Anda di halaman 1dari 27

RENCANA ANGGARAN BIAYA ( R A B )

Nama Pekerjaan : Pavingisasi RT 01 RW 04


Lokasi : Kel. Gedog Kec. Sananwetan
Tahun Anggaran : 2023
Sumber Dana : APBD Kota Blitar

NOMOR HARGA JUMLAH HARGA


NO URAIAN PEKERJAAN SAT VOLUME
ANALISA SAT (Rp.) (Rp.)

I BIAYA OPERASIONAL
1 Honor Tim 60 % dari 5 % Pagu Ls 1.00 1,050,000.00 1,050,000.00
2 ATK/ Biaya lainya 40 % dari 5 % pagu Ls 1.00 700,000.00 700,000.00
1,750,000.00

II BIAYA KEBUTUHAN KONSTRUKSI


A KEBUTUHAN BAHAN
1 Semen PC Zak 50.00 60,200.00 3,010,000.00
2 Pasir Beton m3 3.00 146,700.00 440,100.00
3 Batu Kali Pecah m3 4.00 210,900.00 843,600.00
4 Paving Stone (10x20x8) cm m2 149.40 82,000.00 12,250,800.00
5 Pasir Urug m3 21.28 90,000.00 1,915,200.00
6 Kayu Klas IV (papan) m3 0.80 1,344,000.00 1,075,200.00
7 paku 3" (5-10 cm) kg 5.00 20,000.00 100,000.00
8 Minyak bekisting/Solar ltr 2.00 18,300.00 36,600.00

19,671,500.00

B KEBUTUHAN PEKERJA (dalam waktu 15 hari)


1 Pekerja Oh 4.00 86,500.00 5,190,000.00
2 Tukang Batu Oh 2.00 98,500.00 2,955,000.00
3 Kepala Tukang Oh 1.00 103,000.00 515,000.00
4 Mandor Oh 1.00 112,000.00 560,000.00
9,220,000.00

C BPJS
1 Pembayaran Iuran BPJS Ketenagakerjaan Ls 1.00 72,545.45 72,545.45

JUMLAH 30,714,045.45
Pajak 14 % 4,299,966.36
JUMLAH TOTAL 35,014,011.82
Dibulatkan 35,000,000.00

Blitar, 9 Maret 2023


Mengetahui, Menyetujui Dibuat Oleh
PEJABAT PEMBUAT KOMITMEN Ketua Kelompok Masyarakat Tim Persiapan
" MAJU BERSAMA "

Page 1 of 27
NOMOR HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
ANALISA SAT (Rp.) (Rp.)

SUJARWA SUGENG INDRA ISDIANTO


NIP. 19650609 199202 1 004 Ketua

Page 2 of 27
REKAPITULASI BIAYA

Nama Pekerjaan : Pavingisasi RT 01 RW 04


Lokasi : Kel. Gedog Kec. Sananwetan
Tahun Anggaran : 2023

NO URAIAN KEGIATAN JUMLAH

I BIAYA OPERASIONAL Rp 1,750,000.00

A PEKERJAAN PERSIAPAN Rp 1,244,954.40

B PEKERJAAN TANAH Rp 2,962,759.60

C PEKERJAAN PASANGAN Rp 17,948,088.60

D PEKERJAAN BETON Rp 6,749,705.03

E BPJS Rp 72,545.45

JUMLAH Rp 30,728,053.08
Pajak 14 % Rp 4,301,927.43
JUMLAH TOTAL Rp 35,029,980.52
DIBULATKAN Rp 35,000,000.00

Blitar, 9 Maret 2023


Mengetahui, Menyetujui Dibuat Oleh
PEJABAT PEMBUAT KOMITMEN Ketua Kelompok Masyarakat Tim Persiapan
" MAJU BERSAMA "

SUJARWA SUGENG ??????


NIP. 19650609 199202 1 004 Ketua
RENCANA ANGGARAN BIAYA ( R A B )

Nama Pekerjaan : Pavingisasi RT 01 RW 04


Lokasi : Kel. Gedog Kec. Sananwetan
Tahun Anggaran : 2023
Sumber Dana : APBD Kota Blitar

NOMOR HARGA JUMLAH HARGA


NO URAIAN PEKERJAAN SAT VOLUME
ANALISA SAT (Rp.) (Rp.)

I BIAYA OPERASIONAL
1 Honor Tim 60 % dari 5 % Pagu Ls 1.00 1,050,000.00 1,050,000.00
2 ATK/ Biaya lainya 40 % dari 5 % pagu Ls 1.00 700,000.00 700,000.00
1,750,000.00

II BIAYA KONTRUKSI
A PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan dan Persiapan m2 T.01 161.20 5,862.00 944,954.40
2 Pasang Papan Nama Kegiatan ( Prasasti ) bh 1.00 300,000.00 300,000.00

