JADWAL WAKTU PELAKSANAAN

180 HARI
Nama Pekerjaan : Lanjutan Rekonstruksi Jalan Sp. Jln Nas Jemb Sihapilis-Sp. Jln Nas Tanjungan Kec Nainggolan (DAK) KALENDER
Lokasi : Kec. Nainggolan Kab. Samosir
Tahun Anggaran : 2022

WAKTU PELAKSANAAN 180 HARI KALENDER


HARI KE-
BOBOT
SESUAI 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
NO URAIAN PEKERJAAN SATUAN VOLUME KET.
KONTRAK 11-Apr-22 18-Apr-22 25-Apr-22 02-May-22 09-May-22 16-May-22 23-May-22 30-May-22 06-Jun-22 13-Jun-22 20-Jun-22 27-Jun-22 04-Jul-22 11-Jul-22 18-Jul-22 25-Jul-22 01-Aug-22 08-Aug-22 15-Aug-22 22-Aug-22 29-Aug-22 05-Sep-22 12-Sep-22 19-Sep-22 26-Sep-22 03-Oct-22
/ SPK (%)
S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D
17-Apr-22 24-Apr-22 01-May-22 08-May-22 15-May-22 22-May-22 29-May-22 05-Jun-22 12-Jun-22 19-Jun-22 26-Jun-22 03-Jul-22 10-Jul-22 17-Jul-22 24-Jul-22 31-Jul-22 07-Aug-22 14-Aug-22 21-Aug-22 28-Aug-22 04-Sep-22 11-Sep-22 18-Sep-22 25-Sep-22 02-Oct-22 07-Oct-22

I. DEVISI 1 UMUM 1,020% 0,434% 0,434% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006%

1 Mobilisasi Ls 1,000 0,869% 0,434% 0,434%


2 Management dan Keselamatan Lalu Lintas Ls 1,000 0,010% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000%
3 Keselamatan dan Kesesatahan Kerja Ls 1,000 0,142% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006% 0,006%

II. DEVISI 2 DRAINASE 4,124% 0,000% 0,000% 0,837% 0,938% 0,938% 0,938% 0,472% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000%

1 Galian Untuk Selokan Drainase dan Saluran Air M3 626,280 0,265% 0,265%
2 Pasangan Batu Dengan Mortar M3 277,030 3,859% 0,572% 0,938% 0,938% 0,938% 0,472%

III. DEVISI 3 PEKERJAAN TANAH DAN GEOSINTETIK 2,343% 0,000% 0,000% 0,000% 0,146% 0,146% 0,146% 0,063% 0,463% 0,660% 0,660% 0,060% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000%

1 Galian Biasa M3 1.709,300 0,437% 0,146% 0,146% 0,146%


2 Timbunan Pilihan dari Sumber Galian M3 168,500 0,525% 0,063% 0,463%
3 Penyiapan Badan Jalan M2 10.110,000 1,381% 0,660% 0,660% 0,060%

IV. DEVISI 5 PERKERASAN BERBUTIR 33,923% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 2,592% 3,258% 3,746% 4,043% 4,197% 4,358% 4,377% 4,377% 2,975% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000%

1 Lapis Pondasi Agregat Kelas A M3 2.022,000 24,298% 2,592% 3,258% 2,371% 2,668% 3,361% 4,344% 4,302% 1,402%
2 Lapis Pondasi Agregat Kelas B M3 842,500 9,625% 1,375% 1,375% 0,836% 0,014% 0,075% 2,975% 2,975%

V. DEVISI 6 PERKERASAN ASPAL 32,462% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 2,087% 5,062% 5,062% 5,062% 5,062% 5,062% 5,062% 0,000% 0,000% 0,000%

1 Lapis Resap Pengikat - Aspal Cair (Emulsi) Liter 10.784,000 2,548% 0,274% 2,274%
2 Laston Lapis Aus (AC-WC) Ton 1.529,980 29,631% 1,813% 2,788% 5,062% 5,062% 5,062% 5,062% 4,779%
3 Bahan Anti Pengelupasan Kg 275,400 0,283% 0,283%

