Anda di halaman 1dari 4

FORM CEKLIST OPNAM 50%

PEKERJAAN : PEMBANGUNAN GUDMURAH XIII/MERDEKA 2


LOKASI : MANADO, SULAWESI UTARA
MINGGU KE : 25 ( DUAPULUH LIMA )

Bobot Pekerjaan Mutual Chek awal (MC-0) OPNAM LAPANGAN 50%


VOLUME
NO. URAIAN JENIS PEKERJAAN SAT KETERANGAN
KONTRAK (%) Trhdp Pekerjaan Trhdp Bangunan
Volume Bobot (%) Volume
(%) (%)

GUDANG MKK ( @ 380 m2 ) 100% 100% 50,060%

A. PEKERJAAN PERSIAPAN 0,148% 0,148% 0,148% 0,000%


1 Pasangan bouwplank M' 384,00 0,148% 384,00 0,148% 384,00 100,000% 0,148%

B. PEKERJAAN BOREPILE 13,210% 13,210% 13,210% 0,000%


1 Pengeboran Pondasi Straus Pile Ø60 cm, Elv. - 3.00 m M' 1.776,00 4,597% 1.776,00 4,597% 1.776,00 100,000% 4,597%
2 Pek. Beton K.300 M3 125,47 0,952% 125,47 0,952% 125,47 100,000% 0,952%
3 Pek. Besi Penulangan Kg 55.292,80 7,661% 55.292,80 7,661% 55.292,80 100,000% 7,661%

C. PEKERJAAN TANAH 2,872% 2,872% 2,872% 0,000%


1 Pek. Galian Tanah Pondasi Footplate Type FT1 M3 448,80 0,346% 448,80 0,346% 448,80 100,000% 0,346%
2 Pek. Galian Tanah Pondasi Footplate Type FT2 M3 120,00 0,033% 120,00 0,033% 120,00 100,000% 0,033%
3 Pek. Galian Tanah Pondasi Batu Belah M3 430,08 0,332% 430,08 0,332% 430,08 100,000% 0,332%
4 Pek. Urugan Tanah Kembali Pondasi M3 299,66 0,141% 299,66 0,141% 299,66 100,000% 0,141%
5 Pek. Urugan Pasir Bawah Pondasi dan Lantai M3 120,60 0,148% 120,60 0,148% 120,60 100,000% 0,148%
6 Pek. Urugan Tanah Sirtu Tb. 60 cm (Didatangkan) M3 912,00 1,445% 912,00 1,445% 912,00 100,000% 1,445%
7 Pek. Pemadatan Tanah M3 912,00 0,428% 912,00 0,428% 912,00 100,000% 0,428%

D. PEKERJAAN PASANGAN 3,001% 3,001% 2,001% 0,000%


1 Pas. Batu Kosong (Aanstamping) M3 107,52 0,223% 107,52 0,223% 107,52 100,000% 0,223%
2 Pas. Pondasi Batu Belah Hitam, Adk. 1 pc : 5 ps M3 322,56 1,778% 322,56 1,778% 322,56 100,000% 1,778%
3 Pas. Bata 1/2 bt Saluran Air, Selasar dan Bak, Adk. 1 Pc : 5 Ps M2 616,96 0,534% 616,96 0,534% - 0,000% 0,000%
4 Pek. Plesteran Dinding M2 985,60 0,279% 985,60 0,279% - 0,000% 0,000%
5 Pek. Acian Dinding M2 985,60 0,188% 985,60 0,188% - 0,000% 0,000%

E. PEKERJAAN STRUKTUR BETON BERTULANG 73,504% 73,504% 31,828% 0,000%

STRUKTUR BAWAH

1 Pek. Lantai Kerja Pondasi Footplate Tb. 5 cm M3 14,22 0,075% 14,22 0,075% 14,22 100,000% 0,075%

2 Pek. Lantai Kerja Gudang Munisi Tb. 5 cm M3 79,50 0,422% 79,50 0,422% 79,50 100,000% 0,422%

3 Pek. Pondasi Footplate 150/170 cm (FT1)


- Beton K-300 M3 89,76 0,681% 89,76 0,681% 89,76 100,000% 0,681%
- Besi Tulangan Kg 23.207,95 3,216% 23.207,95 3,216% 23.207,95 100,000% 3,216%

