DIV.II PEKERJAAN PEMATANGAN LANTAI DALAM BANGUNAN T = 10 CM 1.02 0.34 0.34 0.34
DIV. V PEKERJAAN DINDING 18.99 3.17 3.17 3.17 3.17 3.17 3.17
50
DIV. VI PEKERJAAN BETON STRUKTUR 26.02 8.67 8.67 8.67
DIV. VII PEKERJAAN BETON BERTULANG KOLOM PRAKTIS 6.52 1.63 1.63 1.63 1.63
DIV. VIII PEKERJAAN BETON BERTULANG BALOK LATEI 3.02 1.51 1.51 25
DIV. IX PEKERJAAN RABAT LANTAI BETON TEBAL 15 CM 7.58 2.53 2.53 2.53
DIV. X PEKERJAAN ATAP BAJA 35.94 7.19 7.19 7.19 7.19 7.19
BOBOT RENCANA 100.00 0.46 0.34 9.01 9.01 19.03 11.98 14.51 16.02 16.02 3.63 0
BOBOT RENCANA KOMULATIF 0 0.46 0.80 9.81 18.82 37.85 49.83 64.34 80.36 96.37 100.0 RENCANA
BOBOT REALISASI 0 0.18
BOBOT REALISASI KOMULATIF 0.18 REALISASI
DEVIASI -0.28
DIV.II PEKERJAAN PEMATANGAN LANTAI DALAM BANGUNAN T = 10 CM 1.02 0.34 0.34 0.34
DIV. V PEKERJAAN DINDING 18.99 3.17 3.17 3.17 3.17 3.17 3.17
50
DIV. VI PEKERJAAN BETON STRUKTUR 26.02 8.67 8.67 8.67
DIV. VII PEKERJAAN BETON BERTULANG KOLOM PRAKTIS 6.52 1.63 1.63 1.63 1.63
DIV. VIII PEKERJAAN BETON BERTULANG BALOK LATEI 3.02 1.51 1.51 25
DIV. IX PEKERJAAN RABAT LANTAI BETON TEBAL 15 CM 7.58 2.53 2.53 2.53
DIV. X PEKERJAAN ATAP BAJA 35.94 7.19 7.19 7.19 7.19 7.19
0
BOBOT RENCANA 100.00 0.46 0.34 9.01 9.01 19.03 11.98 14.51 16.02 16.02 3.63
BOBOT RENCANA KOMULATIF 0 0.46 0.80 9.81 18.82 37.85 49.83 64.34 80.36 96.37 100.0 RENCANA
BOBOT REALISASI 0 0.18 0.53
BOBOT REALISASI KOMULATIF 0.18 0.72 REALISASI
DEVIASI -0.28 -0.08
DIV.II PEKERJAAN PEMATANGAN LANTAI DALAM BANGUNAN T = 10 CM 1.02 0.34 0.34 0.34
DIV. V PEKERJAAN DINDING 18.99 3.17 3.17 3.17 3.17 3.17 3.17
DIV. VII PEKERJAAN BETON BERTULANG KOLOM PRAKTIS 6.52 1.63 1.63 1.63 1.63
DIV. VIII PEKERJAAN BETON BERTULANG BALOK LATEI 3.02 1.51 1.51
25
DIV. IX PEKERJAAN RABAT LANTAI BETON TEBAL 15 CM 7.58 2.53 2.53 2.53
DIV. X PEKERJAAN ATAP BAJA 35.94 7.19 7.19 7.19 7.19 7.19
BOBOT RENCANA 100.00 0.46 0.34 9.01 9.01 19.03 11.98 14.51 16.02 16.02 3.63
0
BOBOT RENCANA KOMULATIF 0 0.46 0.80 9.81 18.82 37.85 49.83 64.34 80.36 96.37 100.0 RENCANA
BOBOT REALISASI 0 0.18 0.53 #REF!
BOBOT REALISASI KOMULATIF 0.18 0.72 #REF! REALISASI
DEVIASI -0.28 -0.08 #REF!
DIV. V PEKERJAAN DINDING 18.99 3.17 3.17 3.17 3.17 3.17 3.17
DIV. VIII PEKERJAAN BETON BERTULANG BALOK LATEI 3.02 1.51 1.51
25
DIV. IX PEKERJAAN RABAT LANTAI BETON TEBAL 15 CM 7.58 2.53 2.53 2.53
DIV. X PEKERJAAN ATAP BAJA 35.94 7.19 7.19 7.19 7.19 7.19
BOBOT RENCANA 100.00 0.46 0.34 9.01 9.01 19.03 11.98 14.51 16.02 16.02 3.63
0
BOBOT RENCANA KOMULATIF 0 0.46 0.80 9.81 18.82 37.85 49.83 64.34 80.36 96.37 100.0 RENCANA
BOBOT REALISASI 0 0.18 0.53 #REF! #REF!
BOBOT REALISASI KOMULATIF 0.18 0.72 #REF! #REF! REALISASI
DEVIASI -0.28 -0.08 #REF! #REF!
DIV. V PEKERJAAN DINDING 18.99 3.17 3.17 3.17 3.17 3.17 3.17
DIV. VIII PEKERJAAN BETON BERTULANG BALOK LATEI 3.02 1.51 1.51
DIV. IX PEKERJAAN RABAT LANTAI BETON TEBAL 15 CM 7.58 2.53 2.53 2.53 25
DIV. X PEKERJAAN ATAP BAJA 35.94 7.19 7.19 7.19 7.19 7.19
BOBOT RENCANA 100.00 0.46 0.34 9.01 9.01 19.03 11.98 14.51 16.02 16.02 3.63
BOBOT RENCANA KOMULATIF 0 0.46 0.80 9.81 18.82 37.85 49.83 64.34 80.36 96.37 100.0 0
RENCANA
BOBOT REALISASI 0 0.18 0.53 #REF! #REF!
BOBOT REALISASI KOMULATIF 0.18 0.72 #REF! #REF! REALISASI
DEVIASI -0.28 -0.08 #REF! #REF!
