Rab Toilet
Rab Toilet
REKAPITULASI
No. URAIAN PEKERJAAN JUMLAH
1 LANTAI 1
A. PEKERJAAN PERSIAPAN Rp 13,535,845.40
B. PEKERJAAN GALIAN DAN PONDASI Rp 104,403,961.37
C. PEKERJAAN BETON Rp 232,723,122.50
D. PEKERJAAN PASANGAN Rp 95,727,607.53
E. PEKERJAAN KUSEN Rp 68,001,619.95
F. PEKERJAAN PLAFOND Rp 57,332,975.48
G. PEKERJAAN PENGECATAN DAN LABURAN Rp 35,602,574.37
H. PEKERJAAN INSTALASI LISTRIK BERIKUT ARMATUR Rp 34,894,035.00
I. PEKERJAAN INS. AIR BERSIH DAN AIR KOTOR Rp 19,035,731.00
J. PEKERJAAN INSTALASI TATA UDARA Rp 53,515,000.00
K. PEKERJAAN INSTALASI TELEPON Rp 1,480,500.00
2 LANTAI 2
A. PEKERJAAN BETON Rp 101,641,963.50
B. PEKERJAAN PASANGAN Rp 187,997,230.71
C. PEKERJAAN KUSEN Rp 57,021,742.25
D. PEKERJAAN PLAFOND Rp 58,395,418.84
E. PEKERJAAN PENGECATAN DAN LABURAN Rp 21,655,775.79
F. PEKERJAAN INST. LISTRIK BERIKUT AMATUR Rp 22,171,792.50
G. PEKERJAAN INS. AIR BERSIH DAN AIR KOTOR Rp 19,155,177.25
H. PEKERJAAN INSTALASI TATA UDARA Rp 69,410,000.00
I.PEKERJAAN ATAP Rp 682,463,759.95
J. PEKERJAAN INSTALASI TELEPON Rp 2,309,500.00
Ir. Mansur
DIREKTUR
1
RENCANA ANGGARAN BIAYA
PROYEK : GEDUNG LABORATORIUM GEOSINTETIK, MEKANIKA TANAH DAN BATUAN
PEKERJAAN : PEMBANGUNAN GEDUNG
LOKASI : BANDUNG
LANTAI 1
A. PEKERJAAN PERSIAPAN
1 Pek.Pengukuran kembali (site) 348 m2 Rp 1,936.00 Rp 673,728.00
2 Pek. Pasangan bouwplank 82 m1 Rp 33,667.70 Rp 2,760,751.40
3 Pembuatan Los kerja/gudang 9 m2 Rp 391,270.00 Rp 3,521,430.00
4 Pek. Kantor direksi 4 m2 Rp 520,008.50 Rp 2,080,034.00
5 Pasang papan nama proyek 1 ls Rp 539,902.00 Rp 539,902.00
6 Pemakaian Air dan listrik untuk kerja 1 ls Rp 3,960,000.00 Rp 3,960,000.00
Rp 13,535,845.40
Rp 104,403,961.37
C. PEKERJAAN BETON
1 Pek. Sloof beton 15/20 9.68 m3 Rp 3,187,250.00 Rp 30,852,580.00
2 Pek. Kolom beton 30/30 11.97 m3 Rp 3,261,500.00 Rp 39,040,155.00
3 Pek. Ringbalk beton 15/25 5.45 m3 Rp 3,187,250.00 Rp 17,370,512.50
4 Pek. Dak Beton t= 15cm 27.75 m3 Rp 3,010,700.00 Rp 83,546,925.00
5 Pek. Tangga beton 2.74 m3 Rp 3,492,500.00 Rp 9,569,450.00
6 Pek. Dinding Core beton t=30cm 15.35 m3 Rp 3,410,000.00 Rp 52,343,500.00
Rp 232,723,122.50
D. PEKERJAAN PASANGAN
1 Pek. Dinding bata 197.1 m2 Rp 78,555.62 Rp 15,483,312.70
2 Pas. Plesteran dinding berikut acian 490.8 m2 Rp 35,367.20 Rp 17,358,221.76
3 Pek. Lantai Floor Harderner 5.94 m2 Rp 381,865.00 Rp 2,268,278.10
4 Pas. Lantai keramik 30 x 30 cm 281.39 m2 Rp 108,110.20 Rp 30,421,129.18
5 Pas. Plin keramik 10/30 250.8 m2 Rp 101,905.10 Rp 25,557,799.08
6 Pas. Lantai keramik KM/WC 20 x 20cm 18.6 m2 Rp 90,250.33 Rp 1,678,656.05
7 Pas. Dinding keramik KM/WC 20 x 20cm 32.8 m2 Rp 90,250.33 Rp 2,960,210.66
Rp 95,727,607.53
E. PEKERJAAN KUSEN
1 Pas. Kusen & Daun Pintu alumunium type P1 1 bh Rp 2,115,850.00 Rp 2,115,850.00
2 Pas. Kusen & Daun Pintu alumunium type P2 2 bh Rp 3,563,147.50 Rp 7,126,295.00
3 Pas. Kusen & Daun Pintu alumunium type P3 9 bh Rp 1,393,122.50 Rp 12,538,102.50
4 Pas. Kusen & Daun Pintu alumunium type P4 1 bh Rp 1,206,947.50 Rp 1,206,947.50
5 Pas. Kusen & Daun Pintu PVC type P5 7 bh Rp 1,074,645.00 Rp 7,522,515.00
6 Pas. Kusen & Daun Pintu alumunium type P6 1 bh Rp 829,259.75 Rp 829,259.75
7 Pas. Kusen & Daun Jendela type J1 20 bh Rp 1,833,132.51 Rp 36,662,650.20
Rp 68,001,619.95
F. PEKERJAAN PLAFOND
1 Pek. Pasang rangka plafond + Gypsum t= 9 mm 306 m2 Rp 173,136.26 Rp 52,979,695.56
2 Pas. List plafond gypsum 253 m' Rp 17,206.64 Rp 4,353,279.92
Rp 57,332,975.48
Rp 35,602,574.37
Rp 34,894,035.00
2
RENCANA ANGGARAN BIAYA
PROYEK : GEDUNG LABORATORIUM GEOSINTETIK, MEKANIKA TANAH DAN BATUAN
PEKERJAAN : PEMBANGUNAN GEDUNG
LOKASI : BANDUNG
Rp 19,035,731.00
Rp 1,480,500.00
LANTAI 2
A. PEKERJAAN BETON
1 Pek. Kolom beton 30/30 11.34 m3 Rp 3,261,500.00 Rp 36,985,410.00
2 Pek. Balok beton 30/30 0.94 m3 Rp 3,187,250.00 Rp 2,983,266.00
3 Pek. Balok beton 15/30 19.35 m3 Rp 3,187,250.00 Rp 61,673,287.50
Rp 101,641,963.50
B. PEKERJAAN PASANGAN
1 Pek. Dinding bata 283.26 m2 Rp 78,555.62 Rp 22,251,664.92
2 Pek. Plesteran dinding berikut acian 566.52 m2 Rp 35,367.20 Rp 20,036,226.14
3 Pas. Lantai keramik 30 x 30 cm 788.57 m2 Rp 108,110.20 Rp 85,252,460.41
4 Pas. Plin keramik 10/30 561.80 m' Rp 101,905.10 Rp 57,250,285.18
5 Pas. Lantai keramik KM/WC 20 x 20cm 18.70 m2 Rp 90,250.33 Rp 1,687,681.08
6 Pas. Dinding keramik KM/WC 20 x 20cm 16.83 m' Rp 90,250.33 Rp 1,518,912.97
Rp 187,997,230.71
C. PEKERJAAN KUSEN
1 Pas. Kusen & Daun Pintu alumunium type P3 5 bh Rp 1,393,122.50 Rp 6,965,612.50
2 Pas. Kusen & Daun Pintu PVC type P5 6 bh Rp 1,074,645.00 Rp 6,447,870.00
3 Pas. Kusen & Daun Pintu alumunium type P6 1 bh Rp 829,259.75 Rp 829,259.75
4 Pas. Kusen & Daun Jendela type J2 20 bh Rp 2,138,950.00 Rp 42,779,000.00
Rp 57,021,742.25
D. PEKERJAAN PLAFOND
1 Pek. Pasang rangka plafond + Gypsum t= 9 mm 318.00 m2 Rp 173,136.26 Rp 55,057,330.68
