JADWAL PELAKSANAAN PENAMBAHAN TITIK

PEMASANGAN PENERANGAN JALAN UMUM (MENGGUNAKAN PV) WILAYAH BAGIAN TENGAH I

23-Oct-20 30-Oct-20 06-Nov-20 13-Nov-20 20-Nov-20 27-Nov-20 04-Dec-20 11-Dec-20 18-Dec-20 25-Dec-20 01-Jan-21 08-Jan-21 15-Jan-21 22-Jan-21 29-Jan-21 05-Feb-21 12-Feb-21
No Wilayah Vol SAT Durasi
M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 M-25 M-26 M-27 M-28
1 BULELENG 100 Unit Minggu
Site Survey 3
Pengadaan
Gudang 12
Perlengkapan K3 2 PO
Anchor 2 PO
Tiang set 3 PO
Lampu set 7 PO
ETD Raw Material
ETA Raw Material
Produksi
PV Module 7 PO
ETD Raw Material
ETA Raw Material
Produksi
Pengiriman
Anchor 3 MOS
Tiang set 4 MOS
Lampu set 4 MOS
PV Module 4 MOS
Konstruksi
Pekerjaan Sipil 5
Instalasi Komponen 5
Pengujian External
Inspeksi 5

2 TABANAN 100 Unit


Site Survey 3
Pengadaan
Gudang 12
Perlengkapan K3 2 PO
Anchor 2 PO
Tiang set 3 PO
Lampu set 7 PO
ETD Raw Material
ETA Raw Material
Produksi
PV Module 7 PO
ETD Raw Material
ETA Raw Material
Produksi
Pengiriman
Anchor 3 MOS
Tiang set 4 MOS
Lampu set 4 MOS
PV Module 4 MOS
Konstruksi
Pekerjaan Sipil 5
Instalasi Komponen 5
Pengujian External
Inspeksi 5
JADWAL PELAKSANAAN PENAMBAHAN TITIK
PEMASANGAN PENERANGAN JALAN UMUM (MENGGUNAKAN PV) WILAYAH BAGIAN TENGAH I

23-Oct-20 30-Oct-20 06-Nov-20 13-Nov-20 20-Nov-20 27-Nov-20 04-Dec-20 11-Dec-20 18-Dec-20 25-Dec-20 01-Jan-21 08-Jan-21 15-Jan-21 22-Jan-21 29-Jan-21 05-Feb-21 12-Feb-21
No Wilayah Vol SAT Durasi
M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 M-25 M-26 M-27 M-28
1 LOMBOK TENGAH 125 Unit
Site Survey 4
Pengadaan
Gudang 13
Perlengkapan K3 2 PO
Anchor 2 PO
Tiang set 3 PO
Lampu set 7 PO
ETD Raw Material
ETA Raw Material
Produksi
PV Module 7 PO
ETD Raw Material
ETA Raw Material
Produksi
Pengiriman
Anchor 4 MOS
Tiang set 5 MOS
Lampu set 5 MOS
PV Module 5 MOS
Konstruksi
Pekerjaan Sipil 6
Instalasi Komponen 5
Pengujian External
Inspeksi 5