Analisa EI-SS7104

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : SS. 7(10)4 PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Shotcrete TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M2 % THD. BIAYA PROYEK : 0.0000

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 3.9157 16,764.15 65,642.76


2. Tukang (L02) jam 0.9789 20,815.49 20,376.61
3. Mandor (L03) jam 0.4895 20,396.39 9,983.17

JUMLAH HARGA TENAGA 96,002.54


B. BAHAN
1 Beton Shotcrete M3 0.0825 1,964,621.73 162,081.29
2 Additive Ltr 5.7102 45,167.88 257,918.00
3 Wiremesh M2 1.1000 95,000.00 104,500.00
4 Geotekstile M' 0.3600 15,000.00 5,400.00

JUMLAH HARGA BAHAN 529,899.29

C. PERALATAN

1 Concrete Mixer Gouting (E06) jam 0.0979 100,168.23 9,805.63


2 Water Tanker (E23) jam 1.4815 131,467.37 194,766.47
3 Genset (E20) jam 0.0979 230,331.53 22,547.51
4 Compresor jam 0.0979 82,035.29 8,030.56
5 Shotmachine jam 0.2447 90,000.00 22,025.60
6 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 257,175.77

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 883,077.61


E. OVERHEAD & PROFIT 15.0 % x D 132,461.64
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,015,539.25
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

file:///conversion/tmp/scratch/424108856.xls
ITEM PEMBAYARAN NO. : SS. 7(10)3
JENIS PEKERJAAN : Soil Nailing
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 8.7 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
Faktor pengembangan bahan Fk 1.20
6 Kadar Semen Minimum (Spesifikasi) Ks 340 Kg/M3
7 Ukuran Agregat Maksimum Ag 19 mm
9 Volume 1 m' t 0.0345 M3
10 Perbandingan Air/Semen Maksimum (Spesifikasi) Wcr 0.50 -
11 Perbandingan Camp. : Semen Sm 410.0 Kg/M3 Berdasarkan
: Pasir Ps 670.0 Kg/M3 JMF & sesuai
: Agregat Kasar Kr 992.0 Kg/M3 dgn Spesifikasi
12 Berat Isi :
- Beton D1 2.40 T/M3
- Semen D2 1.25 T/M3
- Pasir D3 1.30 T/M3
- Agregat Kasar D4 1.40 T/M3

II. URUTAN KERJA

1 Pekerjaan persiapan / Regreding


Lereng yang akan dikerjakan soil nailing dibersihkan dan diratakan
sesuai kemiringan rencana menggunakan alat bantu

2 Penentuan titik lubang soil nailing berdasarkan gambar kerja,


selanjutnya dilakukan pengeboran dengan cara bor miring,
yaitu tegak lurus pada bidang permukaan. Lereng casing
dimasukkan ke dalam lubang hasil bor, untuk menjaga keruntuhan
atau perubahan lubang. Alat yang digunakan drilling machine yang
ringan dan mudah dipindah-pindah, tempat kedudukan drilling
machine menggunakan penyangga / perancah yang kuat dan
aman.

3 Besi tendon (baja tulangan ulir) dimasukkan pada lubang dan


diupayakan pada posisi tengah - tengah lubang bor dengan
bantuan centralizer sehingga tulangan tidak menempel pada
dinding lubang bor

4 Bahan campuran sesuai proporsi (agregat halus, agregat kasar,


semen dan additive) dicampur kering menggunakan concrete mixer

5 Bahan campuran kering dimasukkan ke corong pengaduk, yang


sebelumnya telah diisi air dari water tank sesuai kebutuhan
campuran kering kemudian diaduk merata menjadi bahan grouting

6 Campuran atau bahan grouting masuk melalui pipa ke pompa


grouting, selanjutnya dipompa keluar melalui selang penghantar

7 Bahan grouting dari selang penghantar, dimasukkan ke dalam


lubang soil nailing melalui tremy pipa, supaya tidak terjadi segregasi
dan lubang terisi penuh / padat dengan materila grouting

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Beton K-250 0.2189 M3 gambar
Baja Tulangan 15.2160 Kg gambar
Additive 0.6000 Ltr gambar

2. ALAT
2.a. Concrete Mixer (E39)
Kapasitas Alat V 500.00 liter
Faktor Efisiensi Alat Fa 0.75 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 10.00 menit
- Mengaduk T2 10.00 menit
- Menuang T3 10.00 menit
- Tunggu, dll. T4 10.00 menit
Ts 40.00 menit

Kap. Prod. / jam = V x Fa x 60 Q1 16.285 M'/jam


1000 x Ts x t

Koefisien Alat / M' = 1 : Q1 (E39) 0.0614 jam

Berlanjut ke hal. berikut.