2 Pas. List plafond gypsum 194.00 m2 Rp 17,206.64 Rp 3,338,088.16
Rp 58,395,418.84
Rp 21,655,775.79
Rp 22,171,792.50
G. PEKERJAAN ATAP
1 Pek. Kuda-kuda Pipa Baja 327.5 m2 Rp 226,325.00 Rp 74,121,437.50
2 Pek. Gording Besi Dia 10 cm 4370.6 kg Rp 24,926.00 Rp 108,941,575.60
3 Pek. Besi Dia 20 cm 5697 kg Rp 29,546.00 Rp 168,323,562.00
4 Pek. Besi Pipa Dia 15 cm 5342 kg Rp 26,466.00 Rp 141,381,372.00
5 Pek. Kolom Besi Dia 30 cm 1941 kg Rp 27,786.00 Rp 53,932,626.00
6 Pek. Plat Besi Tebal = 10 mm 1164 kg Rp 23,595.00 Rp 27,464,580.00
7 Pek. Baut dan Angker 11.78 kg Rp 16,772.25 Rp 197,577.11
8 Penutup atap Zinc Alum 434 m' Rp 167,860.00 Rp 72,851,240.00
9 Pek. Listplank kayu 2/20 82.2 m' Rp 40,751.70 Rp 3,349,789.74
10 Pasang lapisan alumunium foil dan Glass Wool 580 m2 Rp 55,000.00 Rp 31,900,000.00
Rp 682,463,759.95
3
RENCANA ANGGARAN BIAYA
PROYEK : GEDUNG LABORATORIUM GEOSINTETIK, MEKANIKA TANAH DAN BATUAN
PEKERJAAN : PEMBANGUNAN GEDUNG
LOKASI : BANDUNG
Rp 19,155,177.25
Rp 69,410,000.00
Rp 2,309,500.00
4
RENCANA ANGGARAN BIAYA
RENCANA PEMBANGUNAN TAHAP 2
PROYEK : GEDUNG LABORATORIUM GEOSINTETIK, MEKANIKA TANAH DAN BATUAN
PEKERJAAN : PERENCANAAN FURNITURE
LOKASI : BANDUNG
REKAPITULASI
No. URAIAN PEKERJAAN JUMLAH
1 LANTAI 1
A. PEKERJAAN BETON #REF!
B. PEKERJAAN PASANGAN #REF!
C. PEKERJAAN KUSEN Rp 2,115,850.00
D. PEKERJAAN PLAFOND #REF!
E. PEKERJAAN PENGECATAN DAN LABURAN #REF!
2 LANTAI 2
A. PEKERJAAN BETON Rp 101,641,963.50
B. PEKERJAAN PASANGAN Rp 149,561,891.28
C. PEKERJAAN KUSEN Rp 57,021,742.25
D. PEKERJAAN PLAFOND Rp 58,395,418.84
E. PEKERJAAN PENGECATAN DAN LABURAN Rp 21,655,775.79
F. PEKERJAAN INST. LISTRIK BERIKUT AMATUR Rp 22,171,792.50
G. PEKERJAAN INS. AIR BERSIH DAN AIR KOTOR Rp 19,155,177.25
H. PEKERJAAN INSTALASI TATA UDARA Rp 29,265,008.00
I.PEKERJAAN ATAP Rp 682,463,759.95
J. PEKERJAAN INSTALASI TELEPON Rp 2,309,500.00
1 LANTAI 1
A. PEKERJAAN FURNITURE Rp 15,770,000.00
2 LANTAI 2
A. PEKERJAAN FURNITURE Rp 37,215,000.00
Ir. Mansur
DIREKTUR
5
RENCANA ANGGARAN BIAYA
RENCANA PEMBANGUNAN TAHAP 2
PROYEK : DED MASTERPLAN DAN PENGEMBANGAN GEDUNG
PEKERJAAN : PERENCANAAN PEMBANGUNAN LABORATORIUM GEOSINTETIK
LOKASI : BANDUNG
I FISIK
LANTAI 1
A. PEKERJAAN BETON
1 Pek. Tangga Beton 2.74 m3 #REF! #REF!
#REF!
B. PEKERJAAN PASANGAN
1 Pek. Dinding bata #REF! m2 #REF! #REF!
2 Pas. Plesteran dinding berikut acian #REF! m2 #REF! #REF!
3 Pas. Lantai keramik 30 x 30 cm #REF! m2 #REF! #REF!
4 Pas. Plin keramik 10/30 #REF! m2 #REF! #REF!
#REF!
C. PEKERJAAN KUSEN
1 Pas. Kusen & Daun Pintu alumunium type P1 1 bh Rp 2,115,850.00 Rp 2,115,850.00
Rp 2,115,850.00
D. PEKERJAAN PLAFOND
1 Pek. Pasang rangka plafond + Gypsum t= 9 mm #REF! m2 Rp 173,136.26 #REF!
2 Pas. List plafond gypsum #REF! m' Rp 17,206.64 #REF!
#REF!
#REF!
LANTAI 2
A. PEKERJAAN BETON
1 Pek. Kolom beton 30/30 11.34 m3 Rp 3,261,500.00 Rp 36,985,410.00
2 Pek. Balok beton 30/30 0.94 m3 Rp 3,187,250.00 Rp 2,983,266.00
3 Pek. Balok beton 15/30 19.35 m3 Rp 3,187,250.00 Rp 61,673,287.50
Rp 101,641,963.50
B. PEKERJAAN PASANGAN
1 Pek. Dinding bata 283.26 m2 Rp 78,555.62 Rp 22,251,664.92
2 Pek. Plesteran dinding berikut acian 566.52 m2 Rp 35,367.20 Rp 20,036,226.14
3 Pas. Lantai keramik 30 x 30 cm 603.19 m2 Rp 108,110.20 Rp 65,210,991.54
4 Pas. Plin keramik 10/30 381.30 m' Rp 101,905.10 Rp 38,856,414.63
5 Pas. Lantai keramik KM/WC 20 x 20cm 18.70 m2 Rp 90,250.33 Rp 1,687,681.08
6 Pas. Dinding keramik KM/WC 20 x 20cm 16.83 m' Rp 90,250.33 Rp 1,518,912.97
Rp 149,561,891.28
C. PEKERJAAN KUSEN
1 Pas. Kusen & Daun Pintu alumunium type P3 5 bh Rp 1,393,122.50 Rp 6,965,612.50
2 Pas. Kusen & Daun Pintu PVC type P5 6 bh Rp 1,074,645.00 Rp 6,447,870.00
3 Pas. Kusen & Daun Pintu alumunium type P6 1 bh Rp 829,259.75 Rp 829,259.75
4 Pas. Kusen & Daun Jendela type J2 20 bh Rp 2,138,950.00 Rp 42,779,000.00
Rp 57,021,742.25
6
RENCANA ANGGARAN BIAYA
RENCANA PEMBANGUNAN TAHAP 2
PROYEK : DED MASTERPLAN DAN PENGEMBANGAN GEDUNG
PEKERJAAN : PERENCANAAN PEMBANGUNAN LABORATORIUM GEOSINTETIK
LOKASI : BANDUNG
Rp 58,395,418.84
Rp 21,655,775.79
Rp 22,171,792.50
G. PEKERJAAN ATAP
1 Pek. Kuda-kuda Pipa Baja 327.5 m2 Rp 226,325.00 Rp 74,121,437.50
2 Pek. Gording Besi Dia 10 cm 4370.6 kg Rp 24,926.00 Rp 108,941,575.60
3 Pek. Besi Dia 20 cm 5697 kg Rp 29,546.00 Rp 168,323,562.00
4 Pek. Besi Pipa Dia 15 cm 5342 kg Rp 26,466.00 Rp 141,381,372.00
5 Pek. Kolom Besi Dia 30 cm 1941 kg Rp 27,786.00 Rp 53,932,626.00
6 Pek. Plat Besi Tebal = 10 mm 1164 kg Rp 23,595.00 Rp 27,464,580.00
7 Pek. Baut dan Angker 11.78 kg Rp 16,772.25 Rp 197,577.11
8 Penutup atap Zinc Alum 434 m' Rp 167,860.00 Rp 72,851,240.00
9 Pek. Listplank kayu 2/20 82.2 m' Rp 40,751.70 Rp 3,349,789.74
10 Pasang lapisan alumunium foil dan Glass Wool 580 m2 Rp 55,000.00 Rp 31,900,000.00
