PNW Kolam Renang Lanal Upload
PNW Kolam Renang Lanal Upload
PROGRAM : PROGRAM PEMBNGUNAN JALAN, JEMBATAN DAN BANGUNAN PENGAMAN PENDUKUNG KAWASAN PERMUKIMAN
KEGIATAN : PEMBANGUNAN/REHABILITASI PRASARANA KAWASAN PERMUKIMAN (PRASARANA OLARAGA )
KOLAM RENANG LANAL TERNATE
LOKASI : KOMPLEKS LANAL TERNATE
TAHUN ANGGARAN : 2019
A JUMLAH #NAME?
B PPN 10% #NAME?
C JUMLAH TOTAL #NAME?
D DIBULATKAN #NAME?
Terbilang :
TIGA MILYAR SERATUS JUTA RUPIAH
A JUMLAH 2,818,181,818.19
B PPN 10% 281,818,181.82
C JUMLAH TOTAL 3,100,000,000.00
D DIBULATKAN 3,100,000,000.00
Terbilang :
TTD
BARANG
I Material Langsung (Bahan Baku) 2,818,181,818.19 - 2,818,181,818.19 100.00% 100.00%
II Peralatan (Barang Jadi) - - - 0.00% 0.00%
A. Sub Total Barang 2,818,181,818.19 - 2,818,181,818.19 100.00% 100.00%
JASA
III Manajemen Proyek dan Perekayasaan - - - 0.00% 0.00%
IV Alat Kerja/Fasilitas Kerja - - - 0.00% 0.00%
V Konstruksi dan Fabrikasi - - - 0.00% 0.00%
VI Jasa Umum 281,818,181.82 - 281,818,181.82 100.00% 9.09%
B. Sub Total Jasa 281,818,181.82 - 281,818,181.82 100.00% 9.09%
C. Total Biaya (A+B) 3,100,000,000.00 3,100,000,000.00 100.00% 100.00%
D. Pembulatan 3,100,000,000.00 3,100,000,000.00
S
A
NO URAIAN PEKERJAAN VOLUME SAT THARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)
U
A
N
I PEKERJAAN PERSIAPAN (
1 Pek Pembersihan Awal dan Akhir 1.00 Ls ###R 3,300,000.00 3,300,000.00
p
2 Mobilisasi .Demobilisasi Alat 1.00 Ls ###. 16,790,000.00 16,790,000.00
3 Pek. Gudang Bahan + Direksi kit 1.00 Ls ###) 5,000,000.00 5,000,000.00
4 Pek. Papan nama Proyek 1.00 Ls ### 994,451.38 994,451.38
5 Administrasi Pelaporan 1.00 Ls ### 1,000,000.00 1,000,000.00
6 Pembongkaran Kolam Renang Lama 1.00 Ls ### 31,000,000.00 31,000,000.00
7 As Built Drawing dan Shop drawing 1.00 Ls ### 13,500,000.00 13,500,000.00
Jumlah Total 71,584,451.38
II PEKERJAAN TANAH
1 Galian Tanah Menggunakan Alat berat 1,484.42 M3 ### 156,651.37 232,536,426.66
2 Galian Pondasi Talud Kanan Kolam 44.84 M3 ### 156,651.37 7,024,247.43
3 Galian Pondasi Talud timur 18.24 M3 ### 156,651.37 2,857,320.99
4 Timbunan Tanah 123.75 M2 ### 84,233.98 10,423,955.03
5 Pek. Lapisan Pasir di Bawah Lantai Beton 88.02 M3 ### 457,557.41 40,274,203.23
Jumlah Total 293,116,153.33
III PEKERJAAN PASANGAN
1 Pek. Di Bawah Lantai Beton t = 5 cm 59.40 M3 ### 198,506.40 11,791,280.16
2 Pekerjaan Pasangan Dinding bata dilap.Profil roof 242.24 m2 ### 521,312.00 126,282,618.88
3 Plesteran Dinding Bata Merah 108.90 m2 ### 77,511.62 8,441,015.42
4 Pas. Pondasi Talud kiri dan Kanan kolam 38.31 M3 ### 1,263,850.80 48,418,124.15
5 Pasangan Pondasi Tiang Pagar Brc 0.10 M3 ### 1,263,850.80 126,385.08
6 Lantai Kerja T= 5 Cm di bawah Plat beton Dasar 117.80 M3 ### 1,418,722.00 167,125,451.60
Jumlah Total 362,184,875.29
IV PEKERJAAN STRUKTUR
1 Pek. Kolom 20x30 (K250) 7.86 M3 ### 1,647,285.98 12,947,667.80
Pek. Besi Beton 1,101.23 Kg ### 20,967.24 23,089,753.71
Pek. Bekisting 7.88 M2 ### 393,557.68 3,101,234.52
2 Pek. Dinding Beton t = 20 cm (K250) 135.96 M3 ### 1,647,285.98 223,965,001.84
Pek. Besi Beton 9,251.35 Kg ### 20,967.24 193,975,275.77
Pek. Bekisting 239.93 M2 ### 393,557.68 94,426,294.16
3 Pek. Lantai Beton Kolam renang t = 25 cm (K250) 166.90 M3 ### 1,647,285.98 274,932,030.06
Pek. Besi Beton 1,375.70 Kg ### 20,967.24 28,844,632.07
Pek. Bekisting 109.65 M2 ### 393,557.68 43,153,599.61
4 Lapisan Profil Roof 1,017.24 M2 ### 356,526.17 362,672,681.17
5 Lantai Tegel Bagian Atas 264.00 M2 ### 312,521.24 82,505,607.36
6 Dinding Tegel Lantai Tegel Kolam Renang 1,017.24 m2 ### 312,521.24 317,909,106.18
Jumlah Total 1,661,522,884.25
V KAMAR GANTI UK.3.25 x 6 mtr .
