DAFTAR HARGA UPAH & BAHAN

NO URAIAN UPAH DAN BAHAN HARGA SATUAN SATUAN


(Rp)

A. HARGA SATUAN UPAH :


1 Kepala tukang 100,000.00 Oh
2 Tukang kayu 92,000.00 Oh
3 Tukang batu 92,000.00 Oh
4 Tukang besi 92,000.00 Oh
5 Tukang cat 92,000.00 Oh
6 Mandor 92,000.00 Oh
7 Pekerja 70,000.00 Oh

B. HARGA SATUAN BAHAN :


I. BAHAN PEREKAT, BATU & AGREGAT
1 Semen portland (PC) 1,300.00 Kg
2 Semen putih 3,375.00 Kg
3 Semen nat keramik 10,000.00 Kg
4 Pasir Pasang (PP) 160,000.00 m3
5 Pasir Beton (PB) 160,000.00 m3
6 Pasir Urug (PU) 150,000.00 m3
7 Batu kali uk. 15/20 cm 285,000.00 m3
8 Koral Beton uk. 2-3 cm 280,000.00 m3
9 Batu bata lobang 8x8x16 cm 860.00 Bh
10 Besi Beton Polos 10,000.00 Kg
11 Besi hollo Galvalum uk. 40.40 (Rangka Plafond) 5,500.00 m'
12 Besi hollo Galvalum uk. 20.40 (Rangka Plafond) 4,500.00 m'
13 Kawat pengikat/beton 20,000.00 Kg
14 Besi Strip 15,000.00 Kg
15 Kayu Papan kelas II Jenis Merawan/Kulim 5,200,000.00 m3
16 Kayu Balok kelas II Jenis Merawan/Kulim 5,200,000.00 m3
17 Kayu Papan kelas III Jenis Meranti 3,750,000.00 m3
18 Kayu Balok kelas III Jenis Meranti 3,750,000.00 m3
19 Kayu Papan kelas IV Jenis Racuk 2,000,000.00 m3
20 Kayu Balok kelas IV Jenis Racuk 2,000,000.00 m3
21 kayu doken/bulat dia 6-8(pjg.4 m) 12,000.00 Btg
22 kayu doken/bulat dia 8-12(pjg.4 m) 24,000.00 Btg
23 Minyak Bekisting 10,700.00 Ltr
24 Air kerja 62.50 Ltr
25 Zincalume Truss TASO C-75.80 14,500.00 m'
26 Zincalume Truss TASO C-75.75 13,000.00 m'
27 Zincalume Truss TASO TR-32.45 6,000.00 m'
28 Velery Gutter Talang Jurai 39,000.00 m'
29 Screw Truss 12x 3/4 165.00 Bh
30 Dynabolt 1,000.00 Bh
31 Atap Genteng Metal Biasa ex Sakura roof/setara 48,600.00 kpg/m2
32 Nok Genteng Metal l=90 cm 29,000.00 Kpg
33 Seng Talang Alkan 0,35 mm 62,000.00 m'
34 Superplank uk. 9.200 cm 18,852.46 m'
NO URAIAN UPAH DAN BAHAN HARGA SATUAN SATUAN
(Rp)

35 Plywood 240.120.4 mm 65,000.00 Kpg


36 Plywood 240.120.6 mm 80,000.00 Kpg
37 Plywood 240.120.9 mm 135,000.00 Kpg
38 Plywood 240.120.12 mm 165,000.00 Kpg
39 Plywood 240.120.15 mm 210,000.00 Kpg
40 Kalsiboard 3,5 mm 59,000.00 Kpg
41 List Profil Kayu A4 4,473.68 m'
42 List Profil Kayu A3 3,684.21 m'
43 Keramik Putih uk. 30x30 cm Permukaan Halus 4,750.00 Bh
44 Paku biasa 18,000.00 Kg
45 Paku Genteng Metal 27,000.00 Kg
46 Paku Kalsiboard 25,000.00 Kg
47 Paku skrup 400.00 Bh
48 Paku seng 25,000.00 Kg
49 Paku plywood 25,000.00 Kg
50 Denabolt 2,500.00 Bh
51 Lem Kayu 18,000.00 Kg
52 Kaca Polos 5 mm Asahimas 95,000.00 m2
53 Kaca Reiben 5 mm Asahimas 120,000.00 m2
54 Kaca Buram es 5 mm 120,000.00 m2
55 Sealent 25,000.00 Tube
56 Kunci Tanam Mutu Sedang 165,000.00 Bh
57 Kunci Body Pelor Mutu Sedang 150,000.00 Bh
58 Door Holder p=± 30 cm ex Gradino/Solid atau setara 185,000.00 Bh
59 Engsel pintu Steinless steel uk. 4x3" tebal 3 mm 15,000.00 Bh
60 Engsel jendela Steinless steel uk. 3x2,5" tebal 3 mm 12,500.00 Bh
61 Grendel Tanam (Expanoulet) 85,000.00 Bh
62 Grendel uk. 10" Steinless steel 30,000.00 Bh
63 Grendel uk. 3" Steinless steel 12,000.00 Bh
64 Grendel uk. 2" Steinless steel 10,500.00 Bh
65 Hak angin/kait angin 10,500.00 Bh
66 Handle/tarikan Jendela 12,000.00 Bh
67 Fuse Box Presto 4 Group 35,000.00 Set
68 MCB 6 A, 4,5kA 1 phasa 55,000.00 Bh
69 MCB 4 A, 4,5kA 1 phasa 55,000.00 Bh
70 Lampu Kap Simbat + TLD 1x36 Watt Philips 120,000.00 Set
71 Philips Essential 14 Watt 33,000.00 Bh
72 Philips Essential 18 Watt 39,000.00 Bh
73 Kabel NYM 2x2,5 mm Praba 9,000.00 m'
74 Kabel NYM 3x2,5 mm Praba 11,400.00 m'
75 Saklar Tunggal Clipsal/Panasonic 15,000.00 Bh
76 Saklar Ganda Clipsal/Panasonic 17,000.00 Bh
77 Stop Kontak Clipsal / Panasonic 15,000.00 Bh
78 Amplas Niken 6,000.00 Lbr
79 Cat dasar Kayu 32,000.00 Kg
80 Cat menie kayu Nippon 35,000.00 Kg
81 Cat menie besi Nippon 35,000.00 Kg
82 Cat Dasar Tembok / Sealer 25,000.00 Kg
83 Cat tembok Exterior Ex Catylac/setara 29,920.00 Kg
84 Cat tembok Interior Ex Catylac/Setara 19,920.00 Kg
85 Cat Kayu Penutup 45,000.00 Kg
86 Cat Besi Penutup 45,000.00 Kg
87 Plamir tembok Setara Kingkong 6,000.00 Kg
88 Plamur kayu 35,000.00 Kg
NO URAIAN UPAH DAN BAHAN HARGA SATUAN SATUAN
(Rp)

