4. Assembly Process Chart (Sekarang)


PETA PROSES PERAKITAN (SEKARANG)

NAMA OBJEK : RAGUM MINI


NOMOR PETA : 01 SEKARANG : X
DIPETAKAN OLEH : SRI SEPTIANI
TANGGAL DIPETAKAN : 29 APRIL 2021 USULAN :

Base ragum Perakitan 1


Aluminium 85" A-1
(120 x 60 x 50) mm 0% Merakit Penggerak pada
Base Ragum

2
70" Perakitan 2
A-2
Penggerak 0% Merakit Penahan pada
Aluminium Base Ragum
(60 x 30 x 20) mm (Baut)

Penahan
Aluminium
(60 x 42 x 20) mm 60" Perakitan 5
0% A-5 A Produk Jadi
Merakit Poros Ulir Ragum Mini
4 pada Base Ragum

Poros Ulir
Aluminium 15" Perakitan 3
A-3
(Ø12 x 126) mm 0% Merakit Tangkai
pada Poros Ulir

5
30" Perakitan 4
A-4
Tangkai 0% Merakit Penutup Tangkai
Aluminium pada Poros Ulir
(Ø5 x 80) mm

Penutup Tangkai
Bola Baja
(Ø10 x Ø5) mm

Gambar 4.3 Assembly Process Chart (Sekarang)


Sumber : (Sri Septiani, 2021)
5

4. Operation Process Chart (Sekarang)


PETA PROSES OPERASI (SEKARANG)

NAMA OBJEK : RAGUM MINI SEKARANG : X


NOMOR PETA : 002
DIPETAKAN OLEH : MUHAMMAD FAHRIZAL RIZKI USULAN :
TANGGAL DIPETAKAN : 28 APRIL 2021

Penutup Tangkai Tangkai Poros Ulir Penahan Penggerak Base Ragum


Bola Baja Aluminium Aluminium Aluminium Aluminium Aluminium
(Ø10 x Ø5) mm (Ø5 x 80) mm (Ø12 x 126) mm (60 x 42 x 20) mm (60 x 30 x 20) mm (120 x 60 x 50) mm

Ukur dan Tandai Ukur dan Tandai Ukur dan Tandai Ukur dan Tandai Ukur dan Tandai Ukur dan Tandai
18" Bahan Baku 18" Bahan Baku 18" Bahan Baku 18" Bahan Baku 18" Bahan Baku 18" Bahan Baku
O-50 O-43 O-34 O-23 O-12 O-1
0% (Mistar dan 0% (Mistar dan 0% (Mistar dan 0% (Mistar dan 0% (Mistar dan 0% (Mistar dan
Penggores) Penggores) Penggores) Penggores) Penggores) Penggores)

124.75" Set Up Mesin 180.37" Set Up Mesin 180.31" Set Up Mesin 179.99" Set Up Mesin 180.17" Set Up Mesin 179.62" Set Up Mesin
O-51 O-44 O-35 O-24 O-13 O-2
0% Drilling 2 0% Sawing 2 0% Sawing 2 0% Sawing 1 0% Sawing 1 0% Sawing 1

68.16" Proses Pelubangan 79.9" Proses Pemotongan 89.77" Proses Pemotongan 60.15" Proses Pemotongan 82.15" Proses Pemotongan 99.17" Proses Pemotongan
O-52 Benda Kerja O-45 Bahan Baku O-36 Bahan Baku O-25 Bahan Baku O-14 Bahan Baku O-3 Bahan Baku
0.5% (Mesin Drilling 2) 1% (Mesin Sawing 2) 1% (Mesin Sawing 2) 1% (Mesin Sawing 1) 1% (Mesin Sawing 1) 1% (Mesin Sawing 1)

164.9" Set Up Mesin 349.71" Set Up Mesin 349.94" Set Up Mesin 149.82" Set Up Mesin 149.9" Set Up Mesin 149.45" Set Up Mesin
O-53 O-46 O-37 O-26 O-15 O-4
0% Tapping 0% Turning 2 0% Turning 1 0% Milling 2 0% Milling 1 0% Milling 1