1,244,954.40
B PEKERJAAN TANAH
1 Galian tanah m3 T.06.a.1 16.12 55,005.10 886,682.21
2 Urugan Pasir m3 1.An. W1 14.51 143,098.80 2,076,077.39
2,962,759.60
C PEKERJAAN PASANGAN
1 Pasang Paving Persegi T = 8 cm m3 OL.II.1 145.08 120,605.00 17,497,373.40
2 Plesteran m' OL.III.1 32.24 13,980.00 450,715.20
17,948,088.60
D PEKERJAAN BETON
1 Cor Beton Amping Paving T = 10 cm m3 A.4.1.1.5 4.84 914,087.31 4,420,526.23
2 Begisting ( Dipakai 2 Kali ) m2 A.4.1.1.21 16.12 144,490.00 2,329,178.80
6,749,705.03
E BPJS
1 Pembayaran Iuran BPJS Ketenagakerjaan Ls 1.00 72,545.45 72,545.45
72,545.45

JUMLAH 30,728,053.08
Pajak 14 % 4,301,927.43
JUMLAH TOTAL 35,029,980.52
DIBULATKAN 35,000,000.00

Blitar, 9 Maret 2023


Mengetahui, Menyetujui Dibuat Oleh
PEJABAT PEMBUAT KOMITMEN Ketua Kelompok Masyarakat Tim Persiapan
" MAJU BERSAMA "

SUJARWA SUGENG ??????


NIP. 19650609 199202 1 004 Ketua

Page 4 of 27
BACK UP PERHITUNGAN VOLUME

Pekerjaan : Pavingisasi RT 01 RW 04
Lokasi : Kel. Gedog Kec. Sananwetan
Tahun : 2023

NO SKET/GAMBAR PERHITUNGAN VOLUME

Panjang Paving 80,6 m Lebar 2 m Pekerjaan Pembersihan dan Persiapan 2.00 x 80.60 =

Pasang Papan Nama Kegiatan ( Prasasti ) =

Galian tanah 0.10 x 2.00 x 80.60 =

Urugan Pasir 0.10 x 1.80 x 80.60 =

Pasang Paving Persegi T = 8 cm 1.80 x 80.60 =

Plesteran 0.20 x 80.60 x 2.00 =

Cor Beton Amping Paving T = 10 cm 0.10 x 0.30 x 80.60 x 2.00 =

Begisting ( Dipakai 2 Kali ) 0.10 x 80.60 x 2.00 =

Page 5 of 27
PERHITUNGAN VOLUME VOL SAT

161.20 161.20 m2

1.00 1.00 Ls

16.12 16.12 m3

14.51 14.51 m3

145.08 145.08 m2

32.24 32.24 m2

4.84 4.84 m3

16.12 16.12 m2

Page 6 of 27
DAFTAR ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG CIPTA KARYA

BERDASARKAN HARGA RATA-RATA DI PASARAN

A.2.2.1.13 1 m3 Pembongkaran Beton Bertulang


NO URAIAN KODE KOEFISIEN SATUAN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja L.01 1.3334 Oh Rp. 81,800.00 Rp. 109,072.12
Mandor L.04 0.6660 Oh Rp. 102,000.00 Rp. 67,932.00
Jumlah Tenaga Rp. 177,004.12
B BAHAN
-- -- - -- Rp. - Rp. -
Jumlah Bahan Rp. -
C PERALATAN
-- -- - -- Rp. - Rp. -
Jumlah Peralatan Rp. -
D JUMLAH (A+B+C) Rp. 177,004.12
E OVERHEAD & PROFIT 5.0 % x D Rp. 8,850.21
F JUMLAH SELURUHNYA Rp. 185,854.33
Harga Satuan Pekerjaan (HSP) Rp. 185,850.00

Ans. Kons. 1 1 m3 Membongkar lantai lama, berikut pekerjaan membersihkan batu bata/paving atau ubin-ubin yang dibongkar
NO URAIAN KODE KOEFISIEN SATUAN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja L.01 0.1600 Oh Rp. 81,800.00 Rp. 13,088.00
Mandor L.04 0.0100 Oh Rp. 102,000.00 Rp. 1,020.00
Jumlah Tenaga Rp. 14,108.00
B BAHAN
-- -- - -- Rp. - Rp. -
Jumlah Bahan Rp. -
C PERALATAN
-- -- - -- Rp. - Rp. -
Jumlah Peralatan Rp. -
D JUMLAH (A+B+C) Rp. 14,108.00
E OVERHEAD & PROFIT 5.0 % x D Rp. 705.40
F JUMLAH SELURUHNYA Rp. 14,813.40
Harga Satuan Pekerjaan (HSP) Rp. 14,810.00