89 Politur 76,500.00 Ltr


90 Dempul kayu jadi 7,200.00 Kg
91 Thiner Cobra 28,000.00 Kg
92 Kuas Cat uk. 1" 5,000.00 Bh
DAFTAR HARGA PERABOT

HARGA
NO NAMA PERABOT KODE SAT SATUAN
(Rp)
1 Meja Siswa Tunggal M.01 Bh 466,000.00
2 Meja Guru M.07 Bh 888,000.00
3 Kursi Siswa K.01 Bh 264,000.00
4 Kursi Guru K.05 Bh 397,000.00
5 Papan Tulis P.01 Bh 650,000.00
6 Meja Baca Lesehan M.05 Bh 610,000.00
7 Rak Buku 1 muka R.02 Bh 1,970,000.00
8 Rak Buku 2 muka R.03 Bh 3,570,000.00
9 Lemari Simpan L.05 Bh 1,500,000.00
ANALISA HARGA SATUNAN KODE

MEJA SINGLE SISWA SMP M-01


ANALISA

PROSES : ANGGAPAN :

JUMLAH UPAH BIAYA SUB TOTAL


PEKERJA VOL HARI KODE
(Hari/Org) (Rp/Org/hari) (Rp) (Rp)
Pekerja 1.0000 1 1.000 70,000.00 70,000.00
Tukang 1.0000 1 1.000 92,000.00 92,000.00
Kepala Tukang 0.1000 1 0.100 100,000.00 10,000.00
Mandor lapangan 0.0250 1 0.025 92,000.00 2,300.00
PEKERJA 174,300.00
VOL HARGA SAT BIAYA SUB TOTAL
MATERIAL JLM KODE
SATUAN (Rp/unit) (Rp) (Rp)
Kayu 3/5 cm kls II 0.0114 m3 5,200,000.00 59,280.00
Plywood tbl. 15 mm 0.7560 m2 210,000.00 158,760.00
Paku biasa 2 - 3" 0.1500 kg 18,000.00 2,700.00
Lem kayu 0.2500 kg 18,000.00 4,500.00
Plamur 0.2528 kg 35,000.00 8,846.25
Politur 0.6268 ltr 76,500.00 47,951.73
Amplas 1.6850 lbr 6,000.00 10,110.00
MATERIAL 292,147.98

JUMLAH 466,447.98
PEMBULATAN 466,000.00

VOLUME/QUANTITY 1.0000 SATUAN BUAH HRG SATUAN 466,000.00

ANALISA HARGA SATUAN KODE

KURSI SISWA SMP K-01


ANALISA

PROSES : ANGGAPAN :

JUMLAH UPAH BIAYA SUB TOTAL


PEKERJA VOL HARI KODE
(Hari/Org) (Rp/Org/hari) (Rp) (Rp)
Pekerja 0.7500 1 0.750 70,000.00 52,500.00
Tukang 1.0000 1 1.000 92,000.00 92,000.00
Kepala Tukang 0.1000 1 0.100 100,000.00 10,000.00
Mandor lapangan 0.0250 1 0.025 92,000.00 2,300.00
PEKERJA 156,800.00
VOL HARGA SAT BIAYA SUB TOTAL
MATERIAL JLM KODE
SATUAN (Rp/unit) (Rp) (Rp)
Kayu 3/5 cm kls II 0.0059 m3 5,200,000.00 30,680.00
Kayu 3/4 cm kls II 0.0014 m3 5,200,000.00 7,280.00
Papan 2/20 kls II 0.0034 m3 5,200,000.00 17,680.00
Papan 2/12 kls II 0.0008 m3 5,200,000.00 4,160.00
Paku biasa 2 - 3" 0.1280 kg 18,000.00 2,304.00
Lem kayu 0.2500 kg 18,000.00 4,500.00
Plamur 0.1563 kg 35,000.00 5,470.50
Politur 0.3876 ltr 76,500.00 29,653.24
Amplas 1.0420 lbr 6,000.00 6,252.00
MATERIAL 107,979.74

JUMLAH 264,779.74
PEMBULATAN 264,000.00

VOLUME/QUANTITY 1.0000 SATUAN BUAH HRG SATUAN 264,000.00

ANALISA HARGA SATUNAN KODE

MEJA BACA KELOMPOK M-05


ANALISA
PROSES : ANGGAPAN :

JUMLAH UPAH BIAYA SUB TOTAL


PEKERJA VOL HARI KODE
(Hari/Org) (Rp/Org/hari) (Rp) (Rp)
Pekerja 1.0000 1 1.000 70,000.00 70,000.00
Tukang 1.0000 1 1.000 92,000.00 92,000.00
Kepala Tukang 0.1000 1 0.100 100,000.00 10,000.00
Mandor lapangan 0.0250 1 0.025 92,000.00 2,300.00
PEKERJA 174,300.00
VOL HARGA SAT BIAYA SUB TOTAL
MATERIAL JLM KODE
SATUAN (Rp/unit) (Rp) (Rp)
Kayu 5/5 cm kls II 0.0068 m3 5,200,000.00 35,360.00
Kayu 3/5 cm kls II 0.0135 m3 5,200,000.00 70,200.00
Plywood 15 mm 1.0290 m2 210,000.00 216,090.00
Paku biasa 0.5 - 1" 0.1250 kg 25,000.00 3,125.00
Paku biasa 2 - 3" 0.1500 kg 18,000.00 2,700.00
Lem kayu 0.2500 kg 18,000.00 4,500.00
Plamur 0.4259 kg 35,000.00 14,905.80
Politur 1.0562 ltr 76,500.00 80,797.95
Amplas 1.8455 lbr 6,000.00 11,072.88
MATERIAL 438,751.63

JUMLAH 613,051.63
PEMBULATAN 610,000.00

VOLUME/QUANTITY 1.0000 SATUAN BUAH HRG SATUAN 610,000.00

ANALISA HARGA SATUNAN KODE

RAK BUKU 1 MUKA R-02


ANALISA

PROSES : ANGGAPAN :

JUMLAH UPAH BIAYA SUB TOTAL


PEKERJA VOL HARI KODE
(Hari/Org) (Rp/Org/hari) (Rp) (Rp)

Pekerja 1.0000 1 1.000 70,000.00 70,000.00


Tukang 2.2270 1 2.227 92,000.00 204,884.00
Kepala Tukang 0.2500 1 0.250 100,000.00 25,000.00
Mandor lapangan 0.0250 1 0.025 92,000.00 2,300.00
PEKERJA 302,184.00
VOL HARGA SAT BIAYA SUB TOTAL
MATERIAL JLM KODE
SATUAN (Rp/unit) (Rp) (Rp)
Plywood 12 mm 5.9573 m2 165,000.00 982,954.50
Plywood 4 mm 2.2680 m2 65,000.00 147,420.00
Paku biasa 2 - 3" 0.2000 kg 18,000.00 3,600.00
Lem kayu 0.2500 kg 18,000.00 4,500.00
Plamur 2.2338 kg 35,000.00 78,181.43
Politur 5.5397 ltr 76,500.00 423,788.00
Amplas 6.0000 lbr 6,000.00 36,000.00
MATERIAL 1,676,443.93