a Galian Tanah 15.57 M3 ### 117,566.43 1,830,509.32
b Pasir Urug di bawah Pondasi 1.11 M3 ### 457,557.41 507,888.73
c Pas, Batu Kosong 3.34 M3 ### 562,782.43 1,879,693.32
d Pas, Pondasi Batu Kali 11.43 M3 ### 1,222,104.33 13,968,652.49
e Sloof 2.67 M3 ### 2,385,456.02 6,369,167.57
f Kolom Beton 0.82 M3 ### 7,737,232.07 6,344,530.30
g Ringk Balk 1.33 M3 ### 8,776,784.86 11,673,123.86
h Plat Atap Beton 6.48 M3 ### 6,691,762.44 43,362,620.61
i Plesteran Beton 50.00 M2 ### 77,511.62 3,875,581.00
j Kosen Pintu 0.32 M3 ### 11,969,184.65 3,830,139.09
k Kosen Pintu Jendela 0.26 M3 ### 11,969,184.65 3,111,988.01
l Daun Pintu Jendela Kaca 8.20 M2 ### 671,304.79 5,504,699.28
m Kloset Jongkok 4.00 bh ### 962,392.23 3,849,568.92
n Wastafel 2.00 bh ### 1,577,025.02 3,154,050.04
o Septictank 1.00 Ls ### 3,000,000.00 3,000,000.00
p Istalasi Sanitasi 1.00 Ls ### 1,250,000.00 1,250,000.00
q Istalasi Listrik 1.00 Ls ### 1,700,000.00 1,700,000.00
Jumlah Total 115,212,212.53
VI BAK PENAMPUNG AIR 6 x 9 M
a Galian Tanah 10.50 M3 ### 117,566.43 1,234,447.52
b Pasir Urug di bawah Pondasi 0.75 M3 ### 457,557.41 343,168.06
c Pas, Batu Kosong 2.25 M3 ### 562,782.43 1,266,260.47
d Pas, Pondasi Batu Kali 7.80 M3 ### 1,222,104.33 9,532,413.77
e Sloof 0.90 M3 ### 2,385,456.02 2,146,910.42
f Kolom Beton 1.20 M3 ### 7,737,232.07 9,284,678.48
g Ringk Balk 0.90 M3 ### 8,776,784.86 7,899,106.37
h Plat Lantai 10.80 M3 ### 6,691,762.44 72,271,034.35
i Plat Beton 11.25 M3 ### 6,691,762.44 75,282,327.45
j Plesteran Beton 219.60 M2 ### 103,829.21 22,800,894.52
k Instalasi Sanitasi 1.00 Ls ### 2,000,000.00 2,000,000.00
l Mesin Pompa Untuk Kolam Renang 1.00 bh ### 7,000,000.00 7,000,000.00
m Sumur Boor 65.00 m. ### 1,200,000.00 78,000,000.00
Jumlah Total 289,061,241.41
VII LAIN - LAIN
1 Bak Kontrol 3.00 Ls ### 2,500,000.00 7,500,000.00
2 Perpipaan 1.00 Ls ### 18,000,000.00 18,000,000.00
Jumlah Total 25,500,000.00
JADWAL WAKTU PELAKSANAAN PEKERJAAN
I PEKERJAAN PERSIAPAN
1 Pek Pembersihan Awal dan Akhir Ls 0.12 0.06 0.06
2 Mobilisasi .Demobilisasi Alat Ls 0.60 0.15 0.15 0.15 0.15
3 Pek. Gudang Bahan + Direksi kit Ls 0.18 0.18
4 Pek. Papan nama Proyek Ls 0.04 0.04
5 Administrasi Pelaporan Ls 0.04 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003
6 Pembongkaran Kolam Renang Lama Ls 1.10 1.10
7 As Built Drawing dan Shop drawing Ls 0.48 0.12 0.12 0.12 0.12
II PEKERJAAN TANAH
1 Galian Tanah Menggunakan Alat berat M3 8.25 8.25
2 Galian Pondasi Talud Kanan Kolam M3 0.25 0.25
3 Galian Pondasi Talud timur M3 0.10 0.10
4 Timbunan Tanah M2 0.37 0.37
5 Pek. Lapisan Pasir di Bawah Lantai Beton M3 1.43 1.43
III PEKERJAAN PASANGAN
1 Pek. Di Bawah Lantai Beton t = 5 cm M3 0.42 0.42
2 Pekerjaan Pasangan Dinding bata dilap.Profil roof m2 4.48 4.48
3 Plesteran Dinding Bata Merah m2 0.30 0.30
4 Pas. Pondasi Talud kiri dan Kanan kolam M3 1.72 1.72
5 Pasangan Pondasi Tiang Pagar Brc M3 0.004 0.004
6 Lantai Kerja T= 5 Cm di bawah Plat beton Dasar M3 5.93 5.93
IV PEKERJAAN STRUKTUR
1 Pek. Kolom 20x30 (K250) M3 0.46 0.46
Pek. Besi Beton Kg 0.82 0.82
Pek. Bekisting M2 0.11 0.11
2 Pek. Dinding Beton t = 20 cm (K250) M3 7.95 7.95
Pek. Besi Beton Kg 6.88 6.88
Pek. Bekisting M2 3.35 3.35
3 Pek. Lantai Beton Kolam renang t = 25 c (K250) M3 9.76 9.76
Pek. Besi Beton Kg 1.02 1.02
Pek. Bekisting M2 1.53 1.53
4 Lapisan Profil Roof M2 12.87 12.87
5 Lantai Tegel Bagian Atas M2 2.93 2.93
6 Dinding Tegel Lantai Tegel Kolam Renang m2 11.28 11.28
V KAMAR GANTI UK.3.25 x 6 mtr
a. Galian Tanah M3 0.06 0.06
b. Pasir Urug di bawah Pondasi M3 0.02 0.02
c. Pas, Batu Kosong M3 0.07 0.07
d. Pas, Pondasi Batu Kali M3 0.50 0.50
e. Sloof M3 0.23 0.23
f. Kolom Beton M3 0.23 0.23
g. Ringk Balk M3 0.41 0.41
h. Plat Atap Beton M3 1.54 1.54
i. Plesteran Beton M2 0.14 0.14
j. Kosen Pintu M3 0.14 0.14
k. Kosen Pintu Jendela M3 0.11 0.11
l. Daun Pintu Jendela Kaca M2 0.20 0.20
m. Kloset Jongkok bh 0.14 0.14
n. Wastafel bh 0.11 0.11
o. Septictank Ls 0.11 0.11
p. Istalasi Sanitasi Ls 0.04 0.04
q. Istalasi Listrik Ls 0.06 0.06
VI BAK PENAMPUNG AIR 6 x 9 M
a. Galian Tanah M3 0.04 0.04
b. Pasir Urug di bawah Pondasi M3 0.01 0.01
c. Pas, Batu Kosong M3 0.04 0.04
d. Pas, Pondasi Batu Kali M3 0.34 0.34
e. Sloof M3 0.08 0.08
f. Kolom Beton M3 0.33 0.33
g. Ringk Balk M3 0.28 0.28
h. Plat Lantai M3 2.56 2.56
i. Plat Beton M3 2.67 2.67
j. Plesteran Beton M2 0.81 0.40 0.40
k. Instalasi Sanitasi Ls 0.07 0.07
l. Mesin Pompa Untuk Kolam Renang bh 0.25 0.25
m. Sumur Boor m. 2.77 1.38 1.38
V LAIN - LAIN
Bak Kontrol Ls 0.27 0.27
Perpipaan Ls 0.64 0.32 0.32
JUMLAH 100.00
RENCANA PROGRES MINGGUAN (%) - 0.54 1.25 18.54 14.21 10.16 13.93 1.39 2.18 13.60 8.75 14.27 0.86 0.33
RENCANA KOMULATIF MINGGUAN (%) - 0.54 1.79 20.34 34.55 44.71 58.64 60.02 62.20 75.80 84.54 98.81 99.67 100.00
BACK UP VOLUME
Program : PROGRAM PEMBNGUNAN JALAN, JEMBATAN DAN BANGUNAN PENGAMAN PENDUKUNG KAWASAN PERMUKIMAN
#NAME?