OL.VII.4 1 m2 Mengecat Kanstin/Kerb


NO URAIAN KODE KOEFISIEN SATUAN HARGA SATUAN JUMLAH HARGA
A TENAGA
94 Pekerja L.01 0.1500 Oh Rp. 81,800.00 Rp. 12,270.00
94 Tukang Cat L.02 0.0950 Oh Rp. 92,000.00 Rp. 8,740.00
Kepala Tukang L.03 0.0100 Oh Rp. 97,000.00 Rp. 970.00
Mandor L.04 0.0025 Oh Rp. 102,000.00 Rp. 255.00
Jumlah Tenaga Rp. 22,235.00
B BAHAN
94 Plamir Tembok M.72 0.1000 kg Rp. 31,300.00 Rp. 3,130.00
94 Kertas Gosok M.73 0.2000 Lbr Rp. 2,500.00 Rp. 500.00
94 Cat minyak M.74 0.2240 Kg Rp. 69,000.00 Rp. 15,456.00
94 Thinner M.75 0.2260 Ltr Rp. 39,700.00 Rp. 8,972.20
94 Jumlah Bahan Rp. 28,058.20
C PERALATAN
-- -- - -- Rp. - Rp. -
Jumlah Peralatan Rp. -
D JUMLAH (A+B+C) Rp. 50,293.20
E OVERHEAD & PROFIT 5.0 % x D Rp. 2,514.66
F JUMLAH SELURUHNYA Rp. 52,807.86
Harga Satuan Pekerjaan (HSP) Rp. 52,800.00

OL.1.2 1 m3 Pembuangan Tanah Sejauh 3 km(atau lebih)


NO URAIAN KODE KOEFISIEN SATUAN HARGA SATUAN JUMLAH HARGA
A TENAGA

Jumlah Tenaga Rp. -

Page 7 of 27
B BAHAN

Jumlah Bahan Rp. -


C PERALATAN
Dump Truck E.08.b 0.2218 Rp. 316,000.00 70,088.80
Jumlah Peralatan Rp. 70,088.80
D JUMLAH (A+B+C) Rp. 70,088.80
E OVERHEAD & PROFIT 5.0 % x D Rp. 3,504.44
F JUMLAH SELURUHNYA Rp. 73,593.24
Harga Satuan Pekerjaan (HSP) Rp. 73,590.00

Page 8 of 27
A. UMUM
A.1 PEKERJAAN TANAH (T.xx)
Pekerjaan tanah ini meliputi pekerjaan galian dan timbunan tanah serta houling yang dapat dilaksanakan
baik secara manual maupun secara mekanis.

A.1.1 Secara manual menggunakan tenaga manusia


a. AHSP pembersihan dan pengupasan permukaan tanah
T.01 1 m2 Pembersihan dan striping/kosrekan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.060 81,800.00 4,908.00
2 Mandor L.04 OH 0.006 102,000.00 612.00
Jumlah Harga Tenaga Kerja 5,520.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 5,520.00
E Overhead + Profit 5% x D 276.00
F Harga Satuan Pekerjaan per - m2 (D+E) 5,796.00

T.06 Pekerjaan Galian Tanah Biasa


T.06.a Cara manual
T.06.a.1) 1 m3 Galian tanah biasa sedalam < 1 m

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.5630 81,800.00 46,053.40
2 Mandor L.04 OH 0.0563 102,000.00 5,742.60
Jumlah Harga Tenaga Kerja 51,796.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 51,796.00
E Overhead + Profit 5% x D 2,589.80
F Harga Satuan Pekerjaan per - m3 (D+E) 54,385.80

T.14c 1 m3 Timbunan pasir sebagai bahan pengisi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.400 81,800.00 32,720.00
2 Mandor L.04 OH 0.040 102,000.00 4,080.00
Jumlah Harga Tenaga Kerja 36,800.00
B Bahan
1 Pasir Urug M.14.b m3 1.200 90,500.00 108,600.00
Jumlah Harga Bahan 108,600.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 145,400.00
E Overhead + Profit 5% x D 7,270.00
F Harga Satuan Pekerjaan per - m3 (D+E) 152,670.00

T.15a.6) Mengangkut 1 m3 hasil galian dengan jarak angkut 100 m

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)


Page 1 of 27
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.6000 81,800.00 49,080.00
2 Mandor L.04 OH 0.0300 102,000.00 3,060.00
Jumlah Harga Tenaga Kerja 52,140.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 52,140.00
E Overhead + Profit 5% x D 2,607.00
F Harga Satuan Pekerjaan per - m3 (D+E) 54,747.00

Page 2 of 27
A.2
PEKERJAAN PASANGAN (P.xx)
(Normatif)

P.01e.2)
Bongkar 1 m3 pasangan batu (manual)

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah (Rp)
(Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.800 81,800.00 147,240.00
2 Mandor L.04 OH 0.180 102,000.00 18,360.00
Jumlah Harga Tenaga Kerja 165,600.00
B Bahan
Jumlah Harga Bahan -
C Peralatan *)
1 Palu/Godam (Baja keras) E.30 bh 0.006 24,500.00 147.00
2 Pahat Beton (Baja keras) E.29.a bh 0.009 10,000.00 90.00
3 Linggis (Baja keras) E.29 bh 0.020 31,000.00 620.00
Jumlah Harga Peralatan 857.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 166,457.00
E Overhead + Profit 5% x D 8,322.85
F Harga Satuan Pekerjaan per - m3 (D+E) 174,779.85
*) Jika tidak perlu menggunakan peralatan khusus (baja keras), maka HSD = 0
**) Hasil pembersihan 1m3 pasangan batu yang dibongkar, umumnya menghasilkan 0,6 - 0,65 m3 batu

