Page : 1 / 7
AKUNT VOLUME DURASI HARGA TOTAL
URAIAN
(CODE) QTY SAT QTY SAT SATUAN HARGA
5132 UPAH LEMBUR TL / ORGANIK
5132.01 FOREMAN
5132.06.01 - Upah lembur ORG 25 HR 42,000 0
5132.06.02 - Uang makan lembur ORG 25 HR 10,000 0
5132.06.03 - Transport lembur ORG 25 HR 5,000 0
5132.01 (2 Orang) 0
5132.02 WELDER
5132.06.01 - Upah lembur ORG 25 HR 42,000 0
5132.06.02 - Uang makan lembur ORG 25 HR 10,000 0
5132.06.03 - Transport lembur ORG 25 HR 5,000 0
5132.02 (2 Orang) 0
Jumlah (5132) 0
5134 DETASERING
5134.01 PROJECT MANAGER
5134.01.01 - Uang makan & saku 1 ORG 540 HR 225,000 121,500,000
5134.01.02 - Transport, minum & Susu 1 ORG 540 HR -
5134.01.03 - Tunjangan proyek 1 ORG 540 HR 17,500 9,450,000
5134.01.04 - Uang lembur/kompensasi kehadiran 1 ORG 540 HR 26,400 14,256,000
5134.01.05 - U. Makan lembur / Komp. kehadiran 1 ORG 540 HR 15,000 8,100,000
5134.01 (1 orang) 283,900.00 153,306,000
5134.02 STAF PROMAN
5134.02.01 - Uang Makan, Saku & Pemondokan - ORG 540 HR
5134.02.02 - Transport, Minum & Susu - ORG 540 HR -
5134.02.03 - Tunjangan proyek - ORG 540 HR -
5134.02.04 - Uang lembur/kompensasi kehadiran - ORG 540 HR -
5134.02.05 - U. Makan lembur / Komp. kehadiran - ORG 540 HR 0
5134.02.06 - U. Tranp. lembur / Komp. kehadiran - ORG 540 HR -
5134.02 0.00
5134.03 SITE MANAGER
5134.03.01 - Uang Makan, Saku & Pemondokan 1 ORG 540 HR 250,000 135,000,000
5134.03.02 - Transport, Minum & Susu 1 ORG 540 HR -
5134.03.03 - Tunjangan proyek 1 ORG 540 HR 13,200 7,128,000
5134.03.04 - Uang lembur/kompensasi kehadiran 1 ORG 540 HR 26,000 14,040,000
5134.03.05 - U. Makan lembur / Komp. kehadiran 1 ORG 540 HR 75,000 40,500,000
5134.03.06 - U. Tranp. lembur / Komp. kehadiran 1 ORG 540 HR 6,000 3,240,000
5134.03 370,200 199,908,000
5134.04 ENGINEERING MANAGER
5134.04.01 - Uang Makan, Saku & Pemondokan 1 ORG 540 HR 225,000 121,500,000
5134.04.02 - Transport, Minum & Susu 1 ORG 540 HR -
5134.04.03 - Tunjangan proyek 1 ORG 540 HR 13,200 7,128,000
5134.04.04 - Uang lembur/kompensasi kehadiran 1 ORG 540 HR 16,000 8,640,000
5134.04.05 - U. Makan lembur / Komp. kehadiran 1 ORG 540 HR 75,000 40,500,000
5134.04.06 - U. Tranp. lembur / Komp. kehadiran 1 ORG 540 HR 6,000 3,240,000
5134.04 335,200 181,008,000
5134.05 PPC MANAGER
5134.05.01 - Uang makan & saku 1 ORG 540 HR 225,000 121,500,000
5134.05.02 - Transport, Minum & Susu 1 ORG 540 HR -
5134.05.03 - Tunjangan proyek 1 ORG 540 HR 13,200 7,128,000
