Bobot CCO 02 AGUSTUS 2009 SEPTEMBER 2009 OKTOBER 2009 NOPEMBER 2009 DESEMBER 2009 JANUARI 2010 FEBRUARI 2010 MARET 2010 APRIL 2010 MEI 2010 JUNI 2010 JULI 2010
No. Uraian Pekerjaan
(%) 24 - 30 31 - 06 07 - 13 14 - 20 21 - 27 28 - 04 05 - 11 12 - 18 19 - 25 26 - 01 02 - 08 09 - 15 16 - 22 23 - 29 30 - 06 07 - 13 14 - 20 21 - 27 28 - 03 04 - 10 11 - 17 18 - 24 25 - 31 01 - 07 08 - 14 15 - 21 22 - 28 01 - 07 08 - 14 15 - 21 22 - 28 29 - 04 05 - 11 12 - 18 ,19-25 ,26-2 ,3-9 ,10-16 ,17-23 ,24-30 ,31-6 ,7-13 ,14-20 ,21-27 ,28-5 ,6 - 12 ,13- 19 ,20-26 ,27-2
RENCANA CCO 02
RENCANA
I. PEK. PENDAHULUAN / PEMBONGKARAN 2.263 0.461 0.461 0.461 0.190 0.024 0.081 0.014 0.014 0.014 0.014 0.014 0.016 0.043 0.038
II. PEKERJAAN BETON STRUKTUR 37.194 0.703 2.599 3.131 2.834 1.421 0.950 3.144 3.310 3.144 2.923 2.234 4.653 0.211 0.210 2.300 2.300 2.300 2.300 2.300
III. PEKERJAAN PONDASI BATU GUNUNG 0.544 0.432 0.432 0.094 0.094
IV. PEKERJAAN PASANGAN 6.580 0.231 2.207 1.797 0.989 1.895 1.850 2.584 2.238 0.102 0.039 0.198 0.068 0.211 0.610 0.896 0.896 0.896 0.896 0.896 0.896
V. PEKERJAAN KUSEN PINTU, JENDELA & BOVENLIGHT 6.793 1.825 1.825 1.299 1.299 RENCANA CCO 01 0.849 0.849 0.849 0.849 0.849 0.849
REALISASI CCO 01
VI. PEKERJAAN LANTAI 6.597 0.549 0.881 0.046 0.715 0.204 0.823 0.789 0.930 0.058 0.058 0.763 0.763 0.763 0.763 0.763
VII. PEKERJAAN PLAPOND DAN PENGGANTUNG 5.004 0.168 1.130 1.005 0.880 0.837 1.001 1.001 1.001 1.001
CCO 01
REALISASI
CCO 02
VIII. PEKERJAAN SANITASI 2.082 0.466 1.089 0.623 0.283 0.283 0.283 0.283
IX. PEKERJAAN ATAP 8.687 1.511 1.518 1.518 0.582 1.475 1.241 1.241 1.241 1.241 1.241 1.241 1.241
X. PEKERJAAN PENGECATAN 3.078 0.597 0.597 0.597 0.597 0.597 0.769 0.769 0.769 0.769
XI. PEKERJAAN INSTALASI LISTIK, TELEPON DAN INTERNET 13.998 1.170 1.284 1.586 1.316 1.755 1.878 2.292 1.443 0.357 0.444 0.403 0.682 0.214 1.166 1.166 1.166 1.166 1.166 1.166 1.166 1.166
XII. PEKERJAAN LAIN-LAIN 5.356 0.134 1.719 0.080 0.128 0.057 0.342 0.283 0.606 0.315 0.330 0.204 0.204 0.370 0.312 0.765 0.765 0.765 0.765
XIII. PEKERJAAN PAGAR 1.823 1.754 0.108 0.399 0.596 0.197 0.326 0.433 0.286 0.286 0.286 0.286
RENCANA PRESTASI 0.46 0.46 0.46 0.89 3.06 3.64 3.63 3.63 3.63 4.13 5.40 5.71 5.71 5.76 5.44 6.17 5.31 5.30 5.21 4.70 3.24 1.94 2.29 1.73 1.83 1.73 1.28 - 1.34 1.35 1.01 1.01 1.01 0.74 0.78
RENCANA PRESTASI KOMULATIF - 0.46 0.92 1.38 2.28 5.33 8.98 12.60 16.23 19.86 23.99 29.39 35.10 40.81 46.57 52.01 58.19 63.49 68.80 74.01 78.71 81.95 83.89 86.18 87.91 89.74 91.47 92.76 92.76 94.10 95.45 96.46 97.47 98.48 99.22 100.00
RENCANA PRESTASI
- 0.80 0.97 3.46 1.94 1.86 0.03 1.40 0.76 0.62 0.53 0.53 0.53 0.53 0.53 0.64 1.57 1.57 1.57 1.59 1.75 0.27 1.86 0.75 1.09 0.70 1.10 1.08
RENCANA PRESTASI CCO 1 & 2 - 2.30 2.30 2.30 2.30 2.30 0.09 0.99 2.14 2.14 2.99 2.99 3.75 4.02 3.45 2.21 3.50 4.27 3.99 2.99 - 1.53 0.85 3.02
RENCANA PRESTASI KOMULATIF CCO 1 & 2 30.01 32.31 34.61 36.91 39.21 41.51 41.61 42.60 44.73 46.87 49.86 52.84 56.59 60.61 64.06 66.28 69.77 74.05 78.03 81.02 81.02 82.55 83.40 86.42
AGUSTUS 2010
KETERANGAN
,3-9 ,10-16 ,17-23 ,24-30 ,31-2.
100.00
RENCANA CCO 02
0.249 0.249
90.00
80.00
70.00
0.849 0.849
60.00
0.763 0.763 0.763
1.001 50.00
0.283 0.283
40.00
30.00
Dibuat oleh :
PT. TRINANDA KARYA UTAMA
SAIIN
Site Manager
TIME SCHEDULE 100.000
Kegiatan : REHAB BERAT KANTOR DPRD KOTA SAMARINDA
Pekerjaan : REHAB BERAT GEDUNG DPRD KOTA SAMARINDA
Lokasi : KOTA SAMARINDA
Tahun Anggaran : 2009
Bobot Skala AGUSTUS 2009 SEPTEMBER 2009 OKTOBER 2009 NOPEMBER 2009 DESEMBER 2009 JANUARI 2010
No. Uraian Pekerjaan
(%) (%) 24 - 30 31 - 06 07 - 13 14 - 20 21 - 27 28 - 04 05 - 11 12 - 18 19 - 25 26 - 01 02 - 08 09 - 15 16 - 22 23 - 29 30 - 06 07 - 13 14 - 20 21 - 27 28 - 03 04 - 10 11 - 17 18 - 24 25 - 31
1 Pekerjaan Pondasi
a. Poer (P1=130x170x0,40)
1. Galian Tanah 0.024 0.008 0.008 0.008
2. Pancang Ulin 12/12 x 12 mtr x 324 ttk 5.231 0.690 2.542 1.999
3. Pasir urug t = 10 cm 0.016 0.005 0.005 0.006
4. Lantai kerja t = 5 cm 1 : 3 : 5 0.131 0.044 0.087
5. Beton bertulang Ready Mix K=225 1.856 1.031 0.825
6. Urugan Tanah Kembali 0.002 0.002
b. Tie Beam TB1 = 20/40 -
1. Galian Tanah 0.008 0.008
2. Pasir Urug t = 10 cm 0.006 0.006
3. Lantai kerja t = 5 cm, 1 : 3 : 5 0.050 0.050
4. Beton bertulang cor Ready Mix K=225 0.665 0.665
5. Urugan Tanah Kembali 0.001 0.001
c. Tie Beam TB2 = 25/40 -
1. Galian Tanah 0.001 0.001
2. Pasir Urug t = 10 cm 0.001 0.001
3. Lantai kerja t = 5 cm, 1 : 3 : 5 0.005 0.005
4. Beton bertulang cor Ready Mix K=225 0.078 0.039 0.039
5. Urugan Tanah Kembali - 0.000
d. Tie Beam TB3 = 20/30 -
1. Galian Tanah 0.006 0.006
2. Pasir Urug t = 10 cm 0.005 0.005
3. Lantai kerja t = 5 cm, 1 : 3 : 5 0.042 0.042
4. Beton bertulang cor Ready Mix K=225 0.558 0.279 0.279
5. Urugan Tanah Kembali 0.001 0.001
Pekerjaan Struktur Atas -
a. Kolom K1-30/50, Beton Ready Mix K-225 0.203 0.051 0.051 0.051 0.051
b. Kolom K2-30/45, Beton Ready Mix K-225 4.106 0.821 0.821 0.821 0.821 0.821
c. Kolom K3-30/50, Beton Ready Mix K-225 1.814 0.078 0.230 0.078 0.824 0.302 0.302
d. Balok Lantai B1 - 25/50, Beton Ready Mix K-225 0.466 0.155 0.155 0.156
e. Balok Lantai B2 - 25/45, Beton Ready Mix K-225 1.571 0.524 0.524 0.523
f. Balok Lantai B3 - 25/40, Beton Ready Mix K-225 1.900 0.633 0.633 0.634
g. Balok Lantai B4 - 25/30, Beton Ready Mix K-225 0.155 0.052 0.052 0.051
h. Balok Lantai B5 - 25/20, Beton Ready Mix K-225 0.042 0.014 0.014 0.014
i. Plat lantai t=12 cm, Beton Ready Mix K-225 (Floor Deck) 5.298 1.766 1.766 1.766
j Ring Balk R81 25/49, beton Ready Mix K-225 1.769 0.590 0.590 0.589
k Ring Balk R82 20/49, beton Ready Mix K-225 0.632 0.211 0.211 0.210
l. Ring Balk R83 13/15, beton Ready Mix K-225 0.470 0.470
m. Tangga beton Beton Ready Mix K-225 0.452 0.452
n. Balok Latei 10/15 Beton Ready Mix K-225 0.236 0.236
2 o. Plat Atap, Beton Ready Mix K-225 1.749 1.749
3 p. Lisplank Beton t=7 cm, Beton Ready Mix K-225 0.737 0.737
4 q. Sloof beton, 15/20 Beton Ready Mix K-225 0.166 0.166
5 r. Konsol, Ready Mix K-225 1.014 1.014
LANTAI 1
1. lampu TL 2 x 36 watt 0.539 0.270 0.270
2. Lampu Down Light TL 1 x 11 watt 0.223 0.112 0.112
3. Lampu Down Light TL 1x 8 watt 0.161 0.081 0.081
4. Lampu Baret 20 watt 0.031 0.016 0.016
5. Lampu Gantung Utama 0.228 0.114 0.114
6. Lampu Dinding 0.061 0.031 0.031
7. Stop Kontak 0.049 0.025 0.025
8. Saklar Tunggal 0.013 0.007 0.007