FILE:OE-LINGKAR
ITEM PEMBAYARAN NO. : SS. 7(10)3
JENIS PEKERJAAN : Soil Nailing
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.b. Water Tank Truck (E23)


Volume Tanki Air V 4.0 M3
Kebutuhan air / M3 beton Wc 0.187 M3
Faktor Efisiensi Alat Fa 0.83 -
Pengisian Tanki / jam n 0.50 kali

Kap. Prod. / jam = V x Fa x n Q2 0.30 M'


Wc x t

Koefisien Alat / M' = 1 : Q2 (E23) 3.2827 jam

2.c. Driiling Machine (E20)

Kap. Prod. / jam = Q3 24.000 M'/hari

Koefisien Alat / M' = 1 : Q3 (E20) 0.0417 jam

2.d. Compressor

Kap. Prod. / Jam = Q4 16.285 M'/jam

Koef. Alat / M' = 1 : Q4 (E05) 0.0614 Jam

2.e. Generatorset (Genset) (E12)


Kap.Prod. / Jam Q5 16.285 M'/jam

Koefisien Alat/M' = 1 : Q5 (E12) 0.0614 Jam

2.f. PENGEBORAN
Grouting Pump/Shot Machine

Kap. Prod. / Jam = Q6 8.143 M'/jam

Koef. Alat / M' = 1 : Q6 (E05) 0.1228 Jam

2.g. Casing

Kap. Prod. / Jam = Q7 16.285 M'/jam

Koef. Alat / M' = 1 : Q7 0.0614 Jam

2.h. Tremy Pipe

Kap. Prod. / Jam = Q8 16.285 M'/jam

Koef. Alat / M' = 1 : Q8 0.0614 Jam

Berlanjut ke hal. berikut.

FILE:OE-LINGKAR
ITEM PEMBAYARAN NO. : SS. 7(10)3
JENIS PEKERJAAN : Soil Nailing
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

3. TENAGA ( untuk Concrete mixer, water tank truck, drilling machine, )


( compresor,genset )
Produksi dalam 1 hari = Tk x Q1 Qt 114.00 M'/hari

Kebutuhan tenaga : - Mandor M 2.00 orang


- Tukang Tb 4.00 orang
- Pekerja P 16.00 orang

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.1228 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.2456 jam
- Pekerja = (Tk x P) : Qt (L01) 0.9825 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,376,100.00 / M

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : 0.00 bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M

FILE:OE-LINGKAR
Analisa EI-SS7103
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PAKET :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : SS. 7(10)3 PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Soil Nailing TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M' % THD. BIAYA PROYEK : -

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.9825 12,674.60 12,452.43


2. Tukang (L02) jam 0.2456 14,246.03 3,499.08
3. Mandor (L03) jam 0.1228 15,103.17 1,854.80

JUMLAH HARGA TENAGA 17,806.31


B. BAHAN
1 Beton K-250 M3 0.2189 1,876,000.00 410,656.40
2 Baja Tulangan Kg 15.2160 16,400.00 249,542.40
3 Additive Ltr 0.6000 50,000.00 30,000.00

JUMLAH HARGA BAHAN 690,198.80

C. PERALATAN

1 Concrete Mixer jam 0.0000 0.00


2 Water Tank Truck jam 3.2827 131,467.37 431,571.09
3 Driiling Machine jam 0.0417 200,000.00 8,333.33
4 Compressor jam 0.0614 82,035.29 5,037.33
5 Generatorset (Genset) jam 0.0614 230,331.53 14,143.38
6 Grouting Pump/Shot Machine jam 0.1228 177,941.83 21,852.84
7 Casing jam 0.0614 64,816.10 3,980.00
8 Tremy Pipe jam 0.0614 60,021.99 3,685.62
9 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 488,603.58

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,196,608.70


E. OVERHEAD & PROFIT 15.0 % x D 179,491.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,376,100.00
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.