JUMLAH 1,978,627.93
PEMBULATAN 1,970,000.00

VOLUME/QUANTITY 1.0000 SATUAN BUAH HRG SATUAN 1,970,000.00

ANALISA HARGA SATUNAN KODE

RAK BUKU 2 MUKA R-03


ANALISA

PROSES : ANGGAPAN :
JUMLAH UPAH BIAYA SUB TOTAL
PEKERJA VOL HARI KODE
(Hari/Org) (Rp/Org/hari) (Rp) (Rp)
Pekerja 1.4000 1 1.400 70,000.00 98,000.00
Tukang 3.1178 1 3.118 92,000.00 286,837.60
Kepala Tukang 0.3500 1 0.350 100,000.00 35,000.00
Mandor lapangan 0.0350 1 0.035 92,000.00 3,220.00
PEKERJA 423,057.60
VOL HARGA SAT BIAYA SUB TOTAL
MATERIAL JLM KODE
SATUAN (Rp/unit) (Rp) (Rp)
Plywood 12 mm 14.1826 m2 165,000.00 2,340,129.00
Paku biasa 2 - 3" 0.3000 kg 18,000.00 5,400.00
Lem kayu 0.3500 kg 18,000.00 6,300.00
Plamur 3.3506 kg 35,000.00 117,272.40
Politur 8.3096 ltr 76,500.00 635,683.42
Amplas 8.0000 lbr 6,000.00 48,000.00
MATERIAL 3,152,784.82

JUMLAH 3,575,842.42
PEMBULATAN 3,570,000.00

VOLUME/QUANTITY 1.0000 SATUAN BUAH HRG SATUAN 3,570,000.00

ANALISA HARGA SATUNAN KODE

MEJA GURU M-07


ANALISA

PROSES : ANGGAPAN :
JUMLAH UPAH BIAYA SUB TOTAL
PEKERJA VOL HARI KODE
(Hari/Org) (Rp/Org/hari) (Rp) (Rp)
Pekerja 1.0000 1 L-01 1.000 70,000.00 70,000.00
Tukang 2.0000 1 L-02 2.000 92,000.00 184,000.00
Kepala Tukang 0.5000 1 L-01 0.500 100,000.00 50,000.00
Mandor lapangan 0.0250 1 L-03 0.025 92,000.00 2,300.00
PEKERJA 306,300.00
VOL HARGA SAT BIAYA SUB TOTAL
MATERIAL JLM KODE
SATUAN (Rp/unit) (Rp) (Rp)
Kayu 5/5 cm kls II 0.0105 m3 5,200,000.00 54,600.00
Kayu 3/5 cm kls II 0.0020 m3 5,200,000.00 10,400.00
Kayu 2/15 cm kls II 0.0020 m3 5,200,000.00 10,400.00
Plywood 15 mm 1.3313 m2 210,000.00 279,573.00
Paku biasa 2 - 3" 0.2000 kg 18,000.00 3,600.00
Engsel 2.0000 bh 12,000.00 24,000.00
Handle 2.0000 bh 12,000.00 24,000.00
Kunci 2.0000 bh 15,000.00 30,000.00
Lem kayu 0.5000 kg 18,000.00 9,000.00
Plamur 0.5008 kg 35,000.00 17,528.70
Politur 1.2420 ltr 76,500.00 95,015.57
Amplas 4.0000 lbr 6,000.00 24,000.00
MATERIAL 582,117.27

JUMLAH 888,417.27
PEMBULATAN 888,000.00

VOLUME/QUANTITY 1.0000 SATUAN BUAH HRG SATUAN 888,000.00

ANALISA HARGA SATUNAN KODE

KURSI GURU K.05


ANALISA

PROSES : ANGGAPAN :

JUMLAH UPAH BIAYA SUB TOTAL


PEKERJA VOL HARI KODE
(Hari/Org) (Rp/Org/hari) (Rp) (Rp)

Pekerja 1.0000 1 1.000 70,000.00 70,000.00


Tukang 1.0000 1 1.000 92,000.00 92,000.00
Kepala Tukang 0.1500 1 0.150 100,000.00 15,000.00
Mandor lapangan 0.0250 1 0.025 92,000.00 2,300.00
PEKERJA 179,300.00

VOL HARGA SAT BIAYA SUB TOTAL


MATERIAL JLM KODE
SATUAN (Rp/unit) (Rp) (Rp)

Kayu 3/5 cm kls II 0.0073 m3 5,200,000.00 37,960.00


Kayu 3/4 cm kls II 0.0021 m3 5,200,000.00 10,920.00
Kayu 3/12 cm kls II 0.0011 m3 5,200,000.00 5,720.00
Papan kls II 0.0070 m3 5,200,000.00 36,400.00
Busa lapis kain 40x40 cm 1.0000 ls 75,000.00 75,000.00
Paku biasa 2 - 3" 0.1280 kg 18,000.00 2,304.00
Lem kayu 0.2500 kg 18,000.00 4,500.00
Plamur 0.1784 kg 35,000.00 6,244.88
Politur 0.4425 ltr 76,500.00 33,850.79
Amplas 0.8921 lbr 6,000.00 5,352.75
MATERIAL 218,252.42

JUMLAH 397,552.42
PEMBULATAN 397,000.00

VOLUME/QUANTITY 1.0000 SATUAN BUAH HRG SATUAN 397,000.00


ANALISA BIAYA KONSTRUKSI
LAMPIRAN II ANALISA SEMESTER I TH.2015
PEMERINTAH KOTA PALEMBANG

SATUAN HARGA
NO. URAIAN Harga Jumlah Harga Jumlah Biaya Jumlah
Analisa Satuan Bahan Tenaga Bahan+Tenaga
(Rp) (Rp) (Rp) (Rp)

ANS.DPU.2015.1. 1 M² PEMASANGAN RANGKA ATAP BAJA RINGAN EX TASO


a. Bahan :
1.4880 m' TS C-75.80 14,500.00 21,576.00
2.3230 m' TS C-75.75 13,000.00 30,199.00
5.4000 m' Reng AZ TR-40.50 6,000.00 32,400.00
38.0000 bh Screw 165.00 6,270.00
1.6000 bh Dynabolt 1,000.00 1,600.00
0.1240 m' Velery Gutter Talang Jurai 39,000.00 4,836.00
b. Tenaga :
0.2000 oh Pekerja 70,000.00 14,000.00
0.4500 oh Tukang 92,000.00 41,400.00
0.0100 oh Kepala tukang 100,000.00 1,000.00
0.0500 oh Mandor 92,000.00 4,600.00
Jumlah a+b 96,881.00 61,000.00 157,881.00
c. Overhead & Profit 0% - - -
Jumlah a+b+c 96,881.00 61,000.00 157,881.00

2 1 M' PEMASANGAN KALSIPLANK/SUPERPLANK


a. Bahan :
1.0200 m' Kalsiplank/Superplank 18,852.46 19,229.51
0.1000 kg Paku 25,000.00 2,500.00
b. Tenaga :
0.1000 oh Pekerja 70,000.00 7,000.00
0.2000 oh Tukang 92,000.00 18,400.00
0.0200 oh Kepala tukang 100,000.00 2,000.00
0.0050 oh Mandor 92,000.00 460.00
Jumlah a+b 21,729.51 27,860.00 49,589.51
c. Overhead & Profit 0% - - -
Jumlah a+b+c 21,729.51 27,860.00 49,589.51