9. Saklar Ganda 0.018 0.009 0.009
10. Inst. titik lampu NYM 3x1,5 termasuk pipa coundit 20 mm 0.918 0.459 0.459
11. Inst. stop kontak, NYM 3x2,5 termasuk pipacoundit 20mm 0.362 0.181 0.181
12. Inst. lampu Gantung NYM 3x2,5 termasuk pipa coundit 20mm 0.023 0.012 0.012
13. Inst. Hand Drayer NYM 3x2,5 termasuk pipa coundit 20mm 0.034 0.017 0.017
14. Trau 50 x 300 0.191 0.096 0.096
15. Tray 5 x 500 0.020 0.010 0.010
16. Grid Switch 10 G 0.027 0.014 0.014
-
LANTAI 2 -
1. lampu TL 2 x 36 watt 0.642 0.321 0.321
2. Lampu Down Light TL 1 x 11 watt 0.134 0.067 0.067
3. Lampu Down Light TL 1x 8 watt 0.262 0.131 0.131
4. Lampu Baret 20 watt 0.036 0.018 0.018
5. Lampu Dinding 0.061 0.031 0.031
6. Stop Kontak 0.063 0.032 0.032
7. Saklar Tunggal 0.024 0.012 0.012
8. Saklar Ganda 0.015 0.008 0.008
9. Inst. titik lampu NYM 3x1,5 termasuk pipa coundit 20 mm 1.017 0.509 0.509
10. Inst. stop kontak, NYM 3x2,5 termasuk pipacoundit 20mm 0.463 0.232 0.232
11. Inst. Hand Drayer NYM 3x2,5 termasuk pipa coundit 20mm 0.051 0.026 0.026
12. Trau 50 x 300 0.164 0.082 0.082
13. Tray 5 x 500 0.020 0.010 0.010
14. Grid Switch 10 G 0.023 0.012 0.012
-
PEKERJAAN AIR CONDITIONER (AC) -
LANTAI 1 -
1. AC Casset 3 Pk 0.603 0.302 0.302
2. AC Split 2 PK 1.065 0.533 0.533
3. Exhaus Fan 0.051 0.026 0.026
4. Stop kontak Exaus Fan 0.005 0.003 0.003
5. Saklar Exhaust Fan 0.002 0.001 0.001
6. Instalasi Titik AC NYM 3 x 2,5 termasuk pipa counduit 20 0.104 0.052 0.052
7. Instalasi Titik Exhaust NYM 3 2,5 termasuk pipa coundit 2 0.024 0.012 0.012
8. Instalasi AC Casset 0.171 0.086 0.086
-
LANTAI 2 -
1. AC Casset 3 Pk 0.979 0.490 0.152 0.338
2. AC Split 2 PK 0.574 0.287
3. AC Split 3/4 PK 0.250 0.125
4. AS Cplit 1 1/2 PK 0.433 0.217 0.217
5. AC Split 1/2 PK 0.057 0.029 0.029
6. Exhaus Fan 0.017 0.009 0.009
7. Stop kontak Exaus Fan 0.002 0.001 0.001
8. Saklar Exhaust Fan 0.002 0.001 0.001
9. Instalasi Titik AC NYM 3 x 2,5 termasuk pipa counduit 20 0.127 0.064 0.064
10. Instalasi Titik Exhaust NYM 3 2,5 termasuk pipa coundit 0.008 0.004 0.004
11. Instalasi AC Casset 0.114 0.057 0.057
-
PEKERJAAN TELEPON -
MATERIAL UTAMA -
1. Main Unit PABX 36 Extention 0.683 0.171 0.171
2. Digital Key Telepon 0.057 0.014
3. Panel MDF 50 Core 0.159 0.040
4. Console Extention 0.034 0.009
5. Telepon 0.526 0.132 0.132
6. UPS 200 VA 0.102 0.026 0.026
7. Setting 0.068 0.068
8. Material Bantu 0.017 0.004 0.004
9. Kabel Feeder 0.025 0.006
10. Grounding 0.045 25.000 0.011 0.011
-
LANTAI 1 -
1. Outlet Rj 11 0.020
2. Instalasi titik telepon catSE 4 Pair, termasuk pipa koundit 0.123
3. Instalasi Panel MDF, termasuk ducting 0.034
-
LANTAI 2 -
1. Outlet Rj 11 0.017 0.009
2. Instalasi titik telepon catSE 4 Pair, termasuk pipa koundit 0.102
3. Instalasi Panel MDF, termasuk ducting 0.034
-
PEKERJAAN INTERNET -
MATERIAL UTAMA -
1. Wallmount Rack 15 u 0.296
2. Hub/Switch 24 port 0.205
3. Wireles Modem 0.159
4. Internet Conection 0.683
5. Material Bantu 0.017
-
LANTAI 1 -
1. Patchord Rj 45 0.029
2. Conector Rj 45 0.014
3. Moduler Jack 0.017
4. Inetalasi LAN, Cats6E 4 pair, termasuk pipa coundit 20mm 0.135
5. Instalasi Wallmount rack, termasuk duckting 0.011
6. Instalasi wireles modem, termasukpipa coundit 20 mm 0.016
-
LANTAI 2 -
1. Patchord Rj 45 0.026
2. Conector Rj 45 0.012
3. Moduler Jack 0.015
4. Inetalasi LAN, Cats6E 4 pair, termasuk pipa coundit 20mm 0.120
5. Instalasi Wallmount rack, termasuk duckting 0.011
6. Instalasi wireles modem, termasukpipa coundit 20 mm 0.016
2. RENCANA PRESTASI 0.461 0.461 0.461 0.893 3.055 3.644 3.628 3.628 3.628 4.133 5.399 5.709 5.711 5.761 5.442 6.173 5.307 5.304 5.213 4.701 3.240 1.935 2.292
3. RENCANA PRESTASI KOMULATIF 0.461 0.922 1.383 2.276 5.331 8.975 12.603 16.231 19.859 23.992 29.391 35.100 40.811 46.572 52.014 58.187 63.494 68.798 74.011 78.712 81.952 83.887 86.179
4. REALISASI PEKERJAAN
6. PRESTASI
0
Nomor :
Tanggal : 24 Agustusr 2009
Nomor :
~ WAKTU PELAKSANAAN :
Tanggal
~ SERAH TERIMA I (ST 1) :
~ WAKTU PEMELIHARAAN :
0.050
0.059
0.012
0.287
0.125
0.171 0.171
0.014 0.014 0.014
0.040 0.040 0.040
0.009 0.009 0.009
0.132 0.132
0.026 0.026
0.004 0.004
0.006 0.006 0.006
0.011 0.011
0.010 0.010
0.031 0.031 0.031 0.031
0.017 0.017
0.009
0.051 0.051
0.017 0.017
0.000 0.000
0.148 0.148
0.103 0.103
0.080 0.080
0.342 0.342
0.009 0.009
0.015 0.015
0.007 0.007
0.009 0.009
0.068 0.068
0.006 0.006
0.008 0.008
0.013 0.013
0.006 0.006
0.008 0.008
0.060 0.060
0.006 0.006
0.008 0.008
0.226 0.456
0.057 0.057
0.058 0.058
0.285
1.733 1.829 1.732 1.283 1.343 1.350 1.011 1.011 1.011 0.739 0.784 -
87.912 89.741 91.473 92.756 94.099 95.449 96.460 97.471 98.482 99.221 100.005 100.005
Dibuat oleh :
PT. TRINANDA KARYA UTAMA
Sunitiyarso
Kuasa Direktur
PERENCANAAN TIME SCHEDULLE PEMANCANGAN
Kegiatan : REHAB BERAT KANTOR DPRD KOTA SAMARINDA
Pekerjaan : REHAB BERAT GEDUNG DPRD KOTA SAMARINDA
Lokasi : KOTA SAMARINDA
Tahun Anggaran : 2009
4 Galian Poer
KETERANGAN :
1. Distribusi tiang pancang dalam 1 hari direncanakan titik = 30 m, dikirim pada
malam hari
2. Rencana produksi pemancangan pada alat pancang min 15 titik / hari
3. Penempatan tiang pancang disesuaikan dengan perencanaan titik-titik pancangnya
sehingga terwujud efisiensi waktu dan kerja
Oct-09 No
No. Uraian Pekerjaan Sl Rb Km Jm Sb Mg Sn Sl Rb Km Jm Sb Mg Sn Sl Rb Km Jm Sb Mg Sn Sl Rb Km
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
I. PEKERJAAN PEMBONGKARAN
1 Pembongkaran gedung lama
2. Perapian lapangan
KETERANGAN :
1. Pembongkaran mulai dilakukan setelah turunnya ijin mulai pekerjaan dari Pihak Owner
tertanggal 12 Oktober 2009
2. Pembongkaran gedung lama dilakukan dengan diiringi secara simultan pembuatan
pagar pengaman, sehingga barang-barang hasil bongkaran dlm kondisi aman
3. Distribusi tiang pancang dalam 1 hari direncanakan titik = m, dikirim pada
malam hari
4. Rencana produksi pemancangan pada alat pancang min titik / hari
5. Penempatan tiang pancang disesuaikan dengan perencanaan titik-titik pancangnya
sehingga terwujud efisiensi waktu dan kerja Samarinda 14 Sep
PT. TRINANDA KAR
Nov-09
Jm Sb Mg Sn Sl Rb
30 31 1 2 3 4
I. PEKERJAAN PENDAHULUAN
1 Eutzet + bouplank
KETERANGAN :
1.
RAB TERINCI SUB PEKERJAAN
Kegiatan : REHAB BERAT KANTOR DPRD KOTA SAMARINDA
Pekerjaan : REHAB BERAT GEDUNG DPRD KOTA SAMARINDA
Lokasi : KOTA SAMARINDA
Tahun Anggaran : 2009
No. Uraian Pekerjaan VOLUME Harga Satuan (Rp.) Jumlah Harga (Rp.)