Rp 682,463,759.95
Rp 19,155,177.25
Rp 29,265,008.00
Rp 2,309,500.00
II FURNITURE
LANTAI 1
1 Meja Laboratorium Stainless Steel ( 1.5 m x 1 m x 0.80 m ) 1.00 unit Rp 2,500,000.00 Rp 2,500,000.00
2 Loker Stainless Steel Warna Abu - abu Tua 12.80 m2 Rp 350,000.00 Rp 4,480,000.00
3 Meja Komputer 4.00 unit Rp 560,000.00 Rp 2,240,000.00
4 Kursi Kantor setara Chitose 8.00 unit Rp 600,000.00 Rp 4,800,000.00
5 Vertical Blind 14.00 m1 Rp 125,000.00 Rp 1,750,000.00
LANTAI 2
1 Meja Laboratorium Stainless Steel ( 1.5 m x 1 m x 0.80 m ) 4.00 unit Rp 2,500,000.00 Rp 10,000,000.00
2 Meja Laboratorium Stainless Steel ( 0.90 m x 0.50 m x 0.80 m ) 1.00 unit Rp 2,000,000.00 Rp 2,000,000.00
3 Meja Komputer 8.00 unit Rp 560,000.00 Rp 4,480,000.00
4 Kursi Kantor setara Chitose 18.00 unit Rp 600,000.00 Rp 10,800,000.00
5 Meja Rapat ( 2.40 m x 1.20 m x 0.80 m ) 1.00 unit Rp 2,500,000.00 Rp 2,500,000.00
6 Papan tulis White Board 1.00 unit Rp 435,000.00 Rp 435,000.00
7 Vertical Blind 56.00 m1 Rp 125,000.00 Rp 7,000,000.00
7
RENCANA ANGGARAN BIAYA
PROYEK : DED MASTERPLAN PUSJATAN
PEKERJAAN : PERENCANAAN FURNITURE GEDUNG LABORATORIUM GEOSINTETIK
LOKASI : BANDUNG
REKAPITULASI TOTAL
No. URAIAN PEKERJAAN JUMLAH
1 LANTAI 1
A. PEKERJAAN FURNITURE Rp 40,845,000.00
2 LANTAI 2
A. PEKERJAAN FURNITURE Rp 37,215,000.00
Ir. Mansur
DIREKTUR
8
RENCANA ANGGARAN BIAYA
PROYEK : DED MASTERPLAN DAN PENGEMBANGAN GEDUNG
PEKERJAAN : PERENCANAAN FURNITURE GEDUNG LABORATORIUM GEOSINTETIK
LOKASI : BANDUNG
LANTAI 1
1 Meja Laboratorium Stainless Steel ( 1.5 m x 1 m x 0.80 m ) 4.00 unit Rp 2,500,000.00 Rp 10,000,000.00
2 Meja Laboratorium Stainless Steel ( 0.90 m x 0.50 m x 0.80 m ) 1.00 unit Rp 2,000,000.00 Rp 2,000,000.00
3 Loker Stainless Steel Warna Abu - abu Tua 12.80 m2 Rp 350,000.00 Rp 4,480,000.00
4 Meja Komputer 8.00 unit Rp 560,000.00 Rp 4,480,000.00
5 Kursi Kantor setara Chitose 18.00 unit Rp 600,000.00 Rp 10,800,000.00
6 Meja Rapat ( 2.40 m x 1.20 m x 0.80 m ) 1.00 unit Rp 2,650,000.00 Rp 2,650,000.00
7 Papan tulis White Board 1.00 unit Rp 435,000.00 Rp 435,000.00
8 Vertical Blind 48.00 m1 Rp 125,000.00 Rp 6,000,000.00
LANTAI 2
1 Meja Laboratorium Stainless Steel ( 1.5 m x 1 m x 0.80 m ) 4.00 unit Rp 2,500,000.00 Rp 10,000,000.00
2 Meja Laboratorium Stainless Steel ( 0.90 m x 0.50 m x 0.80 m ) 1.00 unit Rp 2,000,000.00 Rp 2,000,000.00
3 Meja Komputer 8.00 unit Rp 560,000.00 Rp 4,480,000.00
4 Kursi Kantor setara Chitose 18.00 unit Rp 600,000.00 Rp 10,800,000.00
5 Meja Rapat ( 2.40 m x 1.20 m x 0.80 m ) 1.00 unit Rp 2,500,000.00 Rp 2,500,000.00
6 Papan tulis White Board 1.00 unit Rp 435,000.00 Rp 435,000.00
7 Vertical Blind 56.00 m1 Rp 125,000.00 Rp 7,000,000.00
9
RENCANA ANGGARAN BIAYA
PROYEK : DED MASTERPLAN PUSJATAN
PEKERJAAN : PERENCANAAN FURNITURE GEDUNG LABORATORIUM GEOSINTETIK
LOKASI : BANDUNG
REKAPITULASI TAHAP 1
No. URAIAN PEKERJAAN JUMLAH
1 LANTAI 1
A. PEKERJAAN FURNITURE Rp 24,680,000.00
Ir. Mansur
DIREKTUR
10
RENCANA ANGGARAN BIAYA
PROYEK : DED MASTERPLAN DAN PENGEMBANGAN GEDUNG
PEKERJAAN : PERENCANAAN FURNITURE GEDUNG LABORATORIUM GEOSINTETIK
LOKASI : BANDUNG
LANTAI 1
1 Meja Laboratorium Stainless Steel ( 1.5 m x 1 m x 0.80 m ) 4.00 unit Rp 2,500,000.00 Rp 10,000,000.00
2 Loker Stainless Steel Warna Abu - abu Tua 12.80 m2 Rp 350,000.00 Rp 4,480,000.00
3 Kursi Kantor setara Chitose 17.00 unit Rp 600,000.00 Rp 10,200,000.00
11
DAFTAR HARGA SATUAN DASAR UPAH
Harga
No. Uraian Satuan
( Rp )
(1) (2) (3) (4)
I. Upah
C BAHAN LOGAM
1 Besi baja beton U-32, ulir kg 11,000.00
2 Besi baja beton U-39 ulir kg 13,000.00
3 Besi baja beton U-42 ulir kg 16,000.00
4 Besi baja beton U-24 polos kg 9,500.00
5 Besi baja beton U-32 polos kg 10,000.00
6 Kuda-kuda rangka Hollow Cremona m2 450,000.00
Besi polos d. 16 mm kg 9,463.16
Plat Strip 5.50 mm kg 11,520.82
7 Besi profil siku, rata-rata ex DN - SII kg 13,000.00
8 Besi profil siku, rata-rata ex Luar Negeri kg 13,000.00
9 Besi profil IWF, rata-rata ex DN-SII kg 13,000.00
10 Besi profil IWF, rata-rata ex Jepang kg 13,000.00
11 Besi kanal "C" Lip Chanel kg 13,000.00
12 Besi Hollow 40 x 40/metal furing btg 105,000.00
18 Seng BJLS 30, lebar 60 cm (1 rol = 50 m') m' 38,500.00
19 Seng BJLS 30, lebar 90 cm (1 rol = 50 m') m' 52,250.00
20 Seng plat BJLS 25 uk. 90 x 180 cm lbr 46,750.00
21 Seng plat BJLS 230 uk. 90 x 180 cm lbr 60,500.00
22 Seng gelombang BJLS 25 uk. 0.90 x 1.80 cm lbr 39,320.00
23 Seng gelombang BJLS 30 uk. 0.90 x 1.80 cm lbr 48,400.00
13 Seng BJLS 30, lebar 90 cm (1 rol = 50 m') m' 45,000.00
14 Kawat beton kg 30,000.00
15 Plat besi tipis 0,5 mm kg 9,775.00
16 Besi Railling Hollow 20 x 40 Finishing Powder Coating m' 65,000.00
17 Besi Railling Hollow 20 x 60 Finishing Powder Coating m' 85,000.00
Jumlah
NO Uraian Jenis Material Sat
Harga Bahan
Rp.
