FORMULIR STANDAR UNTUK

PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET :
LOKASI :
ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Perkerasan Beton Semen FS45
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Jam 0.6024 12,000.00 7,228.92


2 Mandor Jam 0.1506 17,000.00 2,560.24

JUMLAH HARGA TENAGA 9,789.16

B. BAHAN

1 Semen Kg 463.5000 1,250.00 579,375.00


2 Pasir M3 0.4164 230,800.00 96,100.34
3 Agregat Kasar M3 0.9233 204,900.00 189,179.22
4 Air Ltr 163.7700 50.00 8,188.50
5 Curing Compound Ltr 0.6525 45,500.00 29,688.75
6 Kayu Perancah M3 0.4000 1,500,000.00 600,000.00

JUMLAH HARGA BAHAN 1,502,531.82

C. PERALATAN

1 Wheel Loader Jam 0.0071 368,600.00 2,612.33


2 Concrete Mixing Plant Jam 0.0502 1,140,600.00 57,259.04
3 Truck Mixer Agitator Jam 1.1197 176,900.00 198,070.10
4 Concrete Vibrator Jam 0.3012 49,800.00 15,000.00
5 Alat Bantu Ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 273,941.47


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,776,473.29
E. OVERHEAD & PROFIT 10.0 % x D 177,647.33
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,954,120.62
G. PEMBULATAN 1,954,100.00