5134.05.04 - Uang lembur/kompensasi kehadiran 1 ORG 540 HR - 0
5134.05.05 - U. Makan lembur / Komp. kehadiran 1 ORG 540 HR 75,000 40,500,000
Page : 2 / 7
AKUNT VOLUME DURASI HARGA TOTAL
URAIAN
(CODE) QTY SAT QTY SAT SATUAN HARGA
5134.05.06 - U. Tranp. lembur / Komp. kehadiran 1 ORG 540 HR 6,000 3,240,000
5134.05 (1 orang) 319,200 172,368,000
5134.06 QC MANAGER
5134.06.01 - Uang makan & saku 1 ORG 540 HR 225,000 121,500,000
5134.06.02 - Transport, Minum & Susu 1 ORG 540 HR -
5134.06.03 - Tunjangan proyek 1 ORG 540 HR 13,200 7,128,000
5134.06.04 - Uang lembur/kompensasi kehadiran 1 ORG 540 HR 16,000 8,640,000
5134.06.05 - U. Makan lembur / Komp. kehadiran 1 ORG 540 HR 75,000 40,500,000
5134.06.06 - U. Tranp. lembur / Komp. kehadiran 1 ORG 540 HR 6,000 3,240,000
5134.06 (1 orang) 335,200 181,008,000
5134.04 WELDER
5134.04.01 - Uang makan & saku ORG 25 HR 45,000 -
5134.04.02 - Transport, Minum & Susu ORG 25 HR -
5134.04.03 - Tunjangan proyek ORG 25 HR 7,500 -
5134.04.04 - Uang lembur/kompensasi kehadiran ORG 250 HR 7,500 0
5134.04.05 - U. Makan lembur / Komp. kehadiran ORG 250 HR 15,000 -
5134.04.06 - U. Tranp. lembur / Komp. kehadiran ORG 25 HR 6,000 -
5134.04 0
5134.05 S/V STRUKTUR & MEKANIKAL
5134.05.01 - Uang makan & saku ORG 25 HR 45,000 -
5134.05.02 - Transport, Minum & Susu - ORG 25 HR -
5134.05.03 - Tunjangan proyek - ORG 25 HR 7,500 -
5134.05.04 - Uang lembur/kompensasi kehadiran - ORG 25 HR - 0
5134.05.05 - U. Makan lembur / Komp. kehadiran - ORG 25 HR 15,000 -
5134.05.06 - U. Tranp. lembur / Komp. kehadiran - ORG 25 HR 6,000 -
5134.05 (1 orang) 0
5134.06 FORMAN
5134.06.01 - Uang makan & saku ORG 30 HR 45,000 -
5134.06.02 - Transport, Minum & Susu ORG 30 HR -
5134.06.03 - Tunjangan proyek ORG 30 HR 7,500 -
5134.06.04 - Uang lembur/kompensasi kehadiran ORG 30 HR - 0
5134.06.05 - U. Makan lembur / Komp. kehadiran ORG 300 JAM 7,500 -
5134.06.06 - U. Tranp. lembur / Komp. kehadiran ORG 50 JAM 6,000 -
5134.06 (1 orang) 0
5135 KESEJAHTERAAN
5135.01 Pakaian kerja 635 BH 1 BLN 250,000 158,690,404
5135.02 Pengobatan 635 BH 3 BLN 50,000 95,214,242
5135.03 Olah Raga / Rekrteasi BH 3 BLN 5,000 0
5135.04 Sepatu kerja BH 1 BLN 150,000 0
Jumlah (5135) 253,904,646
5136 MOBILISASI
5136.01 Cuti proyek tenaga organik
5136.02 Perjalanan Dinas 36 BH 1 RIT 2,500,000 90,000,000
5136.03 Mob / Demob Tenaga Organik 200 BH 1 RIT 100,000 20,000,000
Jumlah (5136) 110,000,000
5137 KARYAWAN LEPAS :