I PEKERJAAN PERSIAPAN
1 Papan nama proyek 1.00 bh 750,000.00 750,000.00
2 Pagar pengaman 100.00 m1 134,125.00 13,412,500.00
3 Barak kerja / direksi keet 64.00 m2 321,834.00 20,597,376.00
4 Pasang bouwlplank 160.00 m1 59,718.75 9,555,000.00
5 Dokumentasi, adm dan As Build Drwing 1.00 ls 4,000,000.00 4,000,000.00
6 Listrik kerja 1.00 ls 3,300,000.00 3,300,000.00
7 Air kerja 1.00 ls 3,000,000.00 3,000,000.00
8 Bongkar bangunan lama 708.00 m2 62,895.00 44,529,660.00
9 Mobilisasi dan Demobilisasi 1.00 ls 2,500,000.00 2,500,000.00
10 Pembersihan lokasi 750.00 m2 4,875.00 3,656,250.00
SUB TOTAL I 105,300,786
f. Balok Lantai B3 - 25/40, Beton Ready Mix K-225 24.05 m3 4,510,349.62 108,473,908.36
g. Balok Lantai B4 - 25/30, Beton Ready Mix K-225 1.50 m3 5,903,889.80 8,855,834.70
h. Balok Lantai B5 - 25/20, Beton Ready Mix K-225 0.39 m3 6,134,528.45 2,392,466.10
i. Plat lantai t=12 cm, Beton Ready Mix K-225 (Floor Deck) 79.84 m3 3,789,049.10 302,517,680.14
j Ring Balk R81 25/49, beton Ready Mix K-225 22.40 m3 4,510,349.62 101,031,831.49
k Ring Balk R82 20/49, beton Ready Mix K-225 6.98 m3 5,173,634.45 36,111,968.46
l. Ring Balk R83 13/15, beton Ready Mix K-225 5.92 m3 4,530,501.94 26,820,571.48
m. Tangga beton Beton Ready Mix K-225 5.40 m3 4,783,381.65 25,830,260.91
n. Balok Latei 10/15 Beton Ready Mix K-225 2.20 m3 6,134,528.45 13,495,962.59
o. Plat Atap, Beton Ready Mix K-225 20.88 m3 4,783,381.65 99,877,008.85
p. Lisplank Beton t=7 cm, Beton Ready Mix K-225 8.80 m3 4,783,381.65 42,093,758.52
q. Sloof beton, 15/20 Beton Ready Mix K-225 1.96 m3 4,840,856.21 9,488,078.17
r. Konsol, Ready Mix K-225 12.10 m3 4,783,381.65 57,878,917.97
SUB TOTAL II 1,796,844,554.59
IV PEKERJAAN PASANGAN
1 Pasangan dinding bata merah 1:4 1,025.75 m2 69,525.00 71,315,268.75
2 Plesteran Dinding + Acian 1:4 2,051.49 m2 26,455.00 54,272,167.95
3 Plesteran Beton 1:3 440.44 m2 26,702.00 11,760,628.88
4 Dinding Kamprot 18.00 m2 41,325.00 743,850.00
5 Pasang Batu Alam 156.00 m2 251,509.42 39,235,469.52
6 Pasangan dinding Panel Beton Ringan 1,266.70 m2 333,600.00 422,571,120.00
7 Pintu kayu bengkirai dinding Panel beton Ringan Finish cat 302.00 m2 17,110.00 5,167,220.00
8 Pasangan dinding keramik Toilet 20/25 290.85 m2 124,062.50 36,083,578.13
9 Pasangan dinding batu Granit pintu utama 11.20 m2 522,812.50 5,855,500.00
10 Pasang paving 1,880.00 m2 114,000.00 214,320,000.00
SUB TOTAL IV 861,324,803.23
VI PEKERJAAN LANTAI
1 Urugan tanah peninggian lantai 40 cm 459.60 m3 68,250.00 31,367,700.00
2 Urugan pasir bawah lantai 10 cm Padat 114.90 m3 86,250.00 9,910,125.00
3 Lantai kerja Beton rabat t=5, 1:3:5 16.43 m3 658,175.00 10,813,815.25
4 Pasangan lantai keramik Tile 40/40 1,633.48 m2 132,874.50 217,047,838.26
5 Pasangan lantai keramik Anti Slip 20/20 78.00 m2 129,749.50 10,120,461.00
6 Pasangan Lantai Keramik 30/30 Tangga Ari Slip 32.00 m2 287,917.30 9,213,353.60
SUB TOTAL VI 288,473,293.11
IX PEKERJAAN ATAP
1 Rangka Atap Baja Ringan 941.00 M2 275,000.00 258,775,000.00
2 Atap Multi Color 2x5 1,196.00 Lbr 42,500.00 50,830,000.00
3 Atap Multi Color 1x5 422.00 Lbr 35,000.00 14,770,000.00
4 Screw Roofing 5,645.00 bh 200.00 1,129,000.00
5 Pipa Talang uk. 4" PVC Tipe AW 200.00 m1 54,244.38 10,848,876.00
6 Lispalnk 2/25 400.00 m1 53,550.00 21,420,000.00
7 Atap bubungan multi color 166.00 bh 25,000.00 4,150,000.00
8 Water profing plat atap (Coating) 214.00 m2 69,937.50 14,966,625.00
SUB TOTAL IX 376,889,501.00
X PEKERJAAN PENGECATAN
1 Pengecatan Dinding 4,452.78 m2 28,619.00 127,434,110.82
2 Pengecatan Plapond 1,334.00 m2 32,247.50 43,018,165.00
SUB TOTAL XI 170,452,275.82
B LANTAI 1
1. lampu TL 2 x 36 watt 57.00 bh 539,500.00 30,751,500.00
2. Lampu Down Light TL 1 x 11 watt 40.00 bh 318,500.00 12,740,000.00
3. Lampu Down Light TL 1x 8 watt 30.00 bh 305,500.00 9,165,000.00
4. Lampu Baret 20 watt 6.00 bh 292,500.00 1,755,000.00
5. Lampu Gantung Utama 1.00 bh 13,000,000.00 13,000,000.00
6. Lampu Dinding 6.00 bh 585,000.00 3,510,000.00
7. Stop Kontak 43.00 bh 65,000.00 2,795,000.00
8. Saklar Tunggal 11.00 bh 65,000.00 715,000.00
9. Saklar Ganda 16.00 bh 65,000.00 1,040,000.00
10. Inst. titik lampu NYM 3x1,5 termasuk pipa coundit 20 mm 139.00 ttk 377,000.00 52,403,000.00
11. Inst. stop kontak, NYM 3x2,5 termasuk pipacoundit 20mm 43.00 ttk 481,000.00 20,683,000.00
12. Inst. lampu Gantung NYM 3x2,5 termasuk pipa coundit 20mm 1.00 ttk 1,300,000.00 1,300,000.00
13. Inst. Hand Drayer NYM 3x2,5 termasuk pipa coundit 20mm 4.00 ttk 481,000.00 1,924,000.00
14. Trau 50 x 300 56.00 Mtr 195,000.00 10,920,000.00
15. Tray 5 x 500 6.00 Mtr 195,000.00 1,170,000.00
C LANTAI 2
1. lampu TL 2 x 36 watt 68.00 bh 539,500.00 36,686,000.00
2. Lampu Down Light TL 1 x 11 watt 24.00 bh 318,500.00 7,644,000.00
3. Lampu Down Light TL 1x 8 watt 49.00 bh 305,500.00 14,969,500.00
4. Lampu Baret 20 watt 7.00 bh 292,500.00 2,047,500.00
5. Lampu Dinding 6.00 bh 585,000.00 3,510,000.00
6. Stop Kontak 55.00 bh 65,000.00 3,575,000.00
7. Saklar Tunggal 21.00 bh 65,000.00 1,365,000.00
8. Saklar Ganda 13.00 bh 65,000.00 845,000.00
9. Inst. titik lampu NYM 3x1,5 termasuk pipa coundit 20 mm 154.00 ttk 377,000.00 58,058,000.00
10. Inst. stop kontak, NYM 3x2,5 termasuk pipacoundit 20mm 55.00 ttk 481,000.00 26,455,000.00
11. Inst. Hand Drayer NYM 3x2,5 termasuk pipa coundit 20mm 6.00 ttk 481,000.00 2,886,000.00
12. Trau 50 x 300 48.00 Mtr 195,000.00 9,360,000.00
13. Tray 5 x 500 6.00 Mtr 195,000.00 1,170,000.00
14. Grid Switch 10 G 1.00 Ttk 1,300,000.00 1,300,000.00
B LANTAI 2
1. AC Casset 3 Pk 2.00 bh 27,950,000.00 55,900,000.00
2. AC Split 2 PK 7.00 bh 4,680,000.00 32,760,000.00
3. AC Split 3/4 PK 4.00 bh 3,575,000.00 14,300,000.00
4. AS Cplit 1 1/2 PK 4.00 bh 6,175,000.00 24,700,000.00
5. AC Split 1/2 PK 1.00 bh 3,250,000.00 3,250,000.00
6. Exhaus Fan 1.00 bh 975,000.00 975,000.00
7. Stop kontak Exaus Fan 1.00 bh 97,500.00 97,500.00
8. Saklar Exhaust Fan 1.00 bh 97,500.00 97,500.00
9. Instalasi Titik AC NYM 3 x 2,5 termasuk pipa counduit 2 16.00 Ttk 455,000.00 7,280,000.00
10. Instalasi Titik Exhaust NYM 3 2,5 termasuk pipa coundi 1.00 Ttk 455,000.00 455,000.00
11. Instalasi AC Casset 2.00 Ttk 3,250,000.00 6,500,000.00
PEKERJAAN TELEPON
A MATERIAL UTAMA
1. Main Unit PABX 36 Extention 1.00 bh 39,000,000.00 39,000,000.00
2. Digital Key Telepon 1.00 bh 3,250,000.00 3,250,000.00
3. Panel MDF 50 Core 2.00 set 4,550,000.00 9,100,000.00
4. Console Extention 1.00 bh 1,950,000.00 1,950,000.00
5. Telepon 33.00 bh 910,000.00 30,030,000.00
6. UPS 200 VA 1.00 bh 5,850,000.00 5,850,000.00
7. Setting 1.00 Ls 3,900,000.00 3,900,000.00
8. Material Bantu 1.00 Ls 975,000.00 975,000.00
9. Kabel Feeder 20.00 Mtr 71,500.00 1,430,000.00
10. Grounding 1.00 Ls 2,593,000.00 2,593,000.00
B LANTAI 1
1. Outlet Rj 11 18.00 bh 65,000.00 1,170,000.00
2. Instalasi titik telepon catSE 4 Pair, termasuk pipa koundi 18.00 Ttk 390,000.00 7,020,000.00
3. Instalasi Panel MDF, termasuk ducting 1.00 Ls 1,950,000.00 1,950,000.00
C LANTAI 2
1. Outlet Rj 11 15.00 bh 65,000.00 975,000.00
2. Instalasi titik telepon catSE 4 Pair, termasuk pipa koundi 15.00 Ttk 390,000.00 5,850,000.00
3. Instalasi Panel MDF, termasuk ducting 1.00 Ls 1,950,000.00 1,950,000.00
PEKERJAAN INTERNET
A MATERIAL UTAMA
1. Wallmount Rack 15 u 2.00 bh 8,450,000.00 16,900,000.00
2. Hub/Switch 24 port 2.00 bh 5,850,000.00 11,700,000.00
3. Wireles Modem 2.00 bh 4,550,000.00 9,100,000.00
4. Internet Conection 1.00 Th 39,000,000.00 39,000,000.00
5. Material Bantu 1.00 Ls 975,000.00 975,000.00
B LANTAI 1
1. Patchord Rj 45 17.00 bh 97,500.00 1,657,500.00
2. Conector Rj 45 17.00 bh 45,500.00 773,500.00
3. Moduler Jack 17.00 bh 58,500.00 994,500.00
4. Inetalasi LAN, Cats6E 4 pair, termasuk pipa coundit 20m 17.00 Ttk 455,000.00 7,735,000.00
5. Instalasi Wallmount rack, termasuk duckting 1.00 Ls 650,000.00 650,000.00
6. Instalasi wireles modem, termasukpipa coundit 20 mm 1.00 Ls 910,000.00 910,000.00
C LANTAI 2
1. Patchord Rj 45 15.00 bh 97,500.00 1,462,500.00
2. Conector Rj 45 15.00 bh 45,500.00 682,500.00
3. Moduler Jack 15.00 bh 58,500.00 877,500.00
4. Inetalasi LAN, Cats6E 4 pair, termasuk pipa coundit 20m 15.00 Ttk 455,000.00 6,825,000.00
5. Instalasi Wallmount rack, termasuk duckting 1.00 Ls 650,000.00 650,000.00
6. Instalasi wireles modem, termasukpipa coundit 20 mm 1.00 Ls 910,000.00 910,000.00
SUB TOTAL XI 844,128,500.00
14 Pas. Pagar pintu stainles steel lengkap accesories 3.00 unit 7,500,000.00 22,500,000.00
15 Lampu sorot papan nama lengkap accesories dan instalasi 3.00 bh 500,000.00 1,500,000.00
16 Papan nama 1.00 Ls 2,500,000.00 2,500,000.00
SUB TOTAL XIII 217,716,710.23
Jumlah 5,710,185,724.73
IMB 1,2% + 1.000.000 69,522,228.70
PPn 10% 571,018,572.47
TOTAL 6,350,726,525.90
DIBULATKAN 6,350,726,000.00
Terbilang :
No. Uraian Pekerjaan Volume Harga Satuan (Rp.) Jumlah Harga (Rp.)