Kegiatan : FISIK KOLAM RENANG LANAL TERNATE
- Pembangunan Lanjutan
Pagar Keliling
GudangGedung
Umum Kantor
Lokasi : KOMPLEKS LANAL TERNATE
Tahun Angg. : 2018
A INFORMASI UMUM
1 RUAS JALAN YANG DIKERJAKAN 478.00 3.00 1,434.00 M2
2
3
4
5
I PEKERJAAN PERSIAPAN
1 Pek Pembersihan Awal dan Akhir
2 Pembongaran Paving & Pembuangan Material
3 Pek. Gudang Bahan + Direksi kit
4 Pek. Papan nama Proyek
5 Administrasi Pelaporan
6 As Built Drawing dan Shop drawing
II PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi Kanstin 478.00 0.20 0.10 0.02 2.00 19.12 M3
2 Pek Urugan Tanah Kembali
3 Timbunan Tanah Bawah Lantai
4 Urugan Pasir Bawah Lantai
5 Rabat Lantai Kolam Renang 54.00 22.00 0.10 1,188.00 1.00 118.80 M3
Lapisan Pasris 54.00 22.00 0.05 1,188.00 1.00 59.40 M3
Lapisan Profil roof pada dinding Beton 3.37 39.00 2.00 131.43
4.65 3.87 6.59 2.00 18.00
6.20 1.87 2.00 11.59
15.50 1.87 1.00 28.99
15.50 3.37 1.00 52.24
242.24
Lapisan profil Roof Pada Lantai Beton 50.00 15.50 1.00 775.00
1,017.24
V PEKERJAAN PENGECATAN
1 Pengecatan Kanstin 478.00 m
Sisi Pengecatan 0.34 m
2.00 325.04 m2
A. Harga Satuan Upah dan Bahan
1 Pekerja OH 150,898.88
2 Tukang kayu OH 169,444.02
3 Tukang batu OH 169,444.02
4 Tukang besi OH 169,444.02
5 Tukang cat OH 169,444.02
6 Tukang pipa OH 169,444.02
7 Tukang vibrator OH 169,444.02
8 Tukang erection OH 169,444.02
9 Tukang las OH 169,444.02
10 Tukang almunium OH 169,444.02
11 Tukang Listrik OH 169,444.02
12 Kepala tukang OH 205,070.21
13 Mandor OH 175,690.80
14 Juru ukur OH -
15 Pembantu Juru ukur OH -
16 Ahli alat berat (mekanik) OH -
17 Operator alat berat OH 149,825.21
18 Pembantu Operator alat berat OH 114,589.44
19 Supir truk OH 125,033.29
20 Kenek truk OH 114,589.44
21 Penjaga malam OH 114,589.44
22 Juru gambar (drafter) OH -
23 Design Engineer OH -
24 Operator printer OH -
25 Lainnya OH -
1 Air Ltr 78.08
2 Air test (air bersih) M3 4,587.48
3 Almunium strip M' 4,545.19
4 Alumunium foil M2 3,221.00
5 Ampelas Lbr 10,541.45
6 Waterprofilroop M2 43,922.70
7 Pagar BRC di 5 tinggi 1.20 m M2 -
8 Bahan bakar Ltr 12,200.75
9 Baja strip (0,2 x 2) cm Kg 30,648.28
10 Bak cuci piring Unit 1,653,445.64
11 Bak fibreglass Unit 824,087.46
12 Bata berongga M3 -
13 Bata Semen Press Bh 2,147.33
14 Bata Merah Bh 2,049.73
15 Bathcuip Unit 3,473,309.51
16 Batu belah Uk. >15 cm M3 303,457.05
17 Batu Pecah Uk. 10-15 cm M3 300,626.48
18 Besi angker dia. 8 Kg -
19 Besi Baja IWF Kg 16,593.02
20 Besi beton Kg 13,079.20
21 Besi Beton Dia. 10,5 mm Staf 78,963.25
22 Besi Beton Dia. 12,3 mm Staf 114,784.66
23 Besi Beton Dia. 14 mm Staf 207,022.33
24 Besi Beton Dia. 16 mm Staf 205,265.42
25 Besi Beton Dia. 19 mm Staf 293,013.21
26 Besi Beton Dia. 25 mm Staf 710,474.07
27 Besi Beton Dia. 6,7 mm Staf 50,267.09
28 Besi Beton Dia. 8,5 mm Staf 50,657.51
29 Besi hollow 40.40.3 (galvalum) M' -
30 Besi plat baja Kg 19,960.43
31 Besi siku L 30.30.3 Kg 12,918.44
32 Besi hollow 40.40.2mm ( Hitam ) M' 33,348.72
32 Besi strip Kg 30,648.28
33 Besi strip tebal 6mm Kg 16,834.41
44 Besi Wiremesh M4 (54 m x 2,1 m) 154,50 Kg/Roll Roll 156,169.60
45 Besi Wiremesh M4 Kg -
46 Cat kayu/besi Kg 67,152.93
47 Cat menie Kg 68,226.59
48 Cat Tembok Kg -
49 Cat Plafon Kg 43,922.70
49 Cat dasar alkali Kg -
50 Cat kuwalitas anti jamur Kg -
49 Closet duduk Unit 3,407,327.85
50 Closet jongkok Unit 483,052.09
51 Casemnet Jendela M' 177,154.89
52 Dempul Kg 45,679.61
53 Dolken Kayu 5-5 /400 cm Btng 34,357.31
54 Door closer Bh 429,895.87
55 Door stop Bh 38,007.78
56 Engsel Casement Bh -
57 Engsel jendela kupu-kupu Bh 37,090.28
58 Engsel pintu Bh 57,587.54
59 Floor drain Unit 14,348.08
60 Genteng metal Bh 47,631.73
61 Gypsum board Lbr 107,659.42
62 Lis Gibsum 12 cm Lbr 13,196.33
62 GRC Tebal 6 mm Lbr 185,002.41
62 Ijuk M3 325,320.80
63 Kaca buram tebal 12 mm M2 1,253,261.04
64 Kaca cermin tebal 5 mm M2 935,748.72
65 Kaca polos M2 170,810.50
66 Kaca tebal 3 mm M2 -
67 Kaca Polos tebal 5 mm M2 -
68 Kaca Riben tebal 5 mm M2 -
68 Kaca tebal 10 mm M2 0.53
69 Kait angin Bh 18,545.14
70 Kanstin 60 cm x 30 cm x 25 cm x 20 cm Bh 73,204.50
71 Kapur padam M3 48,803.00
72 Karpet M2 302,578.60
73 Kaso-kaso 5x7 cm M3 3,355,206.25
74 Kawat beton Kg 25,475.17
75 Kawat dia. 4 mm Kg 31,721.95
76 Kawat duri M' -
77 Kawat jaring M' 31,721.95
78 Kawat las Kg 16,104.99
79 Kawat las listrik Kg 16,104.99
80 Kawat nyamuk M' 15,714.57
81 Kayu 5/10 (Kls II) M3 2,737,848.30
82 Kayu balok M3 6,441,996.00
83 Kayu balok 6 x 12 M3 6,441,996.00
84 Kayu balok borneo M3 6,441,996.00
85 Kayu balok kls. I M3 6,195,052.82
86 Kayu Balok kls II M3 3,725,621.02
87 Kayu list 2/4 M3 3,355,206.25
88 Kayu papan Kls I M3 5,824,638.05
89 Kayu papan 3/25 (Kls II) M3 3,108,263.07
90 Kayu papan kls II M3 3,355,206.25
91 Kayu papan kls III M3 2,737,848.30
92 Keramik Bh -
93 Koral beton M3 583,879.09
94 Koral beton Kg 333.65
94 Kran air Bh 31,038.71
95 Kuas Bh 38,456.76
96 Kunci slot Bh 69,105.05
97 Kunci tanam Bh 1,650,517.46
98 Kunci tanam antik Bh 229,178.89
99 Kunci tanam biasa Bh 81,012.98
100 Kunci tanam KM Bh 81,012.98
101 Lantai Kerja T = 10 cm M3 -
