R E K A P I T U L A S I
JUMLAH E 29,500,000.00
R. PEKERJAAN MEUBELER LT. 3
1 Pek. Meja Nurse Station 2.5 m2 2,500,000 6,250,000.00
2 Pek. Meja wastafel + backdrop 4.0 m2 2,000,000 8,000,000.00
3 Pek. SPA Bad 16.0 m2 1,600,000 25,600,000.00
4 Pek. Pintu Ruangan 11.0 bh 3,000,000 33,000,000.00
JUMLAH F 72,850,000.00
S. PEKERJAAN TAMBAHAN
1 Pek. Logo Bening's Front Desk 1.0 unit 15,000,000 15,000,000.00
2 Pek. Letter box Logo Bening's 2.0 unit 8,500,000 17,000,000.00
3 Pek. Pas. Cermin 12.0 unit 1,500,000 18,000,000.00
4 Pek. Papan nama ruangan 12.0 unit 500,000 6,000,000.00
5 Pek. waterprofing dinding luar 300.0 m2 65,000 19,500,000.00
6 Pembersihan buang puing / sampah bongkaran 1.0 ls 5,000,000 5,000,000.00
JUMLAH G 80,500,000.00
A. PEKERJAAN BONGKARAN
1 M3 MEMBONGKAR DINDING 1/2 BATA
2.000 Org Pekerja @ Rp. 130,000.00 Rp. 260,000.00
JUMLAH Rp. 260,000.00
overhead dan profit 10% Rp. 26,000.00
Jumlah Total Rp. 286,000.00
1 M2 MEMBONGKAR PLAFOND
0.600 Org Pekerja @ Rp. 130,000.00 Rp. 78,000.00
JUMLAH Rp. 78,000.00
overhead dan profit 10% Rp. 7,800.00
Jumlah Total Rp. 85,800.00
B. PEKERJAAN ACP
1 M2 PEKERJAAN ALUMUNIUM COMPOSITE PANEL (ACP)
1.100 M2 Alumunium composite panel @ Rp. 0.00 Rp. 0.00
0.080 btg besi hollow galvanis @ Rp. 0.00 Rp. 0.00
0.267 btg bracket siku @ Rp. 0.00 Rp. 0.00
0.080 kg dinabolt/ sekrup beton @ Rp. 0.00 Rp. 0.00
0.110 kg sekrup @ Rp. 0.00 Rp. 0.00
0.250 M2 tube @ Rp. 0.00 Rp. 0.00
1.000 ls alat bantu @ Rp. 0.00 Rp. 0.00
1.000 M2 Upah Kerja @ Rp. 0.00 Rp. 0.00
JUMLAH Rp. 0.00
overhead dan profit 10% Rp. 0.00
Jumlah Total Rp. 0.00
1 M2 PEKERJAAN ALUMUNIUM COMPOSITE PANEL (ACP) CUTTING
1.100 M2 Alumunium composite panel @ Rp. 0.00 Rp. 0.00
0.080 btg besi hollow galvanis @ Rp. 0.00 Rp. 0.00
0.267 btg bracket siku @ Rp. 0.00 Rp. 0.00
0.080 kg dinabolt/ sekrup beton @ Rp. 0.00 Rp. 0.00
0.110 kg sekrup @ Rp. 0.00 Rp. 0.00
0.250 M2 tube @ Rp. 0.00 Rp. 0.00
1.000 ls alat bantu @ Rp. 0.00 Rp. 0.00
1.000 M2 Upah cutting @ Rp. 0.00 Rp. 0.00
JUMLAH Rp. 0.00
overhead dan profit 10% Rp. 0.00
Jumlah Total Rp. 0.00
C. PEKERJAAN DINDING
1 M PEKERJAAN WAINSCOTING
0.500 btg List dinding @ Rp. 0.00 Rp. 0.00
0.600 kg compound @ Rp. 0.00 Rp. 0.00
1.000 Lbr Amplas @ Rp. 0.00 Rp. 0.00
20.000 bh Screw 6 @ Rp. 0.00 Rp. 0.00
