Anda di halaman 1dari 451

Analisa EI-611a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. PAKET KONTRAK :


NAMA PAKET : ..
.
PROP / KAB / KODYA : KABUPATEN PEKALONGAN
ITEM PEMBAYARAN NO. : 6.1 (1)(a) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : Liter % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Aspal (L01) Jam 0.0021 14,285.71


2. Mandor (L03) Jam 0.0004 12,857.14

JUMLAH HARGA TENAGA

B. BAHAN

1. Aspal (M10) Kg 0.6790 7,235.41


2. Kerosene (M11) liter 0.3708 13,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Asp. Sprayer E41 Jam 0.0002 73,439.51


2. Compressor E05 Jam 0.0002 174,799.83

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-611a

1.00
5,772.87
0.00

JUMLAH
HARGA
(Rp.)

30.00
5.14

35.14

4,912.84
4,820.40

9,733.24

14.69
34.96

49.65

9,818.03
1,472.70
11,290.73
lume dan/atau ukuran
satu satuan pekerjaan
k dapat diubah kecuali
Kepada Peserta Lelang

pi tidak termasuk PPN


Analisa EI-612a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : ..
.
PROP / KAB / KODYA : KABUPATEN PEKALONGAN
ITEM PEMBAYARAN NO. : 6.1 (2)(a) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Lapis Perekat - Aspal Cair TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : Liter % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 14,285.71


2. Mandor (L03) Jam 0.0004 12,857.14

JUMLAH HARGA TENAGA

B. BAHAN

1. Aspal (M10) Kg 0.8487 7,235.41


2. Kerosene (M11) liter 0.2060 13,000.00

JUMLAH HARGA BAHAN

C. PERALATAN

1. Asp. Sprayer E41 Jam 0.0002 73,439.51


2. Compressor E05 Jam 0.0002 174,799.83

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-612a

1.00
6,709.48
0.00

JUMLAH
HARGA
(Rp.)

30.00
5.14

35.14

6,140.69
2,678.00

8,818.69

14.69
34.96

49.65

8,903.48
1,335.52
10,239.00
lume dan/atau ukuran
satu satuan pekerjaan
k dapat diubah kecuali
Kepada Peserta Lelang

pi tidak termasuk PPN


Analisa EI-635a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : ..
.
PROP / KAB / KODYA : KABUPATEN PEKALONGAN
ITEM PEMBAYARAN NO. : 6.3(5a) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Laston Lapis Aus (AC-WC) (gradasi halus/kasar) :
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2008 14,285.71


2. Mandor (L03) Jam 0.0201 12,857.14

JUMLAH HARGA TENAGA

B. BAHAN

1. Agr 5-10 & 10-20 (M92) M3 0.3283 237,174.61


2. Agr 0-5 (M91) M3 0.3210 281,208.14

JUMLAH HARGA BAHAN

C. PERALATAN
1. Wheel Loader E15 Jam 0.0117 642,723.85
2. AMP E01 Jam 0.0201 5,890,040.05
3. Genset E12 Jam 0.0201 431,715.35
4. Dump Truck E08 Jam 1.7544 283,320.37
5. Asp. Finisher E02 Jam 0.0069 971,554.65
6. Tandem Roller E17 Jam 0.0135 440,913.68
7 P. Tyre Roller E18 Jam 0.0058 533,776.47
8 Alat Bantu Ls 1.0000 0.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-635a

1.00
270,101.73
0.01

JUMLAH
HARGA
(Rp.)

2,868.57
258.43

3,127.00

77,864.42
90,267.81

168,132.23

7,519.87
118,389.81
8,677.48
497,057.26
6,703.73
5,952.33
3,095.90
0.00

647,396.38

818,655.61
122,798.34
941,453.95
lume dan/atau ukuran
satu satuan pekerjaan
k dapat diubah kecuali
Kepada Peserta Lelang

pi tidak termasuk PPN


Analisa EI-552
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
NAMA PAKET : ..
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.5.(1) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Lapis Pondasi Atas Bersemen (CementTOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) jam 1.0542 10,000.00
2. Tukang (L02) jam 0.3012 11,428.57
3. Mandor (L03) jam 0.1506 12,857.14

JUMLAH HARGA TENAGA

B. BAHAN
1. Semen (M12) Kg 87.1250 1,200.00

2 Agregat Kasar (M03) M3 1.2586 237,174.61

JUMLAH HARGA BAHAN

C. PERALATAN
1 Wheel Loader E15 jam 0.0244 642,723.85
2 Batching Plant E53 jam 0.0753 718,754.34
3 Dump Truck E08 jam 0.3589 283,320.37
4 Vibrator Roller E55 jam 0.0054 312,596.71
5 Water Tank Truck E23 jam 0.0422 286,481.79
6 Screed Paver E54 jam 0.0000 -
7 Alat Bantu Ls 1.0000 0.00
8

JUMLAH HARGA PERALATAN


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT 15 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
G. HARGA SATUAN PEKERJAAN / M3
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukura
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerja
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecua
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lela
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PP
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-552
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

1
464,889
-

JUMLAH
HARGA
(Rp.)

10,542
3,442
1,936

15,920

104,550

298,508

403,058

15,682
54,122
101,684
1,688
12,090
-
-

185,266
604,244
90,637
694,881
694,881
n atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

antitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan


an. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
a (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
n sudah termasuk bahan bakar, bahan habis dipakai dan operator.
uk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
Analisa EI-552
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
NAMA PAKET : ..
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 5.5.(2) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Lapis Pondasi Bawah (Cement Treate TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) jam 1.0542 10,000.00
2. Tukang (L02) jam 0.3012 11,428.57
3. Mandor (L03) jam 0.1506 12,857.14

JUMLAH HARGA TENAGA

B. BAHAN
1. Semen (M12) Kg 112.7500 1,200.00

2 Agregat Kasar (M03) M3 1.2586 237,174.61

JUMLAH HARGA BAHAN

C. PERALATAN
1 Wheel Loader E15 jam 0.1221 642,723.85
2 Batching Plant E53 jam 0.0753 718,754.34
3 Dump Truck E08 jam 0.3589 283,320.37
4 Vibrator Roller E55 jam 0.0054 312,596.71
5 Water Tank Truck E23 jam 0.0422 286,481.79
6 Screed Paver E54 jam 0.0000 -
7 Alat Bantu Ls 1.0000 0.00
8

JUMLAH HARGA PERALATAN


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT 15 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
G. HARGA SATUAN PEKERJAAN / M3
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukura
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerja
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecua
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lela
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PP
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-552
FORMULIR STANDAR UNTUK
AN ANALISA MASING-MASING HARGA SATUAN

1
464,889
-

JUMLAH
HARGA
(Rp.)