KEMAJUAN PEKERJAAN
JUMLAH HARGA BOBOT
NO JENIS PEKERJAAN S/D MINGGU LALU MINGGU INI S/D MINGGU INI
(RP) (%) PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
KEMAJUAN PEKERJAAN
JUMLAH HARGA BOBOT
NO JENIS PEKERJAAN S/D MINGGU LALU MINGGU INI S/D MINGGU INI
(RP) (%) PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
KEMAJUAN PEKERJAAN
JUMLAH HARGA BOBOT
NO JENIS PEKERJAAN S/D MINGGU LALU MINGGU INI S/D MINGGU INI
(RP) (%) PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
KEMAJUAN PEKERJAAN
JUMLAH HARGA BOBOT
NO JENIS PEKERJAAN S/D MINGGU LALU MINGGU INI S/D MINGGU INI
(RP) (%) PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
KEMAJUAN PEKERJAAN
JUMLAH HARGA BOBOT
NO JENIS PEKERJAAN S/D BULAN LALU BULAN INI S/D BULAN INI
(RP) (%) PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
1 2 3 5 6 6 6
PEKERJAAN SIPILDAN ARSITEKTUR
DIV. I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 21,112,500 1.00 21,112,500.00 1.00 21,112,500.00 - -
SUB JUMLAH DIV. I 21,112,500.00 21,112,500.00 -
DIV.II PEKERJAAN PEMATANGAN LANTAI DALAM BANGUNAN T = 10 CM
1 Penimbunan dan Pemadatan Lantai Bangunan Depan m³ 103,605.16 156 16,162,404.76 156.00 16,162,404.76 - -
2 Penimbunan dan Pemadatan Lantai Basemant m³ 103,605.16 68.91 7,139,120.58 68.91 7,139,120.58 - -
SUB JUMLAH DIV. II 23,301,525.34 23,301,525.34 -
DIV. III PEKERJAAN TANAH
1 Galian Tanah Pondasi Tangga, Ram dan Selasar m³
2 Urugan Tanah Kembali Galian m³
SUB JUMLAH DIV. III
DIV. IV PEKERJAAN PONDASI MENERUS
1 Pasangan Aanstamping m³
2 Pas. Pondasi Batu Kali pada Tangga dan Selasar m³
SUB JUMLAH DIV. IV
DIV. V PEKERJAAN DINDING
A. Lantai 1
1 Pasangan tembok Bata Trasram (1Pc : 3Psr) m³ 770,522.50 57.70 44,460,307.89 38.77 29,870,845.76 18.93 14,589,462.13
2 Pasangan tembok Bata (1Pc : 4Psr) m³ 739,744.50 126.23 93,376,344.47 90.03 66,596,978.10 36.20 26,779,366.37
3 Plesteran (1Pc : 4Psr) tebal 15 mm m² 42,521.88 1,042.90 44,346,257.34 1,800.54 76,562,345.82 - 757.64 - 32,216,088.48
4 Plesteran (1Pc : 3Psr) Trasram tebal 15 mm m² 43,247.05 541.48 23,417,300.19 775.34 33,531,167.75 - 233.86 - 10,113,867.56
5 Acian - - - - - - -
B. LANTAI 2
1 Pasangan tembok Bata Trasram (1Pc : 3Psr) m³ 770,522.50 58.86 45,352,468.92 25.73 19,822,461.84 33.13 25,530,007.09
2 Pasangan tembok Bata (1Pc : 4Psr) m³ 739,744.50 131.41 97,210,747.21 98.39 72,781,611.99 33.02 24,429,135.21
3 Plesteran (1Pc : 4Psr) tebal 15 mm m² 42,521.88 1,330.80 56,587,956.47 1,967.75 83,672,429.37 - 636.95 - 27,084,472.90
4 Plesteran (1Pc : 3Psr) Trasram tebal 15 mm m² 43,247.05 453.40 19,608,195.17 514.52 22,251,472.17 - 61.12 - 2,643,276.99
5 Acian - -
C. BASEMANT
1 Pasangan tembok Bata Trasram (1Pc : 3Psr) m³ 770,522.50 1.34 1,030,150.06 1.34 1,030,150.06 - -
2 Pasangan tembok Bata (1Pc : 4Psr) m³ 739,744.50 9.72 7,188,696.50 9.72 7,188,696.50 - -
3 Plesteran (1Pc : 4Psr) tebal 15 mm m² 42,521.88 64.79 2,754,796.68 64.79 2,754,796.68 - -
4 Plesteran (1Pc : 3Psr) Trasram tebal 15 mm m² 43,247.05 8.91 385,460.96 8.91 385,460.96 - -
5 Acian
D. TRANSRAM DINDING ATAS
1 Pasangan tembok Bata Trasram (1Pc : 3Psr) m³ - - - - -
2 Pasangan tembok Bata (1Pc : 4Psr) m³ - - - - -
3 Plesteran (1Pc : 4Psr) tebal 15 mm m² - - - - -
4 Plesteran (1Pc : 3Psr) Trasram tebal 15 mm m² - - - - -
SUB JUMLAH DIV. V 435,718,681.85 416,448,416.98 19,270,264.87
1 2 3 5 6 6 6
DIV. VI PEKERJAAN BETON STRUKTUR
A. PEKERJAAN BETON KOLOM
1 Beton K-250 m³ 1,043,261.12 14.52 15,143,143.81 17.10 17,836,784.41 - 2.58 - 2,693,640.60
2 Penulangan Kg 18,730.25 4,162.88 77,971,783.12 3,835.55 71,840,775.92 327.33 6,131,007.20
3 Pemasangan, Pembongkaran Beugesting Beton m² 385,606.33 144.81 55,838,263.88 144.81 55,838,263.88 - -
4 Lem Beton Ls 1,976,000.00 1.00 1,976,000.00 1.00 1,976,000.00 - -
B. PEKERJAAN BETON RINGBALK 25/40
1 Beton K-250 m³ 1,043,261.12 16.69 17,414,114.62 10.56 11,016,837.43 6.13 6,397,277.19
2 Penulangan Kg 18,730.25 279.64 5,237,764.57 1,773.17 33,211,951.86 - 1,493.53 - 27,974,187.29
3 Beugesting Beton m² 385,606.33 148.55 57,281,819.72 148.55 57,281,819.72 - -
C. PEKERJAAN BETON RINGBALK 20/30
1 Beton K-250 m³ 1,043,261.12 16.69 17,414,114.62 4.61 4,807,347.24 12.08 12,606,767.38
2 Penulangan Kg 18,730.25 2,309.32 43,254,187.76 928.17 17,384,932.56 1,381.15 25,869,255.20
3 Beugesting Beton m² 385,606.33 148.55 57,281,819.72 148.55 57,281,819.72 - -
D. PEKERJAAN BETON TALANG
1 Beton K-250 m³ 1,043,261.12 34.52 36,013,478.19 25.87 26,985,252.95 8.65 9,028,225.24
2 Penulangan Kg 18,730.25 4,221.81 79,075,523.60 4,914.59 92,051,452.52 - 692.78 - 12,975,928.92
3 Beugesting Beton m² 385,606.33 345.06 133,058,444.66 345.06 133,058,444.66 - -
SUB JUMLAH DIV. VI 596,960,458.27 580,571,682.86 16,388,775.41
DIV. VII PEKERJAAN BETON BERTULANG KOLOM PRAKTIS
A. PEKERJAAN KOLOM PRAKTIS LT-1 (150X150)
1 Beton K-225 m³ 994,341.92 12.62 12,551,080.89 13.28 13,208,838.07 - 0.66 - 657,757.18
2 Penulangan (BJTP 24) Kg 18,730.25 1,434.90 26,876,046.12 3,218.97 60,292,140.94 - 1,784.07 - 33,416,094.82
3 Beugesting Beton m² 385,606.33 109.82 42,345,647.89 109.82 42,345,647.89 - -
B. PEKERJAAN KOLOM PRAKTIS LT-2 (150X150)
1 Beton K-225 m³ 994,341.92 10.04 9,985,082.13 10.95 10,889,237.23 - 0.91 - 904,155.10
2 Penulangan (BJTP 24) Kg 18,730.25 1,130.32 21,171,106.20 2,653.69 49,704,252.77 - 1,523.37 - 28,533,146.57
3 Beugesting Beton m² 385,606.33 88.07 33,959,370.85 88.07 33,959,370.85 - -