1 2 3 4
18 Kisi-kisi Hollow Alumunium m2 450,000.00
19 Paku triplek kg 18,000.00
20 Paku 1 s/d 3 cm kg 29,000.00
21 Paku 4 s/d 7 cm kg 17,500.00
22 Paku uk. 8 s/d 12 cm kg 17,500.00
23 Paku sekrup dus 8,250.00
24 Paku Khusus bh 1,500.00
30 Almunium profil uk. 4"-4.00 m (bahan kusen) ex. YKK Warna btg 600,000.00
34 Kusen Alumunium ex YKK Fin Duco Warna Coklat Tua m' 145,000.00
35 Daun Jendela Alumunium Natural (Tanpa Kaca) M' 60,000.00
36 Daun Jendela Alumunium Warna (Tanpa Kaca) M' 70,000.00
37 Daun Pintu Alumunium Natural (Tanpa Kaca) M' 65,000.00
38 Daun Pintu Alumunium Warna (Tanpa Kaca) M' 75,000.00
39 Handle Alumunium (Tarikan Pintu Alumunium) Psg 55,000.00
40 Kait angin Alumunium buah 65,000.00
41 Hurup Timbul Stainless cm 9,000.00
42 Alumunium Compossite Panel Terpasang Rangka Hollow m2 475,000.00
43 Kisi-kisi Hollow Alumunium m2 400,000.00
44 Alumunium Composite Panel (Alucobond) 1250 x 4500 t : 0,3 mm m2 342,000.00
45 Alumunium Composite Panel (Alcolux) m2 313,500.00
46 Alumunium Composite Panel (Alcopla) m2 285,000.00
47 Alumunium Composite Panel (Alucopan) m2 200,000.00
48 Alumunium Composite Panel (Seven) m2 226,100.00
49 Alumunium Composite Panel (Aluwell) m2 226,100.00
H. BAHAN FINISHING
1 Wall paper biasa, uk. 0.50 x 10.00 m rol 102,850.00
2 Wall paper corak, uk. 0.50 x 10.00 m rol 242,000.00
3 Cat dasar Alkali ltr 21,275.00
4 Cat dasar tembok , Indo 9000 Sealer Water Base kg 21,170.00
5 Cat dasar kayu ltr 15,120.00
6 Cat tembok Vinilek gln 75,000.00
7 Cat tembok Jotun Interior, warna tua gln 237,000.00
8 Cat tembok Jotun Exterior, warna Stand gln 350,000.00
9 Cat Tembok Jotun Khusus Plafond gln 125,000.00
10 Cat kayu/besi Avian kg 39,600.00
11 Cat Duco kg 181,500.00
12 Cat Brom kg 59,180.00
13 Cay marka kg 41,160.00
14 Cat marka dinding / spotlight kg 107,030.00
15 Cat primer kg 200,970.00
16 Upoxy Primer - Danapaint m2 45,000.00
17 Hardener - Danapaint ltr 35,000.00
18 Meni kayu/besi Bola mas kg 22,000.00
19 Soda coustic kg 8,250.00
20 Cat zinchromate Bola mas kg 54,690.00
21 Plint coat kg 41,030.00
22 Dempul tembok (plamuur) kg 19,000.00
23 Dempul kayu kg 20,570.00
24 Dempul plitur kg 32,000.00
25 Dempul halus / impra (Wood filler) kg 35,000.00
26 Dempul lilin kg 7,860.00
27 Dempul plastik kg 21,170.00
28 Minyak pelebur cat (soda api) kg 38,500.00
29 Hotmix AC / W C ton 875,000.00
30 Terpentin (minyak cat) kg 9,775.00
31 Oker putih kg 27,000.00
32 Oker warna kg 30,000.00
33 Batu Apung Gosok kg 25,000.00
34 Oten (pewarna plituran) bks 8,250.00
35 Melamik kg 46,200.00
36 Sirlak ex India kg 95,000.00
37 Spirtus ltr 15,000.00
38 Plitur jadi DX ltr 42,350.00
39 Plitur jadi Pinogard ltr 51,750.00
40 Tinner ltr 17,290.00
41 Kuas 3" bh 12,500.00
42 Kuas 4" bh 12,650.00
43 Rol cat bh 27,500.00
44 Kape tembok bh 11,000.00
45 Kape kayu bh 10,450.00
46 Ampelas lbr 2,840.00
47 Teak Oil ltr 24,750.00
48 Vernis Batu ltr 68,000.00
49 Minyak bekisting ltr 16,500.00
50 Waterproping Emulsion kg 47,000.00
51 Waterproping Membrance m' 78,650.00
Jumlah
NO Uraian Jenis Material Sat
Harga Bahan
Rp.
1 2 3 4
52 Karbit m' 13,750.00
L BAHAN TAMBAHAN
1 Rumput Jepang m2 16,750.00
2 Rumput Gajah Mini m2 30,000.00
3 Tanaman Euphorbia kuning phn 25,000.00
4 Tanaman Pohon Dadap Merah t = 200 - 300 cm phn 250,000.00
5 Tanaman Pohon Tabebuya Kuning t = 200 - 300 cm phn 250,000.00
6 Tanaman Pohon Katapang kencana t = 200 - 300 cm phn 200,000.00
7 Tanaman Pohon berbatag keras sejenis mahoni / trembesi t = 200 - 300 cm phn 450,000.00
8 Tanaman Cemara Udang t = 100 - 150 cm phn 1,500,000.00
9 Kanstin 15.35.60 bh 60,000.00
10 Buis U dia. 20cm bh 24,000.00
11 Pupuk kg 8,000.00
12 Batu Alam ndesit Bakar m2 175,000.00
13 Batu Bulat Andesit ukuran diameter 60 cm bh 1,600,000.00
14 Tanaman Lee Kwan Yew bh 5,000.00
15 Tanaman Peace Lily bh 12,500.00
16 Pohon Mahoni t=50 - 100 cm bh 400,000.00
17 Pohon Katapang Kencana t = 150 - 200 cm bh 250,000.00
18 Pohon heloconia bh 7,000.00
19 Pohon Tabebuya bh 250,000.00
20
HARGA SATUAN Jumlah Harga JUMLAH HARGA
URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH UPAH BAHAN Bahan+Upah
(Rp.) (Rp.) (Rp.) (Rp.)
2 3 4 5 6=(4 X 5) 7=(4 X 5) 8=(6 + 7)
1 M2 PEMB. DIREKSI KEET DENGAN LANTAI PLESTER (SNI. Edisi Rev. 2005)
Bahan :
Kayu dolken dia 8 - 10/400 cm Btg 1.2500 24,000.00 30,000.00
Kayu papan Albasia M3 0.1800 1,100,000.00 198,000.00
Paku biasa 2" - 5" Kg 0.8500 17,500.00 14,875.00
Besi strip Kg 1.1000 9,775.00 10,752.50
Semen Portland Kg 35.0000 165.00 5,775.00
Pasir pasang m3 0.1500 220,000.00 33,000.00
Pasir beton m3 0.1000 230,000.00 23,000.00
Koral beton m3 0.1500 130,000.00 19,500.00
Bata merah m3 30.0000 800.00 24,000.00
Seng plat , BLJS 25 kg 0.2500 46,750.00 11,687.50
Jendela nako lbr 2.0000 24,750.00 49,500.00
Kaca polos lbr 0.0800 66,000.00 5,280.00
Kunci tanam zak 0.1500 82,500.00 12,375.00
Polywood 4 mm m3 0.0600 57,500.00 3,450.00
Tenaga Kerja :
Pekerja Oh 0.1000 100,000.00 10,000.00
Tukang Kayu Oh 0.5000 140,000.00 70,000.00
Tukang batu Oh 1.0000 140,000.00 140,000.00
Kepala Tukang Oh 0.3000 150,000.00 45,000.00
Mandor Oh 0.0500 175,000.00 8,750.00
Jumlah 273,750.00 441,195.00 714,945.00
Keuntungan maksimal 10% 71,494.50
Jumlah 786,439.50
Dibulatkan 786,430.00
1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC ; 4 PS. (SNI EDISI REV. 2005)
Bahan :
Bata merah kelas 1 Bh 70.000 800.00 56,000.00
Semen portland Kg 11.500 1,260.00 14,490.00
Pasir pasang m3 0.043 220,000.00 9,460.00
Tenaga kerja:
Pekerja Oh 0.3200 100,000.00 32,000.00
Tukang Oh 0.1000 140,000.00 14,000.00
HARGA SATUAN Jumlah Harga JUMLAH HARGA
URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH UPAH BAHAN Bahan+Upah
(Rp.) (Rp.) (Rp.) (Rp.)