10,542
3,442
1,936

15,920

135,300

298,508

433,808

78,477
54,122
101,684
1,688
12,090
-
-

248,061
697,789
104,668
802,457
802,457
n atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

antitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan


an. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
a (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
n sudah termasuk bahan bakar, bahan habis dipakai dan operator.
uk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
PEKERJAAN TOWER AIR

P L T
Galian Tanah pondasi Sumuran 3.14 0.2025 3
Pondasi plat 5.1 5.1 1

Lantai kerja bwh pile cap t= 7 cm


P L T
5.1 5.1 0.07

Pondasi sumuran O 80
P L T
Sumuran 3.14 0.16 3

P JML/ttk JML ttk


Besi D19 4 15 5

25 26.8 670

Begel O 10 2.512 14.333333 5

15.002222 7.4 111.01644


-
-
-
Beton bertulang pondasi plat 5 x 5 m
P L T
5 5 1

Beton bertulang sloof 20/40


P L T
8 0.2 0.4

Beton bertulang kolom 50/50


P L T
13.6 0.5 0.5
Beton bertulang balok ring BR2 25/40
P L T
16 0.25 0.4

Beton bertulang plat elv. +4.60 t= 12 cm


P L T
3.15 3.15 0.12

Beton bertulang balok atap B1 30/75


P L T
8 0.3 0.75

Beton bertulang balok atap BR1 20/50


P L T
15.7 0.2 0.5

Beton bertulang balok atap BC 30x50/75


P L T
10.96 0.3 0.625

Beton bertulang plat lantai el. + 12.60 t= 14 cm


P L T
3.14 6.6564 0.14

Pasangan batu bata 1Pc:6Ps


P L T
15.7 1 1.2
16 1 3

Plesteran 1Pc:6Ps
P L T
15.7 2.55 1
16 1 3
Acian

Tangga besi
Tandon air kap 8 m3

Besi hollow 40x40x1,2 mm


P L brt/m
117.04 1 1.4666667
62.44 1 1.4666667

Wiremesh M6
P L T
13.8 1 2.8
10.8 1 3.8
JML V
5 9.53775
1 26.01

35.54775

JML V
1 1.8207

1.8207

JML V
5 7.536

7.536
P
300

180.02667

781.01644

JML V
1 25

25

JML V
1 0.64

0.64

JML V
4 13.6

13.6
JML V
1 1.6

1.6

JML V
1 1.1907

1.1907

JML V
1 1.8

1.8

JML V
1 1.57

1.57

JML V
1 2.055

2.055

JML V
1 2.92615344

2.92615344

JML LUAS
1 18.84
1 48

66.84

JML LUAS
1 40.035
2 96
136.035

136.035

JML Brt
1 171.658667
1 91.5786667

263.237333

JML LUAS
1 38.64
1 41.04

79.68
RUMAH POWER HOUSE & GWT

No Pekerejaan Perhitungan Volume Sat Ket

I PEKERJAAN TANAH
1 Galian Tanah Panjang x Lebar x tinggi x buah
- Pondasi Foot Plat 1.2 x 1.2 x 1.05 x 4 6.048 m3

- Pondasi Lajur 5x 1.2 x 1.05 x 2 12.6 m3


4x 1.2 x 1.05 x 2 10.08 m3
6x 1.2 x 1.05 x 2 15.12 m3

- GWT 8.3 x 8.3 x 2.65 x 1 182.5585 m3

- Pondasi Dudukan Genset 2.9 x 2.3 x 0.6 x 1 4.002 m3

- Saluran tempat instalasi kabel 6.1 x 1x 0.3 x 2 3.66 m3


2.1 x 1x 0.3 x 1 0.63 m3
3.35 x 1x 0.3 x 1 1.005 m3
1x 1x 0.3 x 1 0.3 m3

Galian Tanah 236.0035 m3

2 Urugan Tanah Kembali


=1/3 x Galian Tanah 1/3 x 236.0035 m3 78.6678333333 m3

Urugan Tanah Kembali 78.6678333333 m3

3 Buangan tanah sisa galian


Galian Tanah - Urugan Tanah Kembali
236.0035 - 78.6678333333 157.3356666667 m3

Buangan tanah sisa galian 157.3356666667 m3

4 Urugan Pasir Panjang x Lebar x tinggi x buah


- Urugan Pasir Bawah Pondasi Lajur 5x 1x 0.1 x 2 1 m3
4x 1x 0.1 x 2 0.8 m3
6x 1x 0.1 x 2 1.2 m3

- Urugan Pasir Bawah Pondasi dudukan genset Panjang x Lebar x tinggi x buah
2.5 x 1.9 x 0.1 x 1 0.475 m3

- Urugan Pasir isian Pondasi dudukan genset Panjang x Lebar x tinggi x buah
1.8 x 1.2 x 0.2 x 1 0.432 m3

- Urugan Pasir Bawah Saluran tempat instalasi kabel Panjang x Lebar x tinggi x buah
6.1 x 0.8 x 0.05 x 2 0.488 m3
2.1 x 0.8 x 0.05 x 1 0.084 m3
3.35 x 0.8 x 0.05 x 1 0.134 m3
1x 0.8 x 0.05 x 1 0.04 m3

- Urugan Pasir Bawah Lantai rabat beton Luasan tinggi buah


22.5 x x 0.05 x 1 1.125 m3
19.85 x x 0.05 x 1 0.9925 m3
0.56 x x 0.05 x 1 0.028 m3
8.3 x x 0.05 x 1 0.415 m3
3.12 x x 0.05 x 1 0.156 m3

- Urugan Pasir Bawah lantai rabat beton keliling luasan x x tinggi x buah
37.35 x x 0.05 x 1 1.8675 m3

- Urugan Pasir isian dinding Panjang x Lebar x tinggi x buah


4.7 x 0.1 x 3.55 x 2 3.337 m3
dikura 2.48 x 0.1 x 2.55 x 1 -0.6324 m3
1.38 x 0.1 x 1x 1 -0.138 m3
0.6 x 0.1 x 0.6 x 2 -0.072 m3

