Anda di halaman 1dari 16

DAFTAR BAHAN

HARGA
NO. NAMA / JENIS BAHAN SATUAN
SATUAN BAHAN
2 3 4 5

1 Oli Pelumas SAE 90 merk Pertamina liter Rp 70,000.00

2 Bearing grase merk Timken 2 Can kg Rp 36,000.00

3 Silicon Lubricant Spray 30 merk WD klng Rp 90,000.00

4 Wire Rope Grease spray 500 ml merk YAC klng Rp 360,000.00

5 Contact Cleaner 300ml merk YAC klng Rp 190,000.00

6 Clear kg Rp 280,000.00

7 Compond kg Rp 330,000.00

8 Gasolin pertalite ltr Rp 7,800.00

9 lampu lift bh Rp 175,000.00

DAFTAR UPAH

NO. URAIAN TENAGA SATUAN UPAH PERHARI

1 PEMBANTU MEKANIK Org / hr Rp 70,000.00

2 TENAGA AHLI Org / hr Rp 450,000.00

DAFTAR ALAT

NO. URAIAN SATUAN UPAH PERHARI


1 Blower Unit milik sendiri
2 Alat keselamatan kerja Unit milik sendiri
3 grease gun Unit Rp 40,000.00
4 Oil can Unit milik sendiri
5 Tooling set Unit milik sendiri
6 Kuas bh Rp 20,000.00
7 Kain majun kg Rp 17,500.00
8 Spot light Unit milik sendiri
9 Grinding polite Unit milik sendiri
RENCANA ANGGARAN BIAYA (RAB)

Pekerjaan : Belanja Modal pengadaan Instalasi listrik


Kegiatan : Peningkatan Pelayanan Penunjang Dan sarana kesehatan
Lokasi : RUMAH SAKIT UMUM DAERAH KOTA MALANG
Tahun : 2017

HARGA SATUAN TOTAL HARGA


No. URAIAN PEKERJAAN SAT VOL
(Rp) (Rp)

I PEKERJAAN PERSIAPAN
1 Pekerjaan pembersihan dan pengukuran ls 1.00 A.005 392,162 392,162
3 #NAME? unit #NAME? #NAME? 1,603,285 #NAME?
4 Pekerjaan pasang tiang besi 7 m 5" unit 4.00 B.004 1,626,299 6,505,196
sub total #NAME?
II PEKERJAAN KABEL INSTALASI
1 Pengadaan dan pemasangan kabel almunium acsr 4 x 95 mm m 306.00 B.001 187,579 57,399,174
2 pengadaan dan pemasangan kabel NYY 1 x 150 mm m 60.00 B.002 378,440 22,706,400
3 Pengadaan dan pemasangan kabel NYY 1 x 120 mm m 20.00 B.003 336,314 6,726,280
sub total 86,831,854
III PEKERJAAN MDP ( MAIN DISTRIBUSI PANEL )
1 Pengadaan dan pemasangan Box Panel 50 x 60 cm unit 2.00 B.006 7,095,222 14,190,444
Dengan komponen panel : -
plat copel 4 cm x 0,5 / 2,5 cm -
pustig -
dinabolt -
pilot lamp + fuse -
nyaf 0,75 -
mur baut 10 mm -
finil -
2 Pengadaan dan pemasangan Box Panel 160 x 60 x 50 cm Unit 1.00 B.005 37,270,477 37,270,477
dengan komponen Panel : -
Mcb 3 phasa / 400 A -
Breaker 75 A 3 Phasa -
Breaker 125 A 3 Phasa -
Breaker 80 A 3 Phasa -
Ampere Meter -
Volt Meter -
Control Transformer -
Switch Selector -
Pilot lamp + fuse -
Skun y -
Nyaaf 0,75 mm -
Cable ties -
Nyaf 16 mm -
Breaker 60 A /3 Phasa -
sub total 51,460,921
Total jumlah #NAME?
Terbilang Dibulatkan
Seratus Lima Puluh Delapan Juta Rupiah
RENCANA ANGGARAN BIAYA (RAB)
PERAWATAN BERKALA PRASARANA PENUNJANG"PASSENGER LIFT " GEDUNG LANTAI 4

