LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 1 (SATU)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 19 JULI 2021 S/D 25 JULI 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 3.75 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu - Progres Minggu Ini 3.75 Progres S/D Mg Ini 3.75
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 2 (DUA)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 26 JULI 2021 S/D 1 AGUSTUS 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 5.21 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 3.75 Progres Minggu Ini 1.46 Progres S/D Mg Ini 5.21
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 3 (TIGA)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 2 AGUSTUS 2021 S/D 8 AGUSTUS 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 10.27 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 5.76 40% 0.32 5.76 40% 0.32
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 5.21 Progres Minggu Ini 5.06 Progres S/D Mg Ini 10.27
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 4 (EMPAT)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 9 AGUSTUS 2021 S/D 15 AGUSTUS 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 14.29 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 5.76 40% 0.32 8.64 60% 0.48 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 10.27 Progres Minggu Ini 4.01 Progres S/D Mg Ini 14.29
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 5 (LIMA)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 16 AGUSTUS 2021 S/D 22 AGUSTUS 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 16.72 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 14.29 Progres Minggu Ini 2.43 Progres S/D Mg Ini 16.72
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 6 (ENAM)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 23 AGUSTUS 2021 S/D 29 AGUSTUS 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 21.01 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68 19.25 100% 3.68 19.25 100% 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62 1.31 100% 0.62 1.31 100% 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 16.72 Progres Minggu Ini 4.29 Progres S/D Mg Ini 21.01
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 7 (TUJUH)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 30 AGUSTUS 2021 S/D 5 SEPTEMBER 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 25.91 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68 19.25 100% 3.68 19.25 100% 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62 1.31 100% 0.62 1.31 100% 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92 143.65 100% 0.92 143.65 100% 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20 6.08 100% 1.20 6.08 100% 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62 43.06 42% 2.78 43.06 42% 2.78
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 21.01 Progres Minggu Ini 4.90 Progres S/D Mg Ini 25.91
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 8 (DELAPAN)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 6 SEPTEMBER 2021 S/D 12 SEPTEMBER 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 30.04 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68 19.25 100% 3.68 19.25 100% 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62 1.31 100% 0.62 1.31 100% 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92 143.65 100% 0.92 143.65 100% 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20 6.08 100% 1.20 6.08 100% 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29 0.61 100% 0.29 0.61 100% 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62 43.06 42% 2.78 59.46 58% 3.84 102.52 100% 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 25.91 Progres Minggu Ini 4.12 Progres S/D Mg Ini 30.04
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 9 (SEMBILAN)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 13 SEPTEMBER 2021 S/D 19 SEPTEMBER 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 33.67 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68 19.25 100% 3.68 19.25 100% 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62 1.31 100% 0.62 1.31 100% 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26 195.77 100% 1.26 195.77 100% 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01 10.20 100% 2.01 10.20 100% 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36 0.77 100% 0.36 0.77 100% 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92 143.65 100% 0.92 143.65 100% 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20 6.08 100% 1.20 6.08 100% 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29 0.61 100% 0.29 0.61 100% 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62 102.52 100% 6.62 102.52 100% 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