VI. DEVISI 7 STRUKTUR 24,778% 0,000% 0,000% 0,000% 0,000% 4,154% 4,154% 4,703% 4,775% 1,986% 1,319% 1,432% 1,194% 1,041% 0,020% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000%

1 Beton Struktur Fc'20 Mpa M3 83,850 3,064% 1,021% 1,021% 1,021%


2 Beton Fc'15 Mpa M3 450,600 10,039% 2,673% 3,803% 1,891% 1,141% 0,391% 0,141%
3 Beton Fc'10 Mpa M3 0,600 0,013% 0,013%
4 Baja Tulangan Polos - BJTP 280 Kg 4.490,290 1,467% 0,293% 0,293% 0,511% 0,293% 0,076%
5 Pasangan Batu M3 697,460 10,195% 3,861% 3,861% 1,520% 0,679% 0,020% 0,179% 0,020% 0,020% 0,020% 0,020%

VII. DEVISI 9 PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN 0,571% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,285% 0,285% 0,000%

1 Marka Jalan Termoplastik M2 161,760 0,514% 0,257% 0,257%


2 Rambu Jalan Tunggal dengan Pemantul Engineering Grade Bh 5,000 0,057% 0,028% 0,028%

VIII. DEVISI 10 PEKERJAAN PEMELIHARAAN KINERJA 0,779% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,260% 0,260% 0,260%

1 Perbaikan Lapis Pondasi Agregat Kelas B M3 108,000 0,779% 0,260% 0,260% 0,260%

RENCANA : 100,000% 0,434% 0,434% 0,844% 1,090% 5,244% 5,244% 5,244% 5,244% 5,244% 5,244% 5,244% 5,244% 5,244% 4,384% 4,384% 4,384% 5,069% 5,069% 5,069% 5,069% 5,069% 5,069% 5,069% 0,551% 0,551% 0,265%

KOMULATIF RENCANA : 0,434% 0,869% 1,712% 2,803% 8,047% 13,291% 18,535% 23,779% 29,023% 34,268% 39,512% 44,756% 50,000% 54,384% 58,767% 63,151% 68,219% 73,288% 78,357% 83,426% 88,495% 93,563% 98,632% 99,183% 99,735% 100,000%

REALISASI :

KOMULATIF REALISASI :

Dibuat Oleh :
PENYEDIA JASA
PT. SANGBUMA GARUDA PERSADA

Riko Aritonang, ST
Manager Lapangan

Page 1 of 3
SCHEDULE MATERIAL ON-SITE
180 HARI
Nama Pekerjaan : Lanjutan Rekonstruksi Jalan Sp. Jln Nas Jemb Sihapilis-Sp. Jln Nas Tanjungan Kec Nainggolan (DAK) KALENDER
Lokasi : Kec. Nainggolan Kab. Samosir
Tahun Anggaran : 2022

WAKTU PELAKSANAAN 180 HARI KALENDER

MINGGU KE-

ESTIMASI 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
NO JENIS BAHAN / MATERIAL SATUAN KEBUTUHAN KET.
VOLUME 11/04/22 18/04/22 25/04/22 02/05/22 09/05/22 16/05/22 23/05/22 30/05/22 06/06/22 13/06/22 20/06/22 27/06/22 04/07/22 11/07/22 18/07/22 25/07/22 01/08/22 08/08/22 15/08/22 22/08/22 29/08/22 05/09/22 12/09/22 19/09/22 26/09/22 03/10/22

S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D

17/04/22 24/04/22 01/05/22 08/05/22 15/05/22 22/05/22 29/05/22 05/06/22 12/06/22 19/06/22 26/06/22 03/07/22 10/07/22 17/07/22 24/07/22 31/07/22 07/08/22 14/08/22 21/08/22 28/08/22 04/09/22 11/09/22 18/09/22 25/09/22 02/10/22 07/10/22