1.000 M Upah Kerja wainscoting @ Rp. 0.00 Rp. 0.00
JUMLAH Rp. 0.00
overhead dan profit 10% Rp. 0.00
Jumlah Total Rp. 0.00
1 M2 PASANG WALLPAPER
1.200 M2 Wallpaper @ Rp. 0.00 Rp. 0.00
0.200 Kg Lem wallpaper @ Rp. 0.00 Rp. 0.00
1.000 Bh Kape @ Rp. 0.00 Rp. 0.00
1.000 M2 Upah Tukang Wallpaper @ Rp. 0.00 Rp. 0.00
JUMLAH Rp. 0.00
overhead dan profit 10% Rp. 0.00
Jumlah Total Rp. 0.00
D. PEKERJAAN PLAFOND
1 M2 PEKERJAAN PLAFOND
2.000 btg Hollow 2/4 Zincromate @ Rp. 0.00 Rp. 0.00
1.200 lbr gipsum board @ Rp. 0.00 Rp. 0.00
0.600 bh sekrup @ Rp. 0.00 Rp. 0.00
4.000 bh paku beton @ Rp. 0.00 Rp. 0.00
0.360 roll kasa gipsum @ Rp. 0.00 Rp. 0.00
0.600 kg compound @ Rp. 0.00 Rp. 0.00
1.000 M2 Upah Kerja Plafond @ Rp. 0.00 0.00
JUMLAH Rp. 0.00
overhead dan profit 10% Rp. 0.00
Jumlah Total Rp. 0.00
E. PEKERJAAN LANTAI
1 M2 PEKERJAAN LANTAI KERAMIK 60X60
1.080 M2 Keramik 60x60 @ Rp. 0.00 Rp. 0.00
9.600 kg semen @ Rp. 0.00 Rp. 0.00
1.500 kg semen nut @ Rp. 0.00 Rp. 0.00
1.000 M2 Upah Kerja Keramik @ Rp. 0.00 0.00
JUMLAH Rp. 0.00
overhead dan profit 10% Rp. 0.00
Jumlah Total Rp. 0.00
F. PEKERJAAN PENGECATAN
1 M2 PENGECATAN TEMBOK LAMA ( 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP )
0.150 Kg Cat dasar @ Rp. 40,000.00 Rp. 6,000.00
0.150 Kg Cat penutup 2 kali @ Rp. 40,000.00 Rp. 6,000.00
2.000 bh Amplas @ Rp. 6,500.00 Rp. 13,000.00
1.000 M2 Upah Cat @ Rp. 27,500.00 Rp. 27,500.00
JUMLAH Rp. 52,500.00
overhead dan profit 10% Rp. 5,250.00
Jumlah Total Rp. 57,750.00
1 M2 PENGECATAN PLAFON ( 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP )
0.150 Kg Cat dasar @ Rp. 40,000.00 Rp. 6,000.00
0.400 Kg Cat penutup 2 kali @ Rp. 45,000.00 Rp. 18,000.00
1.000 BH Amplas @ Rp. 6,500.00 Rp. 6,500.00
1.000 M2 Upah cat @ Rp. 27,500.00 Rp. 27,500.00
JUMLAH Rp. 58,000.00
overhead dan profit 10% Rp. 5,800.00
Jumlah Total Rp. 63,800.00
1 M2 PENGECATAN DUCO
0.300 Kg Cat Meni @ Rp. 20,000.00 Rp. 6,000.00
0.300 Kg Cat Kayu @ Rp. 35,000.00 Rp. 10,500.00
0.300 kg Plitur @ Rp. 35,000.00 Rp. 10,500.00
1.000 ltr Thinner @ Rp. 15,000.00 Rp. 15,000.00
2.000 Bh Amplas @ Rp. 6,500.00 Rp. 13,000.00
1.000 M2 Upah Duco @ Rp. 85,000.00 Rp. 85,000.00
JUMLAH Rp. 140,000.00
overhead dan profit 10% Rp. 14,000.00
Jumlah Total Rp. 154,000.00
G. PEKERJAAN INSTALASI
MEMASANG INSTALASI LISTRIK
