LOKASI : MANADO, SULAWESI UTARA TAHUN ANGGARAN : 2022 MINGGU KE : 25 ( DUAPULUH LIMA ) PERIODE : 19 September 2022 S.D 25 September 2022 NO KONTRAK PO : 4210002199 TANGGAL KONTRAK PO : 6 April 2022
OPNAM LAPANGAN 50%
BOBOT NO. URAIAN JENIS PEKERJAAN SAT VOLUME KETERANGAN (%) Volume Trhdp Pekerjaan Trhdp Kontrak (%) (%)
PEMBANGUNAN GUDANG MKK (4 UNIT) + PRASARANA 100% 50,544%
A. PEKERJAAN KONSTRUKSI GUDANG MKK 87,804% 43,954%
1 KONSTRUKSI GUDANG MKK Unit 1,00 87,804% 0,50 50,060% 43,954%
B. PEKERJAAN PRASARANA 12,196% 6,590%
1 PEK. PEMATANGAN LAHAN Ls 1,00 1,170% 1,00 100% 1,170% 2 PEK. PEMBANGUNAN MENARA PANTAU Unit 1,00 0,814% - 0% 0,000% 3 PEK. PLAT DECKER & GORONG - GORONG Unit 1,00 0,469% - 0% 0,000% 4 PEK. PENANGKAL PETIR Titik 4,00 0,734% - 0% 0,000% 5 PEK. DRAINASE Ls 1,00 0,994% - 0% 0,000% 6 PEK. METERISASI 16.500 VA Ls 1,00 0,457% - 0% 0,000% 7 PEK. INSTALASI LISTRIK LUAR DAN KABEL Ls 1,00 0,299% - 0% 0,000% 8 PEK. TIANG LAMPU PJU 4 TITIK Ls 1,00 0,211% - 0% 0,000% 9 PEK. TALUD & TANGGUL PENAHAN TANAH Ls 1,00 6,774% 0,80 80% 5,419% 10 PEK. SUMUR BOR BIASA + MESIN POMPA Ls 1,00 0,274% - 0% 0,000%