102 Lem Wallpaper Kg 23,835.39
103 Lem Karpet Kg 23,835.39
103 Lem kayu Kg 23,835.39
104 List kayu profil M' -
105 Meni besi Ltr #VALUE!
106 Minyak bekisting Ltr 27,378.48
107 Minyak pelumas Ltr 54,756.97
108 Nok standar 40x18 Lbr 28,891.38
109 Oli Ltr 42,458.61
110 Paku Kg 19,228.38
111 Paku 10cm Kg 19,228.38
112 Paku 12cm Bh 19,228.38
113 Paku 1cm - 2,5cm Kg 19,228.38
114 Paku 5 - 10 cm Kg 19,228.38
115 Paku 5 - 12 cm Kg 19,228.38
116 Paku 5 cm Kg 19,228.38
117 Paku 5-7 cm Kg 19,228.38
118 Paku 7 - 10 cm Kg 19,228.38
119 Paku biasa 1/2"-1" Kg 19,228.38
120 Paku biasa 2" - 5" Kg 19,228.38
121 Paku seng (1 - 2,5) cm Kg 31,624.34
122 Paku skrup Kg 37,773.52
123 Paku skrup 3,5" Bh 585.64
124 Paku tripleks Kg 25,475.17
125 Parquet M2 -
126 Pasir beton M3 441,471.94
127 Pasir beton Kg 286.67
128 Pasir pasang M3 399,598.96
129 Pasir Halus M3 478,659.82
130 Pasir urug M3 342,109.03
131 Paving M2 170,810.50
132 Pengencer Ltr 35,528.58
133 Pintu Alumunium M' 1,679,799.26
134 Pipa galvanis 1 1/2" M #DIV/0!
135 Pipa galvanis 1" M #DIV/0!
136 Pipa galvanis 1/2" M #DIV/0!
137 Pipa galvanis 3" M #DIV/0!
138 Pipa galvanis 3/4" M #DIV/0!
139 Pipa PVC 1" M #DIV/0!
140 Pipa PVC 1/2" M #DIV/0!
141 Pipa PVC 2 1/2" M #DIV/0!
142 Pipa PVC 2" M #DIV/0!
143 Pipa PVC 3" M #DIV/0!
144 Pipa PVC 3/4" M #DIV/0!
145 Pipa PVC 4" M #DIV/0!
146 Pipa PVC Ø 110 mm M 10,346.24
147 Pipa PVC Ø 150 mm M 21,473.32
148 Pipa PVC Ø 200 mm M 34,064.49
149 Pipa PVC Ø 250 mm M 52,414.42
150 Pipa PVC Ø 300 mm M 83,160.31
151 Pipa PVC Ø 400 mm M 134,403.46
152 Pipa PVC Ø 450 mm M 134,403.46
153 Pipa PVC Ø 63 mm M 3,513.82
154 Pipa PVC Ø 90 mm M 6,930.03
155 Plamir Kg 12,239.79
156 Plint internal cove Bh 1,854.51
157 Plint keramik Bh 1,854.51
158 Plint ubin granit Bh 1,854.51
159 Plint ubin PC Bh 1,854.51
160 Plint ubin teralux kerang Bh 1,854.51
161 Plint ubin teralux marmer Bh 1,854.51
162 Plint ubin teraso Bh 1,854.51
163 Plint ubin warna Bh 1,854.51
164 Plywood 4mm Lbr 186,329.85
165 Plywood tebal 10 mm Lbr 180,668.71
166 Profil allumunium "T" M' 32,209.98
167 Profil alumunium M' 173,445.86
168 Ram Buncis Bh -
169 Rangka metal hollow 40.40.2 mm M' -
170 Rel pintu sorong Bh 238,353.85
171 Reng 2 x 3 cm M3 3,355,206.25
172 Residu Ltr 5,368.33
173 Rolling door alumunium M2 453,672.69
174 Rooflight 90x180 Lbr 54,112.77
175 Rooster 20x20 Bh 54,112.77
175 Sabun Kg 14,640.90
176 Sealant Tube 36,504.64
177 Sealtape Bh 4,880.30
178 Semen grout Kg 4,023.81
179 Semen merah Kg 1,229.84
180 Semen portland Kg 1,901.36
181 Semen portland Zak 95,068.24
181 Semen warna Kg 22,351.77
182 Seng gelombang Lbr 75,839.86
183 Atap Spandek Lbr 251,823.48
184 Seng plat bjls 30 lbr 90 Lbr -
185 Seng plat bjls 30 lbr 45 Lbr -
185 Seng plat 3"x6" Lbr 85,014.83
186 Seng plat 3"x6" bjls 28 Lbr 72,716.47
187 Sewa alat (Tackal) Jam 4,026.25
188 Sewa alat Las listrik Jam 18,301.13
189 Sirtu M3 332,446.04
190 Skrup fixer Bh 390.42
191 Solar Ltr 11,907.93
192 Stopper Jendela M' 78,807.08
193 Tanah Urug M3 279,153.16
194 Teakwood T=4mm Uk.(90x220)cm Lbr 149,239.57
195 Tripleks 3 mm Lbr 72,716.47
196 Granit 60x60 M2 79,451.28
197 Ubin keramik 25 x 25 Dos 89,407.10
198 Ubin keramik 20 x 20 bh 3,576.28
199 Batu Alam 20x30 Bh 17,081.05
200 Ubin keramik 30 x 30 Dos 66,567.29
201 Ubin keramik 40 x 40 Dos 81,989.04
202 Ubin keramik Mozaik 30 x 30 Bh 112,949.66
203 Ubin Keramik 25x40 Bh -
204 Underlayer M2 97,606.00
205 Vernis Ltr 64,517.57
206 Wallpaper uk 1,07 x 15 m Roll 698,956.57
207 Wallpaper M 46,597.10
207 Wastafel Unit 871,328.76
208 Kaca Cermin Bh 234,254.40
209 Waterdrain Bh 14,348.08
210 Pas. Lampu Philips LED Downlide 15 Waat Bh 138,600.52
211 Pas. Lampu Philips LED Downlide 9 Waat Bh 107,366.60
212 Pas. Lampu Philips LED Downlide 6 Waat Bh 76,132.68
213 Pas. Lampu Sorot 200 Waat Bh 439,227.00
214 Stop Kontak Biasa Bh 41,970.58
215 Stop Kontak AC Bh 52,707.24
216 Saklar Ganda Bh 45,874.82
217 Saklar Tunggal Bh 36,114.22
218 Box Panel 40x60 Bh 4,392,270.00
219 MCB 6 Amper Bh 76,132.68
220 Lampu Sorot 200 Waat Bh 536,833.00
221 Pipa listrik Bh 9,858.21
222 T dus Bh 3,416.21
223 1 M' Kabel NYM Uk. 3x2,5 mm Bh 13,567.23
224 1 M' Kabel NYM Uk. 2x2,5 mm Bh 11,127.08
225 Main Trus M' 19,353.32
226 Reng U tipe 41-33 M' 10,097.34
227 Screw 12-14x20 PC 390.42
228 Screw 10-16x16 PC 585.64
229 Dinabot PC 2,049.73
230 Helmet PC 75,000.00
231 Rompi PC 150,000.00
232 Sepatu safety PC 175,000.00
2.2.1 Analisa Harga Satuan Pekerjaan Persiapan
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
4.1.1.1 Membuat 1 m3 beton mutu f'c = 7,4 mpa (K 100), slump (12-2) cm, w/c = 0,87
Pekerja OH 1.650 154,600 255,090
Tukang batu OH 0.275 173,600 47,740
Kepala tukang OH 0.028 210,100 5,883
Mandor OH 0.083 180,000 14,940
Semen Portland Kg 247.000 1,948 481,156
Pasir beton Kg 869.000 293.701 255,226
Koral beton Kg 999.000 341.829 341,487
Air Ltr 215.000 80.00 17,200
Jumlah 1,418,722
Overhead & Profit -
Harga Satuan Pekerjaan 1,418,722
4.1.1.2 Membuat 1 m3 beton mutu f'c = 9,8 mpa (K 125), slump (12-2) cm, w/c = 0,78
