rp 204,930.00 = Rp 30,739.50
Kepala tukang 0.015 Oh x Rp 265,650.00 = Rp 3,984.75
Mandor 0.008 Oh x Rp 273,240.00 = Rp 2,185.92
Jumlah (II) = Rp 38,959.47
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
Jumlah (I)+(II) = Rp 1,195,664.47
Overhead & profit (15%) = Rp 179,349.67
Harga satuan pekerjaan = Rp 1,375,014.14
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
Tenaga
Pekerja 0.015 Oh x Rp 136,620.00 = Rp 2,049.30
Tukang batu 0.150 Oh x Rp 204,930.00 = Rp 30,739.50
Kepala tukang 0.015 Oh x Rp 265,650.00 = Rp 3,984.75
Mandor 0.008 Oh x Rp 273,240.00 = Rp 2,185.92
Jumlah (II) = Rp 38,959.47
Jumlah (I)+(II) = Rp 1,688,959.47
Overhead & profit (15%) = Rp 253,343.92
Harga satuan pekerjaan = Rp 1,942,303.39
A.4.7.1.4 Pengecatan 1 m2 bidang kayu baru ( 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Bahan
menie kayu 0.200 Kg x Rp 47,158.00 = Rp 9,431.60
Plamir kayu 0.150 Kg x Rp 62,415.00 = Rp 9,362.25
cat dasar 0.170 Kg x Rp 94,316.00 = Rp 16,033.72
Cat penutup 0.260 Kg x Rp 94,316.00 = Rp 24,522.16
Jumlah (I) = Rp 59,349.73
Tenaga
Pekerja 0.070 Oh x Rp 136,620.00 = Rp 9,563.40
Tukang cat 0.009 Oh x Rp 204,930.00 = Rp 1,844.37
Kepala tukang 0.0060 Oh x Rp 265,650.00 = Rp 1,593.90
Mandor 0.0025 Oh x Rp 273,240.00 = Rp 683.10
Jumlah (II) = Rp 13,684.77
Jumlah (I)+(II) = Rp 73,034.50
Overhead & profit (15%) = Rp 10,955.18
Harga satuan pekerjaan = Rp 83,989.68
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
A.4.7.1.10 Pengecatan 1 m2 tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 cat penutup)
Bahan
Plamir tembok 0.100 Kg x Rp 49,932.00 = Rp 4,993.20
Cat dasar (cat tembok) 0.100 Kg x Rp 28,710.90 = Rp 2,871.09
Cat penutup (cat tembok) 0.260 Kg x Rp 143,554.60 = Rp 37,324.20
Jumlah (I) = Rp 45,188.49
Tenaga
Pekerja 0.020 Oh x Rp 136,620.00 = Rp 2,732.40
Tukang cat 0.063 Oh x Rp 204,930.00 = Rp 12,910.59
Kepala tukang 0.0063 Oh x Rp 265,650.00 = Rp 1,673.60
Mandor 0.0025 Oh x Rp 273,240.00 = Rp 683.10
Jumlah (II) = Rp 17,999.68
Jumlah (I)+(II) = Rp 63,188.17
Overhead & profit (15%) = Rp 9,478.23
Harga satuan pekerjaan = Rp 72,666.40
dihitung Pengecatan 1 m2 tembok baru eksterior ( 1 lapis plamuur, 1 lapis cat dasar, 2 cat penutup)
Bahan
Plamir tembok 0.100 Kg x Rp 49,932.00 = Rp 4,993.20
Cat dasar (cat tembok) 0.100 Kg x Rp 28,710.90 = Rp 2,871.09
Cat penutup (cat tembok) 0.260 Kg x Rp 143,554.60 = Rp 37,324.20
Jumlah (I) = Rp 45,188.49
Tenaga
Pekerja 0.020 Oh x Rp 136,620.00 = Rp 2,732.40
Tukang cat 0.063 Oh x Rp 204,930.00 = Rp 12,910.59
Kepala tukang 0.0060 Oh x Rp 265,650.00 = Rp 1,593.90
