FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 5.1.(5)
JENIS PEKERJAAN : Urugan sirtu dipadatkan
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) L01 jam 0.1039 12,270.96 1,274.51


2. Mandor (L03) L03 jam 0.0130 16,218.13 210.56

JUMLAH HARGA TENAGA 1,485.07

B. BAHAN

1. Sirtu M16 M16 M3 1.2000 138,789.71 166,547.65

JUMLAH HARGA BAHAN 166,547.65

C. PERALATAN
1. Wheel Loader (E15) E15 jam 0.0087 440,724.26 3,834.35
2. Dump Truck (E09) E09 jam 0.1329 349,111.30 46,409.01
3. Motor Grader (E13) E13 jam 0.0013 369,981.05 472.20
4. Vibratory Roller (E19a) E19a jam 0.0130 345,796.45 4,489.46
5 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 55,205.02

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 223,237.74


E. OVERHEAD & PROFIT 12.5 % x D 27,904.72
F. HARGA SATUAN PEKERJAAN ( D + E ) 251,100.00