Pekerja OH 1.650 154,600 255,090
Tukang batu OH 0.275 173,600 47,740
Kepala tukang OH 0.028 210,100 5,883
Mandor OH 0.083 180,000 14,940
Semen Portland Kg 276.000 1,948 537,648
Pasir beton Kg 828.000 293.701 243,185
Koral beton Kg 1,012.000 341.829 345,931
Air Ltr 215.000 80.00 17,200
Jumlah 1,467,616
Overhead & Profit -
Harga Satuan Pekerjaan 1,467,616
4.1.1.3 Membuat 1 m3 beton mutu f'c = 12,2 mpa (K 150), slump (12-2) cm, w/c = 0,72
Pekerja OH 1.650 154,600 255,090
Tukang batu OH 0.275 173,600 47,740
Kepala tukang OH 0.028 210,100 5,883
Mandor OH 0.083 180,000 14,940
Semen Portland Kg 299.000 1,948 582,452
Pasir beton Kg 799.000 293.701 234,667
Koral beton Kg 1,017.000 341.829 347,640
Air Ltr 215.000 80.00 17,200
Jumlah 1,505,612
Overhead & Profit -
Harga Satuan Pekerjaan 1,505,612
4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 mpa (K 100), slump (3-6) cm, w/c = 0,87
Pekerja OH 1.200 154,600 185,520
Tukang batu OH 0.200 173,600 34,720
Kepala tukang OH 0.020 210,100 4,202
Mandor OH 0.060 180,000 10,800
Semen Portland Kg 230.000 1,948 448,040
Pasir beton Kg 893.000 293.701 262,275
Koral beton Kg 1,027.000 341.829 351,058
Air Ltr 200.000 80 16,000
Jumlah 1,312,615
Overhead & Profit -
Harga Satuan Pekerjaan 1,312,615
4.1.1.5 Membuat 1 m3 beton mutu f'c = 14,5 mpa (K 175), slump (12-2) cm, w/c = 0,66
Pekerja OH 1.650 154,600 255,090
Tukang batu OH 0.275 173,600 47,740
Kepala tukang OH 0.028 210,100 5,883
Mandor OH 0.083 180,000 14,940
Semen Portland Kg 326.000 1,948 635,048
Pasir beton Kg 760.000 293.701 223,213
Koral beton Kg 1,029.000 341.829 351,742
Air Ltr 215.000 80 17,200
Jumlah 1,550,855
Overhead & Profit -
Harga Satuan Pekerjaan 1,550,855
4.1.1.6 Membuat 1 m3 beton mutu f'c = 16,9 mpa (K 200), slump (12-2) cm, w/c = 0,61
Pekerja OH 1.650 154,600 255,090
Tukang batu OH 0.275 173,600 47,740
Kepala tukang OH 0.028 210,100 5,883
Mandor OH 0.083 180,000 14,940
Semen Portland Kg 352.000 1,948 685,696
Pasir beton Kg 731.000 293.701 214,696
Koral beton Kg 1,031.000 341.829 352,425
Air Ltr 215.000 80 17,200
Jumlah 1,593,670
Overhead & Profit -
Harga Satuan Pekerjaan 1,593,670
4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 mpa (K 225), slump (12-2) cm, w/c = 0,58
Pekerja OH 1.650 154,600 255,090
Tukang batu OH 0.275 173,600 47,740
Kepala tukang OH 0.028 210,100 5,883
Mandor OH 0.083 180,000 14,940
Semen Portland Kg 371.000 1,948 722,708
Pasir beton M3 698.000 293.701 205,004
Koral beton M3 1,047.000 341.829 357,895
Air Ltr 215.000 80 17,200
Jumlah 1,626,459
Overhead & Profit -
Harga Satuan Pekerjaan 1,626,459
4.1.1.8 Membuat 1 m3 beton mutu f'c = 21,7 mpa (K 250), slump (12-2) cm, w/c = 0,56
Pekerja OH 1.650 154,600 255,090
Tukang batu OH 0.275 173,600 47,740
Kepala tukang OH 0.028 210,100 5,883
Mandor OH 0.083 180,000 14,940
Semen Portland Kg 384.000 1,948 748,032
Pasir beton Kg 692.000 293.701 203,241
Koral beton Kg 1,039.000 341.829 355,160
Air Ltr 215.000 80 17,200
Jumlah 1,647,286
Overhead & Profit -
Harga Satuan Pekerjaan 1,647,286
4.1.1.9 Membuat 1 m3 beton mutu f'c = 24,0 mpa (K 275), slump (12-2) cm, w/c = 0,53
Pekerja OH 1.650 154,600 255,090
Tukang batu OH 0.275 173,600 47,740
Kepala tukang OH 0.028 210,100 5,883
Mandor OH 0.083 180,000 14,940
Semen Portland Kg 406.000 1,948 790,888
Pasir beton Kg 684.000 293.701 200,892
Koral beton Kg 1,026.000 341.829 350,716
Air Ltr 215.000 80 17,200
Jumlah 1,683,349
Overhead & Profit -
Harga Satuan Pekerjaan 1,683,349
4.1.1.10 Membuat 1 m3 beton mutu f'c = 26,4 mpa (K 300), slump (12-2) cm, w/c = 0,52
Pekerja OH 1.650 154,600 255,090
Tukang batu OH 0.275 173,600 47,740
Kepala tukang OH 0.028 210,100 5,883
Mandor OH 0.083 180,000 14,940
Semen Portland Kg 413.000 1,948 804,524
Pasir beton Kg 681.000 293.701 200,011
Koral beton Kg 1,021.000 341.829 349,007
Air Ltr 215.000 80 17,200
Jumlah 1,694,394
Overhead & Profit -
Harga Satuan Pekerjaan 1,694,394
4.1.1.11 Membuat 1 m3 beton mutu f'c = 28,8 mpa (K 325), slump (12-2) cm, w/c = 0,49
Pekerja OH 2.100 154,600 324,660
Tukang batu OH 0.350 173,600 60,760
Kepala tukang OH 0.035 210,100 7,354
Mandor OH 0.105 180,000 18,900
Semen Portland Kg 439.000 1,948 855,172
Pasir beton Kg 670.000 293.701 196,780
Koral beton Kg 1,006.000 341.829 343,880
Air Ltr 215.000 80 17,200
Jumlah 1,824,705
Overhead & Profit -
Harga Satuan Pekerjaan 1,824,705
4.1.1.12 Membuat 1 m3 beton mutu f'c = 31,2 mpa (K 350), slump (12-2) cm, w/c = 0,48
Pekerja OH 2.100 154,600 324,660
Tukang batu OH 0.350 173,600 60,760
Kepala tukang OH 0.035 210,100 7,354
Mandor OH 0.105 180,000 18,900
Semen Portland Kg 448.000 1,948 872,704
Pasir beton Kg 667.000 293.701 195,899
Koral beton Kg 1,000.000 341.829 341,829
Air Ltr 215.000 80 17,200
Jumlah 1,839,305
Overhead & Profit -
Harga Satuan Pekerjaan 1,839,305
4.1.1.19 Pemasangan 10 Kg jaring kawat baja (wiremesh)
Pekerja OH 0.025 154,600 3,865
Tukang besi OH 0.025 173,600 4,340
Kepala tukang OH 0.025 210,100 5,253
Mandor OH 0.001 180,000 180
Jaring kawat baja dilas Kg 10.200 - -
Kawat beton Kg 0.050 26,100 1,305
Jumlah 14,943
Overhead & Profit -
