NAMA MAHASISWA : RAJA DOA RIDHA S, ST

NIM : 2004201010029
MATA KULIAH : MANAJEMEN INFRASTRUKTUR SUMBER DAYA AIR
DOSEN PEMBIMBING : DR. IR. ALFIANSYAH YULIANUR BC
BIDANG : REKAYASA DAN MANAJEMEN INFRASTRUKTUR

1. Perkiraan banjir rencana periode yang optimum jika nilai kerusakan dan nilai bangunan contoh soal 2 di atas, masing-masing meningkat dua
kali lipat.

Incremental
Return Annual Damage Risk Capital
Increment Damage Expected Total Cost
Period Exceedence Cost Cost
damage
i T(Years) $ Δdi ($/year) ($/year) ($/year) ($/year)
1 2 3 4 5 6 7 8

1 1.000 0 98,197 98,197


1 2 0.500 40,000 10,000 88,197 6,000 94,197
2 5 0.200 120,000 24,000 64,197 28,000 92,197
3 10 0.100 280,000 20,000 44,197 46,000 90,197
4 15 0.067 354,000 10,461 33,736 50,000 83,736
5 20 0.050 426,000 6,630 27,106 54,000 81,106
6 25 0.040 500,000 4,630 22,476 58,000 80,476
7 50 0.020 600,000 11,000 11,476 80,000 91,476
8 100 0.010 800,000 7,000 4,476 120,000 124,476
9 200 0.005 1,000,000 4,500 - 24 160,000 159,976
Annual Expected Damage = $ 98.187

Maka dari hasil penjumlahan tersebut dapat dilihat bahwa ternyata periode ulang T = 25 tahun memiliki biaya total yang minimal.
Berarti perode ulang rencana diambil T = 25 tahun.