Anda di halaman 1dari 2

FORMULIR STANDAR UNTUK

PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 6.5.(1) PERKIRAAN VOL. PEK. : 1,00
JENIS PEKERJAAN : Laston Lapis Aus Asbuton (AC-WC Asb) TOTAL HARGA (Rp.) : 973.157,73
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK : 0,02

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0,2008 24.996,34 5.019,34

2. Mandor (L03) Jam 0,0201 30.066,21 603,74

JUMLAH HARGA TENAGA 5.623,08

B. BAHAN

1. Agr Pch Mesin 5-10 & 10 (M92) M3 0,3234 305.993,56 98.968,05


2. Agr Pch Mesin 0 - 5 (M91) M3 0,4068 305.993,56 124.476,79
3 Semen (M12) Kg 0,0000 1.340,00 0,00
4 Aspal (M10) Kg 58,7100 6.774,19 397.712,90
5 Asbuton B 5/20 (M161) Kg 25,7500 950,00 24.462,50

JUMLAH HARGA BAHAN 645.620,24

C. PERALATAN
1. Wheel Loader E15 Jam 0,0054 486.854,58 2.613,96
2. AMP E01b Jam 0,0201 9.382.313,91 188.399,88
3. Genset E12 Jam 0,0201 370.071,25 7.431,15
4. Dump Truck E09 Jam 0,0491 420.917,24 20.674,79
5. Asp. Finisher E02 Jam 0,0125 329.908,30 4.132,67
6. Tandem Roller E17a Jam 0,0128 468.218,25 5.972,68
7 P. Tyre Roller E18 Jam 0,0084 501.929,65 4.220,40
8 Alat Bantu Ls 1,0000 0,00 0,00

JUMLAH HARGA PERALATAN 233.445,52

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 884.688,84


E. OVERHEAD & PROFIT 10,0 % x D 88.468,88
F. HARGA SATUAN PEKERJAAN ( D + E ) 973.157,73
Analisa EI-652

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 6.5.(2) PERKIRAAN VOL. PEK. : 1,00
JENIS PEKERJAAN : Laston Lapis Antara Asbuton (AC-BC Asb) TOTAL HARGA (Rp.) : 930.867,87
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK : 0,02

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0,2008 24.996,34 5.019,34

2. Mandor (L03) Jam 0,0201 30.066,21 603,74

JUMLAH HARGA TENAGA 5.623,08

B. BAHAN

1. Agr Pch Mesin 5-10 & 10 (M92) M3 0,3751 305.993,56 114.789,31


2. Agr Pch Mesin 0 - 5 (M91) M3 0,3591 305.993,56 109.872,55
3 Semen (M12) Kg 0,0000 1.340,00 0,00
4 Aspal (M10) Kg 53,5600 6.774,19 362.825,81
5 Asbuton B 5/20 (M161) Kg 25,7500 950,00 24.462,50

JUMLAH HARGA BAHAN 611.950,17

C. PERALATAN
1. Wheel Loader E15 Jam 0,0054 486.854,58 2.613,96
2. AMP E01b Jam 0,0201 9.382.313,91 188.399,88
3. Genset E12 Jam 0,0201 370.071,25 7.431,15
4. Dump Truck E09 Jam 0,0491 420.917,24 20.674,79
5. Asp. Finisher E02 Jam 0,0084 329.908,30 2.755,11
6. Tandem Roller E17a Jam 0,0085 468.218,25 3.981,79
7 P. Tyre Roller E18 Jam 0,0056 501.929,65 2.813,60
8 Alat Bantu Ls 1,0000 0,00 0,00

JUMLAH HARGA PERALATAN 228.670,27

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 846.243,52


E. OVERHEAD & PROFIT 10,0 % x D 84.624,35
F. HARGA SATUAN PEKERJAAN ( D + E ) 930.867,87
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

Anda mungkin juga menyukai