4 Pek. Pondasi Footplate 100/100 cm (FT2)


- Beton K-300 M3 24,00 0,182% 24,00 0,182% 24,00 100,000% 0,182%
- Besi Tulangan Kg 6.444,00 0,893% 6.444,00 0,893% 6.444,00 100,000% 0,893%

5 Pek. Pedestal Kolom K.1 40/60 cm


- Beton K-300 M3 42,24 0,320% 42,24 0,320% 42,24 100,000% 0,320%
- Besi Tulangan Kg 18.710,12 2,592% 18.710,12 2,592% 18.710,12 100,000% 2,592%
- Bekisting M2 352,00 0,824% 352,00 0,824% 352,00 100,000% 0,824%

6 Pek. Pedestal Kolom K.2 40/40 cm


- Beton K-300 M3 19,20 0,146% 19,20 0,146% 19,20 100,000% 0,146%
- Besi Tulangan Kg 9.383,50 1,300% 9.383,50 1,300% 9.383,50 100,000% 1,300%
- Bekisting M2 192,00 0,449% 192,00 0,449% 192,00 100,000% 0,449%

7 Pek. Sloof S.1 30/40 cm


- Beton K-300 M3 82,01 0,622% 82,01 0,622% 82,01 100,000% 0,622%
- Besi Tulangan Kg 21.009,64 2,911% 21.009,64 2,911% 21.009,64 100,000% 2,911%
- Bekisting M2 546,72 0,831% 546,72 0,831% 546,72 100,000% 0,831%

8 Pek. Sloof S.2 20/25 cm


- Beton K-300 M3 7,03 0,053% 7,03 0,053% 7,03 100,000% 0,053%
- Besi Tulangan Kg 2.485,14 0,344% 2.485,14 0,344% 2.485,14 100,000% 0,344%
- Bekisting M2 70,30 0,107% 70,30 0,107% 70,30 100,000% 0,107%
2

Bobot Pekerjaan Mutual Chek awal (MC-0) OPNAM LAPANGAN 50%


VOLUME
NO. URAIAN JENIS PEKERJAAN SAT KETERANGAN
KONTRAK (%) Trhdp Pekerjaan Trhdp Bangunan
Volume Bobot (%) Volume
(%) (%)

9 Pek. Lantai Gudang Tb. 15 cm


- Beton K-300 M3 238,50 1,810% 238,50 1,810% - 0,000% 0,000%
- Pasangan Wiremesh M.10 1 Lapis M2 1.590,00 2,200% 1.590,00 2,200% 238,50 15,000% 0,330%

10 Pek. Floor Hardener Lantai M2 1.590,00 2,053% 1.590,00 2,053% - 0,000% 0,000%

11 Pek. Rabat Beton Selasar Keliling Gudang Tb. 5 cm M3 28,62 0,152% 28,62 0,152% - 0,000% 0,000%

STRUKTUR ATAS

1 Pek. Kolom Struktur K.1 40/60 cm


- Beton K-300 M3 88,70 0,673% 88,70 0,673% 88,70 100,000% 0,673%
- Besi Tulangan Kg 24.437,89 3,386% 24.437,89 3,386% 24.437,89 100,000% 3,386%
- Bekisting M2 739,20 1,730% 739,20 1,730% 739,20 100,000% 1,730%

2 Pek. Kolom Struktur K.2 40/40 cm


- Beton K-300 M3 10,75 0,082% 10,75 0,082% 10,75 100,000% 0,082%
- Besi Tulangan Kg 3.296,80 0,457% 3.296,80 0,457% 3.296,80 100,000% 0,457%
- Bekisting M2 53,76 0,126% 53,76 0,126% 53,76 100,000% 0,126%

3 Pek. Dinding Beton Bertulang Tb. 15 cm


- Beton K-300 M3 196,47 1,491% 196,47 1,491% - 0,000% 0,000%
- Besi Tulangan Kg 1.096,93 0,152% 1.096,93 0,152% 822,70 75,000% 0,114%
- Pasangan Wiremesh M.10 2 Lapis M2 2.800,96 3,876% 2.800,96 3,876% 2.100,72 75,000% 2,907%
- Bekisting M2 2.909,76 7,559% 2.909,76 7,559% 2.211,42 76,000% 5,745%