Page 3 of 27
DAFTAR ANALISA BAHAN DAN UPAH KERJA

OVL.MAN HOLE 1

1. MAN HOLE BERLOGO ( 60 x 60 cm )/PSG/PENGECATAN

Biaya Bahan

1.00 Bh Man Hole Rp. 815,500.00 =Rp. 815,500.00

Upah pekerja Sub total =Rp. 815,500.00

0.1200 Oh Pekerja Rp. 81,800.00 =Rp. 9,816.00


0.0600 Oh Tukang Besi Rp. 92,000.00 =Rp. 5,520.00

0.0060 Oh Kepala Tukang Besi Rp. 97,000.00 =Rp. 582.00

0.0060 Oh Mandor Rp. 102,000.00 =Rp. 612.00


Sub Total = Rp 16,530.00

Sewa Peralatan

0.51 Jam Mesin Las Listrik Rp. 175,000.00 =Rp. 89,250.00

Sub Total = Rp 89,250.00

Total =Rp. 921,280.00

Over Head + Provit ( 5% ) =Rp. 46,064.00

Total =Rp. 967,344.00

Dibulatkan =Rp. 967,344.00

OVL. GRILL 2

2. GRILL TANGKAPAN AIR ( 40 x 60 cm )/PSG/PENGECATAN

Biaya Bahan

1 Bh Grill Tangkapan Air Rp. 650,000.00 =Rp. 650,000.00

Upah pekerja Sub total =Rp. 650,000.00

0.1200 Oh Pekerja Rp. 81,800.00 =Rp. 9,816.00

0.0600 Oh Tukang Besi Rp. 92,000.00 =Rp. 5,520.00

0.0060 Oh Kepala Tukang Besi Rp. 97,000.00 =Rp. 582.00


0.0060 Oh Mandor Rp. 102,000.00 =Rp. 612.00

Sub Total = Rp 16,530.00

Sewa Peralatan
0.51 Jam Mesin Las Listrik Rp. 175,000.00 =Rp. 89,250.00

Sub Total = Rp 89,250.00

Total =Rp. 755,780.00

Over Head + Provit ( 5% ) =Rp. 37,789.00

Total =Rp. 793,569.00

Dibulatkan =Rp. 793,569.00

OVL.KERB 3

3 KANSTEIN / KERB ( 0.5 MTR )

Memasang kerb per / 20 cm x 30 cm x 50 cm

BIAYA BAHAN
1 Bh Kerb Lokal Rp. 29,500.00 =Rp. 29,500.00

29,500.00

Upah Pekerja

0.1400 Oh Pekerja Rp. 81,800.00 =Rp. 11,452.00

0.0700 Oh Tukang Batu Rp. 92,000.00 =Rp. 6,440.00

0.0070 Oh Kepala Tukang Batu Rp. 97,000.00 =Rp. 679.00

0.0070 Oh Mandor Rp. 102,000.00 =Rp. 714.00

19,285.00

Total = Rp 48,785.00

Page 4 of 27
Over Head + Provit ( 5% ) =Rp. 2,439.25

Total =Rp. 51,224.25

Dibulatkan =Rp. 51,224.00

Page 5 of 27
OVL. GRANIT 4

4 GRANIT DIFABLE Uk 30 x 30 cm

BIAYA BAHAN

1.0000 m2 Granit Difable TGSI 30 x 30 cm Rp. 462,500.00 =Rp. 462,500.00

Sub total =Rp. 462,500.00

9.8000 kg Semen PC Rp. 1,500.00 =Rp. 14,700.00

1.3000 kg Semen Putih Rp. 2,462.50 =Rp. 3,201.25

0.0450 m 3
Pasir Pasang Rp. 123,500.00 =Rp. 5,557.50

Upah Pekerja Sub total =Rp. 23,458.75

0.2500 Oh Pekerja Rp. 81,800.00 =Rp. 20,450.00


0.1200 Oh Tukang Batu Rp. 92,000.00 =Rp. 11,040.00

0.0120 Oh Kepala Tukang Batu Rp. 97,000.00 =Rp. 1,164.00

0.0130 Oh Mandor Rp. 102,000.00 =Rp. 1,326.00


Sub Total = Rp 33,980.00

Total =Rp. 519,938.75

Over Head + Provit ( 5% ) =Rp. 25,996.94

Total =Rp. 545,935.69

Dibulatkan =Rp. 545,936.00

OVL. GRANIT 6

6 GRANIT Niro Granite Terra Coarse R 11 Uk 30 x 30 cm

BIAYA BAHAN

1.0000 m2 Niro Granite 30 x 30 cm Rp. 285,000.00 =Rp. 285,000.00

Sub total =Rp. 285,000.00

8.1900 kg Semen PC Rp. 1,500.00 =Rp. 12,285.00

1.6200 kg Semen Putih Rp. 2,462.50 =Rp. 3,989.25

0.0450 m 3
Pasir Pasang Rp. 123,500.00 =Rp. 5,557.50

Upah Pekerja Sub total =Rp. 21,831.75

0.2500 Oh Pekerja Rp. 81,800.00 =Rp. 20,450.00


0.1200 Oh Tukang Batu Rp. 92,000.00 =Rp. 11,040.00

0.0120 Oh Kepala Tukang Batu Rp. 97,000.00 =Rp. 1,164.00

