Anda di halaman 1dari 14

Pemesan PT ABC /PJB

Pekerjaan Daerator
Fabrikasi 1081
No Uraian Tot Volume Hsat H Tot Volume Hsat H Tot
JO Rp Rp JM Rp Rp
1 Unld/Anld
Foreman 1 4 28547 114,188
Fitter 1 4 18750 75,000
Rigger 2 4 10000 80,000
Helper 4 4 9500 152,000
2 Marking/ Steel
Fitter 2 6 18750 225,000
Helper 4 6 9500 228,000
3 Cutting
Fitter 1 10 25817 258,170 15 11,532 172,980
Helper 2 9500 -
4 Welding
Welder 4 15 27643 1,658,580 25 10,537 263,425
Helper 1 9500 -
5 Rool/Prees
Fitter 1 10 28547 285,470 10 24,842 248,420
Helper 2 10 9500 190,000
6 Boor
Fitter 1 29440 - 10 13,950 139,500
Helper 2 9500 -
7 Finsh/Grinding
Fitter 1
Helper 2 15 9500 285,000 15 33,257 498,855

3,551,408 1,323,180
4,874,588

-
Pemesan PT Intan
Pekerjaan Tank
Alat Kerja

HARGA JUMLAH KETERANGA


No. URAIAN VOLUME
SATUAN Rp HARGA Rp N
1 Chain block 10 ton
2 Chain block 5 ton 4 2,000,000 8,000,000
3 Chain block 3 ton bh 2 1,500,000 3,000,000
4 Chain block 1,5 ton
5 Mesin bor magnit
6 Mesin bor beton
7 Mesin bor tangan
8 Mesin gerinda ø 4 bh 8 1,500,000 12,000,000
9 Mesi gerinda ø 6 bh 8 1,750,000 14,000,000
10 Mesin gerinda lilin
11 Hydraulic jack 100 ton
12 Hydraulic jack 50 ton
13 Hydraulic jack 30 ton
14 Hydraulic jack 10 ton
15 Hydraulic jack 5 ton
16 Speed cutter 17"
17 Jack multipurpose 25 ton
18 Container box
19 Peti besi tempat alat 1 2,500,000 2,500,000
20 Tool box 1 2,000,000 2,000,000
21 Pipa seafolding + clamp ljr 60 332,590 19,955,400
22 Level block 5 ton bh 2 3,500,000 7,000,000
23 Level block 3 ton bh 2 2,500,000 5,000,000
24 Level block 1,5 ton
25 Seling kolong m 10 50,000 500,000
26 Wairope m 100 15,000 1,500,000
27 Sabuk pengaman bh 10 47,500 475,000
28 Mesin bonding pipa -
29 Hand Body hardenes 2,750,000 -
30 Pemanas Kawat Las 5kg
31 Pemanas Kawat Las 10kg bh 2 50,000 100,000
32 Stang Laas 500A/600A bh 4 75,000 300,000
33 Blander potong 2 225,000 450,000
34 Blander pemanas -
35 Slang Oksigin m 50 85,000 4,250,000
36 Regulato Oks& Acit -
37 Regulator LPG -
38 Siku tukang -
39 Segel 3/4" ,5/8" bh 4 25,000 100,000
40 Segel 1" ,2" bh 4 40,000 160,000
41 Water Muur 1'', 2" bh 4 20,000 80,000
42 Hamer bh 4 20,000 80,000
43 Kabel Lass m 50 95,000 4,750,000
44 Panel -
45 Kabel Power 50 85,000 4,250,000
46 Kunci Pas 6- 32" bh 2 60,000 120000
47 Kunci Ring 6- 32"
48 Kunci Sook 6-32"
49 Kunci L 6-32"
50 Kunci Inggris bh 2 50,000 100,000
51 Tang Potong
52 Tang kombinasi bh 2 20,000 40,000
53 Obeng Set
54 Fitting Lamp spot light bh 4 250,000 1,000,000
55 Drum Rotator 20ton
56 Drum Rotator 40ton
57 Ms Roll Plat

TOTAL 91,710,400
Pemesan PT INTAN 27,433
Pekerjaan TANK Hitung Perkedatangan nya SAJA
Xray
Kedt& Alat 900,000
Film 600,000
1,500,000 15 22,500,000 820.2 kg

Hydro Tes

Alat 4,500,000 2 9,000,000


Flens 3,500,000 2 7,000,000
Upah 100,000 14 1,400,000
17,400,000
Air 450,000 14 6,300,000
23,700,000 863.9 kg
Pemesan PT INTAN
Pekerjaan TANK