Pekerjaan : Perawatan Lift selama 1 ( satu ) Tahun dengan kunjungan perbulan 1 ( satu )kali
Kegiatan : Perawatan Berkal Prasarana Penunjang
Lokasi : RSUD KOTA MALANG
Tahun : 2018

HARGA SATUAN TOTAL HARGA


No. URAIAN PEKERJAAN SAT VOL
(Rp) (Rp)

I Penambahan oli pelumas sliding pada pintu lift unit 1.00


1 Oli Pelumas SAE 90 merk Pertamina ltr 10.00 80,000.00 800,000.00
Jasa penggantian ls 1.00 200,000.00 200,000.00
Dengan item pekerjaan : -
Penambahan oli pelumas sliding pada pintu lift -
-
2 Pekerjaan wire rope regrease Spraying unit 1.00 - -
Wire Rope Grease spray 500 ml merk YAC klng 10.00 450,000.00 4,500,000.00
Jasa pekerjaan ls 1.00 500,000.00 500,000.00
Dengan item pekerjaan : -
penambahan grease( pelumas) pada setiap seling -
-
3 Pekerjaan regreasing Sliding door unit 4.00 -
Bearing grase merk Timken 2 Can klng 10.00 150,000.00 1,500,000.00
Jasa pekerjaan ls 1.00 400,000.00 400,000.00
Dengan item pekerjaan : -
penambahan dan pengecekan rel sleding door dengan pemberian greasing -
( pelumas) -
-
4 Cleaning unit sangkar dan panel unit 1.00 -
Silicon Lubricant Spray 30 merk WD klng 9.00 138,900.00 1,250,100.00
Contact Cleaner 300ml merk YAC klng 9.00 180,000.00 1,620,000.00
Gasolin pertalite ltr 10.00 9,000.00 90,000.00
Jasa pekerjaan ls 1.00 2,000,000.00 2,000,000.00
Dengan item pekerjaan : -
membersihkan panel panel kontrol lift -
( membersihkan dari kotoran dan kerak) -
membersikar sekitar lift,plafon dan sangkar lift -
-
5 Pekerjaan regreasing bearing set unit 1.00 - -
Bearing grase merk Timken 2 Can kg 10.00 70,000.00 700,000.00
Silicon Lubricant Spray 30 merk WD klng 9.00 90,000.00 810,000.00
grease gun unit 3.00 75,000.00 225,000.00
Kain majun kg 4.00 25,000.00 100,000.00
Kuas bh 2.00 30,000.00 60,000.00
Jasa pekerjaan ls 1.00 1,250,000.00 1,250,000.00
Dengan item pekerjaan : -
Penambahan dan pemberian greas( pelumas) pada setiap roda roda bearing( klaker) -
-
-
6 Pekerjaan setting braking stop lift unit 1.00 -
Bearing grase merk Timken 2 Can kg 9.00 35,000.00 315,000.00
Compond kg 7.00 330,000.00 2,310,000.00
Clear kg 7.00 323,000.00 2,261,000.00
Contact Cleaner 300ml merk YAC klng 6.00 250,000.00 1,500,000.00
Silicon Lubricant Spray 30 merk WD klng 5.00 100,000.00 500,000.00
jasa pekerjaan ls 1.00 1,500,000.00 1,500,000.00
Dengan item pekerjaan : -
mensetting dan mengontrol system operasionalnya lift -
( jalan dan berhentinya lift seuai dengan sensor dan programnya) -
-
-
-
-
-
-
-
-
24,391,100.00
Total jumlah 24,391,100.00
Terbilang Dibulatkan
RENCANA ANGGARAN BIAYA (RAB)
P E K E R J A A N MEKANIKAL & ELEKTRIKAL

Pekerjaan : Prototype Rumah susun Keluarga 4 lantai Type - 36, TNI/Polri, Pekerja, (Prototype 15-06)
Lokasi : PROV. ACEH
Tahun Anggaran : 2015

PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

B PEKERJAAN MEKANIKAL & ELEKTRIKAL NON STANDART

B.1. PEKERJAAN PEMADAM KEBAKARAN

I INSTALASI PEMIPAAN HYDRANT


INSTALASI PEMIPAAN

a LANTAI 1
Pemipaan BSP Sch. 40
(Incl.Fitting & All Accessories)
- dia. 100 mm (Pipa Riser ) m 30.00
- dia. 65 mm m 6.00
- dia. 40 mm m 0.60
- Indoor Hydrant Box (IHB) 750x1200x180 set 2.00
lengkap dengan : Landing Valve, Hose Valve, Hoze Nozzle
dan Accessories
Fire Extinguisher Tabung Cat Oven sesuai SPEK & Skedul :
- Type CO2 Class B & C 3,5 kg Seamless, c/w support bh 1.00
- Type Class ABC 3,5 kg Seamless, c/w support bh 3.00

b LANTAI 2
Pemipaan BSP Sch. 40
(Incl.Fitting & All Accessories)
- dia. 100 mm (Pipa Riser ) m 6.40
- dia. 65 mm m 6.00
- dia. 40 mm m 0.60
- Indoor Hydrant Box (IHB) 750x1200x180 set 2.00
lengkap dengan : Landing Valve, Hose Valve, Hoze Nozzle
dan Accessories
Fire Extinguisher Tabung Cat Oven sesuai SPEK & Skedul :
- Type Class ABC 3,5 kg Seamless, c/w support bh 3.00

c LANTAI 3
Pemipaan BSP Sch. 40
(Incl.Fitting & All Accessories)
- dia. 100 mm (Pipa Riser ) m 6.40
- dia. 65 mm m 6.00
- dia. 40 mm m 0.60
- Indoor Hydrant Box (IHB) 750x1200x180 set 2.00
lengkap dengan : Landing Valve, Hose Valve, Hoze Nozzle
dan Accessories
Fire Extinguisher Tabung Cat Oven sesuai SPEK & Skedul :
HAL-4
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

- Type Class ABC 3,5 kg Seamless, c/w support bh 3.00

d LANTAI 4
Pemipaan BSP Sch. 40
(Incl.Fitting & All Accessories)
- dia. 100 mm (Pipa Riser ) m 6.40
- dia. 65 mm m 6.00
- dia. 40 mm m 0.60
- Indoor Hydrant Box (IHB) 750x1200x180 set 2.00
lengkap dengan : Landing Valve, Hose Valve, Hoze Nozzle
dan Accessories
Fire Extinguisher Tabung Cat Oven sesuai SPEK & Skedul :
- Type Class ABC 3,5 kg Seamless, c/w support bh 3.00

- Automatic Air Vent dia 25, c/w Pressure gate, gate valve bh 2.00

B.2 PEKERJAAN VENTILASI UDARA

INSTALASI VENTILASI UDARA

1 LANTAI DASAR
- Exhaust kap 200 CMH ( ceiling Mounted ) unit 2

Pipa PVC Class AW


- dia. 100 m 11
- Grille 100 x 100 (Alumunium) bh 2

2 LANTAI 2 s/d 4
- Exhaust kap 200 CMH ( ceiling Mounted ) unit 48

Pipa PVC Class AW


- dia. 100 m 352
- Grille 100 x 100 (Alumunium) bh 64

B.3. PEKERJAAN INSTALASI ELEKTRONIK

I. PEKERJAAN SYSTEM TV

a PERALATAN UTAMA SYSTEM TV

Pengadaan dan pemasangan peralatan utama Sistem TV di-


tempatkan di Lantai Atap, dipasang secara lengkap termasuk
pondasi dan tiang penyangga sesuai diuraikan dalam Gam-
bar dan Spesifikasi Teknis.

- Antena UHF unit 1.00


- Antena VHF unit 1.00

HAL-5
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

- MA (Master Amplifier)/Mixer bh 1.00


- Coaxial 7C/2V, dari Antena ke Mixer mtr 35.00
- Termination & supporting material lot 1.00

b SPLITTER TV

Pengadan dan pemasangan Splitter TV, breikut alat / mat-


erial bantu pemasangan lainnya sesuai Gambar dan Spesifi-
kasi Teknis.

