Data Perencanaan :
Panjang jembatan : 20 m
Lebar jembatan : 10 m
Kelas jembatan : I (satu)
Jumlah gelagar : 5 buah
Jarak antar gelagar :2m
Mutu beton (f’c) : 30 Mpa
Tinggi Pilar : 20 m
Berat jenis tanah (ɣ) : 1800 kg/m2
Sudut geser Tanah : 31o
Ka = tan2(45-Ø/2) : 0,32
Kp = tan2(45+Ø/2) : 3,124
Kohesi (c) :0
Ra total 114000
Va pada pilar = = =57000 kg
Jarak antar gelagar 2
Gaya Horizontal :
12000
- Beban garis : P= =4363,63 kg
2,75
2200
-Beban terbagi Rata : q= =800 kg /m
2,75
H = 5% (q L + P ) . 2
= 5% (800 . 20 + 4363,63 ) 2
= 2036,363 kg
MT −MG 195021,64−20006,177
SF = = =8,74>3 ok !
MG 20006,177
F = 0,6 A = 40 m2
Dewa Ketut Surya Pramana (125060102111004)
Σ H = 4001,235 kg Σ V = 67877,52 kg
F ΣV +C A 0,6 x 67877,52+ 0 x 40
= =10,19>3
ΣH 4001,235
Data Perencanaan
f’c = 30 MPa
fy = 240 MPa
1,4 1,4
ρmin = = =5,833 x 10−3
fy 240
( ffy' c β fy+600
ρmaks =0,75 0,85 1
600
)
=0,75 ( 0,85
240+600 )
30 600
ρmaks 0,85
240
ρmaks =0.048
Pw = Ka x 1000 x h2 x 0,5
Mz = 4000 x 0,33 + 2400 x 0,5 + 300 x 1,33 – 300 x 0,33 + 19200 x 0,5
= 12420 kgm
Penulangan
b = 100 cm
d = 100-10 = 90 cm
f’c = 30 MPa
fy = 240 MPa
Mz 12420
Mn= = =15525 kgm
∅ 0,8
Mn 15525 x 10 4
Rn= = =0,19 Mpa
b . d 2 1000. 9002
fy 240
m= = =9.41
0,85 f ' c 0,85 x 30
ρ=
1
m ( √
1− 1−
2. m. Rn
fy )
ρ=
1
9,41( √
1− 1−
2 x 9,41 x 0,19
240 )
ρ=0,0016
−3
5,833 x 10 > 0,0016
ρmin > ρ digunakan ρmin = 0,005833
As = ρ . b . d = 0,005833 x 100 x 90 = 52,5 cm2
Aso = 0,2 x As = 0,2 x 52,5 = 10,5 cm2
Dipakai : Tulangan utama D32-150 mm ; As = 53,00 cm2
Tulangan bagi D32-300 mm; Aso= 1267 cm2
KONTROL:
Keseimbangan gaya
C=T
Cc=T
0.85 . f ’ c . a . b= As . fy
As . fy
a= '
0.85 . f c . b
5300 x 240
¿
0.85 x 30 x 1000
a=50 mm
Letak garis netral:
a 50 '
c= = =58,82 mm< d =90 mm
β 1 0.85
Kontrol tegangan dan regangan baja:
Regangan baja
d −c
ε s=ε c x
c
100−58,82
ε s=0.003 x
58,82
ε s=0,002
Tegangan baja
fs = εs x Es
= 0.002 x 200000
= 400 MPa > 240 MPa OK!
Kontrol momen nominal:
( a2 )
Mn=As . fy d−
Mn=89790480 Nmm
Mn=89790,4 kgm
Mu
≤ Mn
∅
15525
≤ 89790,4
0.8
19406,25 ≤89790,4 OK!
Data Perencanaan :
- Mutu Beton ( f’c ) : 30 MPa
- Mutu Baja ( fy ) : 240 MPa
- Diameter bore pile : 30 cm
- Faktor Keselamatan : 1,5
Data Sondir tanah :
- qc : 200 kg/cm2
-H : 7,8 m
- JHP : 635,782 kg/cm
Dari Analisis :
- Pu : 313880 x 8 = 2511040 kg
- Mu : 820021.6 x 8 = 6560172.8 kgm
Direncanakan pondasi bore pile dengan sengkang spiral (∅ = 0,7) dan tulangan memanjang 6
– D12
Ast = π . D2 . n / 4
= π . 1,22 . 6 / 4
= 6,875 cm2 = 678,5 mm2
Ag =A
= 706,86 cm2
∅Pn = 0,85.∅.[0,85.f'c.(Ag-Ast)+fy.Ast]
= 0,85.0,7.[0,85.250.(70686-678,5)+2400. 678,5]
= 9820471,281 N
= 982047,128 kg
5
1 1,5 1,5 1
1
,5
1
,5
1
8
,5
1
,5
1
1
Ef = η = 1- θ(m-1)n + (n-1) m
90.m.n
Q = n x Qi x Ef = 15 x 181341 x 0,998
1 0,6
II
III
2 1 2
5
W2 = 2 x 1 x 2400 = 4800 kg
Momen Ultimate :
= 175576.2 kgm
Mu per pias 1 m
Mu = 21947.025 kgm
1,4 1,4
ρmin = = =0,00583
fy 240
0,85 x 25 600
¿ 0,75 x x 0,85 x =0,04031
240 600+240
b = 1000 mm
fy 240
m= = =11,294
0,85 x f ' c 0,85 x 25
ρ=
1
11,294 [ √
1− 1−
2 x 11,294 x 0,56
240 ]
=0,0035
KONTROL:
Keseimbangan gaya
C=T
Cc=T
0.85 . f ’ c . a . b= As . fy
As . fy
a=
0.85 . f ' c . b
5300 x 240
¿
0.85 x 30 x 1000
a=50 mm
Letak garis netral:
a 50 '
c= = =58,7 mm<d =100 mm
β 1 0.85
Kontrol tegangan dan regangan baja:
Regangan baja
d −c
ε s=ε c x
c
900−58,7
ε s=0.003 x
58,7
ε s=0,04
Tegangan baja
fs = εs x Es
= 0.04 x 200000
= 800 MPa > 240 MPa OK!
Kontrol momen nominal:
( a2 )
Mn=As . fy d−
Mn=1107466800 Nmm
Mn=110746,68 kgm
Mu
≤ Mn
∅
21947.025
≤ 110746,68
0.8
27433.78 ≤110746,68 OK!