4 Pas. Engsel pintu alluminium 2 Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 30.04 Progres Minggu Ini 3.63 Progres S/D Mg Ini 33.67
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 10 (SEPULUH)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 20 SEPTEMBER 2021 S/D 26 SEPTEMBER 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 40.90 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68 19.25 100% 3.68 19.25 100% 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62 1.31 100% 0.62 1.31 100% 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26 195.77 100% 1.26 195.77 100% 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01 10.20 100% 2.01 10.20 100% 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36 0.77 100% 0.36 0.77 100% 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92 143.65 100% 0.92 143.65 100% 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20 6.08 100% 1.20 6.08 100% 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29 0.61 100% 0.29 0.61 100% 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62 102.52 100% 6.62 102.52 100% 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23 205.04 100% 7.23 205.04 100% 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 33.67 Progres Minggu Ini 7.23 Progres S/D Mg Ini 40.90
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 11 (SEBELAS)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 27 SEPTEMBER 2021 S/D 3 OKTOBER 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 52.55 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68 19.25 100% 3.68 19.25 100% 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62 1.31 100% 0.62 1.31 100% 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26 195.77 100% 1.26 195.77 100% 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01 10.20 100% 2.01 10.20 100% 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36 0.77 100% 0.36 0.77 100% 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92 143.65 100% 0.92 143.65 100% 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20 6.08 100% 1.20 6.08 100% 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29 0.61 100% 0.29 0.61 100% 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65 110.00 100% 11.65 110.00 100% 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62 102.52 100% 6.62 102.52 100% 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23 205.04 100% 7.23 205.04 100% 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 40.90 Progres Minggu Ini 11.65 Progres S/D Mg Ini 52.55
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 12 (DUA BELAS)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 4 OKTOBER 2021 S/D 10 OKTOBER 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 57.66 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68 19.25 100% 3.68 19.25 100% 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62 1.31 100% 0.62 1.31 100% 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26 195.77 100% 1.26 195.77 100% 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01 10.20 100% 2.01 10.20 100% 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36 0.77 100% 0.36 0.77 100% 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92 143.65 100% 0.92 143.65 100% 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20 6.08 100% 1.20 6.08 100% 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29 0.61 100% 0.29 0.61 100% 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65 110.00 100% 11.65 110.00 100% 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74 110.00 100% 3.74 110.00 100% 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22 10.00 100% 0.22 10.00 100% 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14 42.00 100% 1.14 42.00 100% 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62 102.52 100% 6.62 102.52 100% 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23 205.04 100% 7.23 205.04 100% 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 52.55 Progres Minggu Ini 5.11 Progres S/D Mg Ini 57.66
