Report Durasi Proyek

Name Start Finish Duration


Pekerjaan Lantai 1 Thu 4/1/21 Fri 2/4/22 291 days
Pekerjaan Persiapan Thu 4/1/21 Mon 4/5/21 4 days
Pekerjaan Tanah Tue 4/6/21 Sun 6/6/21 52 days
Pekerjaan Pondasi Fri 4/30/21 Thu 5/27/21 19 days
Pekerjaan Beton Wed 4/21/21 Sun 7/18/21 79 days
Pekerjaan Dinding Tue 9/14/21 Fri 11/26/21 73 days
Pekerjaan Pintu dan Jendela Thu 9/16/21 Sat 1/29/22 132 days
Pekerjaan Lantai Thu 12/2/21 Tue 12/14/21 13 days

Pengerjaan Pengecatan Wed 12/15/21 Fri 1/14/22 28 days

Pekerjaan Instalasi Listrik Thu 9/16/21 Mon 1/31/22 134 days

Pekerjaan Sanitasi Mon 6/28/21 Fri 2/4/22 214 days


Pekerjaan Lantai 2 Mon 6/28/21 Fri 1/28/22 208 days
Pekerjaan Beton Mon 6/28/21 Fri 8/27/21 58 days
Pekerjaan Dinding Tue 9/14/21 Fri 11/26/21 73 days
Pekerjaan Kusen Thu 9/16/21 Fri 1/28/22 131 days
Pekerjaan Lantai Thu 12/2/21 Mon 12/13/21 12 days
Pekerjaan Pengecatan Tue 12/14/21 Thu 1/13/22 28 days
Pekerjaan Instalasi Listrik Thu 9/16/21 Wed 12/1/21 76 days

Pekerjaan Atap Sat 8/28/21 Wed 12/1/21 95 days