C. PEKERJAAN KOLOM PRAKTIS BASEMENT(150X150)
1 Beton K-225 m³ 994,341.92 0.41 402,708.48 0.41 402,708.48 - -
2 Penulangan (BJTP 24) Kg 18,730.25 45.45 851,290.91 45.45 851,290.91 - -
3 Beugesting Beton m² 385,606.33 3.55 1,369,615.83 3.55 1,369,615.83 - -
SUB JUMLAH DIV. VII 149,511,949.30 213,023,102.97 - 63,511,153.67
DIV. VIII PEKERJAAN BETON BERTULANG BALOK LATEI
A. Pekerjaan Balok Latei Lantai 1 (150x150)
1 Beton K-225 m³ 994,341.92 5.17 5,137,665.27 9.09 9,036,778.24 - 3.92 - 3,899,112.97
2 Penulangan (BJTP 24) Kg 18,730.25 590.18 11,054,134.88 2,202.25 41,248,647.64 - 1,612.07 - 30,194,512.76
3 Beugesting Beton m² 385,606.33 45.31 17,473,254.39 45.31 17,473,254.39 - -
B. Pekerjaan Balok Latei Lantai 2 (150x150)
1 Beton K-225 m³ 994,341.92 5.43 5,399,873.23 8.25 8,199,144.60 - 2.82 - 2,799,271.37
2 Penulangan (BJTP 24) Kg 18,730.25 620.30 11,618,298.18 1,998.12 37,425,243.58 - 1,377.82 - 25,806,945.40
3 Beugesting Beton m² 385,606.33 47.63 18,365,026.47 47.63 18,365,026.47 - -
C. Pekerjaan Balok Latei Basemant (150x150)
1 Beton K-225 m³ 994,341.92 0.05 49,219.93 0.05 49,219.93 - -
2 Penulangan (BJTP 24) Kg 18,730.25 5.65 105,900.96 5.65 105,900.96 - -
3 Beugesting Beton m² 385,606.33 0.43 167,397.49 0.43 167,397.49 - -
SUB JUMLAH DIV. VIII 69,370,770.80 132,070,613.31 - 62,699,842.51
- 90,551,955.90
- 90,551,955.90
1 2 3 5 6 6 6
DIV. IX PEKERJAAN RABAT LANTAI BETON TEBAL 15 CM
A. Lantai Basemant
1 Beton K-125 m³ 772,876.12 68.91 53,256,574.46 68.91 53,256,574.46 - -
B. Lantai Bangunan Depan
1 Beton K-125 m³ 772,876.12 156.00 120,568,673.94 156.00 120,568,673.94 - -
SUB JUMLAH DIV. IX 173,825,248.40 173,825,248.40 -
DIV. X PEKERJAAN ATAP BAJA
1 Kuda-kuda Pipa Baja
- Baja Jenis P89.1C Kg 21,990.08 6,050.57 133,052,511.71 6,050.57 133,052,511.71 - -
- Baja Jenis P219.3C Kg 21,990.08 7,586.53 166,828,426.26 7,586.53 166,828,426.26 - -
- Baja Jenis P139.8C Kg 21,990.08 7,517.76 165,316,054.28 7,517.76 165,316,054.28 - -
- Baja Jenis P165.2C Kg 21,990.08 8,818.85 193,927,150.54 8,818.85 193,927,150.54 - -
2 Gording Baja Canal Kg - - - - - -
3 Ikatan Angin Ø mm Kg - - - - - -
4 Pengikat Gording (saarodi Ø 10 mm) Kg - - - - - -
5 Pelat Penopang Gording Kg - - - - - -
6 Baut Ø 16 mm Bh 15,000.00 230.00 3,450,000.00 230.00 3,450,000.00 - -
7 Baut Ornamen Accessories Bh - - - - - - -
8 Base Plat/Plat Box (induk) Kg - - - - - - -
9 Plat Baja Kg 18,406.70 5,854.76 107,766,754.33 5,854.76 107,766,754.33 - -
10 Berat Penopang Kaso L.50.50.5 m² - - - - - - -
11 Berat Baja Tumpuan Bh - - - - - - -
12 Angker D16 Bh 23,404.98 544.00 12,732,306.40 544.00 12,732,306.40 - -
13 Penggantung Plafond Ls - - - - - - -
14 Pengelasan titik 33,750.00 900.00 30,375,000.00 900.00 30,375,000.00 - -
15 Kaso dan Kayu Reng Klas II m² - - - - - - -
16 Atap Metal Roof 0.35 mm + Aluminium Foil m² - - - - - - -
17 Bubungan Atap Metal Roof 0.35 mm m¹ - - - - - - -
18 Ornamen Atap pada bangunan induk Ls - - - - - - -
19 Karet Struktur lapis plat m² 150,000.00 74.49 11,173,200.00 74.49 11,173,200.00 - -
20 Pengecatan Konstruksi Baja 2X - - - - - - -
SUB JUMLAH DIV. X 824,621,403.52 824,621,403.52 -
- 362,207,811.58
- 363,982,454.81
1,774,643.22
LAPORAN MINGGUAN KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN
JUMLAH HARGA BOBOT
NO JENIS PEKERJAAN S/D MINGGU LALU MINGGU INI S/D MINGGU INI
(RP) (%) PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
F.X.Y. Wadu, SST Muhamad Darlan Atapukan, ST Ahmad Yunus dan Ronny Wibowo
NIP. ………………. Inspector Pelaksana
62
373
33.33333 1.75 0.2 0.35 11.6666666666667
2.95 0.2 0.59 19.6666666666667 31.33333
5,400,000.00
4,200,000.00
500,000.00
250,000.00
10,350,000.00
0.49
5.2675 14.3
3.84 40.32
11 7.56
2.4 6.72
1.45 20.16
6.4 3.675
1.8 14.08
8.8 1.87
6.72 5.75
6.72 0.9
1.925
1.925
1.76
2.3125
2.695
2.695
6.4
3.6
17.92
2.2
3.3
1.8
1.15
275,000,000 1.85
26.88
3.6
374.00 6.4
245 1.8
1
#REF! 2.56
1.28
3.3
12.8
14.08
8.8
14.08
JOHANIS MILLA 4.2
DIREKTUR 13.44
8.82 1.0005
3.45
LAPORAN MINGGUAN KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN
JUMLAH HARGA BOBOT
NO JENIS PEKERJAAN S/D MINGGU LALU MINGGU INI S/D MINGGU INI
(RP) (%) PRESTASI BOBOT PRESTASIBOBOT PRESTASI BOBOT
F.X.Y. Wadu, SST Muhamad Darlan Atapukan, ST Ahmad Yunus dan Ronny Wibowo
NIP. ………………. Inspector Pelaksana
62
373
33.33333 1.75 0.2 0.35 11.66666667
2.95 0.2 0.59 19.66666667 31.33333
HARGA SATUAN
NO URAIAN SATUAN
(Rp)
II BAHAN
1 Tanah Urug M3 30,000.00
2 Pasir Urug M3 75,000.00
3 Pasir Pasang M3 110,000.00
4 Batu Kali M3 100,000.00
5 Batu Merah Bh 600.00
6 Bataco Bh 3,500.00
7 Sirtu M3 90,000.00
8 Urugan Pilihan M3 90,000.00
9 Pasir Cor Untuk Beton M3 110,000.00
10 Batu 10/15 cm M3 100,000.00
11 Batu Pecah 1/2 cm M3 400,000.00
12 Batu Pecah 2/3 M3 365,000.00
13 Semen PC Zak 47,000.00
14 Semen Putih PC Kg 5,000.00
15 Semen Warna PC Kg 7,500.00
16 Balok Kayu Klas I ( 6/12, 8/12 ) M3 6,000,000.00
17 Balok Kayu Klas II ( 6/12, 8/12 ) M3 2,750,000.00
18 Papan Kayu Klas I M3 6,000,000.00
19 Papan Kayu Klas II M3 2,750,000.00
20 Papan Bakisting klas III M3 1,000,000.00
21 Usuk Klas II ( 5/7 ) M3 980,000.00
22 Tripleks 3 mm Lbr 48,000.00
23 Tripleks 4 mm Lbr 95,000.00
24 Tripleks 6 mm Lbr 110,000.00
25 Tripleks 9 mm Lbr 120,000.00
26 Seng Gelombang BJLS 0.30 Lbr 55,000.00
27 Seng Plat BJLS 0.30 Lbr 50,000.00
28 Seng Plat BJLS 0.20 Lbr 22,500.00
29 Seng Gelombang BJLS 0.20 Lbr 38,000.00
30 Hengsel 4 x 3 cm Pasang 15,000.00
HARGA SATUAN
NO URAIAN SATUAN