5137.01 TENAGA ADMINISTRASI
5137.01.01 - Upah 10 ORG 540 HR 100,000 540,000,000
5137.01.02 - Uang makan 10 ORG 540 HR 15,000 81,000,000
5137.01.03 - Uang transport 10 ORG 540 HR 4,000 21,600,000
5137.01.04 - Upah lembur 10 ORG 540 HR 5,000 27,000,000
5137.01.05 - Uang makan lembur 10 ORG 540 HR 3,000 16,200,000
5137.01.06 - Transport lembur 10 ORG 540 HR 2,000 10,800,000
5137.01.07 - Pesangon 10 ORG 540 HR 5,850 31,590,000
5,137.01 134,850.00 728,190,000
Page : 3 / 7
AKUNT VOLUME DURASI HARGA TOTAL
URAIAN
(CODE) QTY SAT QTY SAT SATUAN HARGA
5137.02 SECURITY
5137.02.01 - Upah / bulan (Upah,Transp & Makan) 40 ORG 540 HR 125,000 2,700,000,000
5137.02.02 - Upah lembur 40 ORG 540 HR -
5137.02.03 - Uang Makan 40 ORG 540 HR 6,000 129,600,000
5137.02.04 - Transport lembur 40 ORG 540 HR -
5137.02.05 - Pesangon 40 ORG 540 HR 5,850 126,360,000
5137.02 (2 Orang) 136,850 2,955,960,000
5137.03 DRIVER
5137.03.01 - Upah / bulan (Upah,Transp & Makan) 6 ORG 540 HR 60,000 194,400,000
5137.03.02 - Upah lembur 6 ORG 540 HR 30,000 97,200,000
5137.03.03 - Uang makan 6 ORG 540 HR 6,000 19,440,000
5137.03.04 - Transport lembur 6 ORG 540 HR -
5137.03.05 - Pesangon 6 ORG 540 HR 5,850 18,954,000
5137.03 (1 Orang) 101,850 329,994,000
5137.04 PEMBANTU MESS
5137.04.01 - Upah / bulan (Upah,Transp & Makan) 5 ORG 6 BLN 500,000 15,000,000
5137.04.02 - Pesangon ORG 1 KALI 500,000 -
5137.05 ( 1 Orang) 15,000,000
5,137.05 OFFICE BOY
5137.05.01 - Upah / bulan (Upah,Transp & Makan) 2 ORG BLN 1,500,000 3,000,000
5137.05.02 - Pesangon 2 ORG KALI 500,000 -
5,137.05 3,000,000
Page : 4 / 7
AKUNT VOLUME DURASI HARGA TOTAL
URAIAN
(CODE) QTY SAT QTY SAT SATUAN HARGA
5140 ALAT BERAT
5140.01 CRANE 150 T
5140.01.01 Sewa 3 UNIT 12 BLN 300,000,000 10,800,000,000
5140.01.02 Operator 6 ORG 360 HR 100,000 216,000,000
5140.01.03 Bahan Bakar 300 LTR 180 HR 8,500 459,000,000
5140.01.04 Olie
5140.01.05 Biaya Perawatan / Service -
5140.01.06 Mob / Demob 3 LS 1 RIT 100,000,000 300,000,000.00
Jumlah (5140.01) 11,775,000,000.00
5140.01 CRANE 80 T
5140.01.01 Sewa 2 UNIT 15 BLN 150,000,000 4,500,000,000
5140.01.02 Operator 2 ORG 450 HR 100,000 90,000,000
5140.01.03 Bahan Bakar 200 LTR 450 HR 8,500 765,000,000
5140.01.04 Olie
5140.01.05 Biaya Perawatan / Service -
5140.01.06 Mob / Demob 2 LS 1 RIT 30,000,000 60,000,000
Jumlah (5140.01) 5,415,000,000
5140.02 MESIN LAS SMAW
5140.02.01 Sewa 50 UNIT 18 BLN 5,000,000 4,500,000,000
5140.02.02 Bahan Bakar -