LANTAI-1
Splitter 7 ports bh 1.00
TB-Splitter-TV/lt.1 bh 1.00

Lantai-2
Splitter 7 ports bh 5.00
TB-Splitter-TV/lt.2 bh 1.00

Lantai-3
Splitter 7 ports bh 5.00
TB-Splitter-TV/lt.3 bh 1.00

Lantai-4
Splitter 7 ports bh 5.00
TB-Splitter-TV/lt.4 bh 1.00

c INSTALASI KABEL FEEDER SPLITTER TV

Instalasi Kabel Feeder Splitter TV menggunakan kabel coaxial


berikut semua aksesoris, material / alat bantu pemasangan
sesuai detail Gambar dan Spesifikasi Teknis.

Lantai-1
Coaxial 7C/2V dari TB-Splitter-TV/lt.2 ke TB-Splitter-lt.1 mtr 10.00

Lantai-2
Coaxial 7C/2V dari TB-Splitter-TV/lt.3 ke TB-Splitter-lt.2 mtr 15.00

Lantai-3
Coaxial 7C/2V dari TB-Splitter-TV/lt.4 ke TB-Splitter-lt.3 mtr 20.00

Lantai-4
Coaxial 7C/2V dari TB-Splitter-TV/lt.5 ke TB-Splitter-lt.4 mtr 25.00

d TV OUTLET

Pengadan dan pemasangan TV Outlet, breikut alat / material


bantu pemasangan lainnya sesuai Gambar dan Spesifikasi
Teknis.

HAL-6
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

Lantai-1
TV Outlet bh 5.00

Lantai-2
TV Outlet bh 16.00

Lantai-3
TV Outlet bh 16.00

Lantai-4
TV Outlet bh 16.00

e INSTALASI OUTLET TV

Instalasi kabel Outlet TV menggunakan kabel Coaxial 5C/2V


dalam conduit PVC HI dia.20 mm2 lengkap dengan bobokan
dan perapihan kembali, peralatan bantu dan aksesoris sesuai
detail Gambar dan Spesifikasi Teknis.

Lantai-1
TV Outlet ttk 5.00

Lantai-2
TV Outlet ttk 16.00

Lantai-3
TV Outlet ttk 16.00

Lantai-4
TV Outlet ttk 16.00

II PEKERJAAN FIRE ALARM

a PERALATAN UTAMA FIRE ALARM SYSTEM

Pengadaan dan pemasangan peralatan Sistem Fire Alarm


ditempatkan di Ruang Kontrol secara lengkap termasuk peng-
kabelan dan koneksi meliputi peralatan sesuai diuraikan dlm
Gambar dan Spesifikasi Teknis, tetapi tidak terbats pada item
sebagai berikut :

MCFA, kapasitas 10 Zone unit 1.00


MDF, kapasitas 10 Zone set 1.00
Rectifier bh 1.00
Power Surge Arrester bh 1.00
Battery & Charger 4 jam bh 1.00
Grounding u/ MCFA dan Surge Arrester ( R < 0,5 Ohm ) lot 1.00

HAL-7
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

b INSTALASI KABEL FEEDER FIRE ALARM

INSTALASI FEEDER MELALUI RISER / SHAFT

Kabel NYA 5 x 2 x 2,5 mm2 in conduit Dia.32 dari MCFA ke MDF mtr 28.00
Kabel NYA 3 x 2 x 2,5 mm2 in conduit Dia.32 dari MDF ke TB-FA-LT.1 mtr 2.00
###
Kabel NYA 3 x 2 x 2,5 mm2 in conduit Dia.32 dari MDF ke TB-FA-LT.2 mtr 6.00
###
Kabel NYA 3 x 2 x 2,5 mm2 in conduit Dia.32 dari MDF ke TB-FA-LT.3 mtr 12.00
###
Kabel NYA 3 x 2 x 2,5 mm2 in conduit Dia.32 dari MDF ke TB-FA-LT.4 mtr 16.00
###

c PERALATAN PENGINDERA dan PENANDA KEBAKARAN

Pengadaan dan pemasangan peralatan pengindera dan penan-


da kebakaran berikut alat / material bantu lainnya sesuai Gam-
bar dan Spesifikasi Teknis.