Harga Satuan Pekerjaan (10 Kg) 14,943
Harga Satuan Pekerjaan/Kg 1,494.25
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
B.17.b Untuk Pembesian Kolom, Balok, Ringbalk dan Sloof (100 Kg)
Pekerja OH 2.100 150,899 316,888
Tukang Besi OH 1.400 169,444 237,222
Kepala tukang OH 0.140 205,070 28,710
Mandor OH 0.210 175,691 36,895
Besi Beton (Polos/Ulir) Kg 105.000 13,079 1,373,316
Kawat Ikat Kg 2.100 25,475 53,498
Jumlah 2,046,528
Overhead & Profit -
Harga Satuan Pekerjaan (100 Kg) 2,046,528
Harga Satuan Pekerjaan/Kg 20,465.28
4.1.1 Analisa Harga Satuan Pekerjaan Beton
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
4.1.1.1 Membuat 1 m3 beton mutu f'c = 7,4 mpa (K 100), slump (12-2) cm, w/c = 0,87
Pekerja OH 1.650 150,899 248,983
Tukang batu OH 0.275 169,444 46,597
Kepala tukang OH 0.028 205,070 5,742
Mandor OH 0.083 175,691 14,582
Semen Portland Kg 247.000 1,901 469,637
Pasir beton Kg 869.000 286.670 249,116
Koral beton Kg 999.000 333.645 333,312
Air Ltr 215.000 78.08 16,788
Jumlah 1,384,758
Overhead & Profit -
Harga Satuan Pekerjaan 1,384,758
4.1.1.2 Membuat 1 m3 beton mutu f'c = 9,8 mpa (K 125), slump (12-2) cm, w/c = 0,78
Pekerja OH 1.650 150,899 248,983
Tukang batu OH 0.275 169,444 46,597
Kepala tukang OH 0.028 205,070 5,742
Mandor OH 0.083 175,691 14,582
Semen Portland Kg 276.000 1,901 524,777
Pasir beton Kg 828.000 286.670 237,363
Koral beton Kg 1,012.000 333.645 337,649
Air Ltr 215.000 78.08 16,788
Jumlah 1,432,481
Overhead & Profit -
Harga Satuan Pekerjaan 1,432,481
4.1.1.3 Membuat 1 m3 beton mutu f'c = 12,2 mpa (K 150), slump (12-2) cm, w/c = 0,72
Pekerja OH 1.650 150,899 248,983
Tukang batu OH 0.275 169,444 46,597
Kepala tukang OH 0.028 205,070 5,742
Mandor OH 0.083 175,691 14,582
Semen Portland Kg 299.000 1,901 568,508
Pasir beton Kg 799.000 286.670 229,049
Koral beton Kg 1,017.000 333.645 339,317
Air Ltr 215.000 78.08 16,788
Jumlah 1,469,567
Overhead & Profit -
Harga Satuan Pekerjaan 1,469,567
4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 mpa (K 100), slump (3-6) cm, w/c = 0,87
Pekerja OH 1.200 150,899 181,079
Tukang batu OH 0.200 169,444 33,889
Kepala tukang OH 0.020 205,070 4,101
Mandor OH 0.060 175,691 10,541
Semen Portland Kg 230.000 1,901 437,314
Pasir beton Kg 893.000 286.670 255,996
Koral beton Kg 1,027.000 333.645 342,654
Air Ltr 200.000 78 15,617
Jumlah 1,281,191
Overhead & Profit -
Harga Satuan Pekerjaan 1,281,191
4.1.1.5 Membuat 1 m3 beton mutu f'c = 14,5 mpa (K 175), slump (12-2) cm, w/c = 0,66
Pekerja OH 1.650 150,899 248,983
Tukang batu OH 0.275 169,444 46,597
Kepala tukang OH 0.028 205,070 5,742
Mandor OH 0.083 175,691 14,582
Semen Portland Kg 326.000 1,901 619,845
Pasir beton Kg 760.000 286.670 217,869
Koral beton Kg 1,029.000 333.645 343,321
Air Ltr 215.000 78 16,788
Jumlah 1,513,728
Overhead & Profit -
Harga Satuan Pekerjaan 1,513,728
4.1.1.6 Membuat 1 m3 beton mutu f'c = 16,9 mpa (K 200), slump (12-2) cm, w/c = 0,61
Pekerja OH 1.650 150,899 248,983
Tukang batu OH 0.275 169,444 46,597
Kepala tukang OH 0.028 205,070 5,742
Mandor OH 0.083 175,691 14,582
Semen Portland Kg 352.000 1,901 669,280
Pasir beton Kg 731.000 286.670 209,556
Koral beton Kg 1,031.000 333.645 343,988
Air Ltr 215.000 78 16,788
Jumlah 1,555,517
Overhead & Profit -
Harga Satuan Pekerjaan 1,555,517
4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 mpa (K 225), slump (12-2) cm, w/c = 0,58
Pekerja OH 1.650 150,899 248,983
Tukang batu OH 0.275 169,444 46,597
Kepala tukang OH 0.028 205,070 5,742
Mandor OH 0.083 175,691 14,582
Semen Portland Kg 371.000 1,901 705,406
Pasir beton M3 698.000 286.670 200,096
Koral beton M3 1,047.000 333.645 349,327
Air Ltr 215.000 78 16,788
Jumlah 1,587,521
Overhead & Profit -
Harga Satuan Pekerjaan 1,587,521
4.1.1.8 Membuat 1 m3 beton mutu f'c = 21,7 mpa (K 250), slump (12-2) cm, w/c = 0,56
Pekerja OH 1.650 150,899 248,983
Tukang batu OH 0.275 169,444 46,597
Kepala tukang OH 0.028 205,070 5,742
Mandor OH 0.083 175,691 14,582
Semen Portland Kg 384.000 1,901 730,124
Pasir beton Kg 692.000 286.670 198,376
Koral beton Kg 1,039.000 333.645 346,657
Air Ltr 215.000 78 16,788
Jumlah 1,607,850
Overhead & Profit -
Harga Satuan Pekerjaan 1,607,850
4.1.1.9 Membuat 1 m3 beton mutu f'c = 24,0 mpa (K 275), slump (12-2) cm, w/c = 0,53
Pekerja OH 1.650 150,899 248,983
Tukang batu OH 0.275 169,444 46,597
Kepala tukang OH 0.028 205,070 5,742
Mandor OH 0.083 175,691 14,582
Semen Portland Kg 406.000 1,901 771,954
Pasir beton Kg 684.000 286.670 196,082
Koral beton Kg 1,026.000 333.645 342,320
Air Ltr 215.000 78 16,788
Jumlah 1,643,049
Overhead & Profit -
Harga Satuan Pekerjaan 1,643,049
4.1.1.10 Membuat 1 m3 beton mutu f'c = 26,4 mpa (K 300), slump (12-2) cm, w/c = 0,52
Pekerja OH 1.650 150,899 248,983
Tukang batu OH 0.275 169,444 46,597
Kepala tukang OH 0.028 205,070 5,742
Mandor OH 0.083 175,691 14,582
Semen Portland Kg 413.000 1,901 785,264
Pasir beton Kg 681.000 286.670 195,222
Koral beton Kg 1,021.000 333.645 340,652
Air Ltr 215.000 78 16,788
Jumlah 1,653,831
Overhead & Profit -
Harga Satuan Pekerjaan 1,653,831