Mandor 0.0025 Oh x Rp 273,240.00 = Rp 683.10
Jumlah (II) = Rp 17,919.99
Jumlah (I)+(II) = Rp 63,108.48
Overhead & profit (15%) = Rp 9,466.27
Harga satuan pekerjaan = Rp 72,574.75
Tenaga
Pekerja 0.028 Oh x Rp 136,620.00 = Rp 3,825.36
Tukang cat 0.042 Oh x Rp 204,930.00 = Rp 8,607.06
Kepala tukang 0.0042 Oh x Rp 265,650.00 = Rp 1,115.73
Mandor 0.0025 Oh x Rp 273,240.00 = Rp 683.10
Jumlah (II) = Rp 14,231.25
Jumlah (I)+(II) = Rp 22,844.52
Overhead & profit (15%) = Rp 3,426.68
Harga satuan pekerjaan = Rp 26,271.20
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI
BANGUNAN KEAMANAN
dihitung Pemasangan 1 unit pintu type P1
kusen aluminium 5.980 m x Rp 200,000.00 = Rp 1,196,000.00
aluminium frame 0.700 m2 x Rp 1,250,000.00 = Rp 875,000.00
kaca tempered 8 mm 2.700 m2 x Rp 1,277,861.00 = Rp 3,450,224.71
handle pintu 2.000 set x Rp 416,100.00 = Rp 832,200.00
door closer 2.000 set x Rp 534,000.00 = Rp 1,068,000.00
engsel 8.000 set x Rp 31,901.00 = Rp 255,208.00
biaya pasang aksesories dan material bantu 1.000 x Rp 107,770.40 = Rp 107,770.40
Harga satuan pekerjaan = Rp 7,784,403.11
BENGKEL ME
dihitung Pemasangan 1 unit pintu type P1
rolling door 5.482 m2 x Rp 2,500,000.00 = Rp 13,706,250.00
handle pintu 2.000 set x Rp 416,100.00 = Rp 832,200.00
Harga satuan pekerjaan = Rp 14,538,450.00
GUDANG KARGO
dihitung Pemasangan 1 unit pintu type P1
rolling door 5.980 m x Rp 2,500,000.00 = Rp 14,950,000.00
handle pintu 2.000 set x Rp 416,100.00 = Rp 832,200.00
Harga satuan pekerjaan = Rp 15,782,200.00
RUMAH DINAS
dihitung Pemasangan 1 unit pintu type PJ1
kusen aluminium 11.330 m x Rp 200,000.00 = Rp 2,266,000.00
daun pintu panil aluminium 3.500 m2 x Rp 1,250,000.00 = Rp 4,375,000.00
daun jendela panil aluminium 0.500 m2 x Rp 1,250,000.00 = Rp 625,000.00
kaca tempered 8 mm 1.000 m2 x Rp 1,277,861.00 = Rp 1,277,861.00
handle pintu 2.000 set x Rp 416,100.00 = Rp 832,200.00
door closer 2.000 set x Rp 534,000.00 = Rp 1,068,000.00
engsel 6.000 set x Rp 31,901.00 = Rp 191,406.00
hak angin 2.000 set x Rp 20,805.00 = Rp 41,610.00
engsel jendela 2.000 set x Rp 31,901.00 = Rp 63,802.00
biaya pasang aksesories dan material bantu 1.000 x Rp 109,850.90 = Rp 109,850.90
Harga satuan pekerjaan = Rp 10,850,729.90
POS JAGA
dihitung Pemasangan 1 unit pintu type P1
kusen aluminium 10.350 m x Rp 200,000.00 = Rp 2,070,000.00
daun pintu panil aluminium 0.450 m2 x Rp 1,250,000.00 = Rp 562,500.00
kaca tempered 8 mm 3.420 m2 x Rp 1,277,861.00 = Rp 4,370,284.63
handle pintu 2.000 set x Rp 416,100.00 = Rp 832,200.00
door closer 2.000 set x Rp 534,000.00 = Rp 1,068,000.00