(Rp)
31 Hengsel Jendela Bh 10,000.00
32 Kunci Tanam 2 Slag ( Kuda Terbang ) Bh 55,000.00
33 Kunci Pintu ( Veronika ) Bh 16,500.00
34 Grendel Kecil Bh 4,500.00
35 Grendel Besar Bh 9,900.00
36 Kait Angin Bh 6,100.00
37 Besi Angker Dook Bh 12,500.00
38 Paku Seng Kg 22,500.00
39 Paku Biasa 5, 6, 7 Cm Kg 17,500.00
40 Paku Biasa 8 - 15 Cm Kg 17,500.00
41 Paku Biasa 3, 4 Cm Kg 17,500.00
42 Closet
Paku Beton ( Paku Putih ) Kg 20,000.00
43 Jongk
Paku Tripleks ( 2 Cm ) Kg 17,500.00
ok
44 Bh 130,000.00
( INA /
45 Pipa
AMER Hawa PVC Ø 2" Bh 30,000.00
46 Pipa PVC
ICAN ) Ø 4" M¹ 35,000.00
47 Pipa PVC Ø 2" M¹ 30,000.00
48 Pipa PVC Ø 1.5" M¹ 25,000.00
49 Pipa PVC Ø 1" M¹ 20,000.00
50 Pipa Instalasi Btg 10,000.00
51 Klem Pipa Buah 1,000.00
52 Pipa GIP Ø 4" M¹ 87,500.00
53 Pipa GIP Ø 2" M¹ 60,000.00
54 Pipa GIP Ø 1.5" M¹ 45,000.00
55 Pipa GIP Ø 1" M¹ 35,000.00
56 Floor Drain Buah 15,000.00
57 Kran Air (Kuningan) Bh 15,000.00
58 Menie Kayu ( Pedang ) Kg 30,000.00
59 Menie Seng Kg 30,000.00
60 Menie Kayu ( Altec ) Kg 30,000.00
61 Minyak Cat Liter 25,000.00
62 Cat Tembok ( Matex 5 Kg ) Kaleng 85,000.00
63 Cat Tembok ( Mawar 5 Kg ) Kaleng 70,000.00
64 Cat Tembok ( V - Tex ) Kaleng 25,000.00
65 Cat ( Emco ) Kg 25,000.00
66 Cat ( Avi ) Kg 24,000.00
67 Thinner ( Spesial A ) Kg 30,000.00
68 List kayu Plafond (diprofil) M' 10,000.00
69 Kwas Rool Bh 20,000.00
70 Kwas Cat ( Nomor 2 ) Bh 7,000.00
71 Kwas Cat ( Nomor 4 ) Bh 9,400.00
HARGA SATUAN
NO URAIAN SATUAN
(Rp)
72 Besi Beton 12 MM Staf 130,000.00
73 Baja Tulangan Beton Kg 13,000.00
74 Kawat Beton / Bindrat Kg 12,500.00
75 Kawat Duri Roll 95,000.00
76 Kertas Amplas Lbr 3,500.00
77 Plamur Kg 22,500.00
78 Cat Kilap ( Deluxe ) Kaleng 25,000.00
79 Kaca 5 mm M2 150,000.00
80 Mur Baut Kg 30,000.00
81 Plat Bh 5,000.00
82 Pekerjaan Bak Air Kamar WC Ls 150,000.00
83 Batu Bunga Bh 7,500.00
84 Teakwood ( 4" x 8" x 3 MM ) Lbr 85,000.00
85 Lem PVC Tube 8,000.00
86 Keramik Putih ( 30 x 30 Cm ) Dos 60,000.00
87 Keramik Putih ( 20 x 20 Cm ) Dos 50,000.00
88 Wafel Keramik 20/20 Dos 45,000.00
89 Kapur / Tanah Putih M3 125,000.00
90 Rangka Nako M' 55,000.00
91 Kaca Nako 5 mm Sisir 15,000.00
92 Skrup Kayu Buah 700.00
93 Teak Oil Kg 50,000.00
94 Politur Kaleng 44,000.00
95 Kapur Gamping M3 125,000.00
96 Batu Roster Bh 5,000.00
97 Meteran Daya 1300 Watt UNIT 5,000,000.00
98 R2 4400 VA UNIT 1,750,000.00
99 Kabel Snur 2 x 23 M ( Kayanuta ) Roll 75,000.00
100 Kabel Snur ( Naga ) Roll 60,000.00
101 Kabel NYM 2 x 11/2 M M¹ 15,000.00
102 Kabel NYA M¹ 15,000.00
103 Saklar Engkel ( Braco ) Buah 15,000.00
104 Saklar Seri ( Braco ) Buah 20,000.00
105 Steker 1250 ( Nico ) Buah 7,000.00
106 Stop Kontak 3650 ( Braco ) Buah 15,000.00
107 Fitting Gandeng ( Nico ) Buah 5,000.00
108 Fitting Tempel ( Braco ) Buah 8,500.00
109 Jeck ( Braco ) Buah 5,000.00
110 Neon TL 40 Watt ( Philips ) Buah 40,000.00
111 Neon TL 20 Watt ( Philips ) Buah 30,000.00
112 Neon TL 10 Watt ( Philips ) Buah 25,000.00
113 Neon TL 40 Watt ( Chioda ) Buah 35,000.00
114 Neon TL 20 Watt ( Chioda ) Buah 20,000.00
115 Lampu Pijar 40 Watt (Philips) Buah 20,000.00
116 Lampu Pijar 25 Watt (Philips) Buah 15,000.00
117 Box Skring Buah 55,000.00
118 Pipa Arde Btg 10,000.00
119 T Dos Buah 3,000.00
120 Isolator Buah 3,000.00
121 Besi Canal Kg 20,000.00
122 Plat Essel t = 5 mm M² 75,000.00
123 Kawat Duri Roll 100,000.00
124 Besi Siku 50.50.5 mm Staf 112,000.00
125 Kawat Las Kg 25,000.00
126 Pagar BRC Unit 265,000.00
DAFTAR HARGA UPAH DAN BAHAN
#REF! #REF!
#REF! #REF!
Lokasi :
Tahun Anggaran :
3434.3
2
NO URAIAN
II BAHAN
1 Tanah Urug
2 Pasir Urug
3 Pasir Pasang
4 Batu Kali
5 Batu Merah
6 Bataco
7 Sirtu
8 Urugan Pilihan
9 Pasir Cor Untuk Beton
10 Batu 10/15 cm
11 Batu Pecah 1/2 cm
12 Batu Pecah 2/3
13 Semen PC
14 Semen Putih PC
15 Semen Warna PC
16 Balok Kayu Klas I ( 6/12, 8/12 )
17 Balok Kayu Klas II ( 6/12, 8/12 )
18 Papan Kayu Klas I
19 Papan Kayu Klas II
20 Papan Bakisting klas III
21 Usuk Klas II ( 5/7 )
22 Tripleks 3 mm
23 Tripleks 4 mm
24 Tripleks 6 mm
25 Tripleks 9 mm
26 Seng Gelombang BJLS 0.30
27 Seng Plat BJLS 0.30
28 Seng Plat BJLS 0.20
29 Seng Gelombang BJLS 0.20
30 Hengsel 4 x 3 cm
2
NO URAIAN
72 Besi Beton 12 MM
73 Baja Tulangan Beton 9.324
74 Kawat Beton / Bindrat 14478.76
75 Kawat Duri
76 Kertas Amplas
77 Plamur
78 Cat Kilap ( Deluxe )
79 Kaca 5 mm
80 Mur Baut
81 Plat
82 Pekerjaan Bak Air Kamar WC
83 Batu Bunga
84 Teakwood ( 4" x 8" x 3 MM )
85 Lem PVC
86 Keramik Putih ( 30 x 30 Cm )
87 Keramik Putih ( 20 x 20 Cm )
88 Wafel Keramik 20/20
89 Kapur / Tanah Putih
90 Rangka Nako
91 Kaca Nako 5 mm
92 Skrup Kayu
93 Teak Oil
94 Politur
95 Kapur Gamping
96 Batu Roster
97 Meteran Daya 1300 Watt
98 R2 4400 VA
99 Kabel Snur 2 x 23 M ( Kayanuta )
100 Kabel Snur ( Naga )
101 Kabel NYM 2 x 11/2 M
102 Kabel NYA
103 Saklar Engkel ( Braco )
104 Saklar Seri ( Braco )
105 Steker 1250 ( Nico )
106 Stop Kontak 3650 ( Braco )
107 Fitting Gandeng ( Nico )
108 Fitting Tempel ( Braco )
109 Jeck ( Braco )
110 Neon TL 40 Watt ( Philips )
111 Neon TL 20 Watt ( Philips )
112 Neon TL 10 Watt ( Philips )
113 Neon TL 40 Watt ( Chioda )
114 Neon TL 20 Watt ( Chioda )
115 Lampu Pijar 40 Watt (Philips)
116 Lampu Pijar 25 Watt (Philips)
117 Box Skring
118 Pipa Arde
119 T Dos
120 Isolator
121 Besi Canal
122 Plat Essel t = 5 mm
123 Kawat Duri
124 Besi Siku 50.50.5 mm
125 Kawat Las
126 Pagar BRC
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
#REF! #REF! #REF!
