RENCANA ANGGARAN BIAYA

(RAB)

KEGIATAN : Pembangunan Ruang Terbuka Hijau


LOKASI : Desa Poncol Kec. Poncol Kab. Magetan
VOLUME : 1 Paket

NO URAIAN VOLUME SATUAN HARGA SATUAN JUMLAH (Rp)


(Rp)
A KEBUTUHAN BAHAN
1 Pasir pasang 35 m3 240,200 8,407,000
2 Pasir Urug 5 m3 177,650 888,250
3 batu gebal 6 m3 210,000 1,260,000
4 batu bata 4,500 bj 750 3,375,000
5 Semen Potland 4,500 Kg 1,700 7,650,000
6 Besi 10" 30 ljr 92,000 2,760,000
7 Besi 6" 15 ljr 33,000 495,000
8 Besi blendrat 5 Kg 17,950 89,750
9 Ornamen aneka bunga 38 m3 250,000 9,500,000
10 papan nama huruf timbul 1 paket 15,000,000 15,000,000
11 belanja bunga 1 paket 10,000,000 10,000,000
12 gasebo 4 bj 5,200,000 20,800,000
13 keramik lantai 35 m 80,000 2,800,000
14 Keramik lantai Kasar 167 m 90,000 15,030,000
15 Paket air mancur 1 paket 9,750,000 9,750,000
16 Perpipaan 10 ptg 90,000 900,000
JUMLAH A 108,705,000
B PERALATAN KERJA
1 Skrop 2 bh 70,000 140,000
2 benang 10 bh 5,000 50,000
3 Paku 2 kg 17,500 35,000
4 timba 6 bh 10,000 60,000
5 Kereta sorong 1 1 450,000 450,000
JUMLAH B 735,000
C KEBUTUHAN TENAGA
1 Upah Tukang 252 OH 80,000 20,160,000
2 Upah Pekerja 340 OH 60,000 20,400,000
JUMLAH B 40,560,000
JUMLAH A+B+C 150,000,000
DIBULATKAN 150,000,000
Poncol, 20 Februari 2020
Kepala Desa Poncol
SAMSUHARI