4 Pek. Balok Beton B.1 30/80 cm


- Beton K-300 M3 98,26 0,746% 98,26 0,746% - 0,000% 0,000%
- Besi Tulangan Kg 26.149,14 3,623% 26.149,14 3,623% - 0,000% 0,000%
- Bekisting M2 655,04 1,799% 655,04 1,799% 65,50 10,000% 0,180%

5 Pek. Balok Beton B.2 30/50 cm


- Beton K-300 M3 41,10 0,312% 41,10 0,312% - 0,000% 0,000%
- Besi Tulangan Kg 14.103,51 1,954% 14.103,51 1,954% - 0,000% 0,000%
- Bekisting M2 274,00 0,753% 274,00 0,753% 27,40 10,000% 0,075%

6 Pek. Balok Beton B.3 20/40 cm


- Beton K-300 M3 22,59 0,171% 22,59 0,171% - 0,000% 0,000%
- Besi Tulangan M2 10.442,84 1,447% 10.442,84 1,447% - 0,000% 0,000%
- Bekisting M2 197,68 0,543% 197,68 0,543% 19,77 10,000% 0,054%

7 Pek. Plat Atap Beton Tb. 15 cm


- Beton K-300 M3 336,15 2,551% 336,15 2,551% - 0,000% 0,000%
- Pasangan Wiremesh M.10 2 Lapis M2 4.482,00 6,202% 4.482,00 6,202% 672,30 15,000% 0,000%
- Pasangan Bondek Galvalum M2 2.241,00 2,826% 2.241,00 2,826% - 0,000% 0,000%
- Bekisting M2 2.241,00 5,821% 2.241,00 5,821% - 0,000% 0,000%
3

Bobot Pekerjaan Mutual Chek awal (MC-0) OPNAM LAPANGAN 50%


VOLUME
NO. URAIAN JENIS PEKERJAAN SAT KETERANGAN
KONTRAK (%) Trhdp Pekerjaan Trhdp Bangunan
Volume Bobot (%) Volume
(%) (%)

8 Pek. Listplank Beton 10/80 Tb. 15 cm


- Beton K-300 M3 28,60 0,217% 28,60 0,217% - 0,000% 0,000%
- Besi Tulangan Kg 4.364,80 0,605% 4.364,80 0,605% - 0,000% 0,000%
- Bekisting M2 352,00 0,914% 352,00 0,914% - 0,000% 0,000%

9 Pek. Pet Beton Tb. 15 cm diatas Kusen


- Beton K-300 M3 10,85 0,082% 10,85 0,082% - 0,000% 0,000%
- Besi Tulangan Kg 896,77 0,124% 896,77 0,124% - 0,000% 0,000%
- Bekisting M2 72,32 0,188% 72,32 0,188% - 0,000% 0,000%

10 Pek. Acian Dinding, Kolom dan Balok M2 4.785,04 0,910% 4.785,04 0,910% - 0,000% 0,000%

F. PEKERJAAN KUSEN PINTU DAN BOVEN 1,796% 1,796% 0,000% 0,000%


1 Pek. Kusen Pintu dan Daun Pintu P.1 (Pintu Plat Besi, Fin. Cat) Unit 8,00 0,711% 8,00 0,711%
2 Pek. Kusen Pintu dan Daun Pintu P.2 (Pintu Plat Besi, Fin. Cat) Unit 8,00 0,624% 8,00 0,624%
3 Pek. Kusen Bouvent Jalusi Besi (Rangka Besi, Fin. Cat) Unit 32,00 0,461% 32,00 0,461%

G. PEKERJAAN PENGECATAN 4,212% 4,212% 0,000% 0,000%


1 Pek. Pengecatan Dinding 2x Lapis M2 9.570,08 2,006% 9.570,08 2,006%
2 Pek. Waterproofing Plat Atap M2 2.241,00 2,206% 2.241,00 2,206%