#REF! #REF! #REF!
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata
Tahun Anggaran : 2011
No Uraian Pekerjaan Sat Koofisien Harga Jumlah Harga
Satuan
1 1 M' Pasangan Bouplank
- Kayu Usuk dan Papan Klas II M3 0.01 1,000,000.00 10,000.00
- Paku Kg 0.12 17,500.00 2,100.00
- Pekerja Org 0.12 25,000.00 3,000.00
- Mandor Org 0.003 40,000.00 120.00
15,220.00
2 1 M3 Galian Tanah Biasa
- Pekerja Org 0.75 25,000.00 18,750.00
- Mandor Org 0.025 40,000.00 1,000.00
19,750.00
3 1 M3 Galian Tanah Keras
- Pekerja Org 1.00 25,000.00 25,000.00
- Mandor Org 0.033 40,000.00 1,320.00
26,320.00
4 1 M3 Urugan Tanah
- Tanah Urug M3 1.20 30,000.00 36,000.00
- Pekerja Org 0.30 25,000.00 7,500.00
- Mandor Org 0.01 40,000.00 400.00
43,900.00
5 1 M3 Urugan Pasir/Sirtu
- Pasir Urug M3 0.20 75,000.00 15,000.00
- Pekerja Org 0.30 25,000.00 7,500.00
- Mandor Org 0.01 40,000.00 400.00
22,900.00
6 1 M3 Pas. Batu Kali / Karang Kosong
- Batu Kali / Karang M3 1.17 100,000.00 117,000.00
- Pekerja Org 1.50 25,000.00 37,500.00
- Mandor Org 0.075 40,000.00 3,000.00
157,500.00
7 1 M3 Pas. Batu Kali / Karang 1 PC : 2 PS
- Batu Kali / Karang M3 1.17 100,000.00 117,000.00
- Semen Zak 6.66 47,000.00 313,020.00
- Pasir M3 0.427 110,000.00 46,970.00
- Tukang Batu Org 1.20 35,000.00 42,000.00
- Kepala Tukang Batu Org 0.12 40,000.00 4,800.00
- Pekerja Org 3.60 25,000.00 90,000.00
- Mandor Org 0.180 40,000.00 7,200.00
620,990.00
8 1 M3 Pas. Batu Kali / Karang 1 PC : 3 PS
- Batu Kali / Karang M3 1.17 100,000.00 117,000.00
- Semen Zak 5.05 47,000.00 237,350.00
- Pasir M3 0.427 110,000.00 46,970.00
- Tukang Batu Org 1.20 35,000.00 42,000.00
- Kepala Tukang Batu Org 0.12 40,000.00 4,800.00
- Pekerja Org 3.60 25,000.00 90,000.00
- Mandor Org 0.180 40,000.00 7,200.00
545,320.00 348,473.50
9 1 M3 Pas. Batu Kali / Karang 1 PC : 4 PS
- Batu Kali / Karang M3 1.17 100,000.00 117,000.00
- Semen Zak 4.07 47,000.00 191,290.00
- Pasir M3 0.520 110,000.00 57,200.00
- Tukang Batu Org 1.20 35,000.00 42,000.00
- Kepala Tukang Batu Org 0.12 40,000.00 4,800.00
- Pekerja Org 3.60 25,000.00 90,000.00
- Mandor Org 0.180 40,000.00 7,200.00
509,490.00
32 1 M2 Tegel Keramik 20 x 20 CM
- Tegel Keramik 20/20 Bh 25.00 2,000.00 50,000.00
- Kapur Gamping M3 0.003 125,000.00 375.00
- Pasir M3 0.032 110,000.00 3,520.00
- Semen Zak 0.003 47,000.00 117.50
- Semen Warna Zak 0.020 300,000.00 6,000.00
- Tukang Batu Org 0.250 35,000.00 8,750.00
- Kepala Tukang Batu Org 0.025 40,000.00 1,000.00
- Pekerja Org 0.50 25,000.00 12,500.00
- Mandor Org 0.025 40,000.00 1,000.00
83,262.50
33 1 M' Pas. Tegel Plint Keramik 10 x 30 CM
- Tegel Plint Keramik Bh 3.30 18,181.82 60,000.00
- Semen Zak 0.096 47,000.00 4,512.00
- Pasir M3 0.007 110,000.00 770.00
- Semen Warna Zak 0.001 300,000.00 300.00
- Tukang Batu Org 0.10 35,000.00 3,500.00
- Kepala Tukang Batu Org 0.010 40,000.00 400.00
- Pekerja Org 0.20 25,000.00 5,000.00
- Mandor Org 0.010 40,000.00 400.00
74,882.00
34 1 M2 Pasangan Mozaik
- Mozaik Bh 11.11 5,400.54 60,000.00
- Kapur Gamping M3 0.007 125,000.00 875.00
- Pasir M3 0.036 110,000.00 3,960.00
- Semen Zak 0.480 47,000.00 22,560.00
- Semen Warna Zak 0.002 300,000.00 600.00
- Tukang Batu Org 0.250 35,000.00 8,750.00
- Kepala Tukang Batu Org 0.025 40,000.00 1,000.00
- Pekerja Org 0.50 25,000.00 12,500.00
- Mandor Org 0.025 40,000.00 1,000.00
111,245.00
1 2 3 4 5 6 7 8
DEPAN
1 10. L-K 3.60 3.60 12.96 0.40 3.60 1.00 1.44 7.20 4.32 11.52
2 10. K-G 13.20 3.60 47.52 0.40 3.60 4.00 5.76 5.28 36.48 41.76
3 10A. L-K 3.60 3.60 12.96 BAS-P70A 0.80 2.15 2.00 3.44 4.00 5.52 9.52
4 11. L-K 3.60 3.60 12.96 BAS-PV70 0.80 2.15 1.00 2.36 BAS-V70 0.80 0.80 3.00 1.92 0.40 3.60 1.00 1.44 5.60 1.64 7.24
5 11. K-G 13.20 3.60 47.52 BAS-P70 0.80 2.15 1.00 1.72 BAS-J2.70 1.55 2.45 1.00 3.80 BAS-V70 0.80 0.80 3.00 1.92 0.40 3.60 4.00 5.76 4.12 25.92 30.04
BAS-PV70 0.80 2.15 1.00 2.36
BAS-PG 1.30 2.80 1.00 3.64
6 G. 10-11 3.60 3.60 12.96 BAS-V70 0.80 0.80 3.00 1.92 0.40 3.60 1.00 1.44 1.44 8.16 9.60
7 I. 10-11 3.60 3.60 12.96 0.40 3.60 1.00 1.44 1.44 11.52 12.96
8 J. 10-11 3.60 3.60 12.96 0.40 3.60 1.00 1.44 1.44 11.52 12.96
9 K.10-11 3.60 3.60 12.96 LUBANG 1.80 2.15 1.00 3.87 0.40 3.60 1.00 1.44 3.60 4.05 7.65
11 L.10-11 3.60 3.60 12.96 BAS-V70 0.80 0.80 3.00 1.92 0.40 3.60 1.00 1.44 7.20 2.40 9.60
JUMLAH 58.80 211.68 17.39 3.80 7.68 21.60 48.52 117.29 165.81
PERHITUNGAN VOLUME PASANGAN DINDING 1/2 BATA LANTAI II
1 2 3 4 5 6 7 8
DEPAN
1 9. A-B 3.60 3.60 12.96 BV1.70 0.80 0.70 2.00 1.12 7.20 4.64 11.84
2 9. B-Q 50.20 3.60 180.72 P70 0.80 2.80 6.00 13.44 J55 0.65 2.45 15.00 23.89 BV1.70 0.80 0.70 2.00 1.12 0.40 3.60 7.00 10.08 113.82 113.82
JMM 1.25 2.45 6.00 18.38
3 9. Q-R 3.60 3.60 12.96 BV1.70 0.80 0.70 2.00 1.12 7.20 4.64 11.84
4 8A. A-B 3.60 3.60 12.96 P70A 0.80 2.15 2.00 3.44 4.00 5.52 9.52
5 8A. Q-R 3.60 3.60 12.96 P70A 0.80 2.15 2.00 3.44 4.00 5.52 9.52
6 7A. A-B 3.60 3.60 12.96 P70V3 0.80 2.15 1.00 3.86 5.60 3.51 9.11
7 7A. Q-R 3.60 3.60 12.96 P70V3 0.80 2.15 1.00 3.86 5.60 3.51 9.11
