C Upah
ANALISA HARGA SATUAN PEKERJAAN UNTUK KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN
B Urugan Tanah
1 = Panjang x Lebar x Tinggi x Jmh 108 m3 1. Upah
= 12.0 x 7.5 x 1.20 x 1.0 a. Pekerja = 108 x 0.192 = 20.74 hok
= 108 m3
2. Bahan
a. Tanah urug = 108 x 1.200 = 129.60 M3
2. Bahan
a. Pasir urug = 20.02 x 0.300 = 6.01 M3
b. Batu Kali 15/20 = 20.02 x 1.100 = 22.02 M3
2. Bahan
a. Semen (50 kg) PCC = 57.20 x 2.000 = 114.40 zak
b. Pasir pasang = 57.20 x 0.544 = 31.12 M3
c. Batu pecah 15/20 = 57.20 x 1.100 = 62.92 M3
PANITIA PEMBANGUNAN MASJID AL - MUNAWWARAH
DESA SELAT NARMADA LOMBOK BARAT
RENCANA ANGGARAN BIAYA RINCI
No RAB : 1
Jenis Kegiatan : Pekerjaan Tanah Dan Fondasi
Ukuran/dimensi : 143.00 m
Sub Total II -
3 Bahan
1 Pasir Pasang 31.00 125,000 M3 3,875,000
2 Pasir Urug 6.00 75,000 M3 450,000
3 Batu Kali 15/20 22.00 175,000 M3 3,850,000
4 Batu Pecah 15/20 63.00 200,000 M3 12,600,000
5 Semen (50 kg) PCC 114.00 60,000 zak 6,840,000