4. 1 M² PEMASANGAN DAUN PINTU DAN JENDELA KACA


a. Bahan :
0.0240 m3 Kayu Kls. III 3,750,000.00 90,000.00
0.3000 kg Lem Kayu 18,000.00 5,400.00
1.0000 m2 Kaca Polos 5 mm 95,000.00 95,000.00
b. Tenaga :
0.8000 oh Pekerja 70,000.00 56,000.00
2.4000 oh Tukang 92,000.00 220,800.00
0.2400 oh Kepala tukang 100,000.00 24,000.00
0.0400 oh Mandor 92,000.00 3,680.00
Jumlah a+b 190,400.00 304,480.00 494,880.00
c. Overhead & Profit 0% - - -
Jumlah a+b+c 190,400.00 304,480.00 494,880.00

5. PEMASANGAN 1 TITIK NYALA LAMPU


a. Bahan :
15.0000 m' Kabel NYM 2x2,5 m² 9,000.00 135,000.00
35% Perlengkapan (Conduit, - 47,250.00
Klem, isolasi, T Dus, Mangkok dll)
b. Tenaga :
0.1350 oh Tukang Instalatur 92,000.00 12,420.00
0.0135 oh Kepala tukang 100,000.00 1,350.00
0.0050 oh Mandor 92,000.00 460.00
Jumlah a+b 182,250.00 14,230.00 196,480.00
c. Overhead & Profit 0% - - -
Jumlah a+b+c 182,250.00 14,230.00 196,480.00

6. PEMASANGAN 1 TITIK NYALA STOP KONTACK


a. Bahan :
15.0000 m' Kabel NYM 3x2,5 m² 11,400.00 171,000.00
35% Perlengkapan (Conduit, - 59,850.00
01+022SRC.Doc file
SATUAN HARGA
NO. URAIAN Harga Jumlah Harga Jumlah Biaya Jumlah
Analisa Satuan Bahan Tenaga Bahan+Tenaga
(Rp) (Rp) (Rp) (Rp)

Klem, isolasi, T Dus, Mangkok dll)


b. Tenaga :
0.1350 oh Tukang Instalatur 92,000.00 12,420.00
0.0135 oh Kepala tukang 100,000.00 1,350.00
0.0050 oh Mandor 92,000.00 460.00
Jumlah a+b 230,850.00 14,230.00 245,080.00
c. Overhead & Profit 0% - - -
Jumlah a+b+c 230,850.00 14,230.00 245,080.00

01+022SRC.Doc file
PEDOMAN
Bahan Konstruksi Bangunan Rekayasa Sipil

ANALISA HARGA SATUAN PEKERJAAN


(AHSP)
BIDANG CIPTA KARYA

KEMENTERIAN PEKERJAAN UMUM


A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

A.2.2.1.9 Pembersihan 1 M² lapangan dan perataan


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.1000 70,000.00 7,000.00
Mandor L.04 OH 0.0500 92,000.00 4,600.00
Jumlah Harga Tenaga Kerja 11,600.00
B. BAHAN
-
Jumlah Harga Bahan -
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 11,600.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 11,600.00

A.2.3.1 PEKERJAAN TANAH

A.2.3.1.1. Pengalian 1 M³ tanah biasa sedalam 1 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 0.7500 70,000.00 52,500.00
Mandor L.04 0.0250 92,000.00 2,300.00
Jumlah Harga Tenaga Kerja 54,800.00
B. BAHAN
-
Jumlah Harga Bahan -
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 52,500.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 52,500.00

A.2.3.1.9. Pembuangan 1 M³ tanah sejauh 30 meter


Pengurugan kembali 1 M³ galian dihitung 1/3 kali dari koefisien pekerjaan galian
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.2500 70,000.00 17,500.00
Mandor L.04 OH 0.0083 92,000.00 766.67
Jumlah Harga Tenaga Kerja 18,266.67
B. BAHAN
-
Jumlah Harga Bahan -
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 18,266.67


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 18,266.67
A.2.3.1.11. Pengurugan 1 M³ dengan pasir urug
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.3000 70,000.00 21,000.00
Mandor L.04 OH 0.0100 92,000.00 920.00
Jumlah Harga Tenaga Kerja 21,920.00
B. BAHAN
Pasir urug 1.2000 150,000.00 180,000.00
Jumlah Harga Bahan 180,000.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 201,920.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 201,920.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.12. Pemasangan 1 M³ Pondasi Batu Bata lobang uk. 8x8x16 cm
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 2.0250 70,000.00 141,750.00
Tukang Batu L.02 OH 0.6750 92,000.00 62,100.00
Kepala Tukang L.03 OH 0.0680 100,000.00 6,800.00
Mandor L.04 OH 0.1010 92,000.00 9,292.00
Jumlah Harga Tenaga Kerja 219,942.00
B. BAHAN
Batu bata 8x8x16 cm Bh 726.0000 860.00 624,360.00
Semen (PC) Kg 136.9980 1,300.00 178,097.40
Pasir Pasang (PP) M³ 0.4800 160,000.00 76,800.00
Jumlah Harga Bahan 879,257.40
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 1,099,199.40


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 1,099,199.40

A.4.1.1 PEKERJAAN BETON


A.4.1.1.1. Membuat 1 M³ beton mutu f'c = 7.4 Mpa (K 100), slump (12 ± 2) cm, w/c = 0.87
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.6500 70,000.00 115,500.00
Tukang Batu L.02 OH 0.2750 92,000.00 25,300.00
Kepala Tukang L.03 OH 0.0280 100,000.00 2,800.00
Mandor L.04 OH 0.0830 92,000.00 7,636.00
Jumlah Harga Tenaga Kerja 151,236.00
B. BAHAN
Semen Portland Kg 247.0000 1,300.00 321,100.00
Pasir Beton m3 0.6207 160,000.00 99,314.29
Kerikil (Maks 30 mm) m3 0.7400 280,000.00 207,200.00
Air Liter 215.0000 62.50 13,437.50
Jumlah Harga Bahan 641,051.79
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 792,287.79


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 792,287.79

A.4.1.1.2. Membuat 1 M³ beton mutu f'c = 9.8 Mpa (K 125), slump (12 ± 2) cm, w/c = 0.78
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.6500 70,000.00 115,500.00
Tukang Batu L.02 OH 0.2750 92,000.00 25,300.00
Kepala Tukang L.03 OH 0.0280 100,000.00 2,800.00
Mandor L.04 OH 0.0830 92,000.00 7,636.00
Jumlah Harga Tenaga Kerja 151,236.00
B. BAHAN
Semen Portland Kg 276.0000 1,300.00 358,800.00
Pasir Beton Kg 0.5914 160,000.00 94,628.57
Kerikil (Maks 30 mm) Kg 0.7496 280,000.00 209,896.30
Air Liter 215.0000 62.50 13,437.50
Jumlah Harga Bahan 676,762.37
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 827,998.37


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 827,998.37

A.4.1.1.5. Membuat 1 M³ beton mutu f'c = 14.5 Mpa (K 175), slump (12±2) cm, w/c = 0.66
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.6500 70,000.00 115,500.00
Tukang Batu L.02 OH 0.2750 92,000.00 25,300.00
Kepala Tukang L.03 OH 0.0280 100,000.00 2,800.00
Mandor L.04 OH 0.0830 92,000.00 7,636.00
Jumlah Harga Tenaga Kerja 151,236.00
B. BAHAN
Semen Portland Kg 326.0000 1,300.00 423,800.00
Pasir Beton Kg 0.5429 160,000.00 86,857.14
Kerikil (Maks 30 mm) Kg 0.7622 280,000.00 213,422.22
Air Liter 215.0000 62.50 13,437.50
Jumlah Harga Bahan 737,516.86
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 888,752.86