5140.02.03 Olie -
5140.02.04 Biaya Perawatan / Service -
Jumlah (5140.02) 4,500,000,000
5140.02 MESIN LAS SAW
5140.02.01 Sewa 5 UNIT 3 BLN 15,000,000 225,000,000
5140.02.02 Bahan Bakar -
5140.02.03 Olie -
5140.02.04 Biaya Perawatan / Service -
Jumlah (5140.02) 225,000,000
5140.03 COMPRESSOR
5140.03.01 Sewa 2 UNIT 18.0 BLN 15,000,000 540,000,000
5140.03.02 Operator - -
5140.03.03 Bahan Bakar 200 LTR 270 HR 8,500 459,000,000
5140.03.04 Olie - -
Jumlah (5140.03) 999,000,000.00
5140.01 Trailer 40 T
5140.01.01 Sewa 2 UNIT 15 BLN 75,000,000 2,250,000,000
5140.01.02 Operator 2 ORG 450 HR 75,000 67,500,000
5140.01.03 Bahan Bakar 60 LTR 450 HR 8,500 229,500,000
5140.01.04 Olie
5140.01.05 Biaya Perawatan / Service
5140.01.06 Mob / Demob RIT 1 RIT 0
Jumlah (5140.01) 2,547,000,000.00
5140.01 Genset 225 KVA
5140.01.01 Sewa 4 UNIT 18 BLN 75,000,000 5,400,000,000
5140.01.02 Operator 1 ORG 540 HR 75,000 40,500,000
5140.01.03 Bahan Bakar 400 LTR 540 HR 8,500 1,836,000,000
5140.01.04 Olie
5140.01.05 Biaya Perawatan / Service
5140.01.06 Mob / Demob RIT 1 RIT 25,000,000
Jumlah (5140.01) 7,301,500,000.00
Jumlah (5140) 32,762,500,000
Page : 5 / 7
AKUNT VOLUME DURASI HARGA TOTAL
URAIAN
(CODE) QTY SAT QTY SAT SATUAN HARGA
5141.11 Segel (1.1/2 Up to 5") 12 BH 150,000 1,800,000
5141.12 Segel (1/2 Up to 1") 2 BH 1,500,000 3,000,000
5141.13 Walter Mur 7/8" Turnbuckle -
5141.14 Walter Mur 1 1/2" Turnbuckle BH 75,000 -
5141.15 Stang Gouging 12 BH 2,500,000 30,000,000
5141.16 Slang compresor 300 M 75,000 22,500,000
5141.17 Roll Kabel u/Lampu @ 25 Mtr 10 BH 250,000 2,500,000
5141.18 Kabel Power NYY 4x70 200 M 100,000 20,000,000
5141.19 Kabel Power NYYHY 150 M 50,000 7,500,000
5141.20 Klem Kabel 50 BH 5,000 250,000
5141.21 Schoen Kabel 25 BH 5,000 125,000
5141.22 Shocket -
5141.23 Lampu Spotlight 500 W 24 BH 250,000 6,000,000
5141.24 Slang Sanblast & Cat
5141.25 Nozzle Sanblast
5141.26 Tang Press 2 BH 50,000 100,000
5141.27 Thermos Las 5 BH 750,000 3,750,000
5141.28 Avometer 1 BH 75,000 75,000
5141.29 Senter 2 BH 15,000 30,000
5141.30 Tools Box 1 SET 150,000 150,000
5141.31 Kunci Ring / Pass / socket 3 SET 250,000 750,000
5141.32 Electric Winch Kap.2.50 Ton -
5141.33 Lampu TL dll u/Lapangan -
5141.34 Electric Tools Box -
5141.35 Blander Potong 10 BH 750,000 7,500,000
5141.36 Chain Block Kap 1,5 Ton 4 BH 1,000,000 4,000,000
5141.37 Chain Block Kap 3 Ton 4 BH 1,500,000 6,000,000