0.0130 Oh Mandor Rp. 102,000.00 =Rp. 1,326.00


Sub Total = Rp 33,980.00

Total =Rp. 340,811.75

Over Head + Provit ( 5% ) =Rp. 17,040.59

Total =Rp. 357,852.34

Dibulatkan =Rp. 357,852.00

OVL. GRANIT 7

7 GRANIT Niro Granite Terra Coarse R 11 Uk 15 x 30 cm

BIAYA BAHAN

1.0000 m2 Niro Granite 15 x 30 cm Rp. 323,500.00 =Rp. 323,500.00

Sub total =Rp. 323,500.00


8.1900 kg Semen PC Rp. 1,500.00 =Rp. 12,285.00

1.6200 kg Semen Putih Rp. 2,462.50 =Rp. 3,989.25

0.0450 m 3
Pasir Pasang Rp. 123,500.00 =Rp. 5,557.50

Upah Pekerja Sub total =Rp. 21,831.75

0.2500 Oh Pekerja Rp. 81,800.00 =Rp. 20,450.00

0.1200 Oh Tukang Batu Rp. 92,000.00 =Rp. 11,040.00

0.0120 Oh Kepala Tukang Batu Rp. 97,000.00 =Rp. 1,164.00

0.0130 Oh Mandor Rp. 102,000.00 =Rp. 1,326.00

Sub Total = Rp 33,980.00

Page 6 of 27
Total =Rp. 379,311.75

Over Head + Provit ( 5% ) =Rp. 18,965.59

Total =Rp. 398,277.34

Dibulatkan =Rp. 398,277.00

Page 7 of 27
OVL. GRANIT 8

8 GRANIT Niro Granite Terra Coarse R 11 Uk 10 x 30 cm

BIAYA BAHAN

1.0000 m2 Niro Granite 10 x 30 cm Rp. 362,500.00 =Rp. 362,500.00

Sub total =Rp. 362,500.00

8.1900 kg Semen PC Rp. 1,500.00 =Rp. 12,285.00

1.6200 kg Semen Putih Rp. 2,462.50 =Rp. 3,989.25

0.0450 m 3
Pasir Pasang Rp. 123,500.00 =Rp. 5,557.50

Upah Pekerja Sub total =Rp. 21,831.75

0.2500 Oh Pekerja Rp. 81,800.00 =Rp. 20,450.00


0.1200 Oh Tukang Batu Rp. 92,000.00 =Rp. 11,040.00

0.0120 Oh Kepala Tukang Batu Rp. 97,000.00 =Rp. 1,164.00

0.0130 Oh Mandor Rp. 102,000.00 =Rp. 1,326.00


Sub Total = Rp 33,980.00

Total =Rp. 418,311.75

Over Head + Provit ( 5% ) =Rp. 20,915.59

Total =Rp. 439,227.34

Dibulatkan =Rp. 439,227.00

Page 8 of 27
RENCANA ANGGARAN BIAYA ( R A B )
PENYELENGGARAAN KEAMANAN DAN KESEHATAN KERJA SERTA KESELAMATAN KONSTRUKSI

### : Err:509
### : Err:509

Nama Pekerjaan : Pavingisasi RT 01 RW 04


Lokasi : Kel. Gedog Kec. Sananwetan

Tahun Anggaran : 2023

SATUAN
NO URAIAN PEKERJAAN KUANTITAS HARGA SATUAN TOTAL HARGA KET
UKURAN

1 2 3 4 5 6 7

1 PENYIAPAN RKK

a Rencana Keselamatan
Memperhatikan jumlah
b Pembuatan Prosedur dan Instruksi Kerja Set 1 Rp255,000.00 Rp255,000.00 dan jenis pekerjaan yang
dikerjakan
c Penyiapan Formulir

A Sub Total Penyiapan RKK Rp255,000.00

2 Sosialisasi Dan Promosi K3

a Induksi K3 (Safety Induction ) Org 1 Rp7,000.00 Rp7,000.00

b Pengarahan K3 (safety briefing) Org 1 Rp31,000.00 Rp31,000.00

c Pelatihan K3 Org 1 Rp32,000.00 Rp32,000.00

d Simulasi K3; Org 1 Rp8,000.00 Rp8,000.00

e Spanduk (banner) Unit 1 Rp145,000.00 Rp145,000.00

f Poster Unit 1 Rp52,000.00 Rp52,000.00

g Papan Informasi K3. Unit 1 Rp480,000.00 Rp480,000.00

B Sub Total Sosialisasi dan Promosi dan Pelatihan Rp755,000.00

3 ALAT PELINDUNG KERJA TERDIRI DARI :

a Pembatas Area Ls 1 Rp152,000.00 Rp152,000.00 Sesuai Kebutuhan

b Tali Keselamatan Ls 1 Rp153,000.00 Rp153,000.00 Sesuai Kebutuhan

C Sub Total Alat Pelindung Kerja Rp305,000.00

4 ALAT PELINDUNG DIRI TERDIRI DARI :

Memperhatikan
1 Topi Pelindung (Safety Helmet) Bh 9 Rp31,000.00 Rp279,000.00 perkiraan jumlah pekerja,
tamu dan staf

