ANALISA HARGA SATUAN PEMASANGAN BOX CULVERT

PROYEK : Penggantian Gorong-Gorong


No. PAKET KONTRAK : 602.1/13.001.ARS/APBD/KONST.JMB/X/22.02/2022
: Penggantian Gorong-Gorong Ruas Jalan TPA-
NAMA PAKET Segawe Pada sub Penggantian Jembatan

PROP / KAB / KODYA : Jawa Timur


ITEM PEMBAYARAN NO. : ............ PERKIRAAN VOL. PEK. : 1,00
JENIS PEKERJAAN : Pasang Box Culvert BC.40.40.120.10 (gandar 20 ton) TOTAL HARGA (Rp.) : 1.850.981,28
% THD. BIAYA
PROYEK : 0,00

                     
      PERKIRAAN HARGA JUMLAH
SATUA
NO.   KOMPONEN N KUANTITAS SATUAN HARGA
        (Rp.) (Rp.)
                     
             
A.   TENAGA          
             
1.   Pekerja (L01) Jam 0,9237 14.285,00   13.194,98  
2.   Tukang (L02) Jam 0,2309 17.142,00   3.958,49  
3.   Mandor (L03) Jam 0,2309 19.285,00   4.453,36  
             
          JUMLAH HARGA TENAGA       21.606,84  
             
B.   BAHAN          
             
1.   Box culvert BC.40.40.120.10 (gandar 20 ton) M1 1,0000 1.137.750,00   1.137.750,00  
             
             
             
             
             
             
             
             
             
             
          JUMLAH HARGA BAHAN       1.137.750,00  
             
C.   PERALATAN          
             
1.   Tamper (E25) Jam 0,1446 190.000,00   27.469,88  
2.   Flat Bed Truck (E11) Jam 0,2309 740.000,00   170.883,53  
3.   Alat Bantu Ls 1,0000 325.000,00   325.000,00  
             
             
             
             
             
JUMLAH HARGA
          PERALATAN       523.353,41  
                     
D.   JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )         1.682.710,25  
OVERHEAD &
E.   PROFIT   10,0 % x D       168.271,03  
F.   HARGA SATUAN PEKERJAAN ( D + E )           1.850.981,28  

Dibuat oleh Pelaksana :


CV.JOYO LESTARI CONSTRUCTION

INDAH LESTARI
Direktur