TUGAS EKOTEK

L= 60 (km)
Q= 2385 (L/det) catatan: 45 dikali dgn dua nim terakhir
∆elevasi= -10 (m)
∆p= 20 (m)
harga listrik Rp 2,500.00 (per kwh)
tahun= 18.00

V Diameter Head Power Investasi Biaya Pemeliharaan TOTAL NPV


Total investasi
(m/det) (mm) Hl (mka) 3 Pompa(m) Pompa(Kw) Pipa Pompa 8 Biaya Operasi Pompa TOTAL OP r=18.00% r=20.00% r=25.00%
4 5 6 7 Pipa Pompa
1 2 fNPV=19.27 fNPV=19.48 fNPV=19.77
0.6 2250.27 4.19 14.19 338.48 Rp 652,684,960,049 Rp 1,084,959,627 Rp 653,769,919,675 Rp 2,965,104,377 Rp 6,526,849,600 Rp 108,495,963 Rp 9,600,449,940 Rp 838,769,508,915 Rp 840,770,545,522 Rp 843,565,205,444
1 1743.05 14.53 24.53 584.94 Rp 377,584,514,084 Rp 1,680,632,190 Rp 379,265,146,274 Rp 5,124,055,922 Rp 3,775,845,141 Rp 168,063,219 Rp 9,067,964,282 Rp 554,003,796,838 Rp 555,893,846,637 Rp 558,533,501,706
1.2 1591.18 22.63 32.63 778.33 Rp 310,360,851,942 Rp 2,112,097,553 Rp 312,472,949,496 Rp 6,818,133,191 Rp 3,103,608,519 Rp 211,209,755 Rp 10,132,951,465 Rp 507,733,783,158 Rp 509,845,809,879 Rp 512,795,479,272
1.5 1423.19 38.95 48.95 1167.49 Rp 244,354,657,245 Rp 2,921,377,207 Rp 247,276,034,452 Rp 10,227,219,090 Rp 2,443,546,572 Rp 292,137,721 Rp 12,962,903,383 Rp 497,069,722,881 Rp 499,771,600,851 Rp 503,545,060,093
2 1232.52 78.43 88.43 2108.99 Rp 180,094,739,350 Rp 4,688,619,601 Rp 184,783,358,951 Rp 18,474,779,447 Rp 1,800,947,394 Rp 468,861,960 Rp 20,744,588,801 Rp 584,529,249,084 Rp 588,853,075,763 Rp 594,891,758,458
159 169 4,024 Rp7,861,964,562 Rp35,252,252,026 Rp786,196,456

BIAYA INVESTASI Rp900,000,000,000

Rp800,000,000,000
POMPA
Rp700,000,000,000
Cost (Rp)= 10.275.072 x POWER(Kw)0,8 Rp600,000,000,000

Power (Kw) = 0,01 x Q (l/det) x Head (m) Rp500,000,000,000 r=10%


r=12%
Rp400,000,000,000
Head = ∆El (selisih elevasi,m) + Hl +∆p (sisa tekan, mka) r=15%
Rp300,000,000,000
Hl(mka)=((Q(m3/det)/(0,2785 x 120 x d(m)2,63))1,85) x L(m) Rp200,000,000,000

PIPA Rp100,000,000,000

Rp-
Cost (Rp)=1.639.341x LEN(m)0,73 x DIAM(mm)0,91 x (DIAM(mm)/(1000 + DIAM(mm))) 1000.00 1200.00 1400.00 1600.00 1800.00 2000.00 2200.00 2400.00

KESIMPULAN
BIAYA OPERASIONAL
Diameter pipa yang optimum adal 2250.27mm. Karena investasi yang dihasilkan memuaskan
Cost Pompa(Rp/year) = Power (kw) x 24(hours/day) x 365(days/year) x
Rp.1000/kwh

BIAYA PEMELIHARAAN
Pompa (Rp/year)= 10% dari investasi

Pipa(Rp/year) = 1% dari investasi

V(kecepatan aliran dalam pipa, m/det)

Q <= 1000 l/det, V=1-2,5 m/det

Q=1000-2000 l/det; V=0,8-2,2 m/det

Q>2000 l/det, V=0,6-2 m/det