Analisa hal.28/56
8 1 M2 PAS. BATU BATA 1 PC : 5 PS
Batu bata 70.000 biji 325.00 22,750.00
Semen Pc @ 50 kg 0.194 zak 52,000.00 10,088.00
Pasir pasang 0.045 m3 95,000.00 4,275.00
Pekerja 0.320 hr 45,000.00 14,400.00
Tukang batu 0.100 hr 35,000.00 3,500.00
Kepala Tukang batu 0.010 hr 65,000.00 650.00
Mandor 0.015 hr 75,000.00 1,125.00
56,788.00
Jadi 1 m3 516,254.55
9 1 M2 PAS. PLESTERAN 1 PC : 5 PS
Semen Pc @ 50 kg 0.146 zak 52,000.00 7,592.00
Pasir pasang 0.028 m3 95,000.00 2,660.00
Pekerja 0.250 hr 45,000.00 11,250.00
Tukang batu 0.200 hr 35,000.00 7,000.00
Kepala Tukang batu 0.020 hr 65,000.00 1,300.00
Mandor 0.013 hr 75,000.00 975.00
30,777.00
Dibulatkan 30,780.00
10 1 M2 PAS. PLESTERAN 1 PC : 2 PS
Semen Pc @ 50 kg 0.141 zak 52,000.00 7,332.00
Pasir pasang 0.021 m3 95,000.00 1,995.00
Pekerja 0.260 hr 45,000.00 11,700.00
Tukang batu 0.200 hr 35,000.00 7,000.00
Kepala Tukang batu 0.020 hr 65,000.00 1,300.00
Mandor 0.013 hr 75,000.00 975.00
30,302.00
Dibulatkan 30,300.00
11 1 M2 MENGERJAKAN BEKESTING BETON
( PONDASI )
Kayu meranti 0.040 m3 1,350,000.00 54,000.00
Paku 0.300 kg 8,000.00 2,400.00
Minyak bekisting 0.100 m3 3,000.00 300.00
Pekerja 0.300 hr 45,000.00 13,500.00
Tukang kayu 0.260 hr 35,000.00 9,100.00
Kepala Tukang kayu 0.026 hr 65,000.00 1,690.00
Mandor 0.005 hr 75,000.00 375.00
81,365.00
2 x pakai 40,682.50
12 1 M2 MENGERJAKAN BEKESTING BETON
( SLOOF )
Kayu meranti 0.045 m3 1,350,000.00 60,750.00
Paku 0.300 kg 8,000.00 2,400.00
Minyak bekisting 0.100 m3 3,000.00 300.00
Pekerja 0.300 hr 45,000.00 13,500.00
Tukang kayu 0.260 hr 35,000.00 9,100.00
Kepala Tukang kayu 0.026 hr 65,000.00 1,690.00
Mandor 0.005 hr 75,000.00 375.00
88,115.00
2 x pakai 44,057.50
13 1 M2 MENGERJAKAN BEKESTING BETON
( KOLOM )
Kayu meranti 0.040 m3 1,350,000.00 54,000.00
Multiplek 9 mm 1.000 m2 33,750.00 33,750.00
Paku 0.400 kg 8,000.00 3,200.00
Minyak bekisting 0.200 m3 3,000.00 600.00
Pekerja 0.300 hr 45,000.00 13,500.00
Tukang kayu 0.330 hr 35,000.00 11,550.00
Kepala Tukang kayu 0.033 hr 65,000.00 2,145.00
Mandor 0.006 hr 75,000.00 450.00
119,195.00
2 x pakai 59,597.50
Analisa hal.29/56
14 1 M2 MENGERJAKAN BEKESTING BETON
( BALOK )
Kayu meranti 0.040 m3 1,350,000.00 54,000.00
Multiplek 9 mm 1.000 m2 33,750.00 33,750.00
Paku 0.400 kg 8,000.00 3,200.00
Minyak bekisting 0.200 m3 3,000.00 600.00
Pekerja 0.320 hr 45,000.00 14,400.00
Tukang kayu 0.330 hr 35,000.00 11,550.00
Kepala Tukang kayu 0.033 hr 65,000.00 2,145.00
Mandor 0.006 hr 75,000.00 450.00
120,095.00
2 x pakai 60,047.50
15 1 M2 MENGERJAKAN BEKESTING BETON
( PLAT )
Kayu meranti 0.040 m3 1,350,000.00 54,000.00
Multiplek 9 mm 1.000 m2 33,750.00 33,750.00
Paku 0.400 kg 8,000.00 3,200.00
Minyak bekisting 0.200 m3 3,000.00 600.00
Pekerja 0.320 hr 45,000.00 14,400.00
Tukang kayu 0.330 hr 35,000.00 11,550.00
Kepala Tukang kayu 0.033 hr 65,000.00 2,145.00
Mandor 0.006 hr 75,000.00 450.00
120,095.00
2 x pakai 60,047.50
16 1 M2 MENGERJAKAN BEKESTING BETON
( TANGGA )
Kayu meranti 0.030 m3 1,350,000.00 40,500.00
Multiplek 9 mm 1.000 m2 33,750.00 33,750.00
Paku 0.400 kg 8,000.00 3,200.00
Minyak bekisting 0.200 m3 3,000.00 600.00
Pekerja 0.320 hr 45,000.00 14,400.00
Tukang kayu 0.330 hr 35,000.00 11,550.00
Kepala Tukang kayu 0.033 hr 65,000.00 2,145.00
Mandor 0.006 hr 75,000.00 450.00
106,595.00
2 x pakai 53,297.50
17 1 KG MENGERJAKAN BESI POLOS
Besi beton polos 1.050 kg 8,150.00 8,557.50
Bendrat 0.015 kg 10,000.00 150.00
Pekerja 0.007 hr 45,000.00 315.00
Tukang besi 0.007 hr 35,000.00 245.00
Kepala Tukang besi 0.001 hr 65,000.00 65.00
Mandor 0.001 hr 75,000.00 75.00
9,407.50
Dibulatkan 9,405.00
18 1 KG MENGERJAKAN BESI ULIR
Besi beton ulir 1.050 kg 8,500.00 8,925.00
Bendrat 0.015 kg 10,000.00 150.00
Pekerja 0.007 hr 45,000.00 315.00
Tukang besi 0.007 hr 35,000.00 245.00
Kepala Tukang besi 0.001 hr 65,000.00 65.00
Mandor 0.001 hr 75,000.00 75.00
9,775.00
Dibulatkan 9,770.00
19 1 M3 BETON ( K 225 )
Semen PC @ 50 kg 7.760 zak 52,000.00 403,520.00
Pasir cor 0.650 m3 225,000.00 146,250.00
Steinslag 0.650 m3 150,000.00 97,500.00
Pekerja 6.000 hr 45,000.00 270,000.00
Tukang batu 1.000 hr 35,000.00 35,000.00
Kepala Tukang batu 0.100 hr 65,000.00 6,500.00
Mandor 0.300 hr 75,000.00 22,500.00
Analisa hal.30/56
981,270.00
Analisa hal.31/56
20 1 M3 COR BETON 1 PC : 2 PS : 3 KR
Semen PC @ 50 kg 6.720 zak 52,000.00 349,440.00
Pasir cor 0.540 m3 225,000.00 121,500.00
Steinslag 0.810 m3 150,000.00 121,500.00
Pekerja 2.000 hr 45,000.00 90,000.00
Tukang batu 0.350 hr 35,000.00 12,250.00
Kepala Tukang batu 0.035 hr 65,000.00 2,275.00
Mandor 1.000 hr 75,000.00 75,000.00
771,965.00
21 1 M3 COR BETON 1 PC : 3 PS : 5 KR
Semen PC @ 50 kg 4.380 zak 52,000.00 227,760.00
Pasir cor 0.520 m3 225,000.00 117,000.00
Steinslag 0.870 m3 150,000.00 130,500.00
Pekerja 1.650 hr 45,000.00 74,250.00
Tukang batu 0.250 hr 35,000.00 8,750.00
Kepala Tukang batu 0.025 hr 65,000.00 1,625.00
Mandor 0.080 hr 75,000.00 6,000.00
565,885.00
22 1 M2 PASANG PAVING STONE T. 6 CM
Paving stone t. 6 cm 1.000 m2 32,500.00 32,500.00
Pekerja 0.500 hr 45,000.00 22,500.00
Tukang batu 0.250 hr 35,000.00 8,750.00
Kepala Tukang batu 0.025 hr 65,000.00 1,625.00
Mandor 0.025 hr 75,000.00 1,875.00
67,250.00
23 1 M2 LANTAI KERAMIK 40 X 40 CM
Keramik lantai 40 x 40 cm 1.000 m2 44,500.00 44,500.00
Semen PC @ 50 kg 0.228 zak 52,000.00 11,856.00
Pasir pasang 0.042 m3 95,000.00 3,990.00
Semen poles 1.500 kg 6,000.00 9,000.00
Pekerja 0.620 hr 45,000.00 27,900.00
Tukang batu 0.350 hr 35,000.00 12,250.00
Kepala Tukang batu 0.035 hr 65,000.00 2,275.00
Mandor 0.030 hr 75,000.00 2,250.00
114,021.00
Dibulatkan 114,020.00
24 1 M2 LANTAI NIRO GRANITE 40 X 40 CM ( TYPE ZIRCONE POLISHED / 821 )
Lantai Niro Granite 40 x 40 cm 1.000 m2 215,000.00 215,000.00
Type Zircone Polished / 821
Semen PC @ 50 kg 0.228 zak 52,000.00 11,856.00
Pasir pasang 0.042 m3 95,000.00 3,990.00
Semen poles 1.500 kg 6,000.00 9,000.00
Pekerja 0.620 hr 45,000.00 27,900.00
Tukang batu 0.350 hr 35,000.00 12,250.00
Kepala Tukang batu 0.035 hr 65,000.00 2,275.00
Mandor 0.030 hr 75,000.00 2,250.00
284,521.00
Dibulatkan 284,520.00
25 1 M2 LANTAI / BORDER NIRO GRANITE 40 X 40 CM ( TYPE SANDRA POLISHED / 790 )
Lantai Niro Granite 40 x 40 cm 1.000 m2 225,000.00 225,000.00
Type Sandra Polished / 790
Semen PC @ 50 kg 0.228 zak 52,000.00 11,856.00
Pasir pasang 0.042 m3 95,000.00 3,990.00
Semen poles 1.500 kg 6,000.00 9,000.00
Pekerja 0.620 hr 45,000.00 27,900.00
Tukang batu 0.350 hr 35,000.00 12,250.00
Kepala Tukang batu 0.035 hr 65,000.00 2,275.00
Mandor 0.030 hr 75,000.00 2,250.00
294,521.00
Dibulatkan 294,520.00