Urugan Pasir 11.7316 m3

5 Urugan Sirtu Panjang x Lebar x tinggi x buah


- Urugan Sirtu Bawah Pondasi Foot Plat 1.3 x 1.3 x 0.15 x 4 1.014 m3

- Urugan Sirtu Bawah GWT Panjang x Lebar x tinggi x buah


No Pekerejaan Perhitungan Volume Sat Ket

7.3 x 7.3 x 0.15 x 1 7.9935 m3


No Pekerejaan Perhitungan Volume Sat Ket

- Urugan Sirtu dudukan genset Panjang x Lebar x tinggi x buah


1.5 x 0.9 x 0.4 x 1 0.54 m3

Urugan Sirtu 9.5475 m3

II PEKERJAAN BETON BERTULANG


1 Lantai Kerja Beton K-100
- Lantai Kerja Bawah Foot Plat Panjang x Lebar x tinggi x buah
0.9 x 0.9 x 0.05 x 4 0.162 m3

- Lantai Kerja Bawah GWT Panjang x Lebar x tinggi x buah


7.1 x 7.1 x 0.05 x 1 2.5205 m3

- Lantai Kerja Bawah Dudukan Genset Panjang x Lebar x tinggi x buah


2.5 x 1.9 x 0.1 x 1 0.475 m3

Lantai Kerja Beton K-100 3.1575 m3

2 Rabat Beton Lantai K-100


- Rabat Beton Lantai bagian dalam Luasan x x tinggi x buah
22.5 x x 0.05 x 1 1.125 m3
19.85 x x 0.05 x 1 0.9925 m3
0.56 x x 0.05 x 1 0.028 m3
8.3 x x 0.05 x 1 0.415 m3
3.12 x x 0.05 x 1 0.156 m3

- Rabat Beton Lantai keliling bangunan Luasan x x tinggi x buah


37.35 x x 0.07 x 1 2.6145 m3

- Rabat Beton Lantai Saluran tempat instalasi kabel Panjang x Lebar x tinggi x buah
6.1 x 0.5 x 0.05 x 2 0.305 m3
2.1 x 0.5 x 0.05 x 1 0.0525 m3
3.35 x 0.5 x 0.05 x 1 0.08375 m3
1x 0.5 x 0.05 x 1 0.025 m3

Rabat Beton Lantai K-100 5.79725 m3

3 Beton Pondasi Foot Plat K-250 Panjang x Lebar x tinggi x buah


0.8 x 0.8 x 0.25 x 4 0.64 m3

Beton Pondasi Foot Plat K-250 0.64 m3

4 Beton Sloof K-250 type S1 40x30 Panjang x Lebar x tinggi x buah


5x 0.4 x 0.3 x 2 1.2 m3

Beton Sloof K-250 type S1 40x30 1.2 m3

5 Beton Sloof K-250 type S2 15x20 Panjang x Lebar x tinggi x buah


6x 0.15 0.2 x 2 0.36 m3
4x 0.15 0.2 x 2 0.24 m3

Beton Sloof K-250 type S2 15x20 0.6 m3

6 Beton Kolom K-250 type K 30x40 Panjang x Lebar x tinggi x buah


Kolom 0.4 x 0.3 x 1.25 x 4 0.6 m3
Kolom 0.4 x 0.3 x 3.7 x 6 2.664 m3

Beton Kolom K-250 type K 30x40 3.264 m3

7 Beton Kolom K-250type K 20x20 Panjang x Lebar x tinggi x buah


0.2 x 0.2 x 3.8 x 3 0.456 m3

Beton Kolom K-250type K 20x20 0.456 m3

8 Beton Kolom K-50 type K 30x40 GWT Panjang x Lebar x tinggi x buah
0.4 x 0.3 x 2.85 x 6 2.052 m3

Beton Kolom K-50 type K 30x40 GWT 2.052 m3

9 Beton Kolom K-250 type K 25x30 GWT Panjang x Lebar x tinggi x buah
0.25 x 0.3 x 2.85 x 2 0.4275 m3
No Pekerejaan Perhitungan Volume Sat Ket

Beton Kolom K-250 type K 25x30 GWT 0.4275 m3


No Pekerejaan Perhitungan Volume Sat Ket

10 Beton Balok K-250 type BU 20x40 (Atap) Panjang x Lebar x tinggi x buah
8x 0.2 x 0.4 x 4 2.56 m3

Beton Balok K-250 type BU 20x40 (Atap) 2.56 m3

11 Beton Balok K-250 type BP 20x30 (Atap) Panjang x Lebar x tinggi x buah
15 x 0.2 x 0.3 x 3 2.7 m3

Beton Balok K-250 type BP 20x30 (Atap) 2.7 m3

12 Beton Plat Dak Atap K-275 tebal 10 cm Luasan x x tinggi x buah


10.62 x x 0.1 x 4 4.248 m3
13.43 x x 0.1 x 2 2.686 m3
16.22 x x 0.1 x 0 0 m3
3.03 x x 0.1 x 4 1.212 m3
3.83 x x 0.1 x 2 0.766 m3
4.63 x x 0.1 x 0 0 m3
2.24 x x 0.1 x 4 0.896 m3
0.64 x x 0.1 x 4 0.256 m3

Beton Plat Dak Atap K-275 tebal 10 cm 10.064 m3

13 Beton K-250 Listplank Panjang x Lebar x tinggi x buah


15 x 0.08 x 0.4 x 2 0.96 m3
8x 0.08 x 0.4 x 2 0.512 m3

Beton K-250 Listplank 1.472 m3

14 Beton Balok K-250 type 30x40 (GWT) Panjang x Lebar x tinggi x buah
6x 0.3 x 0.4 x 3 2.16 m3
6x 0.3 x 0.4 x 2 1.44 m3

Beton Balok K-250 type 30x40 (GWT) 3.6 m3

15 Beton Balok K-250 type 25x40 (GWT) Panjang x Lebar x tinggi x buah
6x 0.25 x 0.4 x 1 0.6 m3

Beton Balok K-250 type 25x40 (GWT) 0.6 m3

16 Beton Plat Lantai Dasar K-250 tebal 25 cm (GWT) Panjang x Lebar x tinggi x buah
7x 7x 0.25 x 1 12.25 m3

Beton Plat Lantai Dasar K-250 tebal 25 cm (GWT) 12.25 m3

17 Beton Dinding K-250 (GWT) Panjang x Lebar x tinggi x buah


6x 0.15 x 2.5 x 2 4.5 m3
6x 0.15 x 2.5 x 2 4.5 m3

Beton Dinding K-250 (GWT) 9 m3

18 Beton Plat Tutup K-250 tebal 15 cm (GWT) Panjang x Lebar x tinggi x buah
6x 6x 0.15 x 1 5.4 m3
0.9 x 0.1 x 0.15 x 4 0.054 m3
Dikura 0.9 x 0.9 x 0.15 x 1 -0.1215 m3