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 13 (TIGA BELAS)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 11 OKTOBER 2021 S/D 17 OKTOBER 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 63.96 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68 19.25 100% 3.68 19.25 100% 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62 1.31 100% 0.62 1.31 100% 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26 195.77 100% 1.26 195.77 100% 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01 10.20 100% 2.01 10.20 100% 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36 0.77 100% 0.36 0.77 100% 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92 143.65 100% 0.92 143.65 100% 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20 6.08 100% 1.20 6.08 100% 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29 0.61 100% 0.29 0.61 100% 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65 110.00 100% 11.65 110.00 100% 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74 110.00 100% 3.74 110.00 100% 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22 10.00 100% 0.22 10.00 100% 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14 42.00 100% 1.14 42.00 100% 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62 102.52 100% 6.62 102.52 100% 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23 205.04 100% 7.23 205.04 100% 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42 205.04 100% 4.42 205.04 100% 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46 3.60 100% 0.46 3.60 100% 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42 3.60 100% 1.42 3.60 100% 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 57.66 Progres Minggu Ini 6.30 Progres S/D Mg Ini 63.96
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

INSTANSI : DINAS PENDIDIKAN DAERAH PROVINSI SULAWESI UTARA KONTRAKTOR PELAKSANA : CV. CHRISTA
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SISWA BESERTA PERABOTNYA KONSULTAN PENGAWAS : PT. WIMA WAYA NUSANTARA
LOKASI : SMAS BUDI LUHUR KEMBANG MERTHA - KAB. BOLAANG MONGONDOW MINGGU KE : 14 (EMPAT BELAS)
NO. KONTRAK : 13/SP-TENDER/DIKDA/RL/VII/2021 PERIODE : 18 OKTOBER 2021 S/D 24 OKTOBER 2021
TGL. KONTRAK : 16 JULI 2021 PROGRES S/D SAAT INI 75.36 %
TAHUN ANGGARAN : 2021

TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN
1 Pembesihan lokasi pekerjaan M2 72.00 24,150.00 1,738,800.00 0.65 72.00 100% 0.65 72.00 100% 0.65
2 Pengukuran dan pasangan bouw plank M 34.00 142,500.00 4,845,000.00 1.81 34.00 100% 1.81 34.00 100% 1.81
3 Biaya K3 Ls 1.00 2,700,000.00 2,700,000.00 1.01 1.00 100% 1.01 1.00 100% 1.01
4 Papan Nama Proyek Ls 1.00 175,000.00 175,000.00 0.07 1.00 100% 0.07 1.00 100% 0.07
5 Pekerjaan air dan listrik Ls 1.00 550,000.00 550,000.00 0.21 1.00 100% 0.21 1.00 100% 0.21
SUB JUMLAH 10,008,800.00 3.75
II PEKERJAAN PONDASI BATU BELAH
1 Galian tanah pondasi M3 17.34 120,750.00 2,093,805.00 0.78 17.34 100% 0.78 17.34 100% 0.78
2 Buangan tanah setempat M3 3.40 52,950.00 180,030.00 0.07 3.40 100% 0.07 3.40 100% 0.07
3 Urugan pasir M3 1.02 344,635.18 351,527.88 0.13 1.02 100% 0.13 1.02 100% 0.13
4 Pas. Batu kosong (Aan stamping) M3 2.04 627,930.00 1,280,977.20 0.48 2.04 100% 0.48 2.04 100% 0.48
5 Pas. Pondasi batu belah sp 1:4 M3 11.90 1,063,400.00 12,654,460.00 4.74 11.90 100% 4.74 11.90 100% 4.74
SUB JUMLAH 16,560,800.08 6.20
III PEKERJAAN BETON
1 Pembesian Sloof Kg 230.55 17,152.00 3,954,393.60 1.48 230.55 100% 1.48 230.55 100% 1.48
2 Bekisting Sloof M2 17.00 321,700.00 5,468,900.00 2.05 17.00 100% 2.05 17.00 100% 2.05
3 Cor Beton Sloof 1:2:3 M3 1.70 1,259,570.00 2,141,269.00 0.80 1.70 100% 0.80 1.70 100% 0.80
4 Pembesian perkuatan gempa pada kolom Kg 6.21 17,152.00 106,513.92 0.04 6.21 100% 0.04 6.21 100% 0.04
5 Pembesian Kolom Kg 247.21 17,152.00 4,240,145.92 1.59 247.21 100% 1.59 247.21 100% 1.59
6 Bekisting Kolom M2 19.25 510,030.00 9,818,077.50 3.68 19.25 100% 3.68 19.25 100% 3.68
7 Cor Beton Kolom 1:2:3 M3 1.31 1,259,570.00 1,650,036.70 0.62 1.31 100% 0.62 1.31 100% 0.62
8 Pembesian ring balok Kg 195.77 17,152.00 3,357,847.04 1.26 195.77 100% 1.26 195.77 100% 1.26
9 Bekisting ring balok M2 10.20 526,660.00 5,371,932.00 2.01 10.20 100% 2.01 10.20 100% 2.01