2 3 4 5 6=(4 X 5) 7=(4 X 5) 8=(6 + 7)
Kepala Tukang Oh 0.0100 150,000.00 1,500.00
Mandor Oh 0.0150 175,000.00 2,625.00
Jumlah 50,125.00 79,950.00 130,075.00
Keuntungan maksimal 10% 13,007.50
Jumlah 143,082.50
Dibulatkan 143,080.00
1 M3 ADUKAN BETON TUMBUK CAMP. 1 PC: 3 PS: 5 KR (SNI EDISI REV. 2005)
Bahan :
Semen portland kg 218.0000 1,260.00 274,680.00
Pasir beton m3 0.5200 230,000.00 119,600.00
Koral beton m3 0.8700 130,000.00 113,100.00
Tenaga Kerja:
Pekerja Oh 1.6500 100,000.00 165,000.00
Tukang Oh 0.2500 140,000.00 35,000.00
Kepala Tukang Oh 0.0250 150,000.00 3,750.00
Mandor Oh 0.0800 175,000.00 14,000.00
Jumlah 217,750.00 507,380.00 725,130.00
Keuntungan maksimal 10% 72,513.00
Jumlah 797,643.00
Dibulatkan 797,640.00
1 M3 BETON MUTU F¹C=19,3 MPA (K-225), SLUMP (12±2) CM, W/C = 0,58
Bahan :
PC kg 371.0000 1,260.00 467,460.00
PB kg 698.0000 164.29 114,671.43
KR kg 1,047.0000 170.00 177,990.00
Air ltr
Tenaga Kerja:
Pekerja Oh 1.6500 100,000.00 165,000.00
Tukang Oh 0.2750 140,000.00 38,500.00
Kepala Tukang Oh 0.0280 150,000.00 4,200.00
Mandor Oh 0.0830 175,000.00 14,525.00
Jumlah 222,225.00 760,121.43 982,346.43
Keuntungan maksimal 10% 98,234.64
Jumlah 1,080,581.07
Dibulatkan 1,080,580.00
1 UNIT KUSEN PINTU ALUMUNIUM FINISHING POWDER COATING LENGKAP AKSESORIS TYPE P1
Bahan Dan Alat :
Kusen Pintu Alumunium Warna Cokelat m' 8.30 100,000.00 830,000.00
Daun Pintu Doble Teakwood bh 1.00 1,250,000.00 1,250,000.00
Kaca polos 5 mm m2 0.45 95,000.00 42,750.00
Lockcase FB 8535-40/60 US32D (Pintu Single) bh 1.00 95,000.00 95,000.00
Double Cylinder DC FB1001-60 US14 bh 1.00 80,000.00 80,000.00
Lever Handle HRE.85.13FB US32D ps 1.00 150,000.00 150,000.00
Engsel Pintu SEL FB09 5x3x3 4BB US32D ps 1.50 50,000.00 75,000.00
Door Stop STP-FB016 US26 ps 1.00 30,000.00 30,000.00
Tenaga Kerja :
Biaya pemasangan LS 1.00 178,692.50 178,692.50
Jumlah 178,692.50 2,552,750.00 2,731,442.50
Keuntungan maksimal 10% 273,144.25
Jumlah 3,004,586.75
Dibulatkan 3,004,580.00
1 UNIT KUSEN & DAUN PINTU ALUMUNIUM FINISHING POWDER COATING LENGKAP AKSESORIS TYPE P2
Bahan Dan Alat :
Kusen Pintu Alumunium Warna Cokelat m' 5.20 100,000.00 520,000.00
Daun pintu alumunium bh 1.00 1,250,000.00 1,250,000.00
Lockcase FB 8535-40/60 US32D (Pintu Single) bh 1.00 95,000.00
Double Cylinder DC FB1001-60 US14 bh 1.00 80,000.00
Lever Handle HRE.85.13FB US32D ps 1.00 150,000.00
Engsel Pintu SEL FB09 5x3x3 4BB US32D ps 2.00 50,000.00 100,000.00
Door Stop STP-FB016 US26 PS 1.00 30,000.00
Tenaga Kerja :
Biaya pemasangan LS 1.00 187,000.00 187,000.00
Jumlah 187,000.00 1,870,000.00 2,057,000.00
Keuntungan maksimal 10% 205,700.00
Jumlah 2,262,700.00
Dibulatkan 2,262,700.00
1 UNIT KUSEN JENDELA ALUMUNIUM FINISHING POWDER COATING LENGKAP AKSESORIS TYPE J1
Bahan Dan Alat :
Kusen Jendela Alumunium Warna Cokelat m' 32.20 100,000.00 3,220,000.00
Rangka Daun Jendela Kaca Kamper Samarinda O bh 4.00 500,000.00 2,000,000.00
Kaca polos 5 mm m2 4.58 95,000.00 434,720.00
Engsel Pintu SEL FB09 5x3x3 4BB US32D ps 4.00 50,000.00 200,000.00
Tenaga Kerja :
Biaya pemasangan LS 1.00 409,830.40 409,830.40
Jumlah 409,830.40 5,854,720.00 6,264,550.40
Keuntungan maksimal 10% 626,455.04
Jumlah 6,891,005.44
Dibulatkan 6,891,000.00
HARGA SATUAN Jumlah Harga JUMLAH HARGA
URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH UPAH BAHAN Bahan+Upah
(Rp.) (Rp.) (Rp.) (Rp.)
2 3 4 5 6=(4 X 5) 7=(4 X 5) 8=(6 + 7)
1 UNIT KUSEN JENDELA ALUMUNIUM FINISHING POWDER COATING LENGKAP AKSESORIS TYPE J2
Bahan Dan Alat :
Kusen Jendela Alumunium Warna Cokelat m' 4.00 100,000.00 400,000.00
Rangka Daun Jendela + Kaca bh 1.00 500,000.00 500,000.00
Kaca polos 5 mm m2 0.58 95,000.00
Engsel Pintu SEL FB09 5x3x3 4BB US32D ps 2.00 50,000.00 100,000.00
Tenaga Kerja :
Biaya pemasangan LS 1.00 70,000.00 70,000.00
Jumlah 70,000.00 1,000,000.00 1,070,000.00
Keuntungan maksimal 10% 107,000.00
Jumlah 1,177,000.00
Dibulatkan 1,177,000.00
1 UNIT KUSEN VENTILASI ALUMUNIUM FINISHING POWDER COATING LENGKAP AKSESORIS TYPE J3
Bahan Dan Alat :
Kusen Jendela Alumunium Warna Cokelat m' 2.26 100,000.00 226,000.00
Kaca Lokal 5 mm m2 0.27 95,000.00 25,650.00
Tenaga Kerja :
Biaya pemasangan LS 1.00 17,615.50 17,615.50
Jumlah 17,615.50 251,650.00 269,265.50
Keuntungan maksimal 10% 26,926.55
Jumlah 296,192.05
Dibulatkan 296,190.00
MEMASANG 1 BH, KRAN AIR DIA 1/2" ATAU 3/4" (SNI EDISI REV. 2005)
Bahan :
Kran air San-Ei Dia 1/2 " bh 1.0000 90,000.00 90,000.00
Seal tape bh 0.0250 2,500.00 62.50
Tenaga kerja:
Pekerja Oh 0.0100 100,000.00 1,000.00
Tukang Oh 0.4000 140,000.00 56,000.00
HARGA SATUAN Jumlah Harga JUMLAH HARGA
URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH UPAH BAHAN Bahan+Upah
(Rp.) (Rp.) (Rp.) (Rp.)