Beton Plat Tutup K-250 tebal 15 cm (GWT) 5.3325 m3

19 Beton Plat Lantai Dudukan Genset K-300 tebal 20 cm Panjang x Lebar x tinggi x buah
2.5 x 1.9 x 0.2 x 1 0.95 m3

Beton Plat Lantai Dudukan Genset K-300 tebal 20 cm 0.95 m3

20 Waterproofing membrane untuk GWT Panjang x Lebar x tinggi x buah


5.7 x x 2.35 x 2 26.79 m2
5.7 x x 2.35 x 2 26.79 m2
5.7 x 5.7 x x 1 32.49 m2

Waterproofing membrane untuk GWT 86.07 m2

21 Waterproofing membrane untuk Dak atap + screed 2 Luas x Lebar x tinggi x buah
117.58 x x x 1 117.58 m2
4.548 x x x 1 4.548 m2
No Pekerejaan Perhitungan Volume Sat Ket

Waterproofing membrane untuk Dak atap + screed 2 cm 122.128 m2


No Pekerejaan Perhitungan Volume Sat Ket

III PEKERJAAN PASANGAN


1 Aanstampeng Panjang x Lebar x tinggi x buah
5x 1x 0.2 x 2 2 m3
4x 1x 0.2 x 2 1.6 m3
6x 1x 0.2 x 2 2.4 m3

Aanstampeng 6 m3

2 Pasangan Batu Belah 1 Pc : 5 Ps Panjang x Lebar x tinggi x buah


Pondasi 5x 0.6 x 0.7 x 2 4.2 m3
4x 0.6 x 0.7 x 2 3.36 m3
6x 0.6 x 0.7 x 2 5.04 m3
Pondas 7.6 x 0.45 x 0.6 x 1 2.052 m3

Pasangan Batu Belah 1 Pc : 5 Ps 14.652 m3

3 Pasangan dinding batu bata 1/2 batu 1 Pc : 5 Ps Panjang x Lebar x tinggi x buah
5x 3.45 x 4 69 m2
4x 3.45 x 4 55.2 m2
6x 3.45 x 4 82.8 m2
Dindin 38.35 x 0.65 x 1 24.9275 m2
Dikurangi Luasan
Pintu 2.72 x x 1 -2.72 m2
3.53 x x 1 -3.53 m2
3.13 x x 1 -3.13 m2
Jendel 0.97 x x 2 -1.94 m2
1.38 x x 1 -1.38 m2
1.53 x x 1 -1.53 m2
Exhous 0.36 x x 6 -2.16 m2

Pasangan dinding batu bata 1/2 batu 1 Pc : 5 Ps 215.5375 m2

4 Plesteran dinding batu bata 1 Pc : 5 Ps Panjang x Lebar x tinggi x buah x sisi


5x 3.45 x 4x 1 69 m2
4x 3.45 x 4x 2 110.4 m2
6x 3.45 x 4x 2 165.6 m2
Dindin 38.35 x 0.65 x 1x 1 24.9275 m2
Pintu 5.44 x 0.15 x 1x 1 0.816 m2
5.83 x 0.4 x 1x 1 2.332 m2
5.64 x 0.15 x 1x 1 0.846 m2
Jendel 4.16 x 0.15 x 2x 1 1.248 m2
4.76 x 0.4 x 1x 1 1.904 m2
5.76 x 0.15 x 1x 1 0.864 m2
Exhous 2.4 x 0.4 x 2x 1 1.92 m2
2.4 x 0.15 x 4x 1 1.44 m2
Dikurangi Luasan
Pintu 2.72 x x 1x 2 -5.44 m2
3.53 x x 1x 2 -7.06 m2
3.13 x x 1x 2 -6.26 m2
Jendel 0.97 x x 2x 2 -3.88 m2
1.38 x x 1x 2 -2.76 m2
1.53 x x 1x 2 -3.06 m2
Exhous 0.36 x x 6x 2 -4.32 m2

Plesteran dinding batu bata 1 Pc : 5 Ps 348.5175 m2

5 Plesteran beton 1 Pc : 3 Ps Panjang x Lebar x tinggi x buah x sisi


kolom 30x40 3.7 x 0.4 x 6x 2 17.76 m2
20x20 3.8 x 0.2 x 3x 2 4.56 m2
Balok BU 8x 0.9 x 4x 1 28.8 m2
BP 15 x 0.7 x 3x 1 31.5 m2
Listpla 15 x 0.76 x 2x 1 22.8 m2
8x 0.76 x 2x 1 12.16 m2

Plesteran beton 1 Pc : 3 Ps 117.58 m2

6 Acian
Plesteran dinding batu bata 1 Pc : 5 Ps 348.5175 m2
Plesteran beton 1 Pc : 3 Ps 117.58 m2

Acian 466.0975 m2
No Pekerejaan Perhitungan Volume Sat Ket

7 Sponengan Sudut 1 Pc : 3 Ps Panjang x Lebar x tinggi x buah x sisi


Kolom 3.65 x x 6x 4 87.6 m'
3.65 x x 3x 4 43.8 m'
Balok BU 8x x 4x 2 64 m'
BP 15 x x 3x 2 90 m'
No Pekerejaan Perhitungan Volume Sat Ket

Listplank 15 x x 2x 5 150 m'


8x x 2x 5 80 m'
Pintu 5.44 x x 1x 2 10.88 m'
5.83 x x 1x 2 11.66 m'
5.64 x x 1x 2 11.28 m'
Jendel 4.16 x x 2x 2 16.64 m'
4.76 x x 1x 2 9.52 m'
5.76 x x 1x 2 11.52 m'
Exhous 2.4 x x 2x 2 9.6 m'
2.4 x x 4x 2 19.2 m'
Saluran 38.35 x x 1x 1 38.35 m'

Sponengan Sudut 1 Pc : 3 Ps 654.05 m'