Analisa hal.32/56
26 1 M2 LANTAI NIRO GRANITE 40 X 40 CM DECORATIF
Lantai Niro Granite 40 x 40 cm 1.000 m2 237,500.00 237,500.00
Type Sandra Polished / 790
Type Granite Black / 989
Type Isabella / 425
Semen PC @ 50 kg 0.228 zak 52,000.00 11,856.00
Pasir pasang 0.042 m3 95,000.00 3,990.00
Semen poles 1.500 kg 6,000.00 9,000.00
Pekerja 0.620 hr 45,000.00 27,900.00
Tukang batu 0.350 hr 35,000.00 12,250.00
Kepala Tukang batu 0.035 hr 65,000.00 2,275.00
Mandor 0.030 hr 75,000.00 2,250.00
307,021.00
Upah kerja untuk mainan decoratif 5,000.00
Jumlah 312,021.00
Dibulatkan 312,020.00
27 1 M2 LANTAI NIRO GRANITE 40 X 40 CM ( TYPE CLEOPATRA UNPOLISHED / 535 )
Lantai Niro Granite 40 x 40 cm 1.000 m2 175,000.00 175,000.00
Type Cleopatra Unpolished / 535
Semen PC @ 50 kg 0.228 zak 52,000.00 11,856.00
Pasir pasang 0.042 m3 95,000.00 3,990.00
Semen poles 1.500 kg 6,000.00 9,000.00
Pekerja 0.620 hr 45,000.00 27,900.00
Tukang batu 0.350 hr 35,000.00 12,250.00
Kepala Tukang batu 0.035 hr 65,000.00 2,275.00
Mandor 0.030 hr 75,000.00 2,250.00
244,521.00
Dibulatkan 244,520.00
28 1 M2 DINDING KERAMIK 20 X 25 CM
Keramik dinding 20 x 25 cm 1.000 m2 45,000.00 45,000.00
Semen PC @ 50 kg 0.186 zak 52,000.00 9,672.00
Pasir pasang 0.018 m3 95,000.00 1,710.00
Semen poles 1.500 kg 6,000.00 9,000.00
Pekerja 0.600 hr 45,000.00 27,000.00
Tukang batu 0.450 hr 35,000.00 15,750.00
Kepala Tukang batu 0.045 hr 65,000.00 2,925.00
Mandor 0.030 hr 75,000.00 2,250.00
113,307.00
Dibulatkan 113,300.00
29 1 M2 PELAPIS DINDING GRANIT
Granit 1.020 m2 300,000.00 306,000.00
Semen PC @ 50 kg 0.249 zak 52,000.00 12,948.00
Pasir pasang 0.025 m3 95,000.00 2,375.00
Semen poles 1.500 kg 6,000.00 9,000.00
Pekerja 0.720 hr 45,000.00 32,400.00
Tukang batu 0.650 hr 35,000.00 22,750.00
Kepala Tukang batu 0.065 hr 65,000.00 4,225.00
Mandor 0.035 hr 75,000.00 2,625.00
392,323.00
Dibulatkan 392,325.00
30 1 M2 CAT TEMBOK
Plamur 0.100 kg 12,500.00 1,250.00
Cat tembok Catylac 0.360 kg 15,000.00 5,400.00
Pekerja 0.020 hr 45,000.00 900.00
Tukang cat 0.063 hr 35,000.00 2,205.00
Kepala Tukang cat 0.006 hr 65,000.00 390.00
Mandor 0.003 hr 75,000.00 225.00
10,370.00
Analisa hal.33/56
31 1 M2 CAT KAYU EMCO
Cat kayu 0.520 kg 38,500.00 20,020.00
Plamir 0.150 kg 12,500.00 1,875.00
Menie 0.200 kg 10,000.00 2,000.00
Pekerja 0.070 hr 45,000.00 3,150.00
Tukang cat 0.105 hr 35,000.00 3,675.00
Kepala Tukang cat 0.004 hr 65,000.00 260.00
Mandor 0.003 hr 75,000.00 225.00
31,205.00
32 1 M2 POLITURAN MELAMIC
Kertas gosok 1.980 lbr 3,000.00 5,940.00
Wood filler ultran 0.490 kg 27,500.00 13,475.00
Wood stain ultran 0.120 kg 27,500.00 3,300.00
Sanding sealer ultran 0.500 kg 30,000.00 15,000.00
Clear dof ultran 0.300 kg 45,000.00 13,500.00
Thinner ND 1.000 ltr 12,500.00 12,500.00
Pekerja 0.500 hr 45,000.00 22,500.00
Tukang cat 0.300 hr 35,000.00 10,500.00
Kepala tukang 0.030 hr 65,000.00 1,950.00
Mandor 0.030 hr 75,000.00 2,250.00
100,915.00
33 1 M' KUSEN ALUMINIUM
Profil Aluminium Uk. 2 " x 5 " + besi plat 1.000 m' 71,500.00 71,500.00
Karet Kusen Aluminium 2.000 m3 1,750.00 3,500.00
Pekerja 1.050 hr 45,000.00 47,250.00
Tukang kayu 1.050 hr 35,000.00 36,750.00
Kepala Tukang kayu 0.105 hr 65,000.00 6,825.00
Mandor 0.011 hr 75,000.00 825.00
166,650.00
34 1 M2 RANGKA PARTISI METAL HOLLOW
40 X 40 MM T. 2,00 MM - A
Metal hollow 40 x 40 mm t. 2,00 mm 4.300 m' 14,250.00 61,275.00
Sekrup 0.050 kg 28,500.00 1,425.00
Menie rangka metal hollow 0.688 m2 8,000.00 5,504.00
Pekerja 0.075 hr 45,000.00 3,375.00
Tukang kayu 0.225 hr 35,000.00 7,875.00
Kepala Tukang kayu 0.023 hr 65,000.00 1,495.00
Mandor 0.038 hr 75,000.00 2,850.00
83,799.00
Dibulatkan 83,795.00
35 1 M2 RANGKA PARTISI METAL HOLLOW
40 X 40 MM T. 2,00 MM - B
Metal hollow 40 x 40 mm t. 2,00 mm 5.700 m' 14,250.00 81,225.00
Sekrup 0.050 kg 28,500.00 1,425.00
Menie rangka metal hollow 0.912 m2 8,000.00 7,296.00
Pekerja 0.075 hr 45,000.00 3,375.00
Tukang kayu 0.225 hr 35,000.00 7,875.00
Kepala Tukang kayu 0.023 hr 65,000.00 1,495.00
Mandor 0.038 hr 75,000.00 2,850.00
105,541.00
Dibulatkan 105,545.00
36 1 M2 RANGKA PARTISI METAL HOLLOW
40 X 40 MM T. 2,00 MM - C
Metal hollow 40 x 40 mm t. 2,00 mm 4.000 m' 14,250.00 57,000.00
Sekrup 0.050 kg 28,500.00 1,425.00
Menie rangka metal hollow 0.640 m2 8,000.00 5,120.00
Pekerja 0.075 hr 45,000.00 3,375.00
Tukang kayu 0.225 hr 35,000.00 7,875.00
Kepala Tukang kayu 0.023 hr 65,000.00 1,495.00
Mandor 0.038 hr 75,000.00 2,850.00
79,140.00
Dibulatkan 79,145.00
Analisa hal.34/56
37 1 M2 PENUTUP PARTISI GYPSUM BOARD 12 MM
Gypsum board 12 mm 1.050 m2 23,500.00 24,675.00
Sekrup 0.110 kg 28,500.00 3,135.00
Pekerja 0.025 hr 45,000.00 1,125.00
Tukang kayu 0.075 hr 35,000.00 2,625.00
Kepala Tukang kayu 0.008 hr 65,000.00 520.00
Mandor 0.001 hr 75,000.00 75.00
32,155.00
Dibulatkan 32,150.00
38 1 M2 PENUTUP PARTISI PLYWOOD 9 MM
Plywood 9 mm 1.050 m2 34,500.00 36,225.00
Sekrup 0.050 kg 28,500.00 1,425.00
Menie 1.000 m2 8,000.00 8,000.00
Pekerja 0.025 hr 45,000.00 1,125.00
Tukang kayu 0.075 hr 35,000.00 2,625.00
Kepala Tukang kayu 0.008 hr 65,000.00 520.00
Mandor 0.001 hr 75,000.00 75.00
49,995.00
Dibulatkan 49,995.00
39 1 M2 PENUTUP PARTISI GRC BOARD 9 MM
GRC Board 9 mm 1.050 m2 26,500.00 27,825.00
Sekrup 0.050 kg 28,500.00 1,425.00
Pekerja 0.025 hr 45,000.00 1,125.00
Tukang kayu 0.075 hr 35,000.00 2,625.00
Kepala Tukang kayu 0.008 hr 65,000.00 520.00
Mandor 0.001 hr 75,000.00 75.00
33,595.00
Dibulatkan 33,590.00
40 1 M2 PELAPIS SUNKAY 4 MM
Sunkay 4 mm 1.050 m2 50,000.00 52,500.00
Lem 0.350 kg 25,000.00 8,750.00
Pekerja 0.025 hr 45,000.00 1,125.00
Tukang kayu 0.075 hr 35,000.00 2,625.00
Kepala Tukang kayu 0.008 hr 65,000.00 520.00
Mandor 0.001 hr 75,000.00 75.00
65,595.00
Dibulatkan 65,590.00
41 1 M2 PELAPIS WALLPAPER
Wallpaper 1.200 m2 50,000.00 60,000.00
Lem 0.200 kg 25,000.00 5,000.00
Pekerja 0.020 hr 45,000.00 900.00
Tukang kayu 0.200 hr 35,000.00 7,000.00
Kepala Tukang kayu 0.002 hr 65,000.00 130.00
Mandor 0.003 hr 75,000.00 225.00
73,255.00
42 1 M2 RANGKA PLAFOND METAL HOLLOW
40 X 40 MM T. 1,20 MM
Metal hollow 40 x 40 mm t. 1,20 mm 4.300 m' 13,000.00 55,900.00
Sekrup 0.050 kg 28,500.00 1,425.00
Menie rangka metal hollow 0.640 m2 8,000.00 5,120.00
Pekerja 0.200 hr 45,000.00 9,000.00
Tukang kayu 0.300 hr 35,000.00 10,500.00
Kepala Tukang kayu 0.030 hr 65,000.00 1,950.00
Mandor 0.010 hr 75,000.00 750.00
84,645.00
43 1 M2 RANGKA PLAFOND KAYU
Kayu meranti 0.012 m3 1,900,000.00 22,800.00
Paku 0.100 kg 8,000.00 800.00
Pekerja 0.150 hr 45,000.00 6,750.00
Tukang kayu 0.250 hr 35,000.00 8,750.00
Kepala Tukang kayu 0.025 hr 65,000.00 1,625.00