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 888,752.86
A.4.1.1.28. Membuat 1 M³ pondasi beton bertulang (135 kg besi + bekisting)
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 5.3000 70,000.00 371,000.00
Tukang Batu L.02 OH 0.2750 92,000.00 25,300.00
Tukang Kayu L.02 OH 1.3000 92,000.00 119,600.00
Tukang Besi L.02 OH 0.9450 92,000.00 86,940.00
Kepala Tukang L.03 OH 0.2620 100,000.00 26,200.00
Mandor L.04 OH 0.2650 92,000.00 24,380.00
Jumlah Harga Tenaga Kerja 653,420.00
B. BAHAN
Kayu kelas IV M³ 0.2000 2,000,000.00 400,000.00
Paku 5 cm - 12 cm Kg 1.5000 18,000.00 27,000.00
Minyak bekisting Liter 0.4000 10,700.00 4,280.00
Besi beton polos Kg 141.7500 10,000.00 1,417,500.00
Kawat beton Kg 2.0250 20,000.00 40,500.00
Semen Portland Kg 336.0000 1,300.00 436,800.00
Pasir Beton M³ 0.5400 160,000.00 86,400.00
Kerikil (Maks 30 mm) M³ 0.8100 280,000.00 226,800.00
Jumlah Harga Bahan 2,639,280.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 3,292,700.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 3,292,700.00

A.4.1.1.29. Membuat 1 M³ sloof beton bertulang (130 kg besi + bekisting)


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 5.6500 70,000.00 395,500.00
Tukang Batu L.02 OH 0.2750 92,000.00 25,300.00
Tukang Kayu L.02 OH 1.5600 92,000.00 143,520.00
Tukang Besi L.02 OH 0.9100 92,000.00 83,720.00
Kepala Tukang L.03 OH 0.3230 100,000.00 32,300.00
Mandor L.04 OH 0.2830 92,000.00 26,036.00
Jumlah Harga Tenaga Kerja 706,376.00
B. BAHAN
Kayu kelas IV M³ 0.2700 2,000,000.00 540,000.00
Paku 5 cm - 12 cm Kg 2.0000 18,000.00 36,000.00
Minyak bekisting Liter 0.6000 10,700.00 6,420.00
Besi beton polos Kg 136.5000 10,000.00 1,365,000.00
Kawat beton Kg 1.9500 20,000.00 39,000.00
Semen Portland Kg 336.0000 1,300.00 436,800.00
Pasir Beton M³ 0.5400 160,000.00 86,400.00
Kerikil (Maks 30 mm) M³ 0.8100 280,000.00 226,800.00
Jumlah Harga Bahan 2,736,420.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 3,442,796.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 3,442,796.00
A.4.1.1.30. Membuat 1 M³ kolom beton bertulang (145 kg besi + bekisting)
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 7.0500 70,000.00 493,500.00
Tukang Batu L.02 OH 0.2750 92,000.00 25,300.00
Tukang Kayu L.02 OH 1.6500 92,000.00 151,800.00
Tukang Besi L.02 OH 1.0150 92,000.00 93,380.00
Kepala Tukang L.03 OH 0.4030 100,000.00 40,300.00
Mandor L.04 OH 0.3530 92,000.00 32,476.00
Jumlah Harga Tenaga Kerja 836,756.00
B. BAHAN
Kayu papan kelas IV M³ 0.4000 2,000,000.00 800,000.00
Paku 5 cm - 12 cm Kg 4.0000 18,000.00 72,000.00
Minyak bekisting Liter 2.0000 10,700.00 21,400.00
Besi beton polos Kg 152.2500 10,000.00 1,522,500.00
Kawat beton Kg 2.1750 20,000.00 43,500.00
Semen Portland Kg 336.0000 1,300.00 436,800.00
Pasir Beton M³ 0.5400 160,000.00 86,400.00
Kerikil (Maks 30 mm) M³ 0.8100 280,000.00 226,800.00
Kayu kelas IV balok M³ 0.1500 2,000,000.00 300,000.00
Dolken Kayu ф (8-10) cm, Panj 4 m Batang 20.0000 12,000.00 240,000.00
Jumlah Harga Bahan 3,749,400.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 4,586,156.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 4,586,156.00

A.4.1.1.31. Membuat 1 M³ balok beton bertulang (135 kg besi + bekisting)


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 6.3500 70,000.00 444,500.00
Tukang Batu L.02 OH 0.2750 92,000.00 25,300.00
Tukang Kayu L.02 OH 1.6500 92,000.00 151,800.00
Tukang Besi L.02 OH 0.9450 92,000.00 86,940.00
Kepala Tukang L.03 OH 0.3330 100,000.00 33,300.00
Mandor L.04 OH 0.3180 92,000.00 29,256.00
Jumlah Harga Tenaga Kerja 771,096.00
B. BAHAN
Kayu kelas IV M³ 0.3200 2,000,000.00 640,000.00
Paku 5 cm - 12 cm Kg 3.2000 18,000.00 57,600.00
Minyak bekisting Liter 1.6000 10,700.00 17,120.00
Besi beton polos Kg 141.7500 10,000.00 1,417,500.00
Kawat beton Kg 2.0250 20,000.00 40,500.00
Semen Portland Kg 336.0000 1,300.00 436,800.00
Pasir Beton M³ 0.5400 160,000.00 86,400.00
Kerikil (Maks 30 mm) M³ 0.8100 280,000.00 226,800.00
Kayu kelas IV balok M³ 0.1400 2,000,000.00 280,000.00
Dolken Kayu Ø (8-10) cm, panj 4 m Batang 16.0000 12,000.00 192,000.00
Jumlah Harga Bahan 3,394,720.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 4,165,816.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 4,165,816.00
A.4.1.1.32. Membuat 1 M³ Plat beton bertulang (130 kg besi + bekisting)
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 5.3000 70,000.00 371,000.00
Tukang Batu L.02 OH 0.2750 92,000.00 25,300.00
Tukang Kayu L.02 OH 1.3000 92,000.00 119,600.00
Tukang Besi L.02 OH 0.9100 92,000.00 83,720.00
Kepala Tukang L.03 OH 0.2650 100,000.00 26,500.00
Mandor L.04 OH 0.2650 92,000.00 24,380.00
Jumlah Harga Tenaga Kerja 650,500.00
B. BAHAN
Kayu kelas IV M³ 0.3200 2,000,000.00 640,000.00
Paku 5 cm - 12 cm Kg 3.2000 18,000.00 57,600.00
Minyak bekisting Liter 1.6000 10,700.00 17,120.00
Besi beton polos Kg 136.5000 10,000.00 1,365,000.00
Kawat beton Kg 1.9500 20,000.00 39,000.00
Semen Portland Kg 336.0000 1,300.00 436,800.00
Pasir Beton M³ 0.5400 160,000.00 86,400.00
Kerikil (Maks 30 mm) M³ 0.8100 280,000.00 226,800.00
Kayu kelas IV balok M³ 0.1200 2,000,000.00 240,000.00
Dolken Kayu ф (8-10) cm, panj 4 m Batang 32.0000 12,000.00 384,000.00
Jumlah Harga Bahan 3,492,720.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 4,143,220.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 4,143,220.00