Lantai-1
- Rate Of Rise Temperature - Heat detector bh 27.00
- Manual push button bh 1.00
- Lampu Indikator bh 1.00
- Bell alarm bh 1.00
- End of Line Resistor bh 2.00
- TB-FA-Lt.Ground bh 1.00

Lantai-2
- Rate Of Rise Temperature - Heat detector bh 31.00
- Manual push button bh 1.00
- Lampu Indikator bh 1.00
- Bell alarm bh 1.00
- End of Line Resistor bh 2.00
- TB-FA-Lt2 bh 1.00

Lantai-3
- Rate Of Rise Temperature - Heat detector bh 31.00
- Manual push button bh 1.00
- Lampu Indikator bh 1.00
- Bell alarm bh 1.00
- End of Line Resistor bh 2.00
- TB-FA-Lt3 bh 1.00

Lantai-4
- Rate Of Rise Temperature - Heat detector bh 31.00
- Manual push button bh 1.00
- Lampu Indikator bh 1.00
- Bell alarm bh 1.00
- End of Line Resistor bh 2.00
- TB-FA-Lt4 bh 1.00

d PERALATAN PENGINDERA dan PENANDA KEBAKARAN

HAL-8
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

Instalasi titik detector dari TB-FA dengan kabel NYA 2 x 1,5 mm2
didalam conduit dia. 20 mm2 lengkap dengan aksesoris dan
semua peralatan / material bantu pemasangan sesuai detail
Gambar dan Spesifikasi Teknis.

Lantai-1
- Rate Of Rise Temperature - Heat detector ttk 27.00
- Manual push button ttk 1.00
- Lampu Indikator ttk 1.00
- Bell alarm ttk 1.00

Lantai-2
- Rate Of Rise Temperature - Heat detector ttk 31.00
- Manual push button ttk 1.00
- Lampu Indikator ttk 1.00
- Bell alarm ttk 1.00

Lantai-3
- Rate Of Rise Temperature - Heat detector ttk 31.00
- Manual push button ttk 1.00
- Lampu Indikator ttk 1.00
- Bell alarm ttk 1.00

Lantai-4
- Rate Of Rise Temperature - Heat detector ttk 31.00
- Manual push button ttk 1.00
- Lampu Indikator ttk 1.00
- Bell alarm ttk 1.00

Perijinan dgn Depnaker lot 1.00

Material Bantu lot 1.00


Testing & Commissioning lot 1.00

B.4. PEKERJAAN SARANA DAN PRASARANA LINGKUNGAN (LUAR BANGUNAN)

I PEKERJAAN INSTALASI PLAMBING

a. INSTALASI AIR BERSIH


PERALATAN UTAMA
Pengadaan dan pemasangan unit
1 Lift Pump bh 2.00
Kapasitas : 250 l/menit
Head : 37 mtr
Speed : 1450 rpm
PI : 5,5 KW/380V/50Hz/3ph

HAL-9
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

1 duty, 1 standby ( bergantian), lengkap dengan


panel control, wlc di Tanki Air Atas dan accessories

2 Booster Pump set 1


Kapasitas : 160 l/menit
Head : 20 mka
Speed : 1450 rpm
PI : 2,2 KW/380V/50Hz/3ph
Lengkap dengan Pump & Electromotor (2),Pressure Tank, Panel Kontrol, Pressure switch,
, Presure Gauge, Accessories, Gate Valve, Header & base Plat.