Mandor 0.075 hr 75,000.00 5,625.00
Analisa hal.35/56
46,350.00
Analisa hal.36/56
44 1 M2 PLAFOND GYPSUM BOARD 9 MM
Gypsum board 9 mm 1.050 m2 17,250.00 18,112.50
Paku 0.110 kg 12,500.00 1,375.00
Pekerja 0.100 hr 45,000.00 4,500.00
Tukang kayu 0.050 hr 35,000.00 1,750.00
Kepala Tukang kayu 0.005 hr 65,000.00 325.00
Mandor 0.005 hr 75,000.00 375.00
26,437.50
45 1 M2 PLAFOND TRIPLEK 6 MM
Triplek 6 mm 1.050 m2 20,000.00 21,000.00
Paku 0.110 kg 8,000.00 880.00
Pekerja 0.100 hr 45,000.00 4,500.00
Tukang kayu 0.050 hr 35,000.00 1,750.00
Kepala Tukang kayu 0.005 hr 65,000.00 325.00
Mandor 0.005 hr 75,000.00 375.00
28,830.00
46 1 M2 PLAFOND HARPLEK 100 X 100 CM
Harplek 100 x 100 cm 1.100 m2 15,000.00 16,500.00
Paku 0.010 kg 10,000.00 100.00
Pekerja 0.030 hr 45,000.00 1,350.00
Tukang kayu 0.070 hr 35,000.00 2,450.00
Kepala Tukang kayu 0.007 hr 65,000.00 455.00
Mandor 0.002 hr 75,000.00 150.00
21,005.00
47 1 M2 PENUTUP ATAP GENTENG
Penutup atap genteng 25.000 m2 2,250.00 56,250.00
Pekerja 0.150 hr 45,000.00 6,750.00
Tukang kayu 0.075 hr 35,000.00 2,625.00
Kepala Tukang kayu 0.008 hr 65,000.00 520.00
Mandor 0.008 hr 75,000.00 600.00
66,745.00
48 1 M2 PENUTUP ATAP ASBES GELOMBANG
Penutup atap asbes gelombang 1.000 m2 30,000.00 30,000.00
Paku pancing 0.120 kg 12,500.00 1,500.00
Pekerja 0.140 hr 45,000.00 6,300.00
Tukang kayu 0.075 hr 35,000.00 2,625.00
Kepala Tukang kayu 0.008 hr 65,000.00 520.00
Mandor 0.008 hr 75,000.00 600.00
41,545.00
48 1 M2 PASANG USUK BENGKIRAI +
RENG KAYU BENGKIRAI
Usuk kayu bengkirai 0.008 m3 2,650,000.00 21,200.00
Reng kayu bengkirai 0.004 m3 2,400,000.00 9,600.00
Paku 0.150 kg 8,000.00 1,200.00
Pekerja 0.150 hr 45,000.00 6,750.00
Tukang kayu 0.100 hr 35,000.00 3,500.00
Kepala Tukang kayu 0.010 hr 65,000.00 650.00
Mandor 0.005 hr 75,000.00 375.00
43,275.00
49 1 M3 KUDA - KUDA KAYU BENGKIRAI
Kayu bengkirai 1.100 m3 3,700,000.00 4,070,000.00
Baut / alat sambung 15.800 kg 9,405.00 148,599.00
Pekerja 4.000 hr 45,000.00 180,000.00
Tukang kayu 12.000 hr 35,000.00 420,000.00
Kepala Tukang kayu 1.200 hr 65,000.00 78,000.00
Mandor 0.200 hr 75,000.00 15,000.00
4,911,599.00
50 1 M3 NOK / GORDING KAYU BENGKIRAI
Kayu bengkirai 1.100 m3 3,700,000.00 4,070,000.00
Pekerja 4.000 hr 45,000.00 180,000.00
Tukang kayu 12.000 hr 35,000.00 420,000.00
Kepala Tukang kayu 1.200 hr 65,000.00 78,000.00
Analisa hal.37/56
Mandor 0.200 hr 75,000.00 15,000.00
4,763,000.00
Analisa hal.38/56
51 1 M' PAPAN KOMPRES 3 / 15 CM KAMPER
Papan kayu kamper 3 / 15 cm 0.006 m3 4,500,000.00 27,000.00
Paku 0.050 kg 8,000.00 400.00
Pekerja 0.110 hr 45,000.00 4,950.00
Tukang kayu 0.220 hr 35,000.00 7,700.00
Kepala Tukang kayu 0.022 hr 65,000.00 1,430.00
Mandor 0.005 hr 75,000.00 375.00
41,855.00
52 1 M' PAPAN LISTPLANK 3 / 20 CM KAMPER
Papan kayu kamper 3 / 20 cm 0.008 m3 4,500,000.00 36,000.00
Paku 0.050 kg 8,000.00 400.00
Pekerja 0.110 hr 45,000.00 4,950.00
Tukang kayu 0.220 hr 35,000.00 7,700.00
Kepala Tukang kayu 0.022 hr 65,000.00 1,430.00
Mandor 0.005 hr 75,000.00 375.00
50,855.00
53 1 M' PAPAN LISTPLANK 3 / 25 CM KAMPER
Papan kayu kamper 3 / 25 cm 0.009 m3 4,500,000.00 40,500.00
Paku 0.050 kg 8,000.00 400.00
Pekerja 0.110 hr 45,000.00 4,950.00
Tukang kayu 0.220 hr 35,000.00 7,700.00
Kepala Tukang kayu 0.022 hr 65,000.00 1,430.00
Mandor 0.005 hr 75,000.00 375.00
55,355.00
54 1 KG BESI WF
Besi WF 1.100 kg 9,000.00 9,900.00
Menie besi 0.080 kg 10,000.00 800.00
Pekerja 0.006 hr 45,000.00 270.00
Tukang besi 0.060 hr 35,000.00 2,100.00
Kepala Tukang besi 0.006 hr 65,000.00 390.00
Mandor 0.001 hr 75,000.00 75.00
13,535.00
55 1 KG BESI CANAL
Besi Canal 1.100 kg 9,150.00 10,065.00
Menie besi 0.080 kg 10,000.00 800.00
Pekerja 0.006 hr 45,000.00 270.00
Tukang besi 0.060 hr 35,000.00 2,100.00
Kepala Tukang besi 0.006 hr 65,000.00 390.00
Mandor 0.001 hr 75,000.00 75.00
13,700.00
56 1 KG BESI SIKU
Besi Siku 1.100 kg 9,000.00 9,900.00
Menie besi 0.080 kg 10,000.00 800.00
Pekerja 0.006 hr 45,000.00 270.00
Tukang besi 0.060 hr 35,000.00 2,100.00
Kepala Tukang besi 0.006 hr 65,000.00 390.00
Mandor 0.001 hr 75,000.00 75.00
13,535.00
57 1 KG BESI PLAT
Besi Plat 1.100 kg 9,000.00 9,900.00
Menie besi 0.080 kg 10,000.00 800.00
Pekerja 0.006 hr 45,000.00 270.00
Tukang besi 0.060 hr 35,000.00 2,100.00
Kepala Tukang besi 0.006 hr 65,000.00 390.00
Mandor 0.001 hr 75,000.00 75.00
13,535.00
58 1M3 PONDASI POER TYPE - 1
Bekesting 3.500 m2 40,682.50 142,388.75
Besi beton ulir 200.192 kg 9,770.00 1,955,875.84
Beton K 225 1.000 m3 981,270.00 981,270.00
3,079,534.59
Dibulatkan 3,079,530.00
Analisa hal.39/56
59 1M3 PONDASI POER TYPE - 2
Bekesting 1.600 m2 40,682.50 65,092.00
Besi beton ulir 125.629 kg 9,770.00 1,227,395.33
Beton K 225 1.000 m3 981,270.00 981,270.00
2,273,757.33
Dibulatkan 2,273,750.00
60 1M3 PONDASI POER TYPE - 3
Bekesting 2.500 m2 40,682.50 101,706.25
Besi beton ulir 330.369 kg 9,770.00 3,227,705.13
Beton K 225 1.000 m3 981,270.00 981,270.00
4,310,681.38
Dibulatkan 4,310,680.00
61 1M3 PONDASI POER TYPE - 4
Bekesting 1.600 m2 40,682.50 65,092.00
Besi beton ulir 125.629 kg 9,770.00 1,227,395.33
Beton K 225 1.000 m3 981,270.00 981,270.00
2,273,757.33
Dibulatkan 2,273,750.00
61 1M3 BETON COR PADA LUBANG
TIANG PANCANG O 40 CM
Besi beton polos 19.867 kg 9,405.00 186,849.14
Besi beton ulir 252.436 kg 9,770.00 2,466,299.72
Beton K 225 1.000 m3 981,270.00 981,270.00
3,634,418.86
Dibulatkan 3,634,420.00
62 1M3 SLOOF 15 / 20 CM
Bekesting 13.332 m2 44,057.50 587,374.59
Besi beton polos 146.149 kg 9,405.00 1,374,531.35
Cor beton 1 PC : 2 PS : 3 KR 1.000 m3 771,965.00 771,965.00
2,733,870.94
Dibulatkan 2,733,870.00
63 1M3 SLOOF 20 / 30 CM
Bekesting 9.996 m2 44,057.50 440,398.77
Besi beton polos 179.071 kg 9,405.00 1,684,162.76
Beton K 225 1.000 m3 981,270.00 981,270.00
3,105,831.53
Dibulatkan 3,105,830.00
64 1M3 SLOOF 30 / 30 CM
Bekesting 6.666 m2 44,057.50 293,687.30
Besi beton polos 31.106 kg 9,405.00 292,551.93
Besi beton ulir 198.202 kg 9,770.00 1,936,433.54
Beton K 225 1.000 m3 981,270.00 981,270.00
3,503,942.77
Dibulatkan 3,503,945.00
65 1M3 SLOOF 30 / 55 CM
Bekesting 6.666 m2 44,057.50 293,687.30
Besi beton polos 56.687 kg 9,405.00 533,141.24
Besi beton ulir 144.228 kg 9,770.00 1,409,107.56
Beton K 225 1.000 m3 981,270.00 981,270.00
3,217,206.09
Dibulatkan 3,217,200.00
66 1M3 SLOOF 35 / 65 CM
Bekesting 5.720 m2 44,057.50 252,008.90
Besi beton polos 49.506 kg 9,405.00 465,603.93
Besi beton ulir 104.720 kg 9,770.00 1,023,114.40
Beton K 225 1.000 m3 981,270.00 981,270.00
2,721,997.23
Dibulatkan 2,721,990.00
Analisa hal.40/56
67 1M3 STEKAN SLOOF 30 / 55 CM DICOR LUNAK