2 Pelindung mata (Googles Spectacles) Psg 9 Rp11,000.00 Rp99,000.00 Sesuai Kebutuhan

3 Pelindung Pernafasan dan Mulut (Masker) Bh 9 Rp9,000.00 Rp81,000.00 Sesuai Kebutuhan

4 Sarung Tangan (Safety Gloves) Psg 9 Rp15,500.00 Rp139,500.00 Sesuai Kebutuhan

Memperhatikan
5 Sepatu Keselamatan (Rubber Safety Shoes) Psg 9 Rp93,000.00 Rp837,000.00 perkiraan jumlah pekerja,
tamu dan staf

6 Rompi Safety Bh 9 Rp31,000.00 Rp279,000.00 Sesuai Kebutuhan

D Sub Total Alat Pelindung Diri Rp1,714,500.00

5 ASURANSI DAM PERJANJIAN Nilai Kontak =

a Asuransi BPJS Ls 1 Rp1,529,500.00 Rp1,529,500.00 < 5M

E Sub Total Asuransi Dan Perjanjian Rp1,529,500.00

6 PERSONIL K3

Personil K3 Konstruksi

a Petugas K3

Page 9 of 27
SATUAN
NO URAIAN PEKERJAAN KUANTITAS HARGA SATUAN TOTAL HARGA KET
UKURAN

1 2 3 4 5 6 7
Memperhatikan waktu
F Sub Total Personil K3 Konstruksi OB 1 Rp2,350,000.00 Rp2,350,000.00
pekerjaan

Rp2,350,000.00

Page 10 of 27
SATUAN
NO URAIAN PEKERJAAN KUANTITAS HARGA SATUAN TOTAL HARGA KET
UKURAN

1 2 3 4 5 6 7

7 FASILITAS SARANA KESEHATAN

Memperhatikan
a Peralatan P3K (Kotak P3K, Obat Luka, Perban, dll) Ls 1 Rp78,000.00 Rp78,000.00 perkiraan jumlah pekerja,
tamu dan staf

b Protokol Kesehatan Pencegahan Covid-19

1 Pengukur Suhu Badan Nir Sentuh Thermometer Scan Bh 1 Rp655,000.00 Rp655,000.00 Sesuai Kebutuhan

2 Pencuci Tangan (Tandon Air dan Sabun) Bh 1 Rp158,000.00 Rp158,000.00 Sesuai Kebutuhan

G Sub Total Fasilitas Sarana dan Prasarana Kesehatan: Rp891,000.00

8 RAMBU - RAMBU TERDIRI


Memperhatikan lokasi
a Sanduk ( Banner ) uk 0.75m x 3.00 m Lb 2 Rp78,000.00 Rp156,000.00 pekerjaan dan waktu
pekerjaan
b Rambu Peringatan dengan Kata-Kata unit 2 Rp78,000.00 Rp156,000.00 Sesuai Kebutuhan

c Rambu Peringatan Pekerjaan di Jalan unit 2 Rp78,000.00 Rp156,000.00 Sesuai Kebutuhan

H Sub Total Fasilitas Sarana dan Prasarana Kesehatan: Rp468,000.00

9 LAIN - LAIN TERKAIT PENGENDALIAN RESIKO K3


Memperhatikan lokasi
a Alat Pemadam Api ( APAR ) 10 kg Unit 1 Rp745,000.00 Rp745,000.00 pekerjaan dan waktu
pekerjaan
b Lampu Darurat unit 1 Rp74,000.00 Rp74,000.00 Sesuai Kebutuhan

c Bendera K3 unit 1 Rp70,000.00 Rp70,000.00 Sesuai Kebutuhan

I Sub Total Fasilitas Sarana dan Prasarana Kesehatan: Rp889,000.00

Total Mata Pembayaran Penyelenggaraan SMKK Rp9,157,000.00

Page 11 of 27
Analisa EI-

ITEM PEMBAYARAN NO. : 2.3.(10)


JENIS PEKERJAAN : Saluran Berbentuk U Tipe Ds 2 ( Uk. 60 . 70 )
SATUAN PEMBAYARAN : M'

No Uraian Satuan Koef Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
1 Pekerja L.01 jam 2.3333 11,685.71 27,266.67
2 Tukang L.02 jam 0.9333 13,142.86 12,266.67
3 Mandor L.04 jam 0.4667 14,571.43 6,800.00
JUMLAH HARGA TENAGA 46,333.33

B BAHAN
1 Saluran U Tipe DS 2 ( uk 60.70.120.8 cm ) M.71 M' 0.8333 850,500.00 708,750.00
2 Galian M3 0.4200 54,385.80 22,842.04
3 Material Pilihan M.11 M3 0.4200 123,500.00 51,870.00