engsel 4.000 set x Rp 31,901.00 = Rp 127,604.00
biaya pasang aksesories dan material bantu 1.000 x Rp 101,390.20 = Rp 101,390.20
Harga satuan pekerjaan = Rp 9,131,978.83
POS TICKETING
dihitung Pemasangan 1 unit pintu type P1
kusen aluminium 6.160 m x Rp 200,000.00 = Rp 1,232,000.00
daun pintu panel kayu kamper oven fin coating 1.760 m2 x Rp 1,212,813.00 = Rp 2,134,550.88
handle pintu 1.000 set x Rp 416,100.00 = Rp 416,100.00
engsel 3.000 set x Rp 31,901.00 = Rp 95,703.00
biaya pasang aksesories dan material bantu 1.000 x Rp 25,590.15 = Rp 25,590.15
Harga satuan pekerjaan = Rp 3,903,944.03
KODE URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
RUMAH GENSET
dihitung Pemasangan 1 unit pintu type PU
kusen besi 6.480 m x Rp 350,000.00 = Rp 2,268,000.00
daun pintu plat besi t = 1,5 mm 4.644 m2 x Rp 1,750,000.00 = Rp 8,126,650.00
rangka daun pintu 4.644 m2 x Rp 250,000.00 = Rp 1,160,950.00
handle pintu 2.000 set x Rp 416,100.00 = Rp 832,200.00
engsel 6.000 set x Rp 31,901.00 = Rp 191,406.00
grendel pintu 2.000 set x Rp 36,062.00 = Rp 72,124.00
biaya pasang aksesories dan material bantu 1.000 x Rp 54,786.50 = Rp 54,786.50
Harga satuan pekerjaan = Rp 12,706,116.50
Pekerjaan 1 m3 base B
Bahan
produksi batu pecah 2-3 mm 0.285 m3 x Rp 4,161,000.00 = Rp 1,186,188.34
produksi batu pecah 5-20 mm 0.285 m3 x Rp 4,161,000.00 = Rp 1,186,188.34
sirtu 1.014 m3 x Rp 1,109,600.00 = Rp 1,124,915.03
peralatan 1.000 x Rp 350,000.00 = Rp 350,000.00
Jumlah (II) = Rp 3,847,291.71
Tenaga
Pekerja 0.004 Oh x Rp 136,620.00 = Rp 546.48
Tukang - Oh x Rp 204,930.00 = Rp -
Kepala tukang - Oh x Rp 265,650.00 = Rp -
Mandor 0.001 Oh x Rp 273,240.00 = Rp 355.21
Jumlah (III) = Rp 901.69
Jumlah (I)+(II) = Rp 3,848,193.40
Overhead & profit (15%) = Rp 577,229.01
Harga satuan pekerjaan = Rp 4,425,422.41
Pekerjaan 1 m3 base A
Bahan
produksi batu pecah 20-30 mm 0.444 m3 x Rp 1,872,450.00 = Rp 830,488.95
produksi batu pecah 5-20 mm 0.665 m3 x Rp 4,161,000.00 = Rp 2,768,296.49
sirtu 0.475 m3 x Rp 1,109,600.00 = Rp 527,334.47
peralatan 1.000 x Rp 350,000.00 = Rp 350,000.00
Jumlah (II) = Rp 4,476,119.91
Tenaga
Pekerja 0.004 Oh x Rp 136,620.00 = Rp 546.48
Tukang - Oh x Rp 204,930.00 = Rp -
Kepala tukang - Oh x Rp 265,650.00 = Rp -
Mandor 0.001 Oh x Rp 273,240.00 = Rp 355.21
Jumlah (III) = Rp 901.69
Jumlah (I)+(II) = Rp 4,477,021.60
Overhead & profit (15%) = Rp 671,553.24
Harga satuan pekerjaan = Rp 5,148,574.84
TENAGA
1 pekerja Oh Rp 136,620.00
2 tukang Oh Rp 204,930.00
3 kepala tukang Oh Rp 265,650.00
4 mandor Oh Rp 273,240.00
BAHAN
1 aluminium foil m2 Rp 9,000.00
2 amplas lbr Rp 5,000.00