5141.38 Chain Block Kap 5 Ton 2 BH 2,500,000 5,000,000
5141.39 Chain Block Kap 10 Ton -
Page : 6 / 7
AKUNT VOLUME DURASI HARGA TOTAL
URAIAN
(CODE) QTY SAT QTY SAT SATUAN HARGA
5141.40 Lever Block 1,5 Ton 2 BH 1,000,000 2,000,000
5141.41 Lever Block 3 Ton BH 1,500,000 -
5141.42 Lever Block 5 Ton -
5141.43 Combination plier & cutting plier 1 BH 25,000 25,000
5141.44 Kunci Pukul 10 BH 1,500,000 15,000,000
5141.45 Pipe wrench BH 200,000 -
5141.46 Adjustable wrench BH 50,000 -
5141.47 Double & spanner BH 50,000 -
5141.48 Hammers 5 BH 150,000 750,000
5141.49 Electric soldering 1 BH 25,000 25,000
5141.5 Hand saw blade BH 50,000 -
5141.51 Multi tester BH 75,000 -
5141.52 Cutting otomatis BH 35,000,000 -
5141.53 Isulasi unibel 50 BH 15,000 750,000
#REF! Eching Motor 1 BH 50,000,000 50,000,000
Jumlah (5141) 1,911,330,000
5142 BAHAN BANTU LAINNYA
5142.01 Kawat Las SMAW 3,000 KG 30,000 90,000,000
5142.02 Kawat Las SAW 3,500 KG 25,000 87,500,000
5142.03 Flux @ 25 Kg 1,000 KG 25,000 25,000,000
5142.04 LPG 125 BTL 500,000 62,500,000
5142.05 Cat Minyak BTL 20,000 -
5142.06 Oxigen / Zat Asam 600 BTL 41,000 24,600,000
5142.07 Acetylene 200 BTL 125,000 25,000,000
5142.08 Batu Gerinda 4" 200 BH 9,000 1,800,000
5142.09 Batu Gerinda 7" 225 BH 20,000 4,500,000
5142.1 Kawat gouging 750 BH 4,000 3,000,000
5142.11 Ampelas / Kertas Gosok 50 LBR 2,500 125,000
5142.12 Sarung Tangan Panjang 60 BH 25,000 1,500,000
5142.13 Sarung Tangan Pendek 500 BH 15,000 7,500,000
5142.14 Kaca Mata Potong 90 BH 5,000 450,000
5142.15 Kaca Mata Gerinda 90 BH 7,500 675,000
5142.16 Kaca Putih 450 BH 1,000 450,000
5142.17 Kaca Hitam 200 BH 5,000 1,000,000
5142.18 Sikat Baja 10 BH 12,500 125,000
5142.19 Masker Plastik 100 BH 25,000 2,500,000
5142.2 Holder 36 BH 60,000 2,160,000
5142.21 Ground weld 15 KG 80,000 1,200,000
5142.22 Wire brush dia. 4" 10 BH 12,500 125,000
5142.23 Roll Kabel @ 25 Mtr 1 BH 125,000 125,000
5142.24 Roll Meter @ 5 Mtr 15 BH 12,500 187,500
5142.25 Piano Wire 2 KG 75,000 150,000
5142.26 Cat Pylox 5 KLG 17,500 87,500
5142.27 Spidol Solid Marker KLG -
5142.28 Burning rod KG -
5142.29 Grease @ 5 Kg KG -
5142.3 Olie LTR -
5142.31 Spot Check SET 300,000 -
5142.32 Contact Cleaner LS -
5142.33 Die Penetran 15 SET 325,000 4,875,000
5142.34 Colour Check SET -
5142.35 Majun Lap 50 KG 2,500 125,000
5142.36 Kayu Balok 3 M-3 1,500,000 4,500,000
5142.37 Seal tape BH 1,500 -
5142.38 Batu Bateray 20 BH 2,500 50,000
5142.39 Tambang Manila 100 M 20,000 2,000,000