3 Tangki Air Atas unit 2.00


kapasitas : 5m3
Fiber Rainforcement Plastic, lengkap dengan dudukan

4 Jet Pump + Pengeboran Sumur set 2.00


(Incl. Pipa,Fitting & Accessories, Berfungsi )
kapasitas : 100 l/menit
Total Head : 50 meter
Daya : 500 w / 1ph/ 220

4 Ground Water Tank - 1 unit by sipil


kapasitas : 100 m3
Rainforced Concrete Made
6 ACCESSORIES POMPA
- Gate Valve
dia. 100 ( Untuk Penghubung/penyeimbang GWT) bh 1.00
- Check Valve ( CV )
dia. 50 bh 2.00
- Strainer ( STR )
dia. 50 bh 2.00
- Flexible Joint ( FJ )
dia. 50 bh 4.00
- Foot Valve
dia. 50 bh 2.00
- Pressure Gauge bh 2.00
- GIP med dia. 100 ( pipa header ) set 1.00
- Instalasi pemipaan area pompa lot 1.00
c/w fiting-fitting & support.
- Meteran Air c/w GV dia. 50 & Box meteran unit 1.00

a.1. INSTALASI PEMIPAAN


Pengadaan dan pemasangan unit.
Pemipaan PPR PN 10 (Incl. Fitting & All Accessories)
1 SITE PLAN
1. Dari Box Meter PDAM ke GWT
- GIP dia. 50 (Dari Box Meter PDAM ke GWT) m 6.00
2. Pemipaan R.Pompa ke Shaft Lt-1
- GIP dia. 65 ( pipa dari GWT ke Shaft ) m 20.00

HAL-10
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

2 Penyambungan pipa PDAM, pipa gip dia. 65 termasuk lot


Perijinan.

b. INSTALASI AIR KOTOR & AIR BEKAS


Pipa PVC Kelas AW(Incl. Fitting & Accessories)

a SITE PLAN
- dia. 150 (air kotor dan air bekas ) m 15.00
###
- dia. 150 (air kotor dan air bekas) m 15.00
###

- Bak Kontro 40x40x30 cm ( air bekas) unit 4.00

b Septic Tank Bio Media (Air Kotor) unit 2.00


Kapasitas : 15 m3/Day
c/w Air Blower

c Tangki Sumur Resapan (Air Bekas) unit 2.00


Kapasitas : 5 m3

- Struktur Pondasi By Sipil

c. MATERIAL BANTU lot 1.00


d. TESTING COMMISSIONING lot 1.00

II PEKERJAAN PEMADAM KEBAKARAN


a. PERALATAN UTAMA
Termasuk dudukan/pondasi pompa
1 Diesel Fire Pump (DFP) Unit 1.00
Kapasitas : 500 GPM
Head : 85 mka
Speed : 2900 rpm
Type : Centrifugal
& suction c/w Fuel Tank
2 Jockey Pump (JP) Unit 1.00
Kapasitas : 25 GPM
Head : 90 mka
Speed : 2900 rpm
PI : 5,5 KW/380V/50Hz/3Ph
Type : Vertical Multi
Stage Pump
3 Diesel Fire Pump Controller set
4 Jockey Pump Controller set

5 Gate Valve
- dia. 150 mm bh 3.00
- dia. 50 mm bh 2.00
- dia. 25 mm bh 1.00

HAL-11
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

6 Strainer
- dia. 150 mm bh 1.00
- dia. 50 mm bh 1.00
7 Check Valve
- dia. 150 mm bh 1.00
- dia. 50 mm bh 1.00
8 Flexible Joint
- dia. 150 mm bh 2.00
- dia. 50 mm bh 2.00
9 Foot Valve
- dia. 150 mm bh 1.00
- dia. 50 mm bh 1.00
10 - Savety valve dia 100 bh 1.00
11 - Flow Meter (FM) dia 100 bh 2.00
12 - Automatic Air Vent dia 25 bh 1.00
12 - Pressure Gauge bh 2.00
14 - Pressure Switch bh 1.00
15 - Pipa BSP Sch dia. 200 ( pipa header ) set 1.00
16 Pemipaan area pompa
Pipa Sch. 40 ASTM A-120 (warna Putih )
- Dari Pompa ke Ground Tank (dia 150) m 6.00
- Dari Pompa ke Ground Tank (dia 100) m 6.00
- Dari Pompa ke Ground Tank (dia 50) m 6.00

