NO. 1
JENIS PEKERJAAN
NO. 2
I. PEKERJAAN PENDAHULUAN
1. PEKERJAAN PEMBERSIHAN
TANAH
Panjang = 12 m
Lebar = 6 m
Volume = p x l
= 12 x 6
= 72 m²
Panjang = 12 m
Lebar = 6 m
Volume = 2(p + l)
= 2(12+6)
= 36 m²
3. PEKERJAAN BOWPLANK
1A - 1C 12 A1 - A3 6
2A - 2B 4 B1- B3 6
3A - 3C 12 C1 - C3 6
JUMLAH 28 JUMLAH 18
AS L Volume Galian
(m) Pondasi
A (m²) Vol (m³)
1A - 1C 12 0,420 5,040
2A- 2B 4 0,420 1,680
3A - 3C 12 0,420 5,040
A1 - A3 6 0,420 2,520
B1- B3 6 0,420 2,520
C1 - C3 6 0,420 2,520
Jumlah 46 19,320
Volume Pondasi
AxL 5,520 m³
NO. 3
1. PEKERJAAN SLOOF
1.1 PEMBESIAN SLOOF
Tulangan Utama 4Ø10
panjang Jumlah
Sloof d (mm) (m) tekukan (mm) (btg) berat (kg)
ls 10 66,040 0 0 23 165,6
Ø8-
Tulangan Sengkang 150
ukuran kait panjan Jumlah Jumlah
cm cm d (mm) (cm) g (cm) begel (btg) berat (kg)
15 20 8 4,8 71,6 441 27 127,98
Jumlah = 293,58
Kawat (10%) = 29,358
322,93
=
Total Volume (kg) 8