8 7. B-G 18.00 3.60 64.80 PG-120 1.30 2.80 2.00 7.28 BV4-70 3.05 0.70 4.00 8.54 0.40 3.60 5.00 7.20 41.78 41.78
9 7. L-Q 18.00 3.60 64.80 PG-V70 1.30 2.15 2.00 9.51 BV4-70 3.05 0.70 3.00 6.41 0.40 3.60 5.00 7.20 41.69 41.69
10 6. B-H 21.60 3.60 77.76 PG-V70 1.30 2.15 2.00 9.51 BV4-70 3.05 0.70 3.00 6.41 0.40 3.60 6.00 8.64 49.57 49.57
PG-120 1.30 2.80 1.00 3.64
11 6. K-Q 21.60 3.60 77.76 PG-V70 1.30 2.15 3.00 14.27 BV4-70 3.05 0.70 3.00 6.41 0.40 3.60 6.00 8.64 48.45 48.45
12 5A. A-B 3.60 3.60 12.96 P70V3 0.80 2.15 1.00 3.86 5.60 3.51 9.11
13 5A. Q-R 3.60 3.60 12.96 P70V3 0.80 2.15 1.00 3.86 5.60 3.51 9.11
14 4A. A-B 3.60 3.60 12.96 P70A 0.80 2.15 2.00 3.44 4.00 5.52 9.52
15 4A. Q-R 3.60 3.60 12.96 P70A 0.80 2.15 2.00 3.44 4.00 5.52 9.52
16 4. A-B 3.60 3.60 12.96 BV1.70 0.80 0.70 2.00 1.12 7.20 4.64 11.84
17 4. B-Q 60.30 3.60 217.08 P70 0.80 2.80 8.00 17.92 J55 0.65 2.45 11.00 17.52 BV1.70 0.80 0.70 2.00 1.12 0.40 3.60 15.00 21.60 117.59 117.59
PUT 2.60 2.80 1.00 7.28 J55A 0.65 2.45 6.00 9.56
JM 1.25 2.45 8.00 24.50
34 KM DE-98 10.80 3.60 38.88 P70 0.80 2.80 1.00 2.24 16.80 16.40 33.20
P70A 0.80 2.15 2.00 3.44
1 2 3 4 5 6 7
18 4. Q-R 3.60 3.60 12.96 BV1.70 0.80 0.70 2.00 1.12 7.20 4.64 11.84
20 R. 9-7A 9.60 3.60 34.56 BV1.70 0.80 0.70 1.00 0.56 0.40 3.60 2.00 2.88 19.20 11.32 30.52
PS 0.60 1.00 1.00 0.60
21 R. 5A-4 9.60 3.60 34.56 BV1.70 0.80 0.70 1.00 0.56 0.40 3.60 2.00 2.88 19.20 11.32 30.52
PS 0.60 1.00 1.00 0.60
22 A. 9-7A 9.60 3.60 34.56 BV1.70 0.80 0.70 1.00 0.56 0.40 3.60 2.00 2.88 19.20 11.32 30.52
PS 0.60 1.00 1.00 0.60
23 A. 5A-4 9.60 3.60 34.56 BV1.70 0.80 0.70 1.00 0.56 0.40 3.60 2.00 2.88 19.20 11.32 30.52
PS 0.60 1.00 1.00 0.60
24 R.7A-5A 8.20 3.60 29.52 PUS 1.30 2.80 1.00 3.64 BV1.70 0.80 0.70 2.00 1.12 0.40 3.60 2.00 2.88 25.52 25.52
25 A.7A-5A 8.20 3.60 29.52 PUS 1.30 2.80 1.00 3.64 BV1.70 0.80 0.70 2.00 1.12 0.40 3.60 2.00 2.88 25.52 25.52
27 Q. 9-4 14.40 3.60 51.84 0.40 3.60 4.00 5.76 21.60 24.48 46.08
28 A. 9-4 14.40 3.60 51.84 0.40 3.60 4.00 5.76 21.60 24.48 46.08
29 L. 9-7 7.20 3.60 25.92 0.40 3.60 2.00 2.88 23.04 23.04
30 G. 9-7 7.20 3.60 25.92 0.40 3.60 2.00 2.88 23.04 23.04
31 K. 10-4 16.10 3.60 57.96 PG-120 1.30 2.80 1.00 3.64 0.40 3.60 5.00 7.20 4.83 45.93 50.76
32 H. 10-4 16.10 3.60 57.96 PG-120 1.30 2.80 1.00 3.64 0.40 3.60 5.00 7.20 4.83 45.93 50.76
34 KM FE-45 18.00 3.60 64.80 P70 0.80 2.80 1.00 2.24 29.20 27.77 56.97
P70A 0.80 2.15 2.00 3.44
LUBANG 1.00 2.15 1.00 2.15
BELAKANG
37 L1. 14-9 18.70 3.60 67.32 BV370 2.30 0.70 5.00 8.05 0.40 3.60 5.00 7.20 52.07 52.07
38 L. 15-14 5.40 3.60 19.44 P70 0.80 2.80 1.00 2.24 17.20 17.20
39 G. 15-14 5.40 3.60 19.44 P70 0.80 2.80 1.00 2.24 17.20 17.20
40 F1. 14-9 18.70 3.60 67.32 BV370 2.30 0.70 5.00 8.05 0.40 3.60 5.00 7.20 52.07 52.07
JUMLAH 458.10 1649.16 144.58 93.84 57.46 126.72 257.26 983.88 1241.14
PERHITUNGAN VOLUME PASANGAN DINDING 1/2 BATA LANTAI I
TINGI DINDING = 3.6 M
TINGGI TRASRAM = 0.4 M
TINGGI TRASRAM KM/WC = 2.0 M
1 2 3 4 5 6 7 8
DEPAN
1 9. A-B 3.60 3.60 12.96 BV1.70 0.80 0.70 2.00 1.12 7.20 4.64 11.84
2 9. B-Q 48.20 3.60 173.52 P80B 0.90 2.15 2.00 3.87 J55 0.65 2.45 20.00 31.85 0.40 3.60 7.00 10.08 19.28 83.94 103.22
JM 1.25 2.45 8.00 24.50
3 9. Q-R 3.60 3.60 12.96 BV1.70 0.80 0.70 2.00 1.12 7.20 4.64 11.84
4 8A. A-B 3.60 3.60 12.96 P70A 0.80 2.15 2.00 3.44 4.00 5.52 9.52
5 8A. Q-R 3.60 3.60 12.96 P70A 0.80 2.15 2.00 3.44 4.00 5.52 9.52
6 7A. A-B 3.60 3.60 12.96 P70V3 0.80 2.80 1.00 3.86 5.60 3.51 9.11
7 7A. Q-R 3.60 3.60 12.96 P70V3 0.80 2.80 1.00 3.86 5.60 3.51 9.11
8 7. B-G 18.00 3.60 64.80 PGV70 1.30 2.50 2.00 9.51 BV470 3.05 0.70 2.00 4.27 0.40 3.60 5.00 7.20 6.16 35.49 41.65
BV270 1.55 0.70 2.00 2.17
9 7. N-Q 10.80 3.60 38.88 PGV70 1.30 2.80 2.00 9.51 BV470 3.05 0.70 1.00 2.14 0.40 3.60 3.00 4.32 3.28 19.64 22.92
10 6. B-H 21.60 3.60 77.76 PGV70 1.30 2.80 2.00 9.51 BV470 3.05 0.70 2.00 8.54 0.40 3.60 6.00 8.64 7.08 38.74 45.82
PG120 1.30 2.80 1.00 3.64 BV370 2.30 0.70 1.00 1.61
11 6. K-Q 21.60 3.60 77.76 PGV70 1.30 2.80 4.00 19.02 BV470 3.05 0.70 2.00 4.27 0.40 3.60 6.00 8.64 5.31 40.52 45.83
16 4. A-B 3.60 3.60 12.96 BV1.70 0.80 0.70 2.00 1.12 7.20 4.64 11.84
17 4. B-Q 48.20 3.60 173.52 J55 0.65 2.45 20.00 31.85 BV1.70 0.80 0.70 2.00 1.12 0.40 3.60 7.00 10.08 19.28 86.69 105.97
JM 1.25 2.45 8.00 24.50
18 4. Q-R 3.60 3.60 12.96 BV1.70 0.80 0.70 2.00 1.12 7.20 4.64 11.84
19 3. H-L 18.80 3.60 67.68 PUT 2.60 2.80 1.00 7.28 J55A 0.65 2.45 6.00 9.56 7.52 31.33 38.85
JK5 2.40 2.50 2.00 12.00
20 R. 9-7A 9.60 3.60 34.56 PS 0.60 1.00 1.00 0.60 BV1.70 0.80 0.70 1.00 0.56 0.40 3.60 2.00 2.88 19.20 11.32 30.52
21 R. 5A-4 9.60 3.60 34.56 PS 0.60 1.00 1.00 0.60 BV1.70 0.80 0.70 1.00 0.56 0.40 3.60 2.00 2.88 19.20 11.32 30.52
1 2 3 4 5 6 7
22 A. 9-7A 9.60 3.60 34.56 PS 0.60 1.00 1.00 0.60 BV1.70 0.80 0.70 1.00 0.56 0.40 3.60 2.00 2.88 19.20 11.32 30.52
23 A. 5A-4 9.60 3.60 34.56 PS 0.60 1.00 1.00 0.60 BV1.70 0.80 0.70 1.00 0.56 0.40 3.60 2.00 2.88 19.20 11.32 30.52
