PROYEK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 5.3.(3) PERKIRAAN VOL. PEK. : 1,00
JENIS PEKERJAAN : Lapis Pondasi Bawah Beton Kurus TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : #REF!
A. TENAGA
1. Pekerja (L01) jam 0,4016 17.857,14 7.171,54
2. Tukang (L02) jam 5,7831 21.428,57 123.924,27
3. Mandor (L03) jam 0,1004 25.000,00 2.510,04
B. BAHAN
1. Semen (M12) Kg 233,8100 1.560,00 364.743,60
2 Pasir (M01a) M3 0,5996 195.000,00 116.919,31
3 Agregat Kasar (M03) M3 0,9247 370.000,00 342.147,93
4 Air (M170) Ltr 163,7700 14,65 2.399,23
5 Plasticizer (M171) Kg 0,7014 40.000,00 28.057,20
6 Formwork Plate (M195) M2 0,1900 45.000,00 8.550,00
C. PERALATAN
1 Concrete Mixer (E43) jam 0,4819 109.592,27 52.815,55
2 Concrete Vibrator (E20) jam 2,8916 55.373,35 160.115,72
3 Water TankTruck (E23) jam 0,0382 373.758,90 14.259,88
4 Alat Bantu Ls 1,0000 1.000,00 1.000,00