2 3 4 5 6=(4 X 5) 7=(4 X 5) 8=(6 + 7)
Kepala tukang Oh 0.0100 150,000.00 1,500.00
Mandor Oh 0.0050 175,000.00 875.00
Jumlah 59,375.00 90,062.50 149,437.50
Keuntungan maksimal 10% 14,943.75
Jumlah 164,381.25
Dibulatkan 164,380.00
1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI (SNI EDISI REV. 2005)
Bahan :
Meni besi kg 0.1000 22,000.00 2,200.00
Kuas bh 0.0100 12,650.00 126.50
Tenaga kerja:
Pekerja Oh 0.0200 100,000.00 2,000.00
Tukang Oh 0.2000 140,000.00 28,000.00
Kepala tukang Oh 0.0200 150,000.00 3,000.00
Mandor Oh 0.0100 175,000.00 1,750.00
Jumlah 34,750.00 2,326.50 37,076.50
Keuntungan maksimal 10% 3,707.65
Jumlah 40,784.15
Dibulatkan 40,780.00
Tenaga Kerja :
Pekerja Org 0.1500 100,000.00 15,000.00
Tukang Org 0.2500 140,000.00 35,000.00
Kepala Tukang Org 0.0250 150,000.00 3,750.00
Mandor Org 0.0100 175,000.00 1,750.00
Jumlah 55,500.00 100,000.00 155,500.00
Keuntungan maksimal 10% 15,550.00
Jumlah 171,050.00
Dibulatkan 171,050.00
Tenaga Kerja :
Pekerja Org 0.1000 100,000.00 10,000.00
Tukang Org 0.0500 140,000.00 7,000.00
Kepala Tukang Org 0.0050 150,000.00 750.00
Mandor Org 0.0050 175,000.00 875.00
Jumlah 18,625.00 56,660.00 75,285.00
Keuntungan maksimal 10% 7,528.50
Jumlah 82,813.50
Dibulatkan 82,810.00
Tenaga Kerja :
Pekerja Org 0.0200 100,000.00 2,000.00
Tukang Org 0.0630 140,000.00 8,820.00
Kepala Tukang Org 0.0063 150,000.00 945.00
Mandor Org 0.0030 175,000.00 525.00
Jumlah 12,290.00 29,265.00 41,555.00
Keuntungan maksimal 10% 4,155.50
Jumlah 45,710.50
Dibulatkan 45,710.00
Tenaga Kerja :
biasa pasang % 0.1500 387,600.00 58,140.00
Jumlah 58,140.00 387,600.00 445,740.00
Keuntungan maksimal 10% 44,574.00
HARGA SATUAN Jumlah Harga JUMLAH HARGA
URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH UPAH BAHAN Bahan+Upah
(Rp.) (Rp.) (Rp.) (Rp.)
2 3 4 5 6=(4 X 5) 7=(4 X 5) 8=(6 + 7)
Jumlah 490,314.00
Dibulatkan 490,310.00
Tenaga Kerja :
Pekerja Org 0.20 100,000.00 20,000.00
Tukang Org 0.10 140,000.00 14,000.00
Kepala Tukang Org 0.01 150,000.00 1,500.00
Mandor Org 0.01 175,000.00 1,750.00
Jumlah 37,250.00 4,095.00 41,345.00
Keuntungan maksimal 10% 4,134.50
Jumlah 45,479.50
Dibulatkan 45,470.00
Tenaga Kerja :
Pekerja OH 1.2000 100,000.00 120,000.00
Tukang batu OH 0.2000 140,000.00 28,000.00
Kepala tukang OH 0.0200 150,000.00 3,000.00
Mandor OH 0.0600 175,000.00 10,500.00
Jumlah 161,500.00 539,673.96 701,173.96
Keuntungan maksimal 10% 70,117.40
Jumlah 771,291.35
Dibulatkan 771,290.00
Tenaga Kerja :
Pekerja OH 1.6500 100,000.00 165,000.00
Tukang batu OH 0.2750 140,000.00 38,500.00
Kepala tukang OH 0.0280 150,000.00 4,200.00
Mandor OH 0.0830 175,000.00 14,525.00
Jumlah 222,225.00 768,822.00 991,047.00
Keuntungan maksimal 10% 99,104.70
Jumlah 1,090,151.70
Dibulatkan 1,090,150.00
Tenaga Kerja :
Biaya Pasang ls 0.0150 198,000,000.00 2,970,000.00
Jumlah 2,970,000.00 198,000,000.00 200,970,000.00
Keuntungan maksimal 10% 20,097,000.00
Jumlah 221,067,000.00
Dibulatkan 221,060,000.00
Tenaga Kerja :
Biaya Pasang ls 0.0150 27,500,000.00 412,500.00
Jumlah 412,500.00 27,500,000.00 27,912,500.00
Keuntungan maksimal 10% 2,791,250.00
Jumlah 30,703,750.00
Dibulatkan 30,700,000.00
HARGA SATUAN Jumlah Harga JUMLAH HARGA
URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH UPAH BAHAN Bahan+Upah
(Rp.) (Rp.) (Rp.) (Rp.)
2 3 4 5 6=(4 X 5) 7=(4 X 5) 8=(6 + 7)
Tenaga Kerja :
Biaya Pasang ls 0.1500 4,950,000.00 742,500.00
Jumlah 742,500.00 4,950,000.00 5,692,500.00
Keuntungan maksimal 10% 569,250.00
Jumlah 6,261,750.00
Dibulatkan 6,261,750.00
PEKERJAAN SEESAW
Bahan :
Seesaw unit 1.0000 8,250,000.00 8,250,000.00
Tenaga Kerja :
Biaya Pasang ls 0.1500 8,250,000.00 1,237,500.00
Jumlah 1,237,500.00 8,250,000.00 9,487,500.00
Keuntungan maksimal 10% 948,750.00
Jumlah 10,436,250.00
Dibulatkan 10,436,250.00
PEKERJAAN 1 KG BESI
Bahan :
Besi d. 10 mm kg 1.1500 9,391.89 10,800.68
Tenaga Kerja :
Pekerja OH 0.0600 100,000.00 6,000.00
Tukang las kontruksi OH 0.0600 140,000.00 8,400.00
Kepala tukang OH 0.0060 150,000.00 900.00
Mandor OH 0.0030 175,000.00 525.00
Jumlah 15,825.00 10,800.68 26,625.68
Dibulatkan 26,620.00
PEKERJAAN 10 CM PENGELASAN
Bahan :
Kawat Las kg 0.4000 39,500.00 15,800.00
Solar ltr 0.3000 10,200.00 3,060.00
Minyak Las ltr 0.4000 21,000.00 8,400.00
Peralatan :
Peralatan ls 0.1250 8,178.00 1,022.25
Tenaga Kerja :
Pekerja OH 0.0400 100,000.00 4,000.00
Tukang Batu OH 0.0200 140,000.00 2,800.00
Kepala Tukang OH 0.0020 150,000.00 300.00
Mandor OH 0.0020 175,000.00 350.00
Jumlah 28,282.25 7,450.00 35,732.25
Keuntungan 10% 3,573.23
Jumlah Total 39,305.48
39,300.00
3,930.00
Bahan :
semen portland kg 276.0000 1,260.00 347,760.00
pasir beton kg 828.0000 164.29 136,028.57
kerikil mak 3cm kg 1,012.0000 116.67 118,066.67
air ltr 215.0000 0.00
Tenaga Kerja :
Pekerja OH 1.6500 100,000.00 165,000.00
HARGA SATUAN Jumlah Harga JUMLAH HARGA
URAIAN JENIS PEKERJAAN SAT KOEFF BAHAN/UPAH UPAH BAHAN Bahan+Upah
(Rp.) (Rp.) (Rp.) (Rp.)