a.1. INSTALASI PEMIPAAN HYDRANT


1 SITE PLAN
Pemipaan BSP Sch. 40
(Incl.Fitting & All Accessories)
- dia. 150 mm (dari Header ) m 20.00
###
- dia. 100 mm m 220.50
###
- Out Hydrant Box set 3.00
- Siamese Connection (SMC) bh 1.00
- Hydrant Pillar (HP) bh 3.00
Gate Valve
- dia. 100 mm bh 3.00
Check Valve
- dia. 100 mm bh 1.00
Pit Valve
- ukuran 500 x 500 mm bh 3.00
- ukuran 1000 x 500 mm bh 1.00
Fire Extinguisher Tabung Cat Oven sesuai SPEK & Skedul :
- Type CO2 Class 5 kg Seamless, c/w support bh 1.00

b. MATERIAL BANTU lot 1.00


c. TESTING COMMISSIONING lot 1.00

III PENYAMBUNGAN DAYA PLN

- BP ( Biaya penyambungan ) va 240,000.00

HAL-12
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART

No. URAIAN PEKERJAAN SAT VOL

- UJL ( UANG Jaminan Langanan ) va 240,000.00

IV PEKERJAAN INSTALASI KABEL FEEDER


Kabel Distribusi Daya dari Panel Pompa - Air Bersih
- NYY 4 x 4 mm2 ke LP-1 m' 10.00
- NYY 4 x 4 mm2 ke LP-2 m' 10.00

Kabel Distribusi Daya dari Panel Pompa - Kebakaran


- FRC 4 x 4 mm2 + NYA 4 mm2 ke PC Jockey Pump m' 10.00
- FRC 3 x 2.5 mm2 ke PC Diesel Fire Pump m' 10.00
- FRC 3 x 2.5 mm2 ke Control m' 8.00

- Proteksi Kabel dengan Pipa Gip Dia 100 m' 20.00


Pengadaan Pipa Gip Dia 100, termasuk galian dan material bantu lainya

- Material Bantu lot 1.00


- Testing & Commissioning lot 1.00

HAL-13
ANALISA HARGA SATUAN

KODE ANALISA : A.005


JENIS PEKERJAAN : Pengukuran dan pembersihan lokasi
SATUAN PEMBAYARAN : m¹

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

4 PEMBANTU MEKANIK Org / hr 1.00 70,000.00 70,000.00

JUMLAH HARGA TENAGA 70,000.00

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN
1 Alat ukur meteran /avo bh 1.00 - -

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 70,000.00


70,000.00
B.001 Penambahan oli pelumas slidiing
Bahan An. SNI ( Revisi ) 6.12.1
1.000 ltr Oli Pelumas SAE 90 merk Pertamina @ Rp. 70,000 = Rp 70,000.00
-
Sub total : = Rp 70,000.00
Upah An. SNI ( Revisi ) 6.12.2
0.050 Oh TENAGA AHLI @ Rp. 450,000 = Rp 22,500.00
1.000 Oh PEMBANTU MEKANIK @ Rp. 70,000 = Rp 70,000.00

Sub total : = Rp 92,500.00

Alat 1 bh Corong @ Rp. - = Rp

Total upah+bahan : = Rp 162,500.00


162,500.00

B.002 Pekerjaan wire rope regrease Spraying


Bahan An. SNI ( Revisi ) 6.11.1
10.000 klng Wire Rope Grease spray 500 ml merk YAC @ Rp. 360,000 = Rp 3,600,000.00
-
Sub total : = Rp 3,600,000.00
Upah An. SNI ( Revisi ) 6.11.2
1.000 Oh PEMBANTU MEKANIK @ Rp. 70,000 = Rp 70,000.00
0.050 Oh TENAGA AHLI @ Rp. 450,000 = Rp 22,500.00

Sub total : = Rp 92,500.00

Total upah+bahan : = Rp 3,692,500.00


3,692,500.00

B.003 Pekerjaan regreasing Sliding door


Bahan An. SNI ( Revisi ) 6.10.1
10.000 kg Bearing grase merk Timken 2 Can @ Rp. 36,000 = Rp 360,000.00
-
Sub total : = Rp 360,000.00
Upah An. SNI ( Revisi ) 6.9.2
1.000 Oh PEMBANTU MEKANIK @ Rp. 70,000 = Rp 70,000.00
0.050 Oh TENAGA AHLI @ Rp. 450,000 = Rp 22,500.00