8 Kolom praktis 11x11 Panjang x Lebar x tinggi x buah x sisi


x 3.75 x 9x 33.75 m'
x 3.75 x 10 x 37.5 m'

Kolom praktis 11x11 71.25 m'

9 Balok latiu 10x15 Panjang x Lebar x tinggi x buah x sisi


4x x 4x 16 m'
3x x 1x 3 m'
6x x 2x 12 m'

Balok latiu 10x15 31 m'

V PEKERJAAN PLAFOND
1 Pasang Plafond Beton Expose luasan x Lebar x tinggi x buah
10.62 x x x 4 42.48 m2
13.43 x x x 2 26.86 m2
16.22 x x x 0 0 m2
3.03 x x x 4 12.12 m2
3.83 x x x 2 7.66 m2
4.63 x x x 0 0 m2
2.24 x x x 4 8.96 m2
0.64 x x x 4 2.56 m2

Pasang Plafond Beton Expose 100.64 m2


BACK UP PERHITUNGAN VOLUME ARSITEKTUR LA
KEGIATAN : PENYUSUNAN DED PEMBANGUNAN KAWASAN EXIT TOLL
PEKERJAAN : DED PEMBANGUNAN KAWASAN EXIT TOLL
LOKASI : KAB, PEKALONGAN
TAHUN ANGGARAN : 2017

NO PEKERJAAN PERHITUNGAN VOLUME

PEKERJAAN LAVATORY PUBLIK


II.3. PEKERJAAN PASANGAN

1 PEKERJAN PASANGAN ROOSTER p x l x t x


5.14 x 2.00 x

2 PEKERJAN PASANGAN GLASS BLOCK p x l x t x


2.51 x 2.00 x

3 Pasangan Batu Tempel Andesit


p x l x t x
4.15 x x 3.40 x
2.30 x x 0.63 x
0.50 x x 0.20 x
0.25 x x 2.30 x
2.34 x x 0.25 x
0.25 x x 0.20 x
4 Pas. dinding bata 1/2 batu 1 pc : 4 ps
p x bh x t x
1.33 x 3.00 x
1.33 x 2.05 x
1.33 x 2.35 x
1.35 x 3.00 x
2.20 x 2.05 x
4.15 x 3.40 x

DI ATAS DAK p x bh x t x
2.85 X X 1.20

DIKURANGI

Pas. Kusen dan jendela luas x l x t x


P 1.72 x x
BV 0.665 x x
BV1 1.421 x x

Pas. Roster
luas x l x t x
5.135 x

Pas. Glass Block luas x l x t x


2.509 x

5 Plesteran dinding bata 1 pc : 4 ps


p x sisi x t x
1.33 x 2.00 x 3.00 x
1.33 x 2.00 x 2.05 x
1.33 x 2.00 x 2.35 x
1.35 x 2.00 x 3.00 x
2.20 x 2.00 x 2.05 x
4.15 x 2.00 x 3.40 x
DI ATAS DAK p x sisi x t x
2.85 x 2.00 x 1.20 x
Dikurangi

Pas. Kusen Pintu dan Jendela


luas x sisi x t x
P 1.72 x 2.00 x
BV 0.67 x 2.00 x
BV1 1.42 x 2.00 x

Pas. Roster luas x sisi x t x


5.14 x 2.00 x

Pas. Glass Block luas x sisi x t x


2.51 x 2.00 x

6 Plesteran beton 1 pc : 3 ps
p x l x t x
Kolom K1 20x20 0.40 x x 3.00 x
KP 15X15 0.30 x x 3.00 x

Kolom K1 20x20 0.40 x x 2.35 x


KP 15X15 0.30 x x 2.35 x

KP 15X15 0.30 x x 2.05 x

K2 15X20 0.06 x x 0.10 x

7 Acian
Plesteran dinding bata 1 pc : 4 ps
Plesteran beton 1 pc : 3 ps
dikurangi
pasangan keramk dinding

8 Plesteran Skoning
p x sisi x t x
Kolom K1 0.12 x 3.00 x
0.12 x 2.35 x

Kusen pintu & jendela


P 5.10 x 2.00 0.03 x
BV 3.30 x 2.00 0.03 x
BV1 5.46 x 2.00 0.03 x

II.4. PEKERJAAN KUSEN, PINTU & JENDELA


p x l x t x
1 Pintu P
2 BOUVEN BV
3 BOUVEN BV1

II.5. PEKERJAAN PLAFOND


1 PLAFOND KALSI BOARD,T=3,5MM
(PL1) P x l x t x
2.73 x x
0.72 x x
3.55 x x
22.32 x x

2 COUMPON (PL2) 16.38 x x

3 List tepi profil gypsum


p x l x t x
39.66 x
7.90 x
18.50 x

II.6. PEKERJAAN PENUTUP LANTAI & DINDING


1 Keramik Lantai 30 x 30 Unpolished
luas x l x t x
139.13 x x
2 Keramik Dinding 40x 20
p x l x t x
3.51 x 2.46 x
12.45 x 2.25 x
37.43 x 2.25 x
Dikurangi
Pas. Kusen dan jendela luas x l x t x
P 1.72 x x
BV 0.665 x x

Pas. Roster
luas x l x t x
5.135 x

Pas. Glass Block luas x l x t x


2.509 x

II.7. PEKERJAAN CAT-CATAN


1 Cat tembok eksterior
p x sisi x t x
18.20 x 1.00 x 3.00 x
12.00 x 1.00 x 3.80 x

dikurangi luas x sisi x t x


Pintu & jendela BV1 1.42 x 2.00 x

2 Cat tembok interior


p x sisi x t x
Acian
dikurangi
Dinding sisi luar
3 Cat plafond
PLAFOND KALSI BOARD + COUMPOND luas x l x t x
47.24 x x

III.7. PEKERJAAN ATAP


1 GORDING p x besi x lembar x
C150x75 19.20 x 18.67 x x

2 Lapisan Alumunium Foil Single side luas x l x t x


128.64
3 Pas. Atap Genteng PVC Gelombang
p x l x t x
19.20 x 6.7 x x

4 Talang Air luas x l x t x


5 Listplank GRC
p x l x t x
19.20 x x x
6.70 x x x

6 Water Proof p x l x t x
19.20 1.63
III PEKERJAAN LAIN-LAIN

PEMASANGAN BUIS U20 p x l x t x


20.00 1

tutup saluran grid besi p x l x t x


17.40 x
ARSITEKTUR LAVATORY

TUNGAN VOLUME VOLUME

Unit = Vol
2.00 = 20.56 m2 20.56 m2

Unit = Vol
2.00 = 10.04 m2 10.04 m2

Unit = Vol
2.00 = 28.22 m2 58.39 m2
14.00 = 20.29 m2
14.00 = 1.40 m2
7.00 = 4.03 m2
7.00 = 4.10 m2
7.00 = 0.35 m2