H. PEKERJAAN BAK PASIR DAN BAK AIR 0,652% 0,652% 0,000% 0,000%
1 Pas. Pondasi Batu Belah Hitam, Adk. 1 pc : 5 ps M3 28,51 0,157% 28,51 0,157%
2 Pas. Bata 1/2 bt Saluran Air, Selasar dan Bak, Adk. 1 Pc : 5 Ps M2 105,60 0,091% 105,60 0,091%
3 Pek. Sloof 15/20 cm
- Beton K-125 M3 3,17 0,017% 3,17 0,017%
- Besi Tulangan Kg 438,18 0,047% 438,18 0,047%
- Bekisting M2 21,12 0,016% 21,12 0,016%

4 Pek. Kolom Praktis 11/11 cm


- Beton K-125 M3 0,77 0,004% 0,77 0,004%
- Besi Tulangan Kg 228,53 0,025% 228,53 0,025%
- Bekisting M2 7,04 0,005% 7,04 0,005%

5 Pek. Ringbalk 10/15 cm


- Beton K-125 M3 1,58 0,008% 1,58 0,008%
- Besi Tulangan Kg 393,74 0,042% 393,74 0,042%
- Bekisting M2 21,12 0,016% 21,12 0,016%

6 Pek. Latai Dasar Bak (Rabat Beton) M3 4,36 0,023% 4,36 0,023%

7 Pek. Plesteran Dinding M2 422,40 0,119% 422,40 0,119%

8 Pek. Acian Dinding M2 422,40 0,080% 422,40 0,080%

I. PEKERJAAN LAIN-LAIN 0,604% 0,604% 0,000% 0,000%


1 Pek. Instalasi Pipa Pembuangan Air Hujan PCV 4'' M' 676,00 0,520% 676,00 0,520%
2 Pek. Pengadaan Gembok Pcs 16,00 0,013% 16,00 0,013%
3 Pek. Perapihan dan Pembersihan Lokasi Akhir Ls 4,00 0,071% 4,00 0,071%
REKAP CEKLIST OPNAM 50%
PEKERJAAN : PEMBANGUNAN GUDMURAH XIII/MERDEKA 2
LOKASI : MANADO, SULAWESI UTARA
TAHUN ANGGARAN : 2022
MINGGU KE : 25 ( DUAPULUH LIMA )
PERIODE : 19 September 2022 S.D 25 September 2022
NO KONTRAK PO : 4210002199
TANGGAL KONTRAK PO : 6 April 2022

OPNAM LAPANGAN 50%


BOBOT
NO. URAIAN JENIS PEKERJAAN SAT VOLUME KETERANGAN
(%) Volume Trhdp Pekerjaan Trhdp Kontrak
(%) (%)

PEMBANGUNAN GUDANG MKK (4 UNIT) + PRASARANA 100% 50,544%

A. PEKERJAAN KONSTRUKSI GUDANG MKK 87,804% 43,954%


1 KONSTRUKSI GUDANG MKK Unit 1,00 87,804% 0,50 50,060% 43,954%

B. PEKERJAAN PRASARANA 12,196% 6,590%


1 PEK. PEMATANGAN LAHAN Ls 1,00 1,170% 1,00 100% 1,170%
2 PEK. PEMBANGUNAN MENARA PANTAU Unit 1,00 0,814% - 0% 0,000%
3 PEK. PLAT DECKER & GORONG - GORONG Unit 1,00 0,469% - 0% 0,000%
4 PEK. PENANGKAL PETIR Titik 4,00 0,734% - 0% 0,000%
5 PEK. DRAINASE Ls 1,00 0,994% - 0% 0,000%
6 PEK. METERISASI 16.500 VA Ls 1,00 0,457% - 0% 0,000%
7 PEK. INSTALASI LISTRIK LUAR DAN KABEL Ls 1,00 0,299% - 0% 0,000%
8 PEK. TIANG LAMPU PJU 4 TITIK Ls 1,00 0,211% - 0% 0,000%
9 PEK. TALUD & TANGGUL PENAHAN TANAH Ls 1,00 6,774% 0,80 80% 5,419%
10 PEK. SUMUR BOR BIASA + MESIN POMPA Ls 1,00 0,274% - 0% 0,000%

Anda mungkin juga menyukai