Sub total : = Rp 92,500.00

Total upah+bahan : = Rp 452,500.00


452,500.00
B.004 Cleaning unit sangkar dan panel
bahan
9.000 klng Silicon Lubricant Spray 30 merk WD Rp 90,000 = Rp 810,000.00
9.000 klng Contact Cleaner 300ml merk YAC Rp 190,000 = Rp 1,710,000.00
10.000 ltr Gasolin pertalite Rp 7,800 = Rp 78,000.00
Sub total : = Rp 2,598,000.00
Upah An. SNI ( Revisi ) 6.15.2
1.000 Oh PEMBANTU MEKANIK @ Rp. 70,000 = Rp 70,000.00
1.990 Oh TENAGA AHLI @ Rp. 450,000 = Rp 895,500.00

-
Sub total : = Rp 965,500.00

alat An. SNI ( Revisi ) 6.15.2

4.000 kg Kain majun @ Rp. 17,500 = Rp 70,000.00


2.000 bh Kuas @ Rp. 20,000 = Rp 40,000.00

Sub total : = Rp 110,000.00

Total upah+bahan : = Rp 3,673,500.00


3,673,500.00

B.005 Pekerjaan regreasing bearing set


Bahan An. SNI ( Revisi ) 6.35.1
10.00 kg Bearing grase merk Timken 2 Can @ Rp. 36,000 Rp 360,000.00
9.00 klng Silicon Lubricant Spray 30 merk WD @ Rp. 90,000 Rp 810,000.00
Sub total : bahan Rp 1,170,000.00

Upah An. SNI ( Revisi ) 6.35.2


1.000 Oh PEMBANTU MEKANIK @ Rp. 70,000 = Rp 70,000.00
1.000 Oh TENAGA AHLI @ Rp. 450,000 = Rp 450,000.00

Sub total : = Rp 520,000.00

Alat 3.000 unit grease gun @ Rp. 40,000 = Rp 120,000.00


4.000 kg Kain majun @ Rp. 17,500 = Rp 70,000.00
2.000 bh Kuas 0 20,000 - - 40,000.00
Sub total : Rp 230,000.00

Total upah+bahan : = Rp 1,920,000.00


1,920,000.00

B.006 Pekerjaan setting braking stop lift


Bahan An. SNI ( Revisi ) 6.35.1

9.000 kg Bearing grase merk Timken 2 Can @ Rp. 36,000 Rp 324,000.00


7.000 kg Compond @ Rp. 330,000 Rp 2,310,000.00
7.000 kg Clear @ Rp. 280,000 Rp 1,960,000.00
6.000 klng Contact Cleaner 300ml merk YAC @ Rp. 190,000 Rp 1,140,000.00
5.000 klng Silicon Lubricant Spray 30 merk WD @ Rp. 90,000 Rp 450,000.00
-
Sub total : bahan jumlah 6,184,000.00
Upah An. SNI ( Revisi ) 6.35.2
1.000 Oh PEMBANTU MEKANIK @ Rp. 70,000 = Rp 70,000.00
1.000 Oh TENAGA AHLI @ Rp. 450,000 = Rp 450,000.00

Sub total : = Rp 520,000.00

Total upah+bahan : = Rp 6,704,000.00


6,704,000.00

B.007 0
Bahan An. SNI ( Revisi ) 6.35.1
1.000 bh lampu lift @ Rp. 175,000 = Rp 175,000.00
= Rp -
Sub total : = Rp 175,000.00
Upah An. SNI ( Revisi ) 6.35.2
1.000 Oh PEMBANTU MEKANIK @ Rp. 70,000 = Rp 70,000.00
1.000 Oh TENAGA AHLI @ Rp. 450,000 = Rp 450,000.00

Sub total : = Rp 520,000.00

Total upah+bahan : = Rp 695,000.00


695,000.00