Unit = Vol
12.00 = 47.88 m2 196.63 m2
7.00 = 19.09 m2
9.00 = 28.13 m2
21.00 = 85.05 m2
6.00 = 27.06 m2
2.00 = 28.22 m2

Unit = Vol
6 20.52 m2

Unit
16.00 = -27.52 m2
12.00 = -7.98 m2
6.00 = -8.53 m2

Unit
2.00 = -10.27 m2

Unit
2.00 = -5.02 m2

Unit = Vol
12.00 = 95.76 m2 393.13 m2
7.00 = 38.17 m2
9.00 = 56.26 m2
21.00 = 170.10 m2
6.00 = 54.12 m2
2.00 = 56.44 m2
Unit =
6.00 = 41.04 m2

Unit = Vol
16.00 = -55.04 m2
12.00 = -16.08 m2
6.00 = -17.04 m2

Unit = Vol
2.00 = -20.56 m2

Unit = Vol
2.00 = -10.04 m2

Unit = Vol
7.00 = 8.40 m2 37.57 m2
6.00 = 5.40 m2

7.00 = 6.58 m2
6.00 = 4.23 m2

21.00 = 12.92 m2

7.00 = 0.04 m2

= 393.13 m2 180.32 m2
= 37.57 m2

= -250.38 m2

Unit = Vol
7.00 = 2.52 m' 13.74 m'
7.00 = 1.97 m'

16.00 = 4.90 m'


12.00 = 2.38 m'
6.00 = 1.97 m'

unit = vol
16.00 = 16.00 unit 16.00 unit
12.00 = 12.00 unit 12.00 unit
1.00 = 1.00 unit 1.00 unit

Unit = Vol
6.00 = 16.38 m2 47.24 m2
2.00 = 1.44 m2
2.00 = 7.10 m2
1.00 = 22.32 m2

1.00 = 16.38 m2 16.38 m2

Unit = Vol
1.00 = 39.66 m' 73.96 m'
2.00 = 15.80 m'
1.00 = 18.50 m'

Unit = Vol
1.00 = 139.13 m2 139.13 m2

Unit = Vol
16.00 = 138.15 m2 199.59 m2
1.00 = 28.01 m2
1.00 = 84.22 m2

Unit
16.00 = -27.52 m2
12.00 = -7.98 m2

Unit
2.00 = -10.27 m2

Unit
2.00 = -5.02 m2

Unit = Vol
1.00 = 54.60 m2 83.15 m2
1.00 = 45.60 m2

Unit = Vol
6.00 = -17.05 m2

Unit = Vol
= 180.32 m2 125.72 m2

= -54.60 m2
Unit = Vol
1.00 = 47.24 m2 47.24 m2

jml = vol
6.00 = 2150.40 kg 2,150.40 kg

jml = vol
1.00 = 128.64 m2 128.64 m2

jml = vol
1.00 = 128.64 m2 128.64 m2

jml = vol 19.20 m'


19.20 m'
jml = vol
2.00 = 38.40 m' 51.80 m'
2.00 = 13.40 m'

jml = vol
1.00 = 31.30 m2 31.30 m2

jml = vol
1.00 = 20.00 m' 20.00 m2

jml = vol
1.00 = 17.40 m' 17.40 m'
BACK UP PERHITUNGAN VOLUME ARSITEKTUR MU
KEGIATAN : PENYUSUNAN DED PEMBANGUNAN KAWASAN EXIT TOLL
PEKERJAAN : DED PEMBANGUNAN KAWASAN EXIT TOLL
LOKASI : KAB. PEKALONGAN
TAHUN ANGGARAN : 2017

NO PEKERJAAN PERHITUNGAN VOLUME

PEKERJAAN MUSHOLLA
II.3. PEKERJAAN PASANGAN

1 PEKERJAN PASANGAN ROSTER p x l x t x


R2 5.76 x
R3 2.88 x
R4 6.24 x
R5 2.35 x

2 PEKERJAN PASANGAN GLASS BLOCK p x l x t x


RO 3.12 x
R1 5.76 x

3 Pas. dinding bata 1/2 batu 1 pc : 4 ps


p x bh x t x
2.55 x 3.17 x
2.87 x 4.10 x
2.40 x 4.10 x
4.50 x 4.10 x
2.67 x 2.75 x
1.35 x 2.75 x
1.25 x 2.75 x
2.18 x 2.75 x
2.62 x 2.75 x

DI ATAS DAK p x bh x t x
1.95 X X 1.10 X
2.55 X X 0.73 X

DIKURANGI

Pas. Kusen dan jendela luas x l x t x


P 1.94 x x
lb 0.408 x x

Pas. Glass Block


luas x l x t x
RO 3.12 x
R1 5.76 x
Pas. Roster luas x l x t x
R2 5.76 x
R3 2.88 x
R4 6.24 x
R5 2.35 x

4 Plesteran dinding bata 1 pc : 4 ps


p x sisi x t x
2.55 x 2.00 x 3.17 x
2.87 x 2.00 x 4.10 x
2.40 x 2.00 x 4.10 x
4.50 x 2.00 x 4.10 x
2.67 x 2.00 x 2.75 x
1.35 x 2.00 x 2.75 x
1.25 x 2.00 x 2.75 x
2.18 x 2.00 x 2.75 x
2.62 x 2.00 x 2.75 x

