ZONE STRUKTUR ATAS (LMR)

URUTAN BONGKAR TC
2 1 3

LT. ATAP-ATAP 17-Dec 11-Jan


LT. ATAP/TANGGA PUBLIK #4 05-Jan 03-Dec 04-Jan
LT. DUA 26-Dec
LT. SATU 16-Dec
LT. DASAR 06-Dec 19-Nov 21-Dec
FINISH 25-Nov 09-Nov 11-Dec
BONGKAR TC
START 10-Nov 18-Oct 26-Nov
TC 1 TC 2 TC 3

LT. ATAP LMR 24-Oct 27-Oct 30-Oct 31-Oct 02-Nov 05-Nov 08-Nov 12-Nov
10

LT. LMR & ME 22-Sep 24-Sep 30-Sep 12-Oct 14-Oct 17-Oct 17-Sep 22-Oct 25-Oct 26-Oct 29-Oct 02-Nov

A.1 A.2 A.3 A.4 A.5 A.6 B.1 B.2 B.3 B.4 B.5 C.1 C.2 C.3

UTARA SELATAN TERHALANG


2 3 4 5 6 7 1 8 9 10 11 12 13 14
KEBUTUHAN SISA

REALISASI SD M.59 PT. JAYA KONSTRUKSI MP, Tbk UP DATE

RENCANA M.60 KEBUTUHAN SISA 01-Oct

RENCANA M.61 KEBUTUHAN SISA M.59

RENCANA M.62 KEBUTUHAN SISA Oky Dwi Nur Setiawan

Pekerjaan dilakukan tanpa TC KEBUTUHAN SISA Kepala Proyek