PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 4.2.(1) PERKIRAAN VOL. PEK. : 1,449.50
JENIS PEKERJAAN : Laburan Aspal (Buras) TOTAL HARGA (Rp.) : 26,204,162.47
SATUAN PEMBAYARAN : Meter Persegi % THD. BIAYA PROYEK : 1.75
A. TENAGA
B. BAHAN
1. Aspal (M10) Ltr 0.8240 16,900.00 13,925.60
2. Pasir Urug (M01d) M³ 0.0059 167,200.00 986.02
C. PERALATAN
1. Dump Truck (E09) Jam 0.0005 503,288.50 227.20
2 Wheel Loader (E15) Jam 0.00003 0.00 0.00
3 Phenumatic Tire Roller (E18) Jam 0.0003 0.00 0.00
4 Aspal Distributor (E41) Jam 0.00025 0.00 0.00
5 Compressor (E05) Jam 0.0002 205,105.37 44.13
6 Power Broom (E03) Jam 0.0002 0.00 0.00
7 Alat Bantu Ls 1.0000 200.00 200.00
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : SNI PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN : Lapis Pondasi Koral TOTAL HARGA : 339,726.12
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader (E15) jam 0.0086 0.00 0.00
2. Dump Truck (E09) jam 0.0743 503,288.50 37,408.90
3. Motor Grader (E13) jam 0.0009 521,354.15 481.01
4. Vibratory Roller (E19a) jam 0.0097 315,790.72 3,074.93
5 Alat Bantu Ls 1.0000 200.00 200.00
PROYEK
NAMA PAKET
PROP / KAB / KODYA
ITEM PEMBAYARAN NO. : SNI PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN : Perkerasan Beton Semen (dibantu Excavator) TOTAL HARGA (Rp.) : 1,187,073.25
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :
A. TENAGA
1. Pekerja (L01) jam 2.4096 15,385.71 37,074.01
B. BAHAN
1 Semen (M12) Kg 412.0000 1,848.00 761,376.00
2 Pasir Beton (M01a) M3 0.5728 326,600.00 187,074.23
3 Agregat Kasar (M03) M3 0.7799 292,500.00 228,119.74
4 Air (M170) Ltr 163.7700 21.50 3,521.06
5 Plasticizer (M171) Kg 1.2360 42,600.00 52,653.60
6 Baja Tulangan Polos (M39a) Kg 15.8750 0.00 0.00
7 Joint Sealent (M94) Kg 0.9900 0.00 0.00
8 Cat Anti Karat (M95) Kg 0.0200 0.00 0.00
9 Expansion Cap (M96) M2 0.1700 0.00 0.00
10 Polytene 125 mikron (M97) Kg 0.4375 85,800.00 37,537.50
11 Curing Compound (M98) Ltr 0.8700 0.00 0.00
C. PERALATAN
1 Wheel Loader E15 jam 0.0071 - 0.00
2 Concrete Mixing Plant (E43) jam 0.2410 - 0.00
3 Truck Mixer Agitator (E49) jam 0.3684 719,657.36 265,141.21
4 Concrete Paver (E42) jam 0.0025 - 0.00
5 Excavator E10 jam 0.0800 571,770.25 45,724.13
6 Alat Bantu Ls 1.0000 200.00 200.00
PROYEK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : SNI PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN : Lapis Pondasi Bawah Beton Kurus (dibantu Excavator) TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :
A. TENAGA
1. Pekerja (L01) jam 1.9277 15,385.71 29,659.21
B. BAHAN
1. Semen (M12) Kg 233.8100 1,848.00 432,080.88
2 Pasir Beton (M01a) M3 0.5996 326,600.00 195,824.86
3 Agregat Kasar (M03) M3 0.9247 292,500.00 270,481.81
4 Air (M170) Ltr 163.7700 21.50 3,521.06
5 Plasticizer (M171) Kg 0.7014 42,600.00 29,880.92
6 Formwork Plate (M195) M2 0.1900 47,900.00 9,101.00
C. PERALATAN
1 Wheel Loader E15 jam 0.0071 0.00 0.00
2 Batching Plant (Concrete Pan Mixer)
(E43) jam 0.2410 0.00 0.00
3 Concrete Truck Mixer (E49) jam 0.3593 719,657.36 258,553.32
4 Concrete Vibrator (for manual) (E20) jam 0.2410 55,319.01 13,329.88
5. Excavator E10 jam 0.0600 571,770.25 34,293.10
6 Alat Bantu Ls 1.0000 200.00 200.00