A.4.1.1.35. Membuat 1 M' kolom praktis beton bertulang (11 x 11) cm


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.1800 70,000.00 12,600.00
Tukang Batu L.02 OH 0.0200 92,000.00 1,840.00
Tukang Kayu L.02 OH 0.0200 92,000.00 1,840.00
Tukang Besi L.02 OH 0.0200 92,000.00 1,840.00
Kepala Tukang L.03 OH 0.0060 100,000.00 600.00
Mandor L.04 OH 0.0090 92,000.00 828.00
Jumlah Harga Tenaga Kerja 19,548.00
B. BAHAN
Kayu kelas IV M³ 0.0020 2,000,000.00 4,000.00
Paku 5 cm - 12 cm Kg 0.0100 18,000.00 180.00
Besi beton polos Kg 3.0000 10,000.00 30,000.00
Kawat beton Kg 0.4500 20,000.00 9,000.00
Semen Portland Kg 4.0000 1,300.00 5,200.00
Pasir Beton M³ 0.0060 160,000.00 960.00
Kerikil (Maks 30 mm) M³ 0.0090 280,000.00 2,520.00
Jumlah Harga Bahan 51,860.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 71,408.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 71,408.00
A.4.1.1.36. Membuat 1 M' ring balok beton bertulang (10 x 15) cm
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.2970 70,000.00 20,790.00
Tukang Batu L.02 OH 0.0330 92,000.00 3,036.00
Tukang Kayu L.02 OH 0.0330 92,000.00 3,036.00
Tukang Besi L.02 OH 0.0330 92,000.00 3,036.00
Kepala Tukang L.03 OH 0.0100 100,000.00 1,000.00
Mandor L.04 OH 0.0150 92,000.00 1,380.00
Jumlah Harga Tenaga Kerja 32,278.00
B. BAHAN
Kayu kelas IV M³ 0.0030 2,000,000.00 6,000.00
Paku 5 cm - 12 cm Kg 0.0200 18,000.00 360.00
Besi beton polos Kg 3.6000 10,000.00 36,000.00
Kawat beton Kg 0.0500 20,000.00 1,000.00
Semen Portland Kg 5.5000 1,300.00 7,150.00
Pasir Beton M³ 0.0090 160,000.00 1,440.00
Kerikil (Maks 30 mm) M³ 0.0150 280,000.00 4,200.00
Jumlah Harga Bahan 56,150.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 88,428.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 88,428.00

A.4.2.1 PEKERJAAN BESI DAN ALUMUNIUM

A.4.2.1.21. Pemasangan 1 M² rangka besi hollow 1x40.40.2 mm, modul 60 x 60 cm, plafon
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerjaan L.01 OH 0.3500 70,000.00 24,500.00
Tukang Besi L.03 OH 0.3500 92,000.00 32,200.00
Kepala Tukang L.03 OH 0.0350 100,000.00 3,500.00
Mandor L.04 OH 0.0180 92,000.00 1,656.00
Jumlah Harga Tenaga Kerja 61,856.00
B. BAHAN
Rangka metal hollow 40.40.2 mm M1 4.0000 5,500.00 22,000.00
Assesoris (perkuatan, las dll) Ls 100% 5,500.00 5,500.00
Jumlah Harga Bahan 27,500.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 89,356.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 89,356.00
A.4.4.1 PEKERJAAN PASANGAN DINDING

A.4.4.1.9. Pemasangan 1 M² dinding bata lobang (8x8x16) cm tebal 1/2 batu campuran 1 SP : 4 PP
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.3000 70,000.00 21,000.00
Tukang Batu L.02 OH 0.1000 92,000.00 9,200.00
Kepala Tukang L.03 OH 0.0100 100,000.00 1,000.00
Mandor L.04 OH 0.0150 92,000.00 1,380.00
Jumlah Harga Tenaga Kerja 32,580.00
B. BAHAN
Bata merah M³ 70.0000 860.00 60,200.00
Semen Portland Kg 11.5000 1,300.00 14,950.00
Pasir Pasang M³ 0.0430 160,000.00 6,880.00
Jumlah Harga Bahan 82,030.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 114,610.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 114,610.00

A.4.4.2 PEKERJAAN PLESTERAN


A.4.4.2.3. Pemasangan 1 M² Plesteran 1 SP : 3 PP tebal 15 mm
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.3000 70,000.00 21,000.00
Tukang Batu L.02 OH 0.1500 92,000.00 13,800.00
Kepala Tukang L.03 OH 0.0150 100,000.00 1,500.00
Mandor L.04 OH 0.0150 92,000.00 1,380.00
Jumlah Harga Tenaga Kerja 37,680.00
B. BAHAN
Semen Portland Kg 7.7760 1,300.00 10,108.80
Pasir Pasang M³ 0.0230 160,000.00 3,680.00
Jumlah Harga Bahan 13,788.80
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 51,468.80


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 51,468.80

A.4.4.2.4. Pemasangan 1 M² Plesteran 1 SP : 4 PP tebal 15 mm


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.3000 70,000.00 21,000.00
Tukang Batu L.02 OH 0.1500 92,000.00 13,800.00
Kepala Tukang L.03 OH 0.0150 100,000.00 1,500.00
Mandor L.04 OH 0.0150 92,000.00 1,380.00
Jumlah Harga Tenaga Kerja 37,680.00
B. BAHAN
Semen Portland Kg 6.2400 1,300.00 8,112.00
Pasir Pasang M³ 0.0240 160,000.00 3,840.00
Jumlah Harga Bahan 11,952.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 49,632.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 49,632.00

A.4.4.3 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.35. Pemasangan 1 M² Lantai keramik ukuran 30 cm x 30 cm


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.3500 70,000.00 24,500.00
Tukang Batu L.02 OH 0.3500 92,000.00 32,200.00
Kepala Tukang L.03 OH 0.0350 100,000.00 3,500.00
Mandor L.04 OH 0.0350 92,000.00 3,220.00
Jumlah Harga Tenaga Kerja 63,420.00
B. BAHAN
Keramik Bh 11.8700 4,750.00 56,382.50
Semen Portland Kg 10.0000 1,300.00 13,000.00
Pasir Pasang M³ 0.0450 160,000.00 7,200.00
Semen Warna Kg 1.5000 10,000.00 15,000.00
Jumlah Harga Bahan 91,582.50
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 155,002.50


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 155,002.50

A.4.5.1 PEKERJAAN LANGIT-LANGIT (PLAFOND)


A.4.5.1.5A Pemasangan 1 M² langit-langit tripleks ukuran (120 x 240) cm, tebal 4 mm
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.1000 70,000.00 7,000.00
Tukang kayu L.02 OH 0.1000 92,000.00 9,200.00
Kepala Tukang L.03 OH 0.0100 100,000.00 1,000.00
Mandor L.04 OH 0.0050 92,000.00 460.00
Jumlah Harga Tenaga Kerja 17,660.00
B. BAHAN
Plywood 4 mm Lembar 0.3750 65,000.00 24,375.00
Paku Plywood Kg 0.0300 25,000.00 750.00
Jumlah Harga Bahan 25,125.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 42,785.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 42,785.00