2 3 4 5 6=(4 X 5) 7=(4 X 5) 8=(6 + 7)
Tukang Batu OH 0.2750 140,000.00 38,500.00
Kepala Tukang OH 0.0280 150,000.00 4,200.00
Mandor OH 0.0830 175,000.00 14,525.00
Jumlah 601,855.24 222,225.00 824,080.24
Keuntungan 10% 82,408.02
Jumlah Total 906,488.26
1 M' PASANG BESI PIPA medium t=4.85 DIA 6" fin. Cat
Bahan :
Besi Pipa medium, t=4.85, 6' m' 1.0500 298,333.33 313,250.00
perlengkapan, (las, cat besi) % 0.3500 313,250.00 109,637.50
Tenaga kerja:
Pekerja Oh 0.1350 100,000.00 13,500.00
Tukang Oh 0.2250 140,000.00 31,500.00
Kepala tukang Oh 0.0230 150,000.00 3,450.00
Mandor Oh 0.0070 175,000.00 1,225.00
Jumlah 49,675.00 422,887.50 472,562.50
Keuntungan maksimal 10% 47,256.25
Jumlah 519,818.75
Dibulatkan 519,810.00
1 M' PASANG BESI PIPA medium t=3.6 DIA 2.5" fin. Cat
Bahan :
Besi Pipa medium, t=4.85, 6' m' 1.1000 100,000.00 110,000.00
perlengkapan, (las, cat besi) % 0.3500 110,000.00 38,500.00
Tenaga kerja:
Pekerja Oh 0.1080 100,000.00 10,800.00
Tukang Oh 0.1800 140,000.00 25,200.00
Kepala tukang Oh 0.0180 150,000.00 2,700.00
Mandor Oh 0.0050 175,000.00 875.00
Jumlah 39,575.00 148,500.00 188,075.00
Keuntungan maksimal 10% 18,807.50
Jumlah 206,882.50
Dibulatkan 206,880.00
1 M' PASANG BESI PIPA medium t=3.6 DIA 2" fin. Cat
Bahan :
Besi Pipa medium, t=4.85, 6' m' 1.1000 78,333.33 86,166.67
perlengkapan, (las, cat besi) % 0.3500 86,166.67 30,158.33
Tenaga kerja:
Pekerja Oh 0.1080 100,000.00 10,800.00
Tukang Oh 0.1800 140,000.00 25,200.00
Kepala tukang Oh 0.0180 150,000.00 2,700.00
Mandor Oh 0.0050 175,000.00 875.00
Jumlah 39,575.00 116,325.00 155,900.00
Keuntungan maksimal 10% 15,590.00
Jumlah 171,490.00
Dibulatkan 171,490.00
1 KG PASANG ANGKUR, BESTPLAT,TRAKSTANG DAN BAUT (SNI EDISI REV. 2005)
Bahan :
Angkur, Plat Dan Baut kg 1.1000 10,858.59 11,944.44
Peralatan (Oksigen. Solar. Elpiji. kawat las. dll) Lot 0.1250 30,000.00 3,750.00
Tenaga kerja:
Pekerja Oh 0.0060 100,000.00 600.00
Tukang Oh 0.0600 140,000.00 8,400.00
Kepala tukang Oh 0.0060 150,000.00 900.00
Mandor Oh 0.0030 175,000.00 525.00
Jumlah 10,425.00 15,694.44 26,119.44
Keuntungan maksimal 10% 2,611.94
Jumlah 28,731.39
Dibulatkan 28,730.00
REKAPITULASI ANALISA HARGA SATUAN
(1) (2)
A 0001 1 M' PAS. BOUWPLANK & PENGUKURAN (SNI. Edisi Rev. 2005)
B 0001 1 M2 PEMBERSIHAN, PEMBERSIHAN RUMPUT DAN PERATAAN TANAH (SNI. Edisi Rev. 2005)
A 0002 1 M ' PAGAR SEMENTARA DARI SENG GELOMBANG, T = 2 M (SNI. Edisi Rev 2005)
A 0003 1 M2 PEMB. DIREKSI KEET DENGAN LANTAI PLESTER (SNI. Edisi Rev. 2005)
A 0004 1 M2 PEMB. GUDANG BAHAN & ALAT (SNI. Edisi Rev. 2005)
A 0005 1 UNIT PEK. PAPAN NAMA PROYEK
A 0007 1 LS PEK. AIR KERJA DAN LISTRIK KERJA
PEKERJAAN 1 M3 BONGKARAN BETON
PEKERJAAN 1 M3 BONGKARAN PONDASI BATU BELAH
PEKERJAAN 1 M2 BONGKARAN DINDING BATA
B 0003 1 M3 GALIAN TANAH BIASA KEDALAMAN 1 M' (SNI. Edisi Rev. 2005)
B 0004 1 M3 GALIAN TANAH BIASA KEDALAMAN 3 M' (SNI Edisi Rev. 2005)
B 0005 1 M3 GALIAN TANAH DENGAN ALAT BERAT
B 0006 1 M3 URUGAN TANAH KEMBALI (SNI Edisi Rev. 2005)
B 0007 1 M3 PEK. URUGAN TANAH DARI LUAR SITE
B 0008 1 M3 PEK. URUGAN TANAH GEMBUR
1 M3 PEK. URUGAN TANAH MERAH
B 00010 1 M3 URUGAN PASIR (SNI EDISI REV. 2005)
B 0011 1 M3 URUGAN SIRTU (SNI EDISI REV. 2005)
C 0001 1 M3 PASANGAN BATU KOSONG /AANSTAMPING (SNI EDISI REV. 2005)
C 0002 1 M3 PASANGAN PONDASI BATU BELAH, 1 PC : 5 PS (SNI EDISI REV. 2005)
D 0001 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC ; 2 PS. (SNI EDISI REV. 2005)
D 0002 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC ; 4 PS. (SNI EDISI REV. 2005)
D 0003 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC ; 4 PS. (SNI EDISI REV. 2005)
D 0005 1 M2 PASANGAN GEOTEXTILE
E 0001 1 M2 PLESTERAN DINDING 1 PC ; 2 PS TEB. 15 MM (SNI EDISI REV. 2005)
E 0002 1 M2 PLESTERAN DINDING 1 PC ; 4 PS TEB. 15 MM (SNI EDISI REV. 2005)
E 0003 1 M' PLESTERAN BETON 1PC : 3 PS TEB. 70 MM (PROFIL BETON)
E 0004 1 M' PLESTERAN PRIME MORTAR TEBAL 1 CM + ACIAN
N 0008 PEK. ACIAN
PEKERJAAN 1M2 ACIAN
N 0009 1 M2 ACIAN ROLL
L 0004 1 M2 PASANGAN DINDING BATU ALAM
E 0005 1 M2 WATERPROOFING LIQUID/COATING
PEKERJAAN 1 M3 BETON K-100
PEKERJAAN 1 M3 BETON K-175
PEKERJAAN 1M3 PONDASI TELAPAK
F 0001 1 M3 ADUKAN BETON TUMBUK CAMP. 1 PC: 3 PS: 5 KR (SNI EDISI REV. 2005)
F 0002 1 KG TULANGAN BETON DENGAN BESI POLOS/ULIR (SNI EDISI REV. 2005)
F 0003 1 M3 ADUKAN BETON K.250
F 0012 1 M3 BETON BERTULANG SL1 (SLOOF) UK. 150X200 MM ADUKAN K.250
F 0021 1 M3 BETON BERTULANG RINGBALK RBL1 UK. 150x200 MM ADUKAN K.300
F 0023 1 M3 COR PLAT KANOPI + MEJA PANTRY TEBAL 10 CM ADUKAN K.225
F 0007 1 M2 PASANG BEKISTING UNTUK BALOK (SNI EDISI REV.2005)
F 0008 1 M2 PASANG BEKISTING UNTUK LANTAI (SNI EDISI REV.2005)
F 0009 1 M2 PASANG BEKISTING UNTUK TANGGA (SNI EDISI REV.2005)
0 1 M2 PEK. PAS. STOOT WERK
F 0012 1 M3 BETON BERTULANG SL1 (SLOOF) UK. 150X200 MM ADUKAN K.250
F 0013 1 M3 BETON BERTULANG PONDASI SETEMPAT + POER UK. 700X700 MM ADUKAN K.250
F 0014 1 M3 BETON BERTULANG KOLOM K1 UK. 200X400 MM ADUKAN K.250
F 0017 1 M3 BETON BERTULANG KOLOM PRAKTIS UK. 150X150 MM ADUKAN K.300
F 0021 1 M3 BETON BERTULANG RINGBALK RBL1 UK. 150x200 MM ADUKAN K.300
F 0022 1 M3 COR PLAT LANTAI TEBAL 12 CM ADUKAN K.300
F 0023 1 M3 COR PLAT KANOPI + MEJA PANTRY TEBAL 10 CM ADUKAN K.225
J 0006 1 M' PAS. GREVEL 1/2" 20 CM + PASANGAN (SNI EDISI REV. 2005)
L 0009 BATU SIKAT / PEARL STONE 300 X 300 1 PC : 4 PS