4.1.1.11 Membuat 1 m3 beton mutu f'c = 28,8 mpa (K 325), slump (12-2) cm, w/c = 0,49
Pekerja OH 2.100 150,899 316,888
Tukang batu OH 0.350 169,444 59,305
Kepala tukang OH 0.035 205,070 7,177
Mandor OH 0.105 175,691 18,448
Semen Portland Kg 439.000 1,901 834,699
Pasir beton Kg 670.000 286.670 192,069
Koral beton Kg 1,006.000 333.645 335,647
Air Ltr 215.000 78 16,788
Jumlah 1,781,021
Overhead & Profit -
Harga Satuan Pekerjaan 1,781,021
4.1.1.12 Membuat 1 m3 beton mutu f'c = 31,2 mpa (K 350), slump (12-2) cm, w/c = 0,48
Pekerja OH 2.100 150,899 316,888
Tukang batu OH 0.350 169,444 59,305
Kepala tukang OH 0.035 205,070 7,177
Mandor OH 0.105 175,691 18,448
Semen Portland Kg 448.000 1,901 851,811
Pasir beton Kg 667.000 286.670 191,209
Koral beton Kg 1,000.000 333.645 333,645
Air Ltr 215.000 78 16,788
Jumlah 1,795,272
Overhead & Profit -
Harga Satuan Pekerjaan 1,795,272
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
4.4.1.7 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu camp. 1sp : 2pp
Pekerja OH 0.300 150,899 45,270
Tukang batu OH 0.100 169,444 16,944
Kepala tukang OH 0.010 205,070 2,051
Mandor OH 0.015 175,691 2,635
Bata Press Bh 35.000 2,147 75,157
Semen Portland Kg 9.475 1,901 18,015
Pasir pasang M3 0.019 399,599 7,592
Jumlah 167,665
Overhead & Profit -
Harga Satuan Pekerjaan 167,665
4.4.1.8 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu camp. 1sp : 3pp
Pekerja OH 0.300 150,899 45,270
Tukang batu OH 0.100 169,444 16,944
Kepala tukang OH 0.010 205,070 2,051
Mandor OH 0.015 175,691 2,635
Bata Press Bh 35.000 2,147 75,157
Semen Portland Kg 7.185 1,901 13,661
Pasir pasang M3 0.020 399,599 7,992
Jumlah 163,710
Overhead & Profit -
Harga Satuan Pekerjaan 163,710
4.4.1.9 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu camp. 1sp : 4pp
Pekerja OH 0.300 150,899 45,270
Tukang batu OH 0.100 169,444 16,944
Kepala tukang OH 0.010 205,070 2,051
Mandor OH 0.015 175,691 2,635
Bata Press Bh 35.000 2,147 75,157
Semen Portland Kg 5.750 1,901 10,933
Pasir pasang M3 0.022 399,599 8,591
Jumlah 161,581
Overhead & Profit -
Harga Satuan Pekerjaan 161,581
4.4.1.10 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu camp. 1sp : 5pp
Pekerja OH 0.300 150,899 45,270
Tukang batu OH 0.100 169,444 16,944
Kepala tukang OH 0.010 205,070 2,051
Mandor OH 0.015 175,691 2,635
Bata Press Bh 35.000 2,147 75,157
Semen Portland Kg 4.840 1,901 9,203
Pasir pasang M3 0.023 399,599 8,991
Jumlah 160,250
Overhead & Profit -
Harga Satuan Pekerjaan 160,250
4.4.1.11 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu camp. 1sp : 6pp
Pekerja OH 0.300 150,899 45,270
Tukang batu OH 0.100 169,444 16,944
Kepala tukang OH 0.010 205,070 2,051
Mandor OH 0.015 175,691 2,635
Bata Press Bh 35.000 2,147 75,157
Semen Portland Kg 4.160 1,901 7,910
Pasir pasang M3 0.025 399,599 9,790
Jumlah 159,757
Overhead & Profit -
Harga Satuan Pekerjaan 159,757
4.4.1.12 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu camp. 1sp : 8pp
Pekerja OH 0.300 150,899 45,270
Tukang batu OH 0.100 169,444 16,944
Kepala tukang OH 0.010 205,070 2,051
Mandor OH 0.015 175,691 2,635
Bata Press Bh 35.000 2,147 75,157
Semen Portland Kg 3.250 1,901 6,179
Pasir pasang M3 0.025 399,599 9,990
Jumlah 158,226
Overhead & Profit -
Harga Satuan Pekerjaan 158,226
4.2.1 Analisa Harga Satuan Pekerjaan Besi dan Alumunium
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
4.2.1.4 Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Pekerja OH 1.050 150,899 158,444
Tukang las OH 1.050 169,444 177,916
Kepala tukang OH 0.105 205,070 21,532
Mandor OH 0.052 175,691 9,136
Besi siku L 30.30.3 Kg 15.000 12,918 193,777
Besi plat baja Kg 32.800 19,960 654,702
Kawat las Kg 0.050 16,105 805
Jumlah 1,216,312
Overhead & Profit -
Harga Satuan Pekerjaan 1,216,312
4.2.1.19 Pemasangan 1 m' talang 1/2 lingkaran D-15 cm, seng bjls 30 lebar 45 cm
Pekerja OH 0.150 150,899 22,635
Tukang kayu OH 0.300 169,444 50,833
Kepala tukang OH 0.030 205,070 6,152
Mandor OH 0.008 175,691 1,406
Seng plat M' 1.050 - -
Paku seng (1 - 2,5) cm Kg 0.010 31,624 316
Besi strip 6mm Kg 0.500 16,834 8,417
Jumlah 89,759
Overhead & Profit -
Harga Satuan Pekerjaan 89,759
4.2.1.20 Pemasangan 1 m2 rangka besi hollow 1x40.40.3mm, modul 60x120cm, dinding partisi
Pekerja OH 0.250 150,899 37,725
Tukang besi OH 0.250 169,444 42,361
Kepala tukang OH 0.025 205,070 5,127
Mandor OH 0.013 175,691 2,284
Rangka metal hollow 40.40.3 mm M' 3.500 - -
100% harga
Assesoris (perkuatan, las, dll) Ls rangka - -
Jumlah 87,496
Overhead & Profit -
Harga Satuan Pekerjaan 87,496
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
4.4.1.2 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu camp. 1sp : 3pp
Pekerja OH 0.600 150,899 90,539
Tukang batu OH 0.200 169,444 33,889
Kepala tukang OH 0.020 205,070 4,101
Mandor OH 0.030 175,691 5,271
Bata merah M3 140.000 2,050 286,962
Semen Portland Kg 32.950 1,948 64,187
Pasir pasang M3 0.091 399,599 36,364
Jumlah 521,312
Overhead & Profit -
Harga Satuan Pekerjaan 521,312
4.4.2 Analisa Harga Satuan Pekerjaan Plesteran