Proses Proses Proses


33.93" Proses Penguliran 155.09" Proses Pembubutan 695.28" Proses Pembubutan 148.09" 280.07" 689.79"
Pengefraisan Benda Pengefraisan Benda Pengefraisan Benda
O-54 Benda Kerja O-47 Benda Kerja O-38 Benda Kerja O-27 O-16 O-5
0.5% 1% 4% 1.5% Kerja 2% Kerja 4% Kerja
(Mesin Tapping) (Mesin Turning 2) (Mesin Turning 1)
(Mesin Milling 2) (Mesin Milling 1) (Mesin Milling 1)

124.89" Set Up Mesin 125.07" Set Up Mesin 125.13" Set Up Mesin 125.18" Set Up Mesin 124.9" Set Up Mesin
O-48 O-39 O-28 O-17 O-6
0% Grinding 0% Drilling 2 0% Drilling 1 0% Drilling 1 0% Drilling 1

56.88" Proses Penghalusan 42.1" Proses Pelubangan 269.77" Proses Pelubangan 85.13" Proses Pelubangan 199.91" Proses Pelubangan
O-49 Benda Kerja O-40 Benda Kerja O-29 Benda Kerja O-18 Benda Kerja O-7 Benda Kerja
0.5% (Mesin Grinding) 0.5% (Mesin Drilling 2) 2.5% (Mesin Drilling 1) 1% (Mesin Drilling 1) 2% (Mesin Drilling 1)

124.89" Set Up Mesin 164.93" Set Up Mesin 165.26" Set Up Mesin 165.11" Set Up Mesin
O-41 Grinding O-30 Tapping O-19 Tapping O-8 Tapping
0% 0% 0% 0%

86.15" Proses Penghalusan 163.65" Proses Penguliran 44.87" Proses Penguliran 125.76" Proses Penguliran
O-42 Dalam Benda Kerja O-31 Dalam Benda Kerja O-20 Dalam Benda Kerja O-9 Dalam Benda Kerja
0.5% (Mesin Grinding) 1.5% (Mesin Tapping) 0.5% (Mesin Tapping) 1% (Mesin Tapping)

124.89" Set Up Mesin 125.33" Set Up Mesin 125.05" Set Up Mesin


O-32 O-21 O-10
0% Grinding 0% Grinding 0% Grinding

81.15" Proses Penghalusan 104.37" Proses Penghalusan 116.28" Proses Penghalusan


O-33 Benda Kerja O-22 Benda Kerja O-11 Benda Kerja
0.5% (Mesin Grinding) 0.5% (Mesin Grinding) 0.5% (Mesin Grinding)

75" 75" 75" 75" 75" 75"


I-6 Pemeriksaan I-5 Pemeriksaan I-4 Pemeriksaan I-3 Pemeriksaan I-2 Pemeriksaan I-1 Pemeriksaan
0% 0% 0% 0% 0% 0%

Ass 3 Ass 1

Perakitan
15" Perakitan Tangkai 85" Penggerak Pada
G-3 Pada Poros Ulir G-1 Base Ragum
0% 0%
(Meja Perakitan) (Meja Perakitan)

Baut
Ass 4 Ass 2

Perakitan Penutup
30" 70" Perakitan Penahan
G-4 Tangkai Pada Poros G-2 Pada Base Ragum
0% Ulir 0% (Meja Perakitan)
(Meja Perakitan)

Ass 5

60" Perakitan Poros Ulir


G-5 Pada Base Ragum
0% (Meja Perakitan)

75"
I-7 Pemeriksaan
0%

Penyimpanan
S-1
Produk
(Stasiun Gudang)

RINGKASAN

KEGIATAN JUMLAH WAKTU (DETIK)

OPERASI 54 8107.45

PEMERIKSAAN 7 525

OPERASI GABUNGAN 5 260

PENYIMPANAN 1 0

TOTAL 67 8892.45

Gambar 4. 3 Operation Process Chart (Sekarang)


Sumber: (M. Fahrizal Rizki, 2021)