L 0010 1 M2 PEK.BATU ALAM ANDESIT POLOS BAKAR UK. 40X40 CM,
L 0011 1 M2 PASANG PAVING BLOK NATURAL 6 CM (SNI EDISI REV. 2005)
L 0015 1 M2 PASANG GRASS BLOK UKURAN 30 X 45 CM TEBAL 10 CM (SNI EDISI REV. 2005)
L 0012a 1 M2 PASANG PAVING BLOK NATURAL 8 CM (SNI EDISI REV. 2005)
L 0016 1 M' PEK. KANSTIN 15X35X60 CM
L 0015 1 M2 PEK. PEMADATAN TANAH DASAR
M 0007 1 M2 COATING BATU ALAM
M 0009 1 M2 PENGECATAN LANTAI FLOOR HARDENER
1 M2 PENGECATAN BIDANG BESI BARU 3X LAPIS PENUTUP (SNI EDISI REV. 2005)
B 0009A 1 M3 URUGAN PASIRPANTAI
N 0001 1 M2 PEK. PENANAMAN RUMPUT GAJAH MINI
N 0002 1 BH PEK. PENANAMAN CEMARA UDANG
N 0003 PEK. PENANAMAN KATAPANG KENCANA
N 0011 PEK. PENANAMAN MAHONI
N 0005 PEK. PENANAMAN peace lily
N 0012 PEK. PENANAMAN TABEBUYA
N 0013 PEK. PENANAMAN heloconia
1 M2 PEK.BATU ALAM ANDESIT BAKAR
1 BH PEK. PENANAMAN POHON DENGAN BUIS
N 0004 PEK. PENANAMAN lee kwan yew
N 0006 PEK. BATU ANDESIT BULAT UKURAN DIA. 60 CM
N 0007 PEK. BATU MERAH TUMBUK
N 0010 1 M2 HURUF TIMBUL
N 0001A 1 M2 PEK. PENANAMAN RUMPUT GAJAH
SAMBUNGAN DAYA LISTRIK PLN
PEK. PASANG LAMPU PJU TIANG t=7m
PEK. PANEL LISTRIK
PEK. TIMER LISTRIK
PEK. TITIK LAMPU SOROT
PEK. TITIK LAMPU TAMAN
PEK. TITIK LAMPU HIGH MAST LAMP 4 LAMPU+TIANG
PEK. KABEL TANAM
PEK. LAMPU TANGGA OUT DOOR
Pemasangan 1 bh Kran Ø ¾" atau ½"
Pemasangan 1 m' Pipa PVC tipe AW Ø ¾"
MEMASANG 1 BH, KRAN AIR DIA 1/2" ATAU 3/4" (SNI EDISI REV. 2005)
Pemasangan 1 m' Pipa PVC tipe AW Ø ¾"
Pemasangan 1 m' Pipa PVC tipe AW Ø ½"
pekerjaan 1m' pipa galvanis 6'
PEKERJAAN 1 KG BESI PROFIL, SIKU, IWF, UNP,
PEKERJAAN 100 KG PEKERJAAN PERAKITAN KONTRUKSI BESI/BAJA
PEKERJAAN PENGECATAN DINDING BARU
PEKERJAAN 1 M2 LOSTER BETON
PEKERJAAN PLAFOND GYPSUM
1 M2 PASANGAN LANTAI KERAMIK, UK 40 X 40 CM ANTI SLIP
1 M2 PASANGAN LANTAI KERAMIK, UK 20 X 20 CM
1 UNIT KUSEN & DAUN PINTU ALUMUNIUM FINISHING POWDER COATING LENGKAP AKSESORIS TYPE P2
1 UNIT KUSEN VENTILASI ALUMUNIUM FINISHING POWDER COATING LENGKAP AKSESORIS TYPE J3
1 M2 PEK.BATU ALAM ANDESIT BINTIK BAKAR UK. 30x30 CM
1 M2 PEK.BATU ALAM ANDESIT BINTIK BAKAR UK. 60X60 CM
1 M2 PEK.BATU ALAM ANDESIT POLOS BAKAR UK. 20X20 CM
1 M2 PEK.BATU ALAM ANDESIT POLOS BAKAR UK. 40X40 CM,
PEKERJAAN ADVENTURE PLAY
PEKERJAAN SPRING RIDER / MOBIL
PEKERJAAN SEESAW
PEKERJAAN RUBBER FLOORING
PEKERJAAN 1 M PAGAR TAMAN
PEKERJAAN 1 UNIT PAGAR
PEKERJAAN PEMASANGAN PAVING BLOK TYPE TRUEPAVE UK. 21 X 10.5 cm, TEBAL 6 cm, WARNA ABU-ABU
PEKERJAAN PEMASANGAN PAVING BLOK TYPE TRUEPAVE UK. 10 X 10 cm, TEBAL 6 cm, WARNA MERAH
PEKERJAAN PEMASANGAN PAVING BLOK TYPE MELINGKAR, UK. 12 cm, TEBAL 6 cm, WARNA MERAH & KUNING
PEKERJAAN 1 UNIT PERGOLA
PEKERJAAN 1 UNIT BOLLARD
PEKERJAAN 1 KG BESI POLOS
PEKERJAAN 1 M2 PENGECATAN BESI
PEKERJAAN 10 CM PENGELASAN
PEKERJAAN 1 CM PENGELASAN
pemasangan 1 buah closet jongkok
JUMLAH
(Rp)
(3)
IDR 45,560.00
IDR 20,620.00
IDR 595,640.00
IDR 786,430.00
IDR 611,790.00
IDR 260,670.00
IDR 6,160,000.00
IDR 922,350.00
IDR 179,430.00
IDR 23,920.00
IDR 51,700.00
IDR 94,990.00
IDR 76,030.00
IDR 24,770.00
IDR 141,310.00
IDR 126,690.00
IDR 243,510.00
IDR 219,720.00
IDR 252,140.00
IDR 430,400.00
IDR 807,580.00
IDR 152,190.00
IDR 143,080.00
IDR 293,810.00
IDR 46,470.00
IDR 65,420.00
IDR 60,200.00
IDR 124,720.00
IDR 102,650.00
IDR 68,160.00
IDR 45,470.00
IDR 89,580.00
IDR 264,080.00
IDR 22,130.00
IDR 771,290.00
IDR 981,400.00
IDR 3,475,280.00
IDR 797,640.00
IDR 13,480.00
IDR 1,029,310.00
IDR 4,748,990.00
IDR 4,558,480.00
IDR 6,401,050.00
IDR 336,160.00
IDR 426,250.00
IDR 308,740.00
IDR 140,160.00
IDR 4,748,990.00
IDR 3,103,090.00
IDR 4,883,640.00
IDR 4,838,620.00
IDR 4,558,480.00
IDR 4,532,710.00
IDR 6,401,050.00
IDR 133,920.00
IDR 439,420.00
IDR 286,600.00
IDR 271,600.00
IDR 239,000.00
IDR 234,490.00
IDR 290,640.00
IDR 23,040.00
IDR 31,510.00
IDR 67,990.00
IDR 74,690.00
IDR 165,600.00
IDR 45,560.00
IDR 1,662,560.00
IDR 412,670.00
IDR 460,250.00
IDR 14,630.00
IDR 308,170.00
IDR 40,870.00
IDR 407,330.00
IDR 412,670.00
IDR 19,300.00
IDR 1,794,450.00
IDR 174,160.00
IDR 37,880.00
IDR 26,310.00
3,000,000.00
17,573,460.00
4,695,900.00
951,500.00
621,500.00
621,500.00
24,868,970.00
416,700.00
561,000.00
177,071.25
36,805.75
164,380.00
36,805.75
32,349.50
41,850.00
269,470.00
45,710.00
490,310.00
82,810.00
248,120.00
255,750.00
2,262,700.00
296,190.00
274,500.00
377,300.00
256,300.00
286,600.00
249,200,000.00
6,831,000.00
9,867,000.00
732,050.00
297,120.00
2,857,130.00
187,520.00
303,020.00
327,280.00
4,870,714.40
1,255,790.00
29,280.00
37,560.00
3,930.00
4,110.81
765,501.00
REKAPITULASI HARGA
JUMLAH
No. URAIAN PEKERJAAN
(Rp)
(1) (2) (3)
I PEKERJAAN PEMBANGUNAN GUDANG PERALATAN Rp 50,140,000.00
Terbilang : Tiga Milyar Sembilan ratustiga puluh enam juta sembilan ratus tiga puluh ribu rupiah
RENCANA ANGGARAN BIAYA
HERU NULHAKIM, ST
Direktur
HARGA PERKIRAAN SENDIRI (HPS)
WENDY ARTYANTO, ST
NIP. 19820526 201001 1 007
HARGA PERKIRAAN SENDIRI (HPS)
EDHI HENDARTO, ST
NIP. 19690706 199901 1 001
Bill of Quantity
EDHI HENDARTO, ST
NIP. 19690706 199901 1 001
RENCANA ANGGARAN BIAYA
EDHI HENDARTO, ST
NIP. 19690706 199901 1 001
HARGA PERKIRAAN SENDIRI (HPS)
EDHI HENDARTO, ST
NIP. 19690706 199901 1 001
RENCANA ANGGARAN BIAYA
WENDY ARTYANTO, ST
NIP. 19820526 201001 1 007
RENCANA ANGGARAN BIAYA
WENDY ARTYANTO, ST
NIP. 19820526 201001 1 007
HARGA PERKIRAAN SENDIRI (HPS)
WENDY ARTYANTO, ST
NIP. 19820526 201001 1 007
RENCANA ANGGARAN BIAYA