A.4.5.1.5B Pemasangan 1 M² langit-langit Kalsiboard ukuran (120 x 240) cm, tebal 3,5 mm
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.1000 70,000.00 7,000.00
Tukang kayu L.02 OH 0.1000 92,000.00 9,200.00
Kepala Tukang L.03 OH 0.0100 100,000.00 1,000.00
Mandor L.04 OH 0.0050 92,000.00 460.00
Jumlah Harga Tenaga Kerja 17,660.00
B. BAHAN
Kalsiboard Lembar 0.3750 59,000.00 22,125.00
Paku Kalsiboard Kg 0.0300 25,000.00 750.00
Jumlah Harga Bahan 22,875.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 40,535.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 40,535.00

A.4.5.1.9.a Pemasangan 1 M' list langit-langit kayu profil


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0500 70,000.00 3,500.00
Tukang kayu L.02 OH 0.0500 92,000.00 4,600.00
Kepala Tukang L.03 OH 0.0050 100,000.00 500.00
Mandor L.04 OH 0.0030 92,000.00 276.00
Jumlah Harga Tenaga Kerja 8,876.00
B. BAHAN
List kayu profil A5 M 1.0500 4,473.68 4,697.37
Paku Kg 0.0100 400.00 4.00
Jumlah Harga Bahan 4,701.37
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 13,577.37


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 13,577.37

A.4.5.1.9.b Pemasangan 1 M' list langit-langit kayu profil A5


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0500 70,000.00 3,500.00
Tukang kayu L.02 OH 0.0500 92,000.00 4,600.00
Kepala Tukang L.03 OH 0.0050 100,000.00 500.00
Mandor L.04 OH 0.0030 92,000.00 276.00
Jumlah Harga Tenaga Kerja 8,876.00
B. BAHAN
List kayu profil A5 M 1.0500 3,684.21 3,868.42
Paku Kg 0.0100 18,000.00 180.00
Jumlah Harga Bahan 4,048.42
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 12,924.42


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 12,924.42

A.4.5.2 PEKERJAAN PENUTUP ATAP

A.4.5.2.32a Pemasangan 1 M² genteng metal biasa


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.2000 70,000.00 14,000.00
Tukang kayu L.02 OH 0.1000 92,000.00 9,200.00
Kepala Tukang L.03 OH 0.0100 100,000.00 1,000.00
Mandor L.04 OH 0.0010 92,000.00 92.00
Jumlah Harga Tenaga Kerja 24,292.00
B. BAHAN
Genteng metal Bh 1.0200 48,600.00 49,572.00
Paku genteng metal Kg 0.2000 27,000.00 5,400.00
Jumlah Harga Bahan 54,972.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 79,264.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 79,264.00
A.4.5.2.36 Pemasangan 1 M' genteng Nok metal
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.2500 70,000.00 17,500.00
Tukang kayu L.02 OH 0.1500 92,000.00 13,800.00
Kepala Tukang L.03 OH 0.0150 100,000.00 1,500.00
Mandor L.04 OH 0.0130 92,000.00 1,196.00
Jumlah Harga Tenaga Kerja 33,996.00
B. BAHAN
Nok genteng metal Bh 1.1000 29,000.00 31,900.00
Paku biasa 1/2"-1" Kg 0.0500 27,000.00 1,350.00
Jumlah Harga Bahan 33,250.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 67,246.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 67,246.00

A.4.6.1 PEKERJAAN KAYU

A.4.6.1.2 Pembuatan dan Pemasangan 1 M³ kusen pintu dan kusen jendela, kayu kelas II
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 6.0000 70,000.00 420,000.00
Tukang kayu L.02 OH 18.0000 92,000.00 1,656,000.00
Kepala Tukang L.03 OH 1.8000 100,000.00 180,000.00
Mandor L.04 OH 0.3000 92,000.00 27,600.00
Jumlah Harga Tenaga Kerja 2,283,600.00
B. BAHAN
Balok kayu kls II M³ 1.2000 5,200,000.00 6,240,000.00
Paku 10 cm Kg 1.2500 18,000.00 22,500.00
Lem kayu Kg 1.0000 18,000.00 18,000.00
Jumlah Harga Bahan 6,280,500.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 8,564,100.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 8,564,100.00

A.4.6.1.5 Pembuatan dan pemasangan 1 M² daun pintu panel, kayu kelas II


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.0000 70,000.00 70,000.00
Tukang kayu L.02 OH 3.0000 92,000.00 276,000.00
Kepala Tukang L.03 OH 0.3000 100,000.00 30,000.00
Mandor L.04 OH 0.0500 92,000.00 4,600.00
Jumlah Harga Tenaga Kerja 380,600.00
B. BAHAN
Papan kayu M³ 0.0400 5,200,000.00 208,000.00
Lem kayu Kg 0.5000 18,000.00 9,000.00
Jumlah Harga Bahan 217,000.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 597,600.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 597,600.00

A.4.6.2 PEKERJAAN KUNCI DAN KACA


A.4.6.2.2A Pemasangan 1 buah kunci tanam biasa
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0100 70,000.00 700.00
Tukang kayu L.02 OH 0.5000 92,000.00 46,000.00
Kepala Tukang L.03 OH 0.0500 100,000.00 5,000.00
Mandor L.04 OH 0.0050 92,000.00 460.00
Jumlah Harga Tenaga Kerja 52,160.00
B. BAHAN
Kunci tanam biasa Bh 1.0000 165,000.00 165,000.00
Jumlah Harga Bahan 165,000.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 217,160.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 217,160.00

A.4.6.2.2B Pemasangan 1 buah kunci body pelor


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0100 70,000.00 700.00
Tukang kayu L.02 OH 0.5000 92,000.00 46,000.00
Kepala Tukang L.03 OH 0.0500 100,000.00 5,000.00
Mandor L.04 OH 0.0050 92,000.00 460.00
Jumlah Harga Tenaga Kerja 52,160.00
B. BAHAN
Kunci tanam Cylinder Bh 1.0000 150,000.00 150,000.00
Jumlah Harga Bahan 150,000.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 202,160.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 202,160.00

A.4.6.2.5 Pemasangan 1 buah engsel pintu


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0150 70,000.00 1,050.00
Tukang kayu L.02 OH 0.1500 92,000.00 13,800.00
Kepala Tukang L.03 OH 0.0150 100,000.00 1,500.00
Mandor L.04 OH 0.0008 92,000.00 73.60
Jumlah Harga Tenaga Kerja 16,423.60
B. BAHAN
Engsel pintu Bh 1.0000 15,000.00 15,000.00
Jumlah Harga Bahan 15,000.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 31,423.60


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 31,423.60
A.4.6.2.6a. Pemasangan 1 buah engsel jendela
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0100 70,000.00 700.00
Tukang kayu L.02 OH 0.1000 92,000.00 9,200.00
Kepala Tukang L.03 OH 0.0100 100,000.00 1,000.00
Mandor L.04 OH 0.0005 92,000.00 46.00
Jumlah Harga Tenaga Kerja 10,946.00
B. BAHAN
Engsel jendela Bh 1.0000 12,500.00 12,500.00
Jumlah Harga Bahan 12,500.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 23,446.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 23,446.00