Volume HARGA JUMLAH Keterangan


No. URAIAN
SATUAN Rp HARGA Rp

1 Direksi koot 5x2 m m2 1 8 450,000 3,600,000


2 Kendaraan kijang bh 1 45 150,000 6,750,000
3 Kendaraan Picup bh 1 45 130,000 5,850,000
4 Sepeda montor bh 20 50,000 -
5 Premium lt 1 300 6,000 1,800,000
6 Solar -
7 Olie lt 1 15 25,000 375,000
8 Spare part / service -
9 Pakaian kerja stel 1 250,000 -
10 Sepatu kerja psg 1 150,000 -
11 Helm kerja bh 1 20 25,000 500,000
12 Biaya tamu ls 1 1 1,000,000 1,000,000
13 Biaya pengobatan ls 1 1 1,000,000 1,000,000
14 Biaya minum lapangan ls 1 1 1,000,000 1,000,000
15 Biaya interlokal + surat ls -
16 Biaya sewa rumah u/mes hr 1 20 250,000 5,000,000
17 Biaya fasilitas mess -
18 Biaya fasilitas kantor ls 1 1 750,000 750,000
19 BiayaMob/Demob ten. ls 20 1 150,000 3,000,000
20 Bi.Test Commiss ls -
21 Container Book bh 2 3,000,000 -

30,625,000
Pemesan : PT SG Pelabuan Tuban
Pekerjaan : 649 BC3 Cony
Bahan bantu
No Uraian Tol Volume Hsat Htot Keterangan
Rp Rp
1 Oxcigin bt 10 50,000 500,000
2 Acitilin bt 5 150,000 750,000
3 Elpiji bt 300000 -
4 Bt Gerinda 7" bt 10 100000 1,000,000
5 Bt Gerinda 4" bh 20 15,000 300,000
6 Kawat Lass CS kg 220 30,000 6,600,000
7 Kawat Lass SUS kg 80,000 -
8 Kawat Lass Cor
9 Kawat Gouging
10 Kaca mta u/potong
11 Kaca las hitam bh 10 2,500 25,000
12 Kaca lasputh bh 20 500 10,000
13 Paint maker
14 Sikat bajasus bh 10 15,000 150,000
15 Kap Laas bh 10 35,000 350,000
16 Sarungtangan Pand bh 15 25,000 375,000
17 Sarungtangan Pendek bh 20 10,000 200,000
18 Majun kg 2 5,000 10,000
19 Holder bh 2 105,000 210,000
20 Grease
21 Oil
22 Masker bh 15 2,500 37,500
23 Kacamata u/Grinda bh 20 10,000 200,000
24 Jig kg 250 7,500 1,875,000
25 Baut&Mur
26 Rool meter 5m bh 2 15,000 30,000
27 Coal borster
28 Mata boor bh 25,000 -
29 Argon
30 Tungsten
31 Filler
32 Piao wire
33 Tali manila m 100 15,000 1,500,000
34 Tali nylon
35 Plat umal
36 Kawat tali
37 Bes beton dia12
38 Plat strip
39 PP 2/20
40 Plat 4'x8'
41 Plat u/paju 200x100x30
42 Plat u/strong back
43 Plat u/bracket 150x100
44 Plat u/Stopper
45 Seal Tape
46 Isolasi tape
47 Mata gergaji
48 Benang
49 Kertas gosok
50 Terpal plastik lb 2 25000 50,000
TOTAL 14,172,500
Rate
Pemesan PT PJB PAITON
Pekerjaan Pemasangan PULFURIZER

No Uraian Volume Sat Dur Sat Harga Sat No Uraian Volume Sat
Rp
Tenaga Musiman Tenaga Musiman
1 Foreman 2 Fitter
Upah 1 org 1 hr 80,000 Upah 1 org
U Makan 1 org 1 hr 10,000 U Makan
U transport Lokal 1 org 1 hr 3,000 U transport Lokal
Upah Lembur 1 org 1 hr 40,000 Upah Lembur
U makan Lembur 1 org 1 hr 5,000 U makan Lembur
Transport Lembur 1 org 1 hr 2,000 Transport Lembur
Pesangon 1 org 1 hr 8,000 Pesangon
Total/ hari 148,000 Total/ hari

3 Welder 4 Surveyor
Upah 1 org 1 hr 100,000 Upah 1 org
U Makan 1 org 1 hr 10,000 U Makan 1 org
U transport Lokal 1 org 1 hr 3,000 U transport Lokal 1 org
Upah Lembur 1 org 1 hr 50,000 Upah Lembur 1 org
U makan Lembur 1 org 1 hr 5,000 U makan Lembur 1 org
Transport Lembur 1 org 1 hr 2,000 Transport Lembur 1 org
Pesangon 1 org 1 hr 10,000 Pesangon 1 org
Total/ hari 180,000 Total/ hari