DI ATAS DAK ATAP p x sisi x t x


1.95 x 2.00 x 1.10 x
2.55 x 2.00 x 0.73 x

Dikurangi

Pas. Kusen Pintu dan Jendela


luas x sisi x t x
P 1.94 x 2.00 x
lb 0.41 x 2.00 x

Pas. Glass block luas x sisi x t x


3.12 x 2.00 x
5.76 x 2.00 x

Pas. Roster luas x sisi x t x


5.76 x 2.00 x x
2.88 x 2.00 x x
6.24 x 2.00 x x
2.35 x 2.00 x x

5 Plesteran beton 1 pc : 3 ps
p x l x t x
Kolom K1 35x35 1.00 x x 4.10 x
1.00 x x 2.80
1.00 x x 3.16

kolom k2 15x25 0.70 x x 2.75


0.70 x x 3.16

x x
kolom k3 25x15 0.35 x x 2.75
0.35 x x 2.75
0.50 x x 2.75
0.30 3.16

kolom kp 15x15 0.30 x x 4.10 x

kolom kp1 0.15 x x 2.75 x


0.30 x x 2.75 x

6 Acian
Plesteran dinding bata 1 pc : 4 ps
Plesteran beton 1 pc : 3 ps
dikurangi
pasangan keramik dinding

7 Plesteran Skoning
p x sisi x t x
P 3.75 X 2.00 0.03 X
LB 3.08 X 2.00 0.03 X

II.4. PEKERJAAN KUSEN, PINTU & JENDELA


p x l x t x
1 Pintu P
2 LB

II.5. PEKERJAAN PLAFOND


luas x l x t x
1 COUMPON (PL2) 129.83 x x
8.18 x x
6.05 x x
3.85 x x
1.82 x x

2 List tepi profil gypsum


p x l x t x
31.84 x
5.72 x
5.27 x
4.20 x
2.70 x

3 Plafond Motif Asma'ul Husna luas x l x t x


93.22 x

II.6. PEKERJAAN PENUTUP LANTAI & DINDING


a. pekerjaan pasangan keramik lantai
1 k1 60x120 polished
luas x l x t x
210.25 x x
9.05 x x

2 k2 60x60 unpolished 38.87 x x


3 k3 30x30 unpolished 7.13 x
4.61 x
3.63 x
3.83 x
4.06 x
1.82 x
b. pasangan keramik dinding
1 Keramik Dinding 20x25
p x l x t x
4.02 x 1.00 x
2.97 x 1.00 x
1.35 x 1.00 x
2.67 x 1.00 x
1.25 x 1.00 x
4.40 x 1.00 x
4.60 x 1.10 x
0.55 x 1.00 x

II.7. PEKERJAAN CAT-CATAN


1 Cat tembok eksterior
p x sisi x t x
8.75 x 1.00 x 4.10 x
11.67 x 1.00 x 4.10 x
5.50 x 1.00 x 4.10 x

dikurangi luas x sisi x t x


pas. Roster 5.76 x 1.00 x
2.88 x 1.00 x
6.24 x 1.00 x
2.35 x 1.00 x
pas. Glass block
3.12 x 1.00 x
5.76 x 1.00 x

2 Cat tembok interior


p x sisi x t x
Acian
dikurangi
Dinding sisi luar

3 Cat plafond
PLAFOND luas x l x t x
159.04 x x

II.8 Pekerjaan Beton Rabat luas x l x t x


8.40 x 0.08 x
4.54 x 0.08 x
13.65 x 0.08 x
30.45 x 0.08 x
4.60 x 0.08 x
6.50 x 0.08 x
18.25 x 0.08 x
3.55 x 0.08 x
5.86 x 0.08 x
30.00 x 0.08 x

II.9. PEKERJAAN ATAP


1 kubah luas x besi x lembar x
kubah enamel 163.98399 x x x

2 Water Proof luas x l x t x


65.98 x
8.85
7.34
18.91
II. 10 PEKERJAAN LAIN-LAIN
1 Pekerjaan Saluran
Pek. Pasangan U2 p x l x t x
21.00 x
2.50 x
3.15 x
19.30 x
6.10 x
2.10 x
6.30 x
13.30 x
4.60 x
8.30 x
Penutup Saluran Grill Besi
ARSITEKTUR MUSHOLLA

NGAN VOLUME VOLUME KET

Unit = Vol
8.00 = 46.08 m2 60.43 m2
2.00 = 5.76 m2
1.00 = 6.24 m2
1.00 = 2.35 m2

Unit = Vol
3.00 = 9.36 m2 95.76 m2
15.00 = 86.40 m2

Unit = Vol
1.00 = 8.08 m2 108.49 m2
2.00 = 23.53 m2
8.00 = 78.72 m2
2.00 = 36.90 m2
1.00 = 7.34 m2
5.00 = 18.56 m2
7.00 = 24.06 m2
1.00 = 6.00 m2
1.00 = 7.21 m2

Unit = Vol
1.00 2.15 m2
1.00 1.86 m2

Unit
16.00 = -31.04 m2
6.00 = -2.45 m2

Unit
2.00 = -6.24 m2
2.00 = -11.52 m2
Unit
6.00 = -34.56 m2
4.00 = -11.52 m2
1.00 = -6.24 m2
1.00 = -2.35 m2

Unit = Vol
1.00 = 16.17 m2 216.98 m2
2.00 = 47.07 m2
8.00 = 157.44 m2
2.00 = 73.80 m2
1.00 = 14.69 m2
5.00 = 37.13 m2
7.00 48.13 m2
1.00 11.99 m2
1.00 14.41 m2

Unit = vol
1.00 = 4.29 m2
1.00 = 3.72 m2

Unit = Vol
16.00 = -62.08 m2
6.00 = -4.92 m2

Unit = Vol
2.00 = -12.48 m2
2.00 = -23.04 m2

Unit = Vol
6.00 = -69.12 m2
4.00 = -23.04 m2
1.00 = -12.48 m2
1.00 = -4.70 m2

Unit = Vol
6.00 = 24.60 m2 73.39 m2
1.00 = 2.80 m2
2.00 = 6.32 m2

3.00 = 5.78 m2
2.00 = 4.42 m2

3.00 = 2.89 m2
3.00 = 2.89 m2
3.00 = 4.13 m2
2.00 = 1.90 m2

11.00 = 13.53 m2

6.00 = 2.48 m2
2.00 = 1.65 m2

= 216.98 m2 251.78 m2
= 73.39 m2

= -38.59 m2

Unit = Vol
16.00 = 3.60 m' 4.71 m'
6.00 = 1.11 m'

unit = vol
16.00 = 16.00 unit 16.00 unit
6.00 = 6.00 unit 6.00 unit

Unit = Vol
1.00 = 129.83 m2 159.04 m2
1.00 = 8.18 m2
1.00 = 6.05 m2
2.00 = 7.70 m2
4.00 = 7.28 m2

Unit = Vol
1.00 = 31.84 m' 62.03 m'
1.00 = 5.72 m'
1.00 = 5.27 m'
2.00 = 8.40 m'
4.00 = 10.80 m'