1.000 Ttk Upah Kerja Listrik @ Rp. 75,000.00 Rp. 75,000.00
1.000 bh Terminal Colokan @ Rp. 25,000.00 Rp. 25,000.00
0.010 roll Kabel Listrik NYA @ Rp. 1,100,000.00 Rp. 11,000.00
Bahan Lainnya @ Rp. 10,000.00 Rp. 10,000.00
JUMLAH 121,000.00
overhead dan profit 10% Rp. 12,100.00
Jumlah Total Rp. 133,100.00
H. PEKERJAAN MEUBELER
1 M2 PEKERJAAN PINTU HPL
1.000 Lbr Multipleks 12 mm @ Rp. 155,000.00 Rp. 155,000.00
0.200 Kg Lem Kayu @ Rp. 20,000.00 Rp. 4,000.00
1.000 Lbr HPL @ Rp. 210,000.00 Rp. 210,000.00
1.000 set Engsel pintu @ Rp. 35,000.00 Rp. 35,000.00
1.000 set handle pintu @ Rp. 175,000.00 Rp. 175,000.00
1.000 Lbr Amplas @ Rp. 9,000.00 Rp. 9,000.00
20.000 bh Screw 6 @ Rp. 500.00 Rp. 10,000.00
0.500 Kg Lem HPL @ Rp. 55,000.00 Rp. 27,500.00
0.700 OH Pekerja @ Rp. 650,000.00 Rp. 455,000.00
JUMLAH Rp. 1,080,500.00
overhead dan profit 10% Rp. 108,050.00
Jumlah Total Rp. 1,188,550.00
1 M2 PEKERJAAN MEJA
4.000 Lbr Multipleks 12 mm @ Rp. 155,000.00 Rp. 620,000.00
0.200 Kg Lem Kayu @ Rp. 20,000.00 Rp. 4,000.00
4.000 Lbr HPL @ Rp. 210,000.00 Rp. 840,000.00
1.000 M2 Kaca Polos 5 mm @ Rp. 100,000.00 Rp. 100,000.00
4.000 bh Kaki Meja Steinless Bulat 5 cm @ Rp. 50,000.00 Rp. 200,000.00
1.000 Lbr Amplas @ Rp. 9,000.00 Rp. 9,000.00
20.000 bh Screw 6 @ Rp. 500.00 Rp. 10,000.00
0.140 Kg Lem HPL @ Rp. 55,000.00 Rp. 7,700.00
1.000 M2 Upah Kerja Lemari dan Meja @ Rp. 680,000.00 Rp. 680,000.00
JUMLAH Rp. 2,470,700.00
overhead dan profit 10% Rp. 247,070.00
Jumlah Total Rp. 2,717,770.00
1 M2 PEKERJAAN SIDEBOARD
3.000 Lbr Multipleks 12 mm @ Rp. 155,000.00 Rp. 465,000.00
0.200 Kg Lem Kayu @ Rp. 20,000.00 Rp. 4,000.00
3.000 Lbr HPL @ Rp. 210,000.00 Rp. 630,000.00
1.000 Lbr Amplas @ Rp. 9,000.00 Rp. 9,000.00
20.000 bh Screw 6 @ Rp. 500.00 Rp. 10,000.00
0.200 Kg Lem HPL @ Rp. 55,000.00 Rp. 11,000.00
1.000 M2 Upah kerja @ Rp. 680,000.00 Rp. 680,000.00
JUMLAH Rp. 1,809,000.00
overhead dan profit 10% Rp. 180,900.00
Jumlah Total Rp. 1,989,900.00
I. PEKERJAAN TAMBAHAN
1 M2 PEKERJAAN REPARASI SOFA
3.000 M2 Cover @ Rp. 300,000.00 Rp. 900,000.00
1.000 M2 Upah Kerja @ Rp. 155,000.00 Rp. 155,000.00
1,055,000.00
overhead dan profit 10% Rp. 105,500.00
Jumlah Total Rp. 1,160,500.00
R E K A P I T U L A S I
JUMLAH B 6,908,100.00
TOTAL KESELURUHAN 7,508,100.00
PEMBULATAN 7,500,000.00
R E K A P I T U L A S I