A.4.6.2.10b. Pemasangan 1 buah Handle Jendela/tarikan Jendela


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0060 70,000.00 420.00
Tukang kayu L.02 OH 0.0600 92,000.00 5,520.00
Kepala Tukang L.03 OH 0.0060 100,000.00 600.00
Mandor L.04 OH 0.0003 92,000.00 27.60
Jumlah Harga Tenaga Kerja 6,567.60
B. BAHAN
Handle/Pegangan Jendela Bh 1.0000 12,000.00 12,000.00
Jumlah Harga Bahan 12,000.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 18,567.60


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 18,567.60

A.4.6.2.10c. Pemasangan 1 buah Grendel Jendela


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0060 70,000.00 420.00
Tukang kayu L.02 OH 0.0600 92,000.00 5,520.00
Kepala Tukang L.03 OH 0.0060 100,000.00 600.00
Mandor L.04 OH 0.0003 92,000.00 27.60
Jumlah Harga Tenaga Kerja 6,567.60
B. BAHAN
Grendel uk. 2" Bh 1.0000 10,500.00 10,500.00
Jumlah Harga Bahan 10,500.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 17,067.60


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 17,067.60
A.4.6.2.9 Pemasangan 1 buah Kait Angin
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0100 70,000.00 700.00
Tukang kayu L.02 OH 0.1000 92,000.00 9,200.00
Kepala Tukang L.03 OH 0.0100 100,000.00 1,000.00
Mandor L.04 OH 0.0050 92,000.00 460.00
Jumlah Harga Tenaga Kerja 11,360.00
B. BAHAN
Kait Angin Bh 1.0000 10,500.00 10,500.00
Jumlah Harga Bahan 10,500.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 21,860.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 21,860.00

A.4.6.2.11 Pemasangan 1 buah Kunci Slot (Grendel Tanam)


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0200 70,000.00 1,400.00
Tukang kayu L.02 OH 0.2000 92,000.00 18,400.00
Kepala Tukang L.03 OH 0.0200 100,000.00 2,000.00
Mandor L.04 OH 0.0010 92,000.00 92.00
Jumlah Harga Tenaga Kerja 21,892.00
B. BAHAN
Grendel Tanam Bh 1.0000 85,000.00 85,000.00
Jumlah Harga Bahan 85,000.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 106,892.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 106,892.00

A.4.6.2.12 Pemasangan 1 buah Door holder


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0500 70,000.00 3,500.00
Tukang kayu L.02 OH 0.5000 92,000.00 46,000.00
Kepala Tukang L.03 OH 0.5000 100,000.00 50,000.00
Mandor L.04 OH 0.0030 92,000.00 276.00
Jumlah Harga Tenaga Kerja 99,776.00
B. BAHAN
Door Holder Bh 1.0000 185,000.00 185,000.00
Jumlah Harga Bahan 185,000.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 284,776.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 284,776.00
A.4.6.2.17 Pemasangan 1 M² kaca tebal 5 mm
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0150 70,000.00 1,050.00
Tukang kayu L.02 OH 0.1500 92,000.00 13,800.00
Kepala Tukang L.03 OH 0.0150 100,000.00 1,500.00
Mandor L.04 OH 0.0008 92,000.00 73.60
Jumlah Harga Tenaga Kerja 16,423.60
B. BAHAN
Kaca tebal 5 mm M² 1.1000 120,000.00 132,000.00
Sealant Kg 0.0500 25,000.00 1,250.00
Jumlah Harga Bahan 133,250.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 149,673.60


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 149,673.60

A.4.7.1 PEKERJAAN PENGECATAN

A.4.7.2.4 1 M² Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0700 70,000.00 4,900.00
Tukang kayu L.02 OH 0.0090 92,000.00 828.00
Kepala Tukang L.03 OH 0.0060 100,000.00 600.00
Mandor L.04 OH 0.0030 92,000.00 276.00
Jumlah Harga Tenaga Kerja 6,604.00
B. BAHAN
Cat menie Kg 0.2000 35,000.00 7,000.00
Plamuur Kg 0.1500 35,000.00 5,250.00
Cat dasar Kg 0.1700 32,000.00 5,440.00
Cat penutup Kg 0.2600 45,000.00 11,700.00
Kuas Bh 0.0100 5,000.00 50.00
Thiner Kg 0.0300 28,000.00 840.00
Amplas Lbr 0.2000 6,000.00 1,200.00
Jumlah Harga Bahan 31,480.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 38,084.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 38,084.00
A.4.7.2.5 1 M² Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0700 70,000.00 4,900.00
Tukang kayu L.02 OH 0.1050 92,000.00 9,660.00
Kepala Tukang L.03 OH 0.0040 100,000.00 400.00
Mandor L.04 OH 0.0030 92,000.00 276.00
Jumlah Harga Tenaga Kerja 15,236.00
B. BAHAN
Cat menie Kg 0.2000 35,000.00 7,000.00
Plamuur Kg 0.1500 35,000.00 5,250.00
Cat dasar Kg 0.1700 32,000.00 5,440.00
Cat penutup Kg 0.3500 45,000.00 15,750.00
Kuas Bh 0.0100 5,000.00 50.00
Thiner Kg 0.0300 28,000.00 840.00
Ampelas Lbr 0.2000 6,000.00 1,200.00
Jumlah Harga Bahan 35,530.00
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 50,766.00


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 50,766.00

A.4.7.2.10A Pengecatan 1 M² tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Cat tembok Interior
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0200 70,000.00 1,400.00
Tukang kayu L.02 OH 0.0630 92,000.00 5,796.00
Kepala Tukang L.03 OH 0.0063 100,000.00 630.00
Mandor L.04 OH 0.0030 92,000.00 276.00
Jumlah Harga Tenaga Kerja 8,102.00
B. BAHAN
Plamuur Kg 0.1000 6,000.00 600.00
Cat dasar Kg 0.1000 25,000.00 2,500.00
Cat penutup Kg 0.2600 19,920.00 5,179.20
Jumlah Harga Bahan 8,279.20
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 16,381.20


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 16,381.20
A.4.7.2.10B Pengecatan 1 M² tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Cat tembok Exterior
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.0200 70,000.00 1,400.00
Tukang kayu L.02 OH 0.0630 92,000.00 5,796.00
Kepala Tukang L.03 OH 0.0063 100,000.00 630.00
Mandor L.04 OH 0.0030 92,000.00 276.00
Jumlah Harga Tenaga Kerja 8,102.00
B. BAHAN
Plamuur Kg 0.1000 6,000.00 600.00
Cat dasar Kg 0.1000 25,000.00 2,500.00
Cat penutup Kg 0.2600 29,920.00 7,779.20
Jumlah Harga Bahan 10,879.20
C. PERALATAN
-
Jumlah Harga Peralatan -

D. Jumlah (A+B+C) 18,981.20


E. Overhead & Profit 0% x D -
F. Harga Satuan Pekerjaan (D+E) 18,981.20