10 Cor Beton ring balok 1:2:3 M3 0.77 1,259,570.00 969,868.90 0.36 0.77 100% 0.36 0.77 100% 0.36
11 Pembesian balok lintel Kg 143.65 17,152.00 2,463,884.80 0.92 143.65 100% 0.92 143.65 100% 0.92
12 Bekisting balok lintel M2 6.08 526,660.00 3,202,092.80 1.20 6.08 100% 1.20 6.08 100% 1.20
13 Cor Beton Balok lintel M3 0.61 1,259,570.00 768,337.70 0.29 0.61 100% 0.29 0.61 100% 0.29
SUB JUMLAH 43,513,299.88 16.29
IV PEKERJAAN ATAP
1 Pas. Rangka Baja Ringan C.75.75 M2 110.00 282,880.00 31,116,800.00 11.65 110.00 100% 11.65 110.00 100% 11.65
2 Pas. Penutup atap Spandek, t=0,3 mm M2 110.00 90,790.00 9,986,900.00 3.74 110.00 100% 3.74 110.00 100% 3.74
3 Pas. Nok Atap M 10.00 60,060.00 600,600.00 0.22 10.00 100% 0.22 10.00 100% 0.22
4 Pas. Lisplank GRC 8X200 MM M 42.00 72,530.00 3,046,260.00 1.14 42.00 100% 1.14 42.00 100% 1.14
SUB JUMLAH 44,750,560.00 16.76
V PEKERJAAN DINDING
1 Pekerjaan Pasang bata 1/2 bata sp 1:4 M2 102.52 172,320.00 17,666,246.40 6.62 102.52 100% 6.62 102.52 100% 6.62
2 Pekerjaan Plesteran sp 1:4 M2 205.04 94,170.00 19,308,616.80 7.23 205.04 100% 7.23 205.04 100% 7.23
3 Pekerjaan Acian dinding M2 205.04 57,580.00 11,806,203.20 4.42 205.04 100% 4.42 205.04 100% 4.42
SUB JUMLAH 48,781,066.40 18.27
VI PEKERJAAN KUSEN PINTU DAN JENDELA ALLUMINIUM
1 Pas. Kusen jendala, ventilasi rangka alluminium M 56.73 102,480.00 5,813,690.40 2.18
2 Pas. Pintu kaca rangka alluminium M2 3.36 1,099,430.00 3,694,084.80 1.38
3 Pas. Door closer Bh 2.00 738,070.00 1,476,140.00 0.55
TOTAL PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
VOLUME HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. BOBOT PROGRES BOBOT PROGRES BOBOT PROGRES BOBOT
KONTRAK (Rp) (Rp) VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Pas. Engsel pintu alluminium Bh 4.00 163,840.00 655,360.00 0.25
5 Pas. Kunci pintu Alluminium Bh 2.00 188,030.00 376,060.00 0.14
6 Pas. Door holder / pegangan pintu Bh 2.00 390,430.00 780,860.00 0.29
7 Pas. Jendela kaca rangka alluminium M2 11.17 961,290.00 10,737,609.30 4.02
8 Pas. Rambuncis jendela alluminium / pegangan Bh 10.00 18,720.00 187,200.00 0.07
9 Pas. Engsel jendela alluminium Bh 20.00 58,480.00 1,169,600.00 0.44
SUB JUMLAH 24,890,604.50 9.32
VII PEKERJAAN PLAFON
1 Rangka plafon hollow 4X2,t=0,7 mm, modul 60X60 M2 72.00 173,560.00 12,496,320.00 4.68
2 Pas. Plafon GRC t=4 mm M2 72.00 69,610.00 5,011,920.00 1.88
3 Pas. List plafon profil M 68.00 29,650.00 2,016,200.00 0.76
SUB JUMLAH 19,524,440.00 7.31
VIII PEKERJAAN LANTAI
1 Timbunan tanah lantai M3 14.40 149,860.00 2,157,984.00 0.81 14.40 100% 0.81 14.40 100% 0.81
2 Urugan Pasir M3 3.60 344,635.18 1,240,686.65 0.46 3.60 100% 0.46 3.60 100% 0.46
3 Cor lantai 1:3:5 M3 3.60 1,050,680.00 3,782,448.00 1.42 3.60 100% 1.42 3.60 100% 1.42
4 Cor teras 1:3:5 plus disabilitas akses M3 1.61 1,050,680.00 1,691,594.80 0.63
5 Pemasangan lantai ubin abu-abu 40x40 M2 69.47 312,220.00 21,689,923.40 8.12 69.47 100% 8.12 69.47 100% 8.12
SUB JUMLAH 30,562,636.85 11.45
IX PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi Listrik Titik 10.00 365,360.00 3,653,600.00 1.37
2 Pasang stop kontak Bh 10.00 364,450.00 3,644,500.00 1.36
3 Pasang Saklar Tunggal Bh 2.00 41,430.00 82,860.00 0.03
4 Pasang Saklar Ganda Bh 2.00 44,570.00 89,140.00 0.03
5 Pasang Lampu SL 4 Watt + Feteng Bh 3.00 103,170.00 309,510.00 0.12
6 Pasang Lampu SL 12 Watt + Feteng Bh 6.00 160,730.00 964,380.00 0.36
7 Memasang Box MCB Unit 1.00 438,050.00 438,050.00 0.16
8 Grounding Unit 1.00 752,000.00 752,000.00 0.28
SUB JUMLAH 9,934,040.00 3.72
X PEKERJAAN PENGECATAN
1 Pengecatan dinding baru M2 208.94 41,860.00 8,746,228.40 3.28 208.94 100% 3.28 208.94 100% 3.28
2 Pengecatan plafon M2 72.00 41,860.00 3,013,920.00 1.13
SUB JUMLAH 11,760,148.40 4.40
XI PENGADAAN MEUBELER
1 Pengadaan Meja Siswa Bh 6.00 750,000.00 4,500,000.00 1.69
2 Pengadaan Kursi Siswa Bh 6.00 375,000.00 2,250,000.00 0.84
SUB JUMLAH 6,750,000.00 2.53

JUMLAH HARGA DAN BOBOT 267,036,396.12 100.00 Progres Minggu Lalu 63.96 Progres Minggu Ini 11.40 Progres S/D Mg Ini 75.36
PPN 10% 26,703,639.61
JUMLAH TOTAL 293,740,035.73
DIBULATKAN 293,740,000.00

Mengetahui/Disetujui, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
DINAS PENDIDIKAN DAERAH PROVINSI PT. WIMA WAYA NUSANTARA CV. CHRISTA
SULAWESI UTARA

ARTHUR TUMIPA, M.Ed FRANSISKA LHO CEH RUMAGIT, ST,MT,IAI HANNY PONGANTUNG, ST
NIP. 19710809 199203 1 002 DIREKTUR DIREKTUR