JUMLAH HARGA BAHAN 783,462.04

C PERALATAN
1 Exavator Pc75 E.25 Jam 0.2209 405,000.00 89,464.50

JUMLAH HARGA PERALATAN 89,464.50

D JUMLAH HARGA TENAGA,BAHAN DAN PERALATAN (A+B+C) 919,259.87


E OVERHEAD & PROFIT = 5.00 % 45,962.99
F JUMLAH (D+E) 965,222.86
G HARGA SATUAN PEKERJAAN 965,222.00

Note :
1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran berat untuk bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata
pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali terdapat Penyesuaian Harga
( Eskalasi / Deskalasi ) sesuai ketentuan dalam Intruksi Kepada Peserta Lelang.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan Operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar
dari kontrak ) dan biaya - biaya lainnya.
DAFTAR HARGA SATUAN BAHAN BANGUNAN DAN UPAH KERJA
PEMERINTAH KOTA BLITAR TAHUN ANGGARAN 2022

DAFTAR HARGA RATA-RATA BAHAN BANGUNAN

HARGA RERATA
NO. JENIS BAHAN KODE UKURAN SATUAN
(Rp)

1 Batu kali pecah Crusher M.12 1/2 m3 165,000.00


2 Pasir beton/cor M.14.a - m3 132,500.00
3 Pasir pasang M.11 - m 3
123,500.00
4 Pasir urug M.14.b - m3 90,500.00
5 Urugan Tanah Tanam m 3

6 Batu merah klas I - bh


7 Semen Gresik (PC Gresik) M.15 40 kg zak 60,000.00
8 Semen putih M.15.b 40 kg zak 98,500.00
9 Air M.02 m 3
10,000.00

1 Kayu bekisting, papan randu (mutu kayu klas IV) M.32 3/20-200 m3 1,175,000.00
2 Kayu bekisting, usuk sengon (mutu kayu klas IV) M.33.d 4/6-200 m3 2,125,000.00
3 Multiplek t = 12 mm M.39.d lbr 156,000.00
4 Bambu Apus M.61 bh 18,500.00

1 Besi beton polos M.55.d - kg 12,600.00


2 Besi beton ulir M.56 - kg 13,300.00
3 Kawat ikat beton (bendrat) M.60 - kg 23,500.00

1 Kanstin (home industri) M.62 20x30x50 bh 29,500.00


2 Man Hole M.63 60 x 60 cm unit 815,500.00
3 Grill Tangkapan Air M.76 40 x 60 cm unit 650,000.00
4 Roman Granit Difable TGSI M.64 30 x 30 m2 462,500.00
5 Niro Granite 60 x 60 cm M.65 60 x 60 m2
6 Niro Granite 30 x 60 cm M.66 30 x 60 m2
7 Niro Granite 30 x 30 cm M.67 30 x 30 m2 285,000.00
8 Niro Granite 15 x 30 cm M.68 15 x 30 m2 323,500.00
9 Niro Granite 10 x 30 cm M.69 10 x 30 m2 362,500.00
10 Keramik Warna 30 x 30 Asia Tile ( setara ) M.70 30 x 30 m2
11 Uditch 60 .70.120.8 cm ( Gandar 10 Ton ) M.71 unit 850,500.00

1 Plamir Tembok M.72 kg 31,300.00


2 Kertas Gosok M.73 Lbr 2,500.00
3 Cat minyak ( Cat besi Emco ) M.74 Kg 69,000.00
4 Thinner M.75 Ltr 39,700.00
5 Paku kayu M.71.b 2,5" - 3" kg 21,500.00

1 Solar Industri M.129 ltr 13,500.00

Page 13 of 27
2 Minyak tanah non subsidi - ltr
3 Minyak pelumas - ltr
4 Exavator Pc75 E.25 Jam 405,000.00
5 Palu / Bodem E.30 Bh hari 24,500.00
6 Mollen E.28.b Bh hari 181,000.00
7 Dump Truck E.08.b Jam 316,000.00
8 Linggis E.29 Bh hari 31,000.00
9 Mesin Las Listrik E.31 250A, diesel Jam 175,000.00
10 Betel E.29.a Bh hari 10,000.00

Page 14 of 27
HARGA RERATA
DAFTAR UPAH KERJA HARIAN KODE SATUAN
(Rp)

1 MANDOR L.04 7 jam/hari Org/hr 102,000.00


2 KEPALA TK. BATU L.03 7 jam/hari Org/hr 97,000.00
3 KEPALA TK. BESI L.03 7 jam/hari Org/hr 97,000.00
4 KEPALA TK. CAT L.03 7 jam/hari Org/hr 97,000.00
5 TUKANG BATU L.02 7 jam/hari Org/hr 92,000.00
6 TUKANG BESI L.02 7 jam/hari Org/hr 92,000.00
7 TUKANG CAT L.02 7 jam/hari Org/hr 92,000.00
8 PEMBANTU TUKANG / PEKERJA/BURUH TERAMPIL L.01 7 jam/hari Org/hr 81,800.00

Page 15 of 27
A.3 PEKERJAAN BETON (B.xx)
(Normatif)
B.02 1 m3 beton mutu, f’c = 7,4 MPa (K100), slump (12±2) cm, w/c = 0,87
B.02b Menggunakan Molen