5142.4 Tambang Plastik 100 M 5,000 500,000
5142.41 Kuas Cat 30 BH 7,500 225,000
5142.42 Jig & Fixture 200 BH 628,000 125,600,000
5142.43 Papan 50 BTG 250,000 12,500,000
5142.44 Kap Las 50 BH 35,000 1,750,000
5142.45 Temporary bracing 500 KG 8,500 4,250,000
5142.46 Pipe scafolding 250 BH 175,000 43,750,000
5142.47 Clamb scafolding 500 BH 40,000 20,000,000
5142.48 Stud Bolt 250 Bh 300,000 75,000,000
5142.49 Terpal plastik 4 x 6 M 50 BH 150,000 7,500,000
Page : 7 / 7
AKUNT VOLUME DURASI HARGA TOTAL
URAIAN
(CODE) QTY SAT QTY SAT SATUAN HARGA
5142.5 Temporary support 1 BH 177,747,000 177,747,000
5142.51 Bahan Bantu Lainnya 1 LS 5,000,000 5,000,000
5143 Jumlah (5142) 827,632,000
5143.01 BANTUAN TEHNIK
5143.02 - Biaya tamu dilapangan 1 LS 500,000 500,000
5143.03 - Biaya pengurusan tagihan LS -
5143.04 - Biaya ceremony LS -
5143.05 - Sumbangan kepada daerah 1 LS 500,000 500,000
5143.06 - Biaya inspeksi pekerjaan LS -
5143.07 - Honor pengawas lapangan 1 LS 3,000,000 3,000,000
Jumlah (5143) 4,000,000
5144 UJI COBA/ INSPEKSI/COMISIONING. -
5144.01 - X Ray LS 75,000,000 -
Jumlah (5144) -
5145 ASURANSI KARYAWAN 1 LS 25,000,000 25,000,000
ASURANSI CONTRACTOR ALL RISK -
25,000,000
5146 ASBUILD DRAWING LS
-
5147 BIAYA LAIN - LAIN 1 LS 200,000,000 200,000,000
-
5158 BIAYA BANK 185,628,350
-
5149 SUB KONTRAK
T OT A L 67,573,269,606
RB020302
Gresik, 16 Oktober 2006
Mengetahui, Menyetujui, Dibuat,
Kadep Pemasaran Kadep Produksi PIB
Page : 8 / 7
160000
296 53.87205387205 welder
80.80808080808 fitter
161.6161616162 helper
10
6,294,000
58
4,120,500
2,695,500
24
7,660,500
8,470,500
0.15 4,578,781,859
0.15 3,522,139,891
140,832,000.00
30,525,212,392 1.3
Page : 9 / 7
296 53.87205387205 welder
80.80808080808 fitter
8,517,000.00
3,250
11,106,000
2,250
2,000
10,056,000
Page : 10 / 7
296 53.87205387205 welder
80.80808080808 fitter
9,576,000.00
2,000
10,056,000
4,045,500
Page : 11 / 7
296 53.87205387205 welder
80.80808080808 fitter
4,105,500
3,055,500
Page : 12 / 7
296 53.87205387205 welder
80.80808080808 fitter
11,475,000,000
5,355,000,000
360,000,000 360,000,000.00
-
Page : 13 / 7
296 53.87205387205 welder
80.80808080808 fitter
Page : 14 / 7
296 53.87205387205 welder
80.80808080808 fitter
204750000
682500
Page : 15 / 7
296 53.87205387205 welder
80.80808080808 fitter
3,040,797,132
13,514,653,921
1.200 index
81,087,923,527
81,087,000,000 5,067.94
53,361,384,174.00 6,081.53
Page : 16 / 7