24 R.7A-5A 9.20 3.60 33.12 PUS 1.30 2.80 1.00 3.64 BV1.70 0.80 0.70 2.00 1.12 0.40 3.60 2.00 2.88 3.16 25.96 29.12
25 A.7A-5A 9.20 3.60 33.12 PUS 1.30 2.80 1.00 3.64 BV1.70 0.80 0.70 2.00 1.12 0.40 3.60 2.00 2.88 3.16 25.96 29.12
27 Q. 9-4 14.40 3.60 51.84 0.40 3.60 4.00 5.76 23.04 23.04 46.08
28 A. 9-4 14.40 3.60 51.84 0.40 3.60 4.00 5.76 23.04 23.04 46.08
29 L. 9-3 10.80 3.60 38.88 J55A 0.65 2.45 3.00 4.78 0.40 3.60 3.50 5.04 3.24 25.82 29.06
30 G. 9-3 10.80 3.60 38.88 J55A 0.65 2.45 3.00 4.78 0.40 3.60 3.50 5.04 3.24 25.82 29.06
31 K. 9-3 11.80 3.60 42.48 0.40 3.60 3.00 4.32 3.54 34.62 38.16
32 H. 9-3 11.80 3.60 42.48 0.40 3.60 3.00 4.32 3.54 34.62 38.16
33 E1. 6-5 3.60 3.60 12.96 P70V3 1.30 2.80 3.82 1.44 7.71 9.15
34 KM FE-45 11.90 3.60 42.84 P70 0.80 2.80 2.00 4.48 23.80 14.56 38.36
BELAKANG
35 K1. 10-9 4.30 3.60 15.48 PUS J 1.30 2.80 1.00 10.82 1.20 3.47 4.67
36 G1. 10-9 4.30 3.60 15.48 PUS J 1.30 2.80 1.00 10.82 1.20 3.47 4.67
37 L. 14-10 15.40 3.60 55.44 J55 0.65 2.45 10.00 15.93 0.40 3.60 4.00 5.76 6.16 18.41 24.57
JM 1.25 2.45 3.00 9.19
38 G. 14-10 15.40 3.60 55.44 J55 0.65 2.45 10.00 15.93 0.40 3.60 4.00 5.76 6.16 18.41 24.57
JM 1.25 2.45 3.00 9.19
39 J. 14-10 14.40 3.60 51.84 PGV70 1.30 2.80 1.00 4.76 BV470 3.05 0.70 1.00 2.14 0.40 3.60 4.00 5.76 5.44 31.06 36.50
BV370 2.30 0.70 1.00 1.61
BV270 1.55 0.70 1.00 1.09
40 I. 14-10 14.40 3.60 51.84 PGV70 1.30 2.80 1.00 4.76 BV470 3.05 0.70 1.00 2.14 0.40 3.60 4.00 5.76 5.44 31.06 36.50
BV370 2.30 0.70 1.00 1.61
BV270 1.55 0.70 1.00 1.09
41 10. G-L 16.80 3.60 60.48 PG120 1.30 2.80 2.00 7.28 4.12 35.93 40.05
PGV70 1.30 2.80 2.00 9.51
PUS 1.30 2.80 1.00 3.64
42 GDG 14-LK 9.00 3.60 32.40 P80A 0.90 2.15 1.00 1.94 BV370 2.30 0.70 1.00 1.61 3.24 23.10 26.34
P80A 0.90 2.80 1.00 2.52
43 KM. 14-KJ 10.80 3.60 38.88 P70 0.80 2.80 1.00 2.24 BV1.70 0.80 0.70 1.00 0.56 18.40 15.96 34.36
P70A 0.80 2.15 1.00 1.72
44 KM. 14-I-G 16.20 3.60 58.32 P70 0.80 2.80 2.00 4.48 BV1.70 0.80 0.70 2.00 1.12 26.00 23.28 49.28
P70A 0.80 2.15 2.00 3.44
JUMLAH 504.90 1817.64 162.81 194.04 46.03 119.52 387.67 900.27 1287.94
PERHITUNGAN VOLUME PASANGAN DINDING 1/2 BATA
LANTAI I
SAYAP KIRI
1 9. K-R 28.7 3.6 103.3 P80B 0.90 2.10 1.0 1.9 J55 0.65 2.45 10.0 15.9 BV1.7 0.80 0.80 2.0 1.3 0.4 3.6 7.0 10.1 60.0 8.6 53.3 61.9
JM 1.25 2.45 4.0 12.3
8A. Q-R 3.6 3.6 13.0 P70A 0.80 2.10 2.0 3.4 4.0 5.6 9.6
7A. Q-R 3.6 3.6 13.0 P70V3 3.8 5.6 3.5 9.1
7. L-Q 10.8 3.6 38.9 PGV70 2.0 9.4 BV470 1.0 2.1 0.4 3.6 3.0 4.3 2.5 20.6 23.0
6. K-Q 21.6 3.6 77.8 PGV70 18.8 2.0 4.3 0.4 3.6 6.0 8.6 5.3 40.8 46.1
4. K-R 29.7 3.6 106.9 J55 0.65 2.45 10.0 15.9 0.4 3.6 7.0 10.1 8.9 57.8 66.7
JM 1.25 2.45 4.0 12.3
BV1.70 0.80 0.80 3.0 1.9
3. H1-L 9.4 3.6 33.8 J55A 0.65 2.45 3.0 4.8 2.8 16.6 19.4
JK5 2.40 2.50 1.0 6.0
PUSH 2.60 2.80 0.5 3.6
R. 9-4 24.7 3.6 88.9 BV1.70 0.80 0.80 4.0 2.6 0.4 3.6 5.0 7.2 49.4 29.2 78.6
PS 0.60 1.00 1.0 0.6
Q. 9-4 13.4 3.6 48.2 0.4 3.6 4.0 5.8 14.6 27.9 42.5
L. 9-3 10.8 3.6 38.9 J55A 0.65 2.45 3.0 4.8 0.4 3.6 3.5 5.0 3.2 25.8 29.1
K. 9-3 11.8 3.6 42.5 0.4 3.6 3.0 4.3 3.5 34.6 38.2
PELAKSANAAN
TRASRAM = 250.50 M2 = 25.05 M3 = 37.58 M3
BIASA = 661.32 M2 = 66.13 M3 = 99.20 M3
TOTAL = 911.82 M2 = 91.18 M3 = 136.77 M3
KONTRAK
TRASRAM = 577.02 M2 = 57.70 M3 = 384.68 M2
BIASA = 1262.28 M2 = 126.23 M3 = 841.52 M2
TOTAL = 1839.29 M2 = 183.93 M3 = 1226.20 M2
LAPORAN HARIAN PELAKSANAAN PEKERJAAN
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1 Libur
2
3
4
5
6
7
8
9
10
11
12
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 12 (dua belas)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 17 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 2 (dua)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 13 (tiga belas)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 18 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 2 (dua)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 14 (empat belas)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 19 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 2 (dua)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1 Mobilisasi Material
2
3
4
5
6
7
8
9
10
11
12
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 15 (lima belas)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 20 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 3 (tiga)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 16 (enam belas)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 21 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 3 (tiga)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 17 (tujuh belas)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 22 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 3 (tiga)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 18 (delapan belas)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 23 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 3 (tiga)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1 Libur
2
3
4
5
6
7
8
9
10
11
12
