Anda di halaman 1dari 1

Analisa EI-331

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROGRAM : ......................................................................................................
KEGIATAN : ......................................................................................................
PEKERJAAN : ......................................................................................................
PROP. / KAB. / KOTA : RIAU
NOMOR PRODUK : D.10
ITEM PEMBAYARAN NO. : 3.3.(1) PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : PENYIAPAN BADAN JALAN TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : M2 % THD. BIAYA PROYEK : #DIV/0!

PERKIRAAN JUMLAH HARGA


NO. KOMPONEN SATUAN HARGA SATUAN (Rp.)
KUANTITAS (Rp.)

A. TENAGA
1 Pekerja (L01) Jam 0,0034 25.000,00 86,06
2 Mandor (L03) Jam 0,0017 35.000,00 60,24
JUMLAH HARGA TENAGA 146,30

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN
1 Motor Grader (E13) Jam 0,0008 643.013,62 514,41
2 Vibro Roller (E19) Jam 0,0022 378.124,31 831,87
3 Alat Bantu Ls 1,0000 100,00 100,00
JUMLAH HARGA PERALATAN 1.446,28

D. MOBILISASI
1 Motor Grader (E13) Jam 0,0004 643.013,62 282,93
2 Vibro Roller (E19) Jam 0,0012 378.124,31 457,53
JUMLAH HARGA MOBILISASI 740,46

E. PENGUJIAN BAHAN

JUMLAH PENGUJIAN BAHAN -

F. BIAYA SMKK
1 Biaya SMKK Ls 0,0025 2.333,04 5,83
JUMLAH BIAYA SMKK 5,83

G. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.338,87


H. OVERHEAD & PROFIT 15,0% x G 350,83
I. PPN 11,0% 11,0% x G 257,28
J. HARGA SATUAN PEKERJAAN ( G + H + I ) 2.946,98