Bekesting 6.666 m2 44,057.50 293,687.30
Besi beton polos 56.687 kg 9,405.00 533,141.24
Besi beton ulir 144.228 kg 9,770.00 1,409,107.56
Cor beton 1 PC : 3 PS : 5 KR 1.000 m3 565,885.00 565,885.00
2,801,821.09
Dibulatkan 2,801,830.00
68 1M3 KOLOM 12 / 15 CM
Bekesting 16.665 m2 44,057.50 734,218.24
Besi beton polos 174.160 kg 9,405.00 1,637,974.80
Cor beton 1 PC : 2 PS : 3 KR 1.000 m3 771,965.00 771,965.00
3,144,158.04
Dibulatkan 3,144,150.00
69 1M3 KOLOM 20 / 20 CM - A
Bekesting 20.000 m2 59,597.50 1,191,950.00
Besi beton polos 24.098 kg 9,405.00 226,641.69
Besi beton ulir 237.000 kg 9,770.00 2,315,490.00
Beton K 225 1.000 m3 981,270.00 981,270.00
4,715,351.69
Dibulatkan 4,715,355.00
70 1M3 KOLOM 20 / 20 CM - B
Bekesting 20.000 m2 59,597.50 1,191,950.00
Besi beton polos 24.098 kg 9,405.00 226,641.69
Besi beton ulir 316.000 kg 9,770.00 3,087,320.00
Beton K 225 1.000 m3 981,270.00 981,270.00
5,487,181.69
Dibulatkan 5,487,190.00
71 1M3 KOLOM 40 / 40 CM - A
Bekesting 10.000 m2 59,597.50 595,975.00
Besi beton polos 56.363 kg 9,405.00 530,094.02
Besi beton ulir 118.500 kg 9,770.00 1,157,745.00
Beton K 225 1.000 m3 981,270.00 981,270.00
3,265,084.02
Dibulatkan 3,265,080.00
72 1M3 KOLOM 40 / 40 CM - B
Bekesting 10.000 m2 59,597.50 595,975.00
Besi beton polos 56.363 kg 9,405.00 530,094.02
Besi beton ulir 158.000 kg 9,770.00 1,543,660.00
Beton K 225 1.000 m3 981,270.00 981,270.00
3,650,999.02
Dibulatkan 3,650,990.00
73 1M3 KOLOM 40 / 40 CM - C
Bekesting 10.000 m2 59,597.50 595,975.00
Besi beton polos 56.363 kg 9,405.00 530,094.02
Besi beton ulir 167.250 kg 9,770.00 1,634,032.50
Beton K 225 1.000 m3 981,270.00 981,270.00
3,741,371.52
Dibulatkan 3,741,370.00
74 1M3 KOLOM 50 / 50 CM - A
Bekesting 8.000 m2 59,597.50 476,780.00
Besi beton polos 46.799 kg 9,405.00 440,144.60
Besi beton ulir 107.040 kg 9,770.00 1,045,780.80
Beton K 225 1.000 m3 981,270.00 981,270.00
2,943,975.40
Dibulatkan 2,943,970.00
75 1M3 KOLOM 50 / 50 CM - B
Bekesting 8.000 m2 59,597.50 476,780.00
Besi beton polos 46.799 kg 9,405.00 440,144.60
Besi beton ulir 142.720 kg 9,770.00 1,394,374.40
Beton K 225 1.000 m3 981,270.00 981,270.00
3,292,569.00
Dibulatkan 3,292,560.00
Analisa hal.41/56
76 1M3 BALOK PORTAL 30 / 60 CM - A
Bekesting 7.659 m2 60,047.50 459,903.80
Besi beton polos 51.921 kg 9,405.00 488,317.01
Besi beton ulir 112.943 kg 9,770.00 1,103,453.11
Beton K 225 1.000 m3 981,270.00 981,270.00
3,032,943.92
Dibulatkan 3,032,940.00
77 1M3 BALOK PORTAL 30 / 60 CM - B
Bekesting 6.993 m2 60,047.50 419,912.17
Besi beton polos 81.444 kg 9,405.00 765,980.82
Besi beton ulir 147.519 kg 9,770.00 1,441,260.63
Beton K 225 1.000 m3 981,270.00 981,270.00
3,608,423.62
Dibulatkan 3,608,425.00
78 1M3 BALOK PORTAL 30 / 60 CM - C
Bekesting 6.993 m2 60,047.50 419,912.17
Besi beton polos 81.444 kg 9,405.00 765,980.82
Besi beton ulir 171.162 kg 9,770.00 1,672,252.74
Beton K 225 1.000 m3 981,270.00 981,270.00
3,839,415.73
Dibulatkan 3,839,420.00
79 1M3 BALOK PORTAL 30 / 70 CM
Bekesting 6.997 m2 60,047.50 420,152.36
Besi beton polos 72.609 kg 9,405.00 682,887.65
Besi beton ulir 115.906 kg 9,770.00 1,132,401.62
Beton K 225 1.000 m3 981,270.00 981,270.00
3,216,711.62
Dibulatkan 3,216,710.00
80 1M3 BALOK PORTAL 35 / 70 CM - A
Bekesting 6.161 m2 60,047.50 369,952.65
Besi beton polos 71.315 kg 9,405.00 670,717.58
Besi beton ulir 158.794 kg 9,770.00 1,551,417.38
Beton K 225 1.000 m3 981,270.00 981,270.00
3,573,357.60
Dibulatkan 3,573,350.00
81 1M3 BALOK PORTAL 35 / 70 CM - B
Bekesting 6.161 m2 60,047.50 369,952.65
Besi beton polos 80.012 kg 9,405.00 752,512.86
Besi beton ulir 177.031 kg 9,770.00 1,729,592.87
Beton K 225 1.000 m3 981,270.00 981,270.00
3,833,328.38
Dibulatkan 3,833,320.00
82 1M3 BALOK 15 / 20 CM
Bekesting 10.332 m2 60,047.50 620,410.77
Besi beton polos 146.149 kg 9,405.00 1,374,531.35
Beton K 225 1.000 m3 981,270.00 981,270.00
2,976,212.12
2,976,210.00
83 1M3 BALOK 20 / 25 CM
Bekesting 11.600 m2 60,047.50 696,551.00
Besi beton polos 93.013 kg 9,405.00 874,787.27
Besi beton ulir 158.000 kg 9,770.00 1,543,660.00
Beton K 225 1.000 m3 981,270.00 981,270.00
4,096,268.27
Dibulatkan 4,096,270.00
84 1M3 BALOK 25 / 55 CM - A
Bekesting 8.070 m2 60,047.50 484,583.33
Besi beton polos 65.309 kg 9,405.00 614,231.15
Besi beton ulir 103.379 kg 9,770.00 1,010,012.83
Beton K 225 1.000 m3 981,270.00 981,270.00
3,090,097.30
Dibulatkan 3,090,090.00
Analisa hal.42/56
85 1M3 BALOK 25 / 55 CM - B
Bekesting 8.070 m2 60,047.50 484,583.33
Besi beton polos 65.309 kg 9,405.00 614,231.15
Besi beton ulir 137.839 kg 9,770.00 1,346,687.03
Beton K 225 1.000 m3 981,270.00 981,270.00
3,426,771.50
Dibulatkan 3,426,780.00
86 1M3 BALOK 25 / 55 CM - C
Bekesting 8.070 m2 60,047.50 484,583.33
Besi beton polos 43.838 kg 9,405.00 412,296.39
Besi beton ulir 261.284 kg 9,770.00 2,552,744.68
Beton K 225 1.000 m3 981,270.00 981,270.00
4,430,894.40
Dibulatkan 4,430,890.00
87 1M3 BALOK 30 / 60 CM
Bekesting 6.993 m2 60,047.50 419,912.17
Besi beton polos 45.812 kg 9,405.00 430,861.86
Besi beton ulir 128.927 kg 9,770.00 1,259,616.79
Beton K 225 1.000 m3 981,270.00 981,270.00
3,091,660.82
Dibulatkan 3,091,660.00
88 1M3 BALOK KONSOL 25 / 30 CM
Bekesting 8.131 m2 60,047.50 488,246.22
Besi beton polos 50.284 kg 9,405.00 472,921.02
Besi beton ulir 148.630 kg 9,770.00 1,452,115.10
Beton K 225 1.000 m3 981,270.00 981,270.00
3,394,552.34
Dibulatkan 3,394,550.00
89 1M3 PLAT LEUFEL T. 12 CM
Bekesting 8.333 m2 60,047.50 500,375.82
Besi beton polos 45.161 kg 9,405.00 424,739.21
Beton K 225 1.000 m3 981,270.00 981,270.00
1,906,385.02
Dibulatkan 1,906,390.00
90 1M3 PLAT LISTPLANK T. 8 CM
Bekesting 26.000 m2 60,047.50 1,561,235.00
Besi beton polos 104.083 kg 9,405.00 978,900.62
Beton K 225 1.000 m3 981,270.00 981,270.00
3,521,405.62
Dibulatkan 3,521,400.00
91 1M3 BALOK KONSOL 24 / 45 CM
Bekesting 8.325 m2 60,047.50 499,895.44
Besi beton polos 45.919 kg 9,405.00 431,868.20
Besi beton ulir 173.623 kg 9,770.00 1,696,296.71
Beton K 225 1.000 m3 981,270.00 981,270.00
3,609,330.34
Dibulatkan 3,609,340.00
92 1M3 BALOK TALANG 20 / 40 CM
Bekesting 12.500 m2 60,047.50 750,593.75
Besi beton polos 74.559 kg 9,405.00 701,227.40
Besi beton ulir 98.750 kg 9,770.00 964,787.50
Beton K 225 1.000 m3 981,270.00 981,270.00
3,397,878.65
Dibulatkan 3,397,870.00
93 1M3 PLAT TALANG T. 12 CM
Bekesting 8.333 m2 60,047.50 500,375.82
Besi beton polos 101.351 kg 9,405.00 953,206.16
Beton K 225 1.000 m3 981,270.00 981,270.00
2,434,851.97
Dibulatkan 2,434,850.00
Analisa hal.43/56
94 1M3 PLAT LISTPLANK T. 8 CM
Bekesting 26.000 m2 60,047.50 1,561,235.00
