Analisa EI-221

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROGRAM : ......................................................................................................
KEGIATAN : ......................................................................................................
PEKERJAAN : ......................................................................................................
PROP. / KAB. / KOTA : RIAU
NOMOR PRODUK : C.2
ITEM PEMBAYARAN NO. : 2.2.(1) PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : PASANGAN BATU DENGAN MORTAR TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : #DIV/0!

PERKIRAAN JUMLAH HARGA


NO. KOMPONEN SATUAN HARGA SATUAN (Rp.)
KUANTITAS (Rp.)

A. TENAGA
1 Pekerja (L01) Jam 4,8193 25.000,00 120.481,93
2 Tukang Batu (L02) Jam 4,8193 28.500,00 137.349,40
3 Mandor (L03) Jam 0,4016 35.000,00 14.056,22
JUMLAH HARGA TENAGA 271.887,55

B. BAHAN
1 Batu (M02) M3 1,2000 400.000,00 480.000,00
2 Semen (PC) (M12) Kg 232,0000 1.500,00 348.000,00
3 Pasir (M01) M3 0,4808 250.000,00 120.206,90
JUMLAH HARGA BAHAN 948.206,90

C. PERALATAN
1 Concrate Mixer (E06) Jam 0,4016 119.620,00 48.040,16
2 Alat Bantu Ls 1,0000 1.000,00 1.000,00
JUMLAH HARGA PERALATAN 49.040,16

D. MOBILISASI
1 Concrate Mixer (E06) Jam 0,2209 119.620,00 26.422,09
JUMLAH HARGA MOBILISASI 26.422,09

E. PENGUJIAN BAHAN
1 Batu Ls 0,0030 400.000,00 1.200,00
JUMLAH PENGUJIAN BAHAN 1.200,00

F. BIAYA SMKK
1 Biaya SMKK Ls 0,0025 1.296.756,70 3.241,89
JUMLAH BIAYA SMKK 3.241,89

G. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.299.998,59


H. OVERHEAD & PROFIT 15,0% x G 194.999,79
I. PPN 11,0% 11,0% x G 142.999,84
J. HARGA SATUAN PEKERJAAN ( G + H + I ) 1.637.998,22