Analisa EI-421

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 4.2.(1) PERKIRAAN VOL. PEK. : 1,449.50
JENIS PEKERJAAN : Laburan Aspal (Buras) TOTAL HARGA (Rp.) : 26,204,162.47
SATUAN PEMBAYARAN : Meter Persegi % THD. BIAYA PROYEK : 1.75

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 15,385.71 32.05


2. Mandor (L03) Jam 0.0002 24,285.71 5.06

JUMLAH HARGA TENAGA 37.11

B. BAHAN
1. Aspal (M10) Ltr 0.8240 16,900.00 13,925.60
2. Pasir Urug (M01d) M³ 0.0059 167,200.00 986.02

JUMLAH HARGA BAHAN 14,911.62

C. PERALATAN
1. Dump Truck (E09) Jam 0.0005 503,288.50 227.20
2 Wheel Loader (E15) Jam 0.00003 0.00 0.00
3 Phenumatic Tire Roller (E18) Jam 0.0003 0.00 0.00
4 Aspal Distributor (E41) Jam 0.00025 0.00 0.00
5 Compressor (E05) Jam 0.0002 205,105.37 44.13
6 Power Broom (E03) Jam 0.0002 0.00 0.00
7 Alat Bantu Ls 1.0000 200.00 200.00

JUMLAH HARGA PERALATAN 471.33

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 15,420.06


E. OVERHEAD & PROFIT 15.0 % x D 2,313.01
F. HARGA SATUAN PEKERJAAN ( D + E ) 17,733.07
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-513

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : SNI PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN : Lapis Pondasi Koral TOTAL HARGA : 339,726.12
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0779 15,385.71 1,198.51


2. Mandor (L03) jam 0.0097 24,285.71 236.48

JUMLAH HARGA TENAGA 1,434.99

B. BAHAN

1. Koral M3 1.2507 303,100.00 379,091.06

JUMLAH HARGA BAHAN 379,091.06

C. PERALATAN
1. Wheel Loader (E15) jam 0.0086 0.00 0.00
2. Dump Truck (E09) jam 0.0743 503,288.50 37,408.90
3. Motor Grader (E13) jam 0.0009 521,354.15 481.01
4. Vibratory Roller (E19a) jam 0.0097 315,790.72 3,074.93
5 Alat Bantu Ls 1.0000 200.00 200.00

JUMLAH HARGA PERALATAN 41,164.83

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 421,690.88


E. OVERHEAD & PROFIT 15.0 % x D 63,253.63
F. HARGA SATUAN PEKERJAAN ( D + E ) 484,944.51
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-531a
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK
NAMA PAKET
PROP / KAB / KODYA
ITEM PEMBAYARAN NO. : SNI PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN : Perkerasan Beton Semen (dibantu Excavator) TOTAL HARGA (Rp.) : 1,187,073.25
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) jam 2.4096 15,385.71 37,074.01

2 Mandor (L03) jam 0.4819 24,285.71 11,703.96

JUMLAH HARGA TENAGA 48,777.97

B. BAHAN
1 Semen (M12) Kg 412.0000 1,848.00 761,376.00
2 Pasir Beton (M01a) M3 0.5728 326,600.00 187,074.23
3 Agregat Kasar (M03) M3 0.7799 292,500.00 228,119.74
4 Air (M170) Ltr 163.7700 21.50 3,521.06
5 Plasticizer (M171) Kg 1.2360 42,600.00 52,653.60
6 Baja Tulangan Polos (M39a) Kg 15.8750 0.00 0.00
7 Joint Sealent (M94) Kg 0.9900 0.00 0.00
8 Cat Anti Karat (M95) Kg 0.0200 0.00 0.00
9 Expansion Cap (M96) M2 0.1700 0.00 0.00
10 Polytene 125 mikron (M97) Kg 0.4375 85,800.00 37,537.50
11 Curing Compound (M98) Ltr 0.8700 0.00 0.00

JUMLAH HARGA BAHAN 1,270,282.12

C. PERALATAN
1 Wheel Loader E15 jam 0.0071 - 0.00
2 Concrete Mixing Plant (E43) jam 0.2410 - 0.00
3 Truck Mixer Agitator (E49) jam 0.3684 719,657.36 265,141.21
4 Concrete Paver (E42) jam 0.0025 - 0.00
5 Excavator E10 jam 0.0800 571,770.25 45,724.13
6 Alat Bantu Ls 1.0000 200.00 200.00

JUMLAH HARGA PERALATAN 311,065.34


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,630,125.44
E. OVERHEAD & PROFIT 15.0 % x D 244,518.82
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,874,644.25
G. HARGA SATUAN PEKERJAAN / M3 1,874,644.25
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-533
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : SNI PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN : Lapis Pondasi Bawah Beton Kurus (dibantu Excavator) TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) jam 1.9277 15,385.71 29,659.21

3. Mandor (L03) jam 0.4819 24,285.71 11,703.96

JUMLAH HARGA TENAGA 41,363.17

B. BAHAN
1. Semen (M12) Kg 233.8100 1,848.00 432,080.88
2 Pasir Beton (M01a) M3 0.5996 326,600.00 195,824.86
3 Agregat Kasar (M03) M3 0.9247 292,500.00 270,481.81
4 Air (M170) Ltr 163.7700 21.50 3,521.06
5 Plasticizer (M171) Kg 0.7014 42,600.00 29,880.92
6 Formwork Plate (M195) M2 0.1900 47,900.00 9,101.00

JUMLAH HARGA BAHAN 940,890.52

C. PERALATAN
1 Wheel Loader E15 jam 0.0071 0.00 0.00
2 Batching Plant (Concrete Pan Mixer)
(E43) jam 0.2410 0.00 0.00
3 Concrete Truck Mixer (E49) jam 0.3593 719,657.36 258,553.32
4 Concrete Vibrator (for manual) (E20) jam 0.2410 55,319.01 13,329.88
5. Excavator E10 jam 0.0600 571,770.25 34,293.10
6 Alat Bantu Ls 1.0000 200.00 200.00

JUMLAH HARGA PERALATAN 306,376.30


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,288,629.98
E. OVERHEAD & PROFIT 15.0 % x D 193,294.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,481,924.48
G. HARGA SATUAN PEKERJAAN / M3 1,481,924.48
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.