Besi beton polos 105.816 kg 9,405.00 995,199.48
Beton K 225 1.000 m3 981,270.00 981,270.00
3,537,704.48
Dibulatkan 3,537,700.00
95 1M3 PLAT LANTAI T. 12 CM
Bekesting 8.333 m2 60,047.50 500,375.82
Besi beton polos 100.196 kg 9,405.00 942,343.38
Beton K 225 1.000 m3 981,270.00 981,270.00
2,423,989.20
Dibulatkan 2,423,980.00
96 1M3 BALOK BORDES+ BALOK TANGGA 26 / 45 CM
Bekesting 7.353 m2 60,047.50 441,529.27
Besi beton polos 66.328 kg 9,405.00 623,814.84
Besi beton ulir 121.581 kg 9,770.00 1,187,846.37
Beton K 225 1.000 m3 981,270.00 981,270.00
3,234,460.48
Dibulatkan 3,234,460.00
97 1M3 PLAT TANGGA + PLAT BORDES
Bekesting 6.666 m2 53,297.50 355,281.14
Besi beton polos 271.154 kg 9,405.00 2,550,203.37
Beton K 225 1.000 m3 981,270.00 981,270.00
3,886,754.51
Dibulatkan 3,886,755.00
98 1M3 PLAT SIRIP BETON T. 8 CM
Bekesting 26.000 m2 60,047.50 1,561,235.00
Besi beton polos 124.017 kg 9,405.00 1,166,379.89
Beton K 225 1.000 m3 981,270.00 981,270.00
3,708,884.89
Dibulatkan 3,708,880.00
99 1M3 BALOK TANDON 20 / 30 CM
Bekesting 9.330 m2 60,047.50 560,243.18
Besi beton polos 37.604 kg 9,405.00 353,665.62
Besi beton ulir 184.370 kg 9,770.00 1,801,294.90
Beton K 225 1.000 m3 981,270.00 981,270.00
3,696,473.70
Dibulatkan 3,696,470.00
100 1M3 BALOK TANDON 20 / 40 CM
Bekesting 11.000 m2 60,047.50 660,522.50
Besi beton polos 34.839 kg 9,405.00 327,660.80
Besi beton ulir 138.250 kg 9,770.00 1,350,702.50
Beton K 225 1.000 m3 981,270.00 981,270.00
3,320,155.80
Dibulatkan 3,320,160.00
101 1M3 PLAT TANDON T. 12 CM
Bekesting 8.333 m2 60,047.50 500,375.82
Besi beton polos 108.384 kg 9,405.00 1,019,351.52
Beton K 225 1.000 m3 981,270.00 981,270.00
2,500,997.34
Dibulatkan 2,501,000.00
102 1M3 KOLOM GEWEL 12 / 20 CM
Bekesting 16.664 m2 44,057.50 734,174.18
Besi beton polos 136.761 kg 9,405.00 1,286,237.21
Cor beton 1 PC : 2 PS : 3 KR 1.000 m3 771,965.00 771,965.00
2,792,376.39
Dibulatkan 2,792,380.00
103 1M3 KOLOM GEWEL 20 / 20 CM
Bekesting 10.000 m2 59,597.50 595,975.00
Besi beton polos 131.138 kg 9,405.00 1,233,352.89
Beton K 225 1.000 m3 981,270.00 981,270.00
2,810,597.89
Analisa hal.44/56
Dibulatkan 2,810,595.00
Analisa hal.45/56
104 1M3 RING GEWEL 12 / 20 CM
Bekesting 16.664 m2 44,057.50 734,174.18
Besi beton polos 136.761 kg 9,405.00 1,286,237.21
Cor beton 1 PC : 2 PS : 3 KR 1.000 m3 771,965.00 771,965.00
2,792,376.39
Dibulatkan 2,792,380.00
105 1M3 RING GEWEL 15 / 30 CM
Bekesting 13.332 m2 59,597.50 794,553.87
Besi beton polos 104.090 kg 9,405.00 978,966.45
Beton K 225 1.000 m3 981,270.00 981,270.00
2,754,790.32
Dibulatkan 2,754,790.00
106 1M3 RING BALK 20 / 40 CM
Bekesting 12.500 m2 60,047.50 750,593.75
Besi beton polos 74.559 kg 9,405.00 701,227.40
Besi beton ulir 118.500 kg 9,770.00 1,157,745.00
Beton K 225 1.000 m3 981,270.00 981,270.00
3,590,836.15
Dibulatkan 3,590,830.00
107 1M3 RING BALK 30 / 50 CM
Bekesting 8.658 m2 60,047.50 519,891.26
Besi beton polos 40.259 kg 9,405.00 378,635.90
Besi beton ulir 84.182 kg 9,770.00 822,458.14
Beton K 225 1.000 m3 981,270.00 981,270.00
2,702,255.29
Dibulatkan 2,702,250.00
108 1M3 KONSOL BETON PEMIKUL KUDA - KUDA
Bekesting 7.500 m2 59,597.50 446,981.25
Besi beton polos 56.363 kg 9,405.00 530,094.02
Besi beton ulir 118.500 kg 9,770.00 1,157,745.00
Beton K 225 1.000 m3 981,270.00 981,270.00
3,116,090.27
Dibulatkan 3,116,090.00
109 1M3 PLAT BETON BAWAH GROUND TANK T. 20 CM
Bekesting 2.400 m2 40,682.50 97,638.00
Besi beton ulir 260.312 kg 9,770.00 2,543,248.24
Beton K 225 1.000 m3 981,270.00 981,270.00
3,622,156.24
Dibulatkan 3,622,150.00
110 1M3 PLAT BETON DINDING GROUND TANK T. 15 CM
Bekesting 13.332 m2 59,597.50 794,553.87
Besi beton ulir 325.333 kg 9,770.00 3,178,503.41
Beton K 225 1.000 m3 981,270.00 981,270.00
4,954,327.28
Dibulatkan 4,954,320.00
111 1M3 PLAT BETON PENUTUP GROUND TANK T. 10 CM
Bekesting 10.000 m2 60,047.50 600,475.00
Besi beton polos 274.194 kg 9,405.00 2,578,794.57
Beton K 225 1.000 m3 981,270.00 981,270.00
4,160,539.57
Dibulatkan 4,160,530.00
112 1M3 PLAT BETON DINDING MANHOLE T. 12 CM
Bekesting 20.000 m2 59,597.50 1,191,950.00
Besi beton polos 96.784 kg 9,405.00 910,253.52
Beton K 225 1.000 m3 981,270.00 981,270.00
3,083,473.52
Dibulatkan 3,083,470.00
113 1M3 PLAT RAILLING TANGGA T. 7 CM
Bekesting 28.590 m2 60,047.50 1,716,758.03
Besi beton polos 62.307 kg 9,405.00 585,997.34
Beton K 225 1.000 m3 981,270.00 981,270.00
3,284,025.36
Analisa hal.46/56
Dibulatkan 3,284,025.00
Analisa hal.47/56
HARGA SATUAN UPAH
Kegiatan : REHAB BERAT KANTOR DPRD KOTA SAMARINDA
Pekerjaan : REHAB BERAT GEDUNG DPRD KOTA SAMARINDA
Lokasi : KOTA SAMARINDA
Tahun Anggaran : 2009
1 Mandor 75,000.00 hr
2 Kepala Tukang batu 65,000.00 hr
3 Kepala Tukang besi 65,000.00 hr
4 Kepala Tukang cat 65,000.00 hr
5 Kepala Tukang kayu 65,000.00 hr
6 Besi beton ulir hr
7 Tukang besi 55,000.00 hr
8 Tukang cat 55,000.00 hr
9 Tukang kayu 55,000.00 hr
10 Pekerja 45,000.00 hr
Direktur
ember 2009
HARGA SATUAN BAHAN
Kegiatan : REHAB BERAT KANTOR DPRD KOTA SAMARINDA
Pekerjaan : REHAB BERAT GEDUNG DPRD KOTA SAMARINDA
Lokasi : KOTA SAMARINDA
Tahun Anggaran : 2009
Direktur
Keterangan
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 87815.6
0 95257.6
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
ember 2009
PRAKIRAAN DAFTAR HARGA SATUAN UPAH, BAHAN DAN PERALATAN
PROYEK
LOKASI - WILAYAH KALTIM
PERIODE UP DATE :
2. Material
1 Beton K225 m3 860,000.00
2 PC @ 50 kg/zak zak 52,000.00
3 Pasir Pasang m3 85,000.00
4 Pasir Cor m3 225,000.00
5 Batu bata m3 500.00
6 Batu kali/batu gunung m3 180,000.00
7 Batu Pecah /Split 2 - 3 Cm m3 247,000.00
8 Batu Pecah /Split 1-2 Cm m3 247,000.00
9 Batu Pecah /Split 0,5 -1 Cm m3 250,000.00
10 Besi beton U24 kg 7,000.00
11 Besi beton Ulir kg 7,000.00
12 Profil baja kg 13,500.00
13 Waterstop, lebar 25 cm m 125,000.00
PRAKIRAAN DAFTAR HARGA SATUAN UPAH, BAHAN DAN PERALATAN
PROYEK
LOKASI - WILAYAH KALTIM
PERIODE UP DATE :
3. Equipment
1 Excavator PC 200 (standar) hours 444,920.00
2 Dump Truck 4 ton (kap. 5 m3 ) hours 174,990.00
3 Vibrator roller kap. 10 ton hours 247,390.00
4 Buldozzer D65 hours 495,120.00
5 Baby roller hours 120,950.00
6 Truck tanki air hours 174,990.00
7 Concrete Mixer hours 41,000.00
8 Concrete Vibrator hours 15,000.00
9 Concrete Pump hours 180,000.00
10 Crane hours 350,000.00
11 Service crane hours 300,000.00
12 Pile Hammer hours 15,000.00
13 Bar Cutter (GUNTING BESI) hours 15,000.00
14 Bar Bender (MEJA BENGKOK) hours 15,000.00
15 Alat Bantu hours 500.00
16 Mesin Las hours 35,000.00
17 Stamper hours 35,000.00
18 Theodolith hours 6,250.00
19 Waterpass hours 6,250.00