A D W A L    P E L A K S A N A A N     P E K E R J A A N

PEKERJAAN : PEMBANGUNAN GEDUNG ICCU RSUD WALANDA MARAMIS
LOKASI : KABUPATEN MINAHASA UTARA
TAHUN ANGGARAN : 2021

Bobot M I N G G U   K E   ‐
No URAIAN PEKERJAAN KET.
% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

I PEKERJAAN PERSIAPAN 0.631 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032

II PEKERJAAN DINDING 10.106 1.263 1.263 1.263 1.263 1.263 1.263 1.263 1.263

III PEKERJAAN LANTAI 9.931 0.993 0.993 0.993 0.993 0.993 0.993 0.993 0.993 0.993 0.993

IV PEKERJAAN PLAFOND 6.357 1.059 1.059 1.059 1.059 1.059 1.059

V PEKERJAAN PINTU, JENDELA, VENTILA 1.410 0.117 0.117 0.117 0.117 0.117 0.117 0.117 0.117 0.117 0.117 0.117 0.117

VI PEKERJAAN ELEKTRIKAL 1.573 0.131 0.131 0.131 0.131 0.131 0.131 0.131 0.131 0.131 0.131 0.131 0.131

VII PEKERJAAN MEKANIKAL 10.548 1.055 1.055 1.055 1.055 1.055 1.055 1.055 1.055 1.055 1.055

VIII PEKERJAAN INSTALASI GAS 1.131 0.141 0.141 0.141 0.141 0.141 0.141 0.141 0.141

IX PEKERJAAN SANITASI DAN INSTALASI  0.762 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048

X PEKERJAAN RUANG CATHLAB 17.393 1.242 1.242 1.242 1.242 1.242 1.242 1.242 1.242 1.242 1.242 1.242 1.242 1.242 1.242

XI PEKERJAAN PEMASANGAN PENDANT 24.472 1.530 1.530 1.530 1.530 1.530 1.530 1.530 1.530 1.530 1.530 1.530 1.530 1.530 1.530 1.530 1.530

XII PEKERJAAN KORIDOR 15.685 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871 0.871

A Jumlah Bobot 100.00 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 7 HK 3 HK
B Prosentasi Kemajuan Pekerjaan 0 0 1.29 2.54 3.83 4.70 7.43 7.43 8.48 8.48 7.22 7.22 6.16 6.16 5.03 5.03 4.78 3.53 2.48 2.48 2.43 2.43 0.87 0.00 150 HK
C Prosentasi Kumulatif 0 1.29 3.83 7.66 12.36 19.78 27.21 35.70 44.18 51.40 58.62 64.78 70.94 75.97 80.99 85.77 89.30 91.78 94.26 96.70 99.13 100.00 100.00

WAKTU PELAKSANAAN : 150 Hari Kalender Manado, ..  Juni 2021
CV. UKI
 

Direktur
M E T O D E    P E L A K S A N A A N

PEKERJAAN : PEMBANGUNAN GEDUNG ICCU RSUD WALANDA MARAMIS
LOKASI : KABUPATEN MINAHASA UTARA
TAHUN ANGGARAN : 2021

Jadwal Pelaksanaan MINGGU KE KETERANGAN


No. URAIAN PEKERJAAN
Lama  1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

Se
M
ul

le
Mi P k j
I Pekerjaan Persiapan 1 20 20 Minggu  I I I I I I I I I I I I I I I I I I I I

II Pekerjaan Dinding 1 8 8 Minggu  II II II II II II II II

III Pekerjaan Lantai 3 12 10 Minggu  III III III III III III III III III III

IV Pekerjaan Plafond 5 10 6 Minggu  IV IV IV IV IV IV

V Pekerjaan Pintu, Jendela, Ventilasi Pen 3 14 12 Minggu  V V V V V V V V V V V V

VI Pekerjaan Elektrikal 3 14 12 Minggu  VI VI VI VI VI VI VI VI VI VI VI VI

VII Pekerjaan Mekanikal 7 16 10 Minggu  VII VII VII VII VII VII VII VII VII VII

VIII Pekerjaan Instalasi Gas 5 12 8 Minggu  VIII VIII VIII VIII VIII VIII VIII VIII

IX Pekerjaan Sanitasi Dan Instalasi Air Be 3 18 16 Minggu  IX IX IX IX IX IX IX IX IX IX IX IX IX IX IX IX

X Pekerjaan Ruang Cathlab 2 15 14 Minggu  X X X X X X X X X X X X X X

XI Pekerjaan Pemasangan Pendant 5 20 16 Minggu  XI XI XI XI XI XI XI XI XI XI XI XI XI XI XI XI

XII Pekerjaan Koridor 4 21 18 Minggu  XII XII XII XII XII XII XII XII XII XII XII XII XII XII XII XII XII XII

PERSENTASI KEMAJUAN PEKERJAAN 1.29 2.54 3.83 4.70 7.43 7.43 8.48 8.48 7.22 7.22 6.16 6.16 5.03 5.03 4.78 3.53 2.48 2.48 2.43 2.43 0.87 0.00

   

Manado, ..  Juni 2021
CV. UKI

####
Direktur