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 19 (sembilan belas)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 24 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 3 (tiga)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 20 (dua puluh)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 25 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 3 (tiga)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 21 (dua puluh satu)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 26 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 3 (tiga)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 22 (dua puluh dua)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 27 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 4 (empat)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 23 (dua puluh tiga)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 28 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 4 (empat)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 24 (dua puluh empat)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 29 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 4 (empat)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 25 (dua puluh lima)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 30 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 4 (empat)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1 Libur
2
3
4
5
6
7
8
9
10
11
12
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 26 (dua puluh enam)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 31 Oktober 2011
Tahun Anggaran : 2011 Minggu ke : 4 (empat)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 27 (dua puluh tujuh)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 1 Novemberr 2011
Tahun Anggaran : 2011 Minggu ke : 4 (empat)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pekerjaan : Pembangunan Kantor Dewan Perwakilan Rakyat Daerah Hari ke : 28 (dua puluh delapan)
Lokasi : Lewoleba - Kecamatan Nubatukan Kabupaten Lembata Tanggal : 2 Novemberr 2011
Tahun Anggaran : 2011 Minggu ke : 4 (empat)
URAIAN PEKERJAAN
NO. PEKERJAAN VOLUME SATUAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
1 2 3 4 3 3
1 LANTAI I 387.67 0.10 38.77 900.27 0.10 90.03 387.67 775.34 900.27 1,800.54
2 LANTAI II 257.26 0.10 25.73 983.88 0.10 98.39 257.26 514.52 983.88 1,967.75
3 BASEMENT 48.52 0.10 4.85 117.29 0.10 11.73 48.52 97.04 117.29 234.59
BACK UP DATA PEMBANGUNAN KANTOR DPRD KAB. LEMBATA
NO KETERANGAN
DIMENSI DIMENSI PANJAN DIMENSI PANJAN
JUMLAH VOLUME VOLUME VOLUME
G G
B H TINGGI B H LUAS B H LUAS
1 2 5 6 7
1 LANTAI I 0.12 0.15 3.60 205.00 13.28 0.12 0.15 0.02 504.90 9.09 TIDAK ADA
2 LANTAI II 0.12 0.15 3.60 169.00 10.95 0.12 0.15 0.02 458.10 8.25 0.12 0.15 0.02 99.00 1.78
3 BASEMENT 0.12 0.15 3.60 4.00 0.26 0.12 0.15 0.02 58.80 1.06 TIDAK ADA
BACK UP DATA PEMBANGUNAN KANTOR DPRD KAB. LEMBATA
1 2 5
1 TALANG 62.29 1.68 0.10 10.43
JUMLAH 24.38
BACK UP DATA PEMBANGUNAN KANTOR DPRD KAB. LEMBATA
KOLOM STRUKTUR Ø 40 CM BALOK BETON 25/40 CM ELEVASI + BALOK BETON 20/30 CM ELEVASI +
TINGGI 3.80 M TINGGI 4.80 M 7,80 M 8,80 M
NO KETERANGAN JUMLA
VOLUME DIMENSI PANJAN DIMENSI PANJAN
LUAS JUMLAH VOLUME LUAS JUMLAH VOLUME KOLOM VOLUME VOLUME
B H G B H G
1 2 5 6 7
1 LANTAI I
2 LANTAI II 0.13 8.00 3.82 0.13 22.00 13.28 17.10 0.25 0.40 105.60 10.56 0.20 0.30 76.80 4.61
3 BASEMENT
JUMLAH 17.10 10.56 4.61
KETERANGAN :
NO KETERANGAN
LUAS
BANGUN LUAS LUAS TEBAL VOLUME LUAS TEBAL VOLUME
AN
1 2 3 4
1 LANTAI I
2 LANTAI II 257.26 0.10 25.73 983.88 0.10 98.39 0.12 0.15 3.60 169.00 10.95 0.12 0.15 0.02 458.10 8.25 0.12 0.15 0.02 0.00
3 BASEMENT 0.12 0.15 3.60 0.00 0.12 0.15 0.02 0.00 0.12 0.15 0.02 0.00
JUMLAH 644.93 64.49 1,884.15 188.41 24.24 17.33 0.00
URUGAN TANAH KOLOM STRUKTUR Ø 40 CM BALOK BETON 25/40 CM ELEVASI + BALOK BETON 20/30 CM ELEVASI +
RABAT BETON LANTAI
PENINGGIAN LANTAI TINGGI 3.80 M TINGGI 4.80 M 7,80 M 8,80 M
NO KETERANGAN JUMLA
VOLUME DIMENSI PANJAN DIMENSI PANJAN
LUAS TEBAL VOLUME LUAS TEBAL VOLUME LUAS JUMLAH VOLUME LUAS JUMLAH VOLUME KOLOM VOLUME VOLUME
B H G B H G
1 2 3 4 5 6 7
1 LANTAI I 0.10 0.00 0.10 0.00
2 LANTAI II 0.13 8.00 3.82 0.13 22.00 13.28 17.10 0.25 0.40 105.60 10.56 0.20 0.30 76.80 4.61
3 BASEMENT
BEKISTING KOLOM 40 CM
BALOK
PERBANDINGAN VOLUME DAN HARGA
123,290,746.00
PERHITUNGAN KEBUTUHAN BERAT BESI BETON PRAKTIS DAN BETON STRUKTUR
NO KETERANGAN BERAT BESI PER METER KUBIK BETON VOLUME BERAT TOTAL
PEKERJAAN
Dimensi Tul. Utama 4 ø 12 Beugel ø 8 - 200 Jumlah
Pjg/m3
b h Pjg. tul. Berat pjg/beugel Jml beugel Pjg beugel Berat Berat
praktis 12/15, tul. 4
1 ø 12, beugel ø 8 - 24.24 5,872.66
200 0.12 0.15 55.56 222.22 197.33 0.41 277.78 113.89 44.99 242.32
KOLOM PER M3
DIAMETER 0.4 M
PENAMPANG 0.12571429 M2
PANJANG 7.95454545 M
BEUGEL
DIAMETER 0.35 M
KELILING 1.21 M
JARAK BEUGEL 0.125 M
JUMLAH BEUGEL 63.6363636 BH
PANJANG BEUGEL 77 M
TOTAL JUMLAH BESI = 21,462.57
HARGA SATUAN KONTRAK = 18,730.25
TOTAL HARGA KONTRAK = 401,999,305.11