5 Helper Site Man


Upah 1 org 1 hr 40,000 Upah 1 org
U Makan 1 org 1 hr 10,000 U Makan 1 org
U transport Lokal 1 org 1 hr 3,000 U transport Lokal 1 org
Upah Lembur 1 org 1 hr 20,000 Upah Lembur 1 org
U makan Lembur 1 org 1 hr 5,000 U makan Lembur 1 org
Transport Lembur 1 org 1 hr 2,000 Transport Lembur 1 org
Pesangon 1 org 1 hr 5,000 Pesangon 1 org
Total/ hari 85,000 Total/ hari
Dur Sat Harga Sat
Rp

1 hr 65,000
10,000
3,000
30,000
5,000
2,000
6,500
121,500

1 hr 80,000
1 hr 10,000
1 hr 3,000
1 hr 40,000
1 hr 5,000
1 hr 2,000
1 hr 8,000
148,000

1 hr 290,000
1 hr 25,000
1 hr 10,000
1 hr 150,000
1 hr 15,000
1 hr 5,000
1 hr
495,000
Pemesan : PT SG Pelabuan Tuban
Pekerjaan : 649 BC3 Cony RINCIAN - RENCIAN KEBUTUHAN HARGA : U P A H

262,128.00
N HARGA JUMLAH KETERA
URAIAN VOLUME
o. Tot SATUAN Rp HARGA Rp NGAN

1 Manager Proyek HARI 227,488 -


2 Site Manager 1 HARI 90 206,536 18,588,240
3 Manager V P C
4 Manager Admikum
5 Manager Teknologi
6 Manager Quality Control 1 HARI 90 206,536 18,588,240
7 Supervisor Mech
8 Supervisor Elect
9 Supervisor Inst
### Supervisor Fab
### Supervisor Wolder 1 HARI 90 206,536 18,588,240
### Driver 1 HARI 90 75,000 6,750,000
### Operator 1 HARI 90 75,000 6,750,000
### Offioo Boy 1 HARI 90 75,000 6,750,000
### Scourity 2 HARI 90 75,000 13,500,000
### Forman 2 HARI 90 206,536 37,176,480
### Fitter 4 HARI 90 125,000 45,000,000
### Helper 10 HARI 90 75,000 67,500,000
### Welder 4 HARI 90 150,000 54,000,000
### Gas Cutting 2 HARI 90 125,000 22,500,000
### Surveyor 1 HARI 90 150,000 13,500,000
### Rugger 2 HARI 90 150,000 27,000,000
### Main tenan 1 HARI 90 125,000 11,250,000
TOTAL 34 367,441,200
1,401.76
AH
Pemesan : PT SG Pelabuan Tuban
Pekerjaan : 649 BC3 Cony

VOLUME HARGA HARGA Jumlh


No. URAIAN Qty
Waktu SATUAN Rp Rp
1 Mobil crano 20 ton 1 30 1,500,000 45,000,000
2 Mobil crano 50 ton 20 4,500,000 -
3 Mobil crano 80 ton 1 8,500,000 -
4 Mobil crano 125 ton 30 6,644,000 -
5 Traillor 8 ton / 40 ton
6 Truck 8 ton / 10 ton
7 Gonsot 75 KVA
8 Gonsot 125 KVA
9 Gonsot 225 KVA
10 Gonsot 250 KVA 1 450,000 -
11 Electric winch 15 ton
12 Electric winch 25 ton
13 Comprossor 8 bar
14 Mesin las trafo 2 150,000 -
15 Mesin las diesel 2 45 250,000 22,500,000
16 Solar 60 45 8500 22,950,000
17 Promium
18 Olio
19 Sorvico / spare part
20 Mobilisasi & domobilisasi
21 Forklif 3 ton
22 Forklif 5 ton
23 Forklif 10 ton
24 Over head orane
25 Mesin Roll plate

Total 90,450,000
Pemesan PT INTAN
Pekerjaan TANK
RekPemasangan 27,433

No Uraian PT BI sub

1 Upah 367,441,200 0.75 275,580,900


2 Alat Berat 90,450,000 0.5 45,225,000
3 Alat kerja 91,710,400 0.4 36,684,160
4 Bahan bantu 14,172,500 0.75 10,629,375
5 Alat/Ukur 5,000,000 1 5,000,000
6 Keet/Fas 30,625,000 0.45 13,781,250

Total 599,399,100 386,900,685.00


14,103.32

TOTAL -
Pemesan PT KE PG
Pekerjaan STACK PG

No Uraian Qty Volume H Sat H Jml Keterangan

1 Dum level&tripot
2 Theodolit 1 20 250,000 5,000,000
3 Dial gauge
4 Megger
5 Megger
6 Water Pas Persisi
7 Water Pas Alumunium
8 Penggaris stls 1m
9 Penggaris stls 2m
10 Mistar block
11 Roll meter 30m
12 Fuller
13 Out side Mic
14 In sideMic
15 Dept mikro
16 Multitester
17 Tacemeter
18 Thermo meter
19 Stop wacth
20 Kompas
21 Werner caliper
22 Micr test

TOTAL 5,000,000