3 air ltr Rp 50.00
4 bambu btg Rp 84,975.00
5 bata tela uk.10x20x30 bh Rp 16,644.00
6 batu pecah 1/2 m3 Rp 4,161,000.00
7 batu pecah 2/3 m3 Rp 4,161,000.00
8 batu belah 15/20 m3 Rp 1,872,450.00
9 besi beton polos kg Rp 34,983.51
10 besi beton ulir kg Rp 29,995.23
11 besi profil kg Rp 19,387.26
12 besi siku kg Rp 27,618.66
12 cat dasar dinding kg Rp 28,710.90
13 cat dasar kayu kg Rp 94,316.00
14 cat penutup dinding kg Rp 28,710.00
15 cat penutup dinding eksterior kg Rp 143,554.60
16 cat kayu penutup kg Rp 94,316.00
17 cat menie kayu kg Rp 47,158.00
18 corten steel 1,2 mm m2 Rp 75,000.00
19 dolken btg Rp 69,350.00
20 galvalum lbr Rp 155,000.00
21 genteng bh Rp 9,000.00
22 genteng nok bh Rp 12,500.00
23 gypsumboard lbr Rp 208,050.00
24 hollow 40x40 m Rp 35,000.00
25 hollow 50x50 m Rp 43,750.00
26 kalsiboard lbr Rp 166,000.00
27 kawat beton kg Rp 55,480.00
28 kawat duri m Rp 6,942.53
29 kayu 5/7 balok m3 Rp 4,993,200.00
NO BAHAN / TENAGA SATUAN HARGA
30 kayu 3/20 papan m3 Rp 4,993,200.00
31 kayu balok m3 Rp 4,993,200.00
32 kayu balok kelas II m3 Rp 4,993,200.00
33 kayu papan matoa m3 Rp 4,993,200.00
34 kayu terentang m3 Rp 4,993,200.00
35 kansteen bh Rp 55,000.00
36 kerikil halus m3 Rp 832,200.00
37 lem kayu kg Rp 20,250.00
38 minyak bekesting ltr Rp 72,124.00
39 multiplek t = 12 mm lbr Rp 665,760.00
40 paku kg Rp 52,706.00
41 pasir beton m3 Rp 7,905,900.00
42 pasir pasang m3 Rp 7,905,900.00
43 pasir urug m3 Rp 7,905,900.00
44 paving blok m2 Rp 225,000.00
45 pipa PVC 1/2" m Rp 13,523.25
46 pipa PVC 1" m Rp 26,353.00
47 pipa PVC 2" m Rp 47,158.00
48 pipa PVC 4" m Rp 126,910.50
49 pipa PVC 6" m Rp 92,466.67
50 pipa galvanis dia.2" m Rp 151,080.83
51 pipa galvanis dia.3" m Rp 208,333.33
51 plamir kayu kg Rp 62,415.00
52 plamir tembok kg Rp 49,932.00
53 plywood lbr Rp 388,360.00
54 rooster bh Rp 23,579.00
55 sealant kg Rp 36,300.00
56 seal tape bh Rp 8,000.00
NO BAHAN / TENAGA SATUAN HARGA
57 semen portland kg Rp 19,958.93
58 semen warna kg Rp 24,966.00
59 seng plat bjls 20 lbr Rp 117,895.00
60 seng plat bjls 30 lbr Rp 180,310.00
59 sprandel lbr Rp 175,000.00
60 sirtu m3 Rp 1,109,600.00
61 tanah urug m3 Rp 901,550.00
62 triplek tebal 9 mm lbr Rp 624,150.00
63 wiremesh kg Rp 69,350.00
SANITAIR
1 kloset duduk unit Rp 2,635,300.00
2 kloset jongkok unit Rp 1,109,600.00
3 urinoir unit Rp 2,496,600.00
4 shower spray unit Rp 350,000.00
5 toilet paper holder unit Rp 250,000.00
6 floor drain unit Rp 75,000.00
7 tempat sabun unit Rp 150,000.00
8 bak mandi unit Rp 1,317,650.00
9 kran air unit Rp 45,000.00
10 bak cuci stainless unit Rp 936,225.00