Pekerjaan Daerator
Fabrikasi 1081
No Uraian Tot Volume Hsat H Tot Volume Hsat H Tot
JO Rp Rp JM Rp Rp
1 Unld/Anld
Foreman 1 4 28547 114,188
Fitter 1 4 18750 75,000
Rigger 2 4 10000 80,000
Helper 4 4 9500 152,000
2 Marking/ Steel
Fitter 2 6 18750 225,000
Helper 4 6 9500 228,000
3 Cutting
Fitter 1 10 25817 258,170 15 11,532 172,980
Helper 2 9500 -
4 Welding
Welder 4 15 27643 1,658,580 25 10,537 263,425
Helper 1 9500 -
5 Rool/Prees
Fitter 1 10 28547 285,470 10 24,842 248,420
Helper 2 10 9500 190,000
6 Boor
Fitter 1 29440 - 10 13,950 139,500
Helper 2 9500 -
7 Finsh/Grinding
Fitter 1
Helper 2 15 9500 285,000 15 33,257 498,855
3,551,408 1,323,180
4,874,588
-
Pemesan PT Intan
Pekerjaan Tank
Alat Kerja
TOTAL 91,710,400
Pemesan PT INTAN 27,433
Pekerjaan TANK Hitung Perkedatangan nya SAJA
Xray
Kedt& Alat 900,000
Film 600,000
1,500,000 15 22,500,000 820.2 kg
Hydro Tes
30,625,000
Pemesan : PT SG Pelabuan Tuban
Pekerjaan : 649 BC3 Cony
Bahan bantu
No Uraian Tol Volume Hsat Htot Keterangan
Rp Rp
1 Oxcigin bt 10 50,000 500,000
2 Acitilin bt 5 150,000 750,000
3 Elpiji bt 300000 -
4 Bt Gerinda 7" bt 10 100000 1,000,000
5 Bt Gerinda 4" bh 20 15,000 300,000
6 Kawat Lass CS kg 220 30,000 6,600,000
7 Kawat Lass SUS kg 80,000 -
8 Kawat Lass Cor
9 Kawat Gouging
10 Kaca mta u/potong
11 Kaca las hitam bh 10 2,500 25,000
12 Kaca lasputh bh 20 500 10,000
13 Paint maker
14 Sikat bajasus bh 10 15,000 150,000
15 Kap Laas bh 10 35,000 350,000
16 Sarungtangan Pand bh 15 25,000 375,000
17 Sarungtangan Pendek bh 20 10,000 200,000
18 Majun kg 2 5,000 10,000
19 Holder bh 2 105,000 210,000
20 Grease
21 Oil
22 Masker bh 15 2,500 37,500
23 Kacamata u/Grinda bh 20 10,000 200,000
24 Jig kg 250 7,500 1,875,000
25 Baut&Mur
26 Rool meter 5m bh 2 15,000 30,000
27 Coal borster
28 Mata boor bh 25,000 -
29 Argon
30 Tungsten
31 Filler
32 Piao wire
33 Tali manila m 100 15,000 1,500,000
34 Tali nylon
35 Plat umal
36 Kawat tali
37 Bes beton dia12
38 Plat strip
39 PP 2/20
40 Plat 4'x8'
41 Plat u/paju 200x100x30
42 Plat u/strong back
43 Plat u/bracket 150x100
44 Plat u/Stopper
45 Seal Tape
46 Isolasi tape
47 Mata gergaji
48 Benang
49 Kertas gosok
50 Terpal plastik lb 2 25000 50,000
TOTAL 14,172,500
Rate
Pemesan PT PJB PAITON
Pekerjaan Pemasangan PULFURIZER
No Uraian Volume Sat Dur Sat Harga Sat No Uraian Volume Sat
Rp
Tenaga Musiman Tenaga Musiman
1 Foreman 2 Fitter
Upah 1 org 1 hr 80,000 Upah 1 org
U Makan 1 org 1 hr 10,000 U Makan
U transport Lokal 1 org 1 hr 3,000 U transport Lokal
Upah Lembur 1 org 1 hr 40,000 Upah Lembur
U makan Lembur 1 org 1 hr 5,000 U makan Lembur
Transport Lembur 1 org 1 hr 2,000 Transport Lembur
Pesangon 1 org 1 hr 8,000 Pesangon
Total/ hari 148,000 Total/ hari
3 Welder 4 Surveyor
Upah 1 org 1 hr 100,000 Upah 1 org
U Makan 1 org 1 hr 10,000 U Makan 1 org
U transport Lokal 1 org 1 hr 3,000 U transport Lokal 1 org
Upah Lembur 1 org 1 hr 50,000 Upah Lembur 1 org
U makan Lembur 1 org 1 hr 5,000 U makan Lembur 1 org
Transport Lembur 1 org 1 hr 2,000 Transport Lembur 1 org
Pesangon 1 org 1 hr 10,000 Pesangon 1 org
Total/ hari 180,000 Total/ hari
1 hr 65,000
10,000
3,000
30,000
5,000
2,000
6,500
121,500
1 hr 80,000
1 hr 10,000
1 hr 3,000
1 hr 40,000
1 hr 5,000
1 hr 2,000
1 hr 8,000
148,000
1 hr 290,000
1 hr 25,000
1 hr 10,000
1 hr 150,000
1 hr 15,000
1 hr 5,000
1 hr
495,000
Pemesan : PT SG Pelabuan Tuban
Pekerjaan : 649 BC3 Cony RINCIAN - RENCIAN KEBUTUHAN HARGA : U P A H
262,128.00
N HARGA JUMLAH KETERA
URAIAN VOLUME
o. Tot SATUAN Rp HARGA Rp NGAN
Total 90,450,000
Pemesan PT INTAN
Pekerjaan TANK
RekPemasangan 27,433
No Uraian PT BI sub
TOTAL -
Pemesan PT KE PG
Pekerjaan STACK PG
1 Dum level&tripot
2 Theodolit 1 20 250,000 5,000,000
3 Dial gauge
4 Megger
5 Megger
6 Water Pas Persisi
7 Water Pas Alumunium
8 Penggaris stls 1m
9 Penggaris stls 2m
10 Mistar block
11 Roll meter 30m
12 Fuller
13 Out side Mic
14 In sideMic
15 Dept mikro
16 Multitester
17 Tacemeter
18 Thermo meter
19 Stop wacth
20 Kompas
21 Werner caliper
22 Micr test
TOTAL 5,000,000