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah (Rp)
(Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.323 81,800.00 108,221.40
2 Tukang batu L.02 OH 0.189 92,000.00 17,388.00
3 Kepala tukang L.03 OH 0.019 97,000.00 1,843.00
4 Mandor L.04 OH 0.132 102,000.00 13,494.60
Jumlah Harga Tenaga Kerja 140,947.00
B Bahan
1 PC / Portland Cement M.15 kg 247 1,500.00 370,500.00
2 PB / Pasir Beton M.14.a m3 0.621 132,500.00 82,282.50
3 Batu kali pecah 1/2 M.12 m3 0.74 165,000.00 122,100.00
4 Air M.02 L 215 10.00 2,150.00
Jumlah Harga Bahan 577,032.50
C Peralatan
1 Molen 0,35 m3 E.28.b Sewa-hari 0.250 181,000.00 45,250.00
Jumlah Harga Peralatan 45,250.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 763,229.50
E Overhead + Profit 5% x D 38,161.48
F Harga Satuan Pekerjaan per - m3 (D+E) 801,390.98

Harga bahan Pasir beton dan batu pecah dikonversi ke kg (= harga bahan/berat jenis bahan)

B.08 1 m3 beton mutu, f’c = 21,7 MPa (K250), slump (12±2) cm, w/c = 0,56
B.08b Menggunakan Molen

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah (Rp)
(Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.323 81,800.00 108,221.40
2 Tukang batu L.02 OH 0.189 92,000.00 17,388.00
3 Kepala tukang L.03 OH 0.019 97,000.00 1,843.00
4 Mandor L.04 OH 0.132 102,000.00 13,464.00
Jumlah Harga Tenaga Kerja 140,916.40
B Bahan
1 PC / Portland Cement M.15 kg 384.00 1,500.00 576,000.00
2 PB / Pasir Beton M.14.a kg 692.00 94.64 65,492.86
3 Batu kali pecah 1/2 M.12 kg 1,039.00 122.22 126,988.89
4 Air M.02 L 215.00 10.00 2,150.00

Page 16 of 27
Jumlah Harga Bahan 770,631.75
C Peralatan
1 Molen E.28.b Sewa-hari 0.250 181,000.00 45,250.00
Jumlah Harga Peralatan 45,250.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 956,798.15
E Overhead + Profit 5% x D 47,839.91
F Harga Satuan Pekerjaan per - m3 (D+E) 1,004,638.05
Harga bahan Pasir beton dan batu pecah dikonversi ke kg (= harga bahan/berat jenis bahan)

Page 17 of 27
A.3.3 Koefisien untuk analisa harga satuan pekerjaan pembesian beton
B.17 Pembesian 100 kg dengan besi polos atau ulir

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.700 81,800.00 57,260.00
2 Tukang besi L.02 OH 0.700 92,000.00 64,400.00
3 Kepala tukang L.03 OH 0.070 97,000.00 6,790.00
4 Mandor L.04 OH 0.070 102,000.00 7,140.00
Jumlah Harga Tenaga Kerja 135,590.00
B Bahan
1 Besi Beton (polos/ulir) M.55.d kg 105 12,600.00 1,323,000.00
2 Kawat Ikat M.60 kg 1.5 23,500.00 35,250.00
Jumlah Harga Bahan 1,358,250.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,493,840.00
E Overhead + Profit 5% x D 74,692.00
F Harga Satuan Pekerjaan per - 100kg (D+E) 1,568,532.00
G Harga Satuan Pekerjaan per - 1kg (F/100) 15,685.32

A.3.4 Koefisien untuk analisa harga satuan pekerjaan pembuatan/penyediaan bekisting beton
B.21.b 1 m² bekisting lantai beton biasa dengan multiflex 12 mm (TP) 2 x pakai

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)

A TENAGA
Pekerja L.01 OH 0.200 81,800.00 16,360.00
Tukang L.02 OH 0.100 92,000.00 9,200.00
Kepala Tukang L.03 OH 0.010 97,000.00 970.00
Mandor L.04 OH 0.020 102,000.00 2,040.00
Jumlah Harga Tenaga Kerja 28,570.00
B BAHAN
Multiflex 12 (2 x pakai) M.39.d Lembar 0.2030 156,000.00 31,668.00
Kaso 5/7 cm (2 x pakai) M.33.d m3 0.0080 2,125,000.00 17,000.00
Paku 5 cm dan 7 cm M.71.b Kg 0.2200 21,500.00 4,730.00
Minyak bekisting M.129 Liter 0.2000 13,500.00 2,700.00
Jumlah Harga 56,098.00
C PERALATAN

Jumlah Harga Peralatan -


D Jumlah (A+B+C) 84,668.00
E Overhead & Profit 5% x D 4,233.40
F Harga Satuan Pekerjaan (D+E) 88,901.00
CATATAN:
* Bahan digunakan berulang kali, yang ke-1, koefisien 0,353 (multiflex) dan 0,014 (Kaso)

Page 18 of 27
yang ke-2, koefisien menjadi 0,203 (multiflex) dan 0,008 (Kaso)
yang ke-3, koefisien menjadi 0,128 (multiflex) dan 0,005 (Kaso)
yang ke-4, koefisien menjadi 0,091 (multiflex) dan 0,003 (Kaso)

Page 19 of 27

Anda mungkin juga menyukai