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
4.4.3. Pemasangan 1 m2 lantai keramik ukuran 40cm x 40cm
Pekerja OH 0.7 150,899 105,629
Tukang batu OH 0.35 169,444 59,305
Kepala tukang OH 0.035 205,070 7,177
Mandor OH 0.035 175,691 6,149
Ubin keramik 40 x 40 Dos 1.05 81,989 86,088
Semen Portland Kg 10 1,901 19,014
Pasir pasang M3 0.045 399,599 17,982
Semen warna Kg 0.5 22,352 11,176
Jumlah 312,521
Overhead & Profit -
Harga Satuan Pekerjaan 312,521
Analisa Harga Satuan Pekerjaan Elektrikal
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
Memasang 1 Bh MCB
Pekerja OH 0.050 150,899 7,545
Tukang Listrik OH 0.050 169,444 8,472
Mandor OH 0.005 175,691 878
MCB Bh 1.000 76,133 76,133
Jumlah 93,028
-
Harga Satuan Pekerjaan 93,028
4.6.1 Analisa Harga Satuan Pekerjaan Kayu
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
4.6.1.1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
Pekerja OH 7 150,899 1,056,292
Tukang kayu OH 21 169,444 3,558,324
Kepala tukang OH 2.1 205,070 430,647
Mandor OH 0.35 175,691 61,492
Kayu balok kls. I M3 1.1 6,195,053 6,814,558
Paku 10cm Kg 1.25 19,228 24,035
Lem kayu Kg 1 23,835 23,835
Jumlah 11,969,185
Overhead & Profit -
Harga Satuan Pekerjaan 11,969,185
4.6.1.6 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas II
Pekerja OH 0.8 150,899 120,719
Tukang kayu OH 2.4 169,444 406,666
Kepala tukang OH 0.24 205,070 49,217
Mandor OH 0.04 175,691 7,028
Kayu papan kls II M3 0.024 3,355,206 80,525
Lem kayu Kg 0.3 23,835 7,151
Jumlah 671,305
Overhead & Profit -
Harga Satuan Pekerjaan 671,305
5.1.1 Analisa Harga Satuan Pekerjaan Sanitasi Dalam Gedung
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
1 2 3 4 5 6
ITEM PEMBAYARAN NO
: -
JENIS PEKERJAAN : Keselamatan Kerja Konstruksi (K3)
SATUAN PEMBAYARAN: Lump Sum
B. PERALATAN RENCANA
KESELAMATAN DAN KESEHATAN
C. TENAGA / PERSONIL
Catatan1. Harga Satuan Personil tersebut sudah termasuk seluruh pajak dan bea (kecuali PPN),
Asuransi Tenaga Kerja dan pengeluaran lainnya.
2. Biaya Satuan tersebut sudah termasuk biaya perlengkapan personil pengatur lalu-lintas dan
biaya perijinan yang diperlukan dengan pihak terkait dengan manajemen lalu-lintas
3. Biaya satuan tersebut sudah termasuk kebutuhan perlengkapan dan peralatan pendukung yang
diperlukan seperti material habis pakai baterai, lampu dan sebagainya
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP E10
2. Tenaga Pw 133.0 HP
3. Kapasitas Cp 0.93 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,300,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 15,714.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 13,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 12,366.81 Liter
5. Bahan Bakar Solar Ms 9,800.00 Liter
6. Minyak Pelumas Mp 39,200.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3,5 Ton E08
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 3.50 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 380,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 15,714.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 13,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 12,366.81 Liter
5. Bahan Bakar Solar Ms 9,800.00 Liter
6. Minyak Pelumas Mp 39,200.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA
BIAYA
No. URAIAN KO HP KAP. HARGA SEWA KET.
DE ALAT ALAT/JAM
(di luar PPN)
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE VIBRATOR A6
2. Tenaga Pw 5.5 HP
3. Kapasitas Cp 25.00 -
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 7,575,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 15,714.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 13,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 12,366.81 Liter
5. Bahan Bakar Solar Ms 9,800.00 Liter
6. Minyak Pelumas Mp 39,200.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
URAIAN PERALATAN
Jenis Peralatan CONCRETE PAN MIXER E43
Tenaga Pw 134 HP
Kapasitas Cp 600.00 Liter
Alat Baru : a. Umur Ekonomis A 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 1,000,000,000 Rupiah
LAIN - LAIN
Tingkat Suku Bunga i 10.00 % / Tahun
Upah Operator / Sopir U1 15,177.50 Rp./Jam
Upah Pembantu Operator / Pmb.Sopir U2 8,360.00 Rp./Jam
Bahan Bakar Bensin Mb 13,900.00 Liter
Bahan Bakar Solar Ms 13,900.00 Liter
Minyak Pelumas Mp 55,000.00 Liter
PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
URAIAN PERALATAN
Jenis Peralatan CONCRETE PUMP E28
Tenaga Pw 100.0 HP
Kapasitas Cp 8.00 M3
Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 275,500,000 Rupiah
LAIN - LAIN
Tingkat Suku Bunga i 10.00 % / Tahun
Upah Operator / Sopir U1 15,177.50 Rp./Jam
Upah Pembantu Operator / Pmb.Sopir U2 8,360.00 Rp./Jam
Bahan Bakar Bensin Mb 13,900.00 Liter
Bahan Bakar Solar Ms 13,900.00 Liter
Minyak Pelumas Mp 55,000.00 Liter
PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
DAFTAR ANALISA HARGA SATUAN
### :
Lokasi : FISIK KOLAM RENANG LANAL TERNATE
Tahun Anggaran : 2019
Item Pekerjaan : Mobilisasi / Demobilisasi
A Tenaga Kerja
1 Tenaga Kerja Dan Alat Bantu Ls 1.00 3,000,000.00 3,000,000.00
B Peralatan
C Analisa K3
1 K3 Ls 1.00 5,600,000.00 5,600,000.00