SCHEDULE PEKERJAAN RIGID PAVEMENT

PROYEK PENGEMBANGAN PLBN TERPADU YETETKUN


KAB. BOVEN DIGOEL - PAPUA

2022
NO URAIAN SAT VOLUME MEI JUNI
… 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

A Pekerjaan Badan Jalan

A.1 Rigid K-250


A.1.1 Pengadaan Material Ls 1.00 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
A.1.2 Mobilisasi Alat Unit 2.00 1.0 1.0
A.1.3 Pengecoran Beton M3 1 707.24 30.0 30.0 38.0 15.0 42.0 87.0 50.0 93.0 93.0 93.0 93.0 93.0 93.0 50.0 108.0 108.0 108.0 108.0 108.0 108.0 60.0 99.2

PT NINDYA KARYA (PERSERO)


PROYEK PENGEMBANGAN PLBN TERPADU YETETKUN
KAB. BOVEN DIGOEL - PAPUA

MUHAMMAD IGBAL
PROJECT MANAGER