1 Agregat A M3 2.544,908

2 Agregat B M3 1.168,378

3 Agregat Kasar / Batu Split M3 470,833

4 Aspal Kg 103.450,721

5 Bahan Timbunan Pilihan M3 187,035

6 Baja Tulangan (Polos) U24 Kg 4.490,290

7 Batu Kali M3 974,490

8 Cat Marka Thermoplastic Kg 315,432

9 Glass Bead Kg 72,792

10 Kawat Beton Kg 11,226

11 Kayu Perancah M3 61,860

12 Kerosene Liter 3.998,707

13 Lolos screen2 ukuran ( 0 - 5) M3 539,040

14 Lolos screen2 ukuran ( 9.5 - 19,0) M3 455,697

15 Minyak Pencair (Thinner) Liter 169,848

16 Paku Kg 494,880

17 Pasir Pasang M3 387,271

18 Pasir beton M3 272,057

19 Semen 40 Kg Zak 8.269,218

Dibuat Oleh :

PENYEDIA JASA

PT. SANGBUMA GARUDA PERSADA

Riko Aritonang, ST

Manager Lapangan

Page 2 of 3
SCHEDULE TENAGA KERJA ON-SITE
180 HARI
Nama Pekerjaan : Lanjutan Rekonstruksi Jalan Sp. Jln Nas Jemb Sihapilis-Sp. Jln Nas Tanjungan Kec Nainggolan (DAK) KALENDER
Lokasi : Kec. Nainggolan Kab. Samosir
Tahun Anggaran : 2022

WAKTU PELAKSANAAN 180 HARI KALENDER

MINGGU KE-

JUMLAH 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
NO JENIS TENAGA KERJA SATUAN TENAGA KET.
KERJA 11/04/22 18/04/22 25/04/22 02/05/22 09/05/22 16/05/22 23/05/22 30/05/22 06/06/22 13/06/22 20/06/22 27/06/22 04/07/22 11/07/22 18/07/22 25/07/22 01/08/22 08/08/22 15/08/22 22/08/22 29/08/22 05/09/22 12/09/22 19/09/22 26/09/22 03/10/22

S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D

17/04/22 24/04/22 01/05/22 08/05/22 15/05/22 22/05/22 29/05/22 05/06/22 12/06/22 19/06/22 26/06/22 03/07/22 10/07/22 17/07/22 24/07/22 31/07/22 07/08/22 14/08/22 21/08/22 28/08/22 04/09/22 11/09/22 18/09/22 25/09/22 02/10/22 07/10/22

I. TENAGA KERJA PROFESIONAL

1 Manager Lapangan Orang 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2 Pelaksana Lapangan Orang 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

3 Tenaga Ahli K3 Konstruksi Orang 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4 Surveyor / Juru Ukur Orang 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

5 Logistik / Keuangan Orang 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

KURVA QUANTITAS
II. TENAGA KERJA SUBPROFESIONAL MAN POWER
1 Tukang Gali Orang 20 5 20 20 20

2 Tukang Batu Orang 18 10 10 10 10 10 0 0 0 18 18 18 18 18 18 18

3 Tukang Besi Orang 3 3 3 3 3 3

4 Tukang Kayu Orang 2 2 2 2 2 2

5 Tukang Cor Beton Orang 6 6 6 6 6

6 Tukang Marka Jalan Orang 3 3 3

7 Operator Orang 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

8 Mekanik Orang 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

9 Pekerja / Helper Orang 20 4 10 10 10 10 10 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 5 5 5

TOTAL : Orang 81 3 13 34 49 49 49 34 34 34 34 52 53 53 53 53 47 47 29 29 29 29 29 29 17 17 14

Dibuat Oleh :

PENYEDIA JASA

PT. SANGBUMA GARUDA PERSADA

Riko Aritonang, ST

Manager Lapangan