PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 6.5.(1) PERKIRAAN VOL. PEK. : 1,00
JENIS PEKERJAAN : Laston Lapis Aus Asbuton (AC-WC Asb) TOTAL HARGA (Rp.) : 973.157,73
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK : 0,02
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader E15 Jam 0,0054 486.854,58 2.613,96
2. AMP E01b Jam 0,0201 9.382.313,91 188.399,88
3. Genset E12 Jam 0,0201 370.071,25 7.431,15
4. Dump Truck E09 Jam 0,0491 420.917,24 20.674,79
5. Asp. Finisher E02 Jam 0,0125 329.908,30 4.132,67
6. Tandem Roller E17a Jam 0,0128 468.218,25 5.972,68
7 P. Tyre Roller E18 Jam 0,0084 501.929,65 4.220,40
8 Alat Bantu Ls 1,0000 0,00 0,00
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 6.5.(2) PERKIRAAN VOL. PEK. : 1,00
JENIS PEKERJAAN : Laston Lapis Antara Asbuton (AC-BC Asb) TOTAL HARGA (Rp.) : 930.867,87
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK : 0,02
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader E15 Jam 0,0054 486.854,58 2.613,96
2. AMP E01b Jam 0,0201 9.382.313,91 188.399,88
3. Genset E12 Jam 0,0201 370.071,25 7.431,15
4. Dump Truck E09 Jam 0,0491 420.917,24 20.674,79
5. Asp. Finisher E02 Jam 0,0084 329.908,30 2.755,11
6. Tandem Roller E17a Jam 0,0085 468.218,25 3.981,79
7 P. Tyre Roller E18 Jam 0,0056 501.929,65 2.813,60
8 Alat Bantu Ls 1,0000 0,00 0,00