Unit = Vol
1.00 93.22 m2 93.22 m2

Unit = Vol
1.00 = 210.25 m2 219.30 m2
1.00 = 9.05 m2

1.00 = 38.87 m2 38.87 m2


1.00 = 7.13 m2 30.54 m2
1.00 = 4.61 m2
1.00 = 3.63 m2
1.00 = 3.83 m2
1.00 = 4.06 m2
4.00 = 7.28 m2

Unit = Vol
1.00 = 4.02 m2 38.59 m2
1.00 = 2.97 m2
2.00 = 2.70 m2
1.00 = 2.67 m2
4.00 = 5.00 m2
1.00 = 4.40 m2
3.00 = 15.18 m2
3.00 = 1.65 m2

Unit = Vol
2.00 = 71.75 m2 140.11 m2
2.00 = 95.69 m2
2.00 = 45.10 m2

Unit = Vol
6.00 = -34.56 m2
4.00 = -11.52 m2
1.00 = -6.24 m2
1.00 = -2.35 m2
2.00 = -6.24 m2
2.00 = -11.52 m2

Unit = Vol
1.00 = 251.78 m2 111.67 m2

1.00 = -140.11 m2

Unit = Vol
1.00 = 159.04 m2 159.04 m2

Unit = Vol 11.52 m3


1.00 = 0.67 m3
2.00 = 0.73 m3
2.00 = 2.18 m3
1.00 = 2.44 m3
1.00 = 0.37 m3
1.00 = 0.52 m3
1.00 = 1.46 m3
1.00 = 0.28 m3
1.00 = 0.47 m3
1.00 = 2.40 m3

jml = vol 163.98 m2


= 163.98 m2

jml = vol
1.00 = 65.98 m2 101.08 m2
1.00 = 8.85 m2
1.00 = 7.34 m2
1.00 = 18.91 m2

jml = vol 94.85 m'


1.00 = 21.00 m'
1.00 = 2.50 m'
1.00 = 3.15 m'
1.00 = 19.30 m'
2.00 = 12.20 m'
2.00 = 4.20 m'
1.00 = 6.30 m'
1.00 = 13.30 m'
1.00 = 4.60 m'
1.00 = 8.30 m'
BACK UP PLAT BETON REST AREA

NO JENIS PEKERJAAN VOLUME SAT POSISI / TYPE

1 Beton Plat Dak Tb.10 cm POSISI / TYPE =


- Beton K- 250 = 14.40 m3 - BetonK 250 =
- Bekisting untuk lantai = 144.00 m2 - Bekisting untuk lantai =
- Pembesian dengan besi polos atau ulir = 965.57 kg - besi polos atau ulir =
Item Pek. Pnjg Bgl Pnjg Tulgn+40x
1 2 3
Tulangan Horisontal
Tul. Ats 10 150
Tulangan Vertikal
Tul. Ats 10 150

2 Beton Plat Dak Tb.10 cm POSISI / TYPE =


- Beton K- 250 = 7.80 m3 - BetonK 250 =
- Bekisting untuk lantai = 78.00 m2 - Bekisting untuk lantai =
- Pembesian dengan besi polos atau ulir = 529.87 kg - besi polos atau ulir =
Item Pek. Pnjg Bgl Pnjg Tulgn+40x
1 2 3
Tulangan Horisontal
Tul. Ats 10 150
Tulangan Vertikal
Tul. Ats 10 150

3 Beton Plat Dak b.10 cm POSISI / TYPE =


- Beton K- 250 = 2.40 m3 - BetonK 250 =
- Bekisting untuk lantai = 24.00 m2 - Bekisting untuk lantai =
- Pembesian dengan besi polos atau ulir = 171.58 kg - besi polos atau ulir =
Item Pek. Pnjg Bgl Pnjg Tulgn+40x
1 2 3
Tulangan Horisontal
Tul. Ats 10 150
Tulangan Vertikal
Tul. Ats 10 150

4 Beton Plat Dak Tb.10 cm POSISI / TYPE =


- Beton K- 250 = 1.80 m3 - BetonK 250 =
- Bekisting untuk lantai = 18.00 m2 - Bekisting untuk lantai =
- Pembesian dengan besi polos atau ulir = 125.49 kg - besi polos atau ulir =
Item Pek. Pnjg Bgl Pnjg Tulgn+40x
1 2 3
Tulangan Horisontal
Tul. Ats 10 150
Tulangan Vertikal
Tul. Ats 10 150

5 Beton Plat Talang Tb.10 cm POSISI / TYPE =


- Beton K- 250 = 0.94 m3 - BetonK 250 =
- Bekisting untuk lantai = 9.42 m2 - Bekisting untuk lantai =
- Pembesian dengan besi polos atau ulir = 85.75 kg - besi polos atau ulir =
Item Pek. Pnjg Bgl Pnjg Tulgn+40x
1 2 3
Tulangan Horisontal
Tul. Ats 10 150
Tulangan Vertikal
Tul. Ats 10 150
PERHITUNGAN VOLUME
P x L x T x unit =

P x L x T x unit =
18.00 x 8.00 x 0.10 = 14.40 m3
18.00 x 8.00 = 144.00 m2
= 965.57 kg
Pnjg Tulgn+40x Brt Bsi Pjg x Brt Bsi Pjg x Brt Bsi Ttl brt besi
3 4 5 = (2x4) 6 = (3x4) 7

1035.05 0.62 641.731 641.73 kg/m'

522.32 0.62 323.8384 323.84 kg/m'


Begel + Tulangan = 965.57 kg/m'
= 67.05 kg/m3

P x L x T x unit =
13.00 x 6.00 x 0.10 = 7.80 m3
13.00 x 6.00 = 78.00 m2
= 529.87 kg
Pnjg Tulgn+40x Brt Bsi Pjg x Brt Bsi Pjg x Brt Bsi Ttl brt besi
3 4 5 = (2x4) 6 = (3x4) 7

567.51 0.62 351.8562 351.86 kg/m'

287.11 0.62 178.0082 178.01 kg/m'


Begel + Tulangan = 529.87 kg/m'
= 67.93 kg/m3

P x L x T x unit =
3.00 x 8.00 x 0.10 = 2.40 m3
3.00 x 8.00 = 24.00 m2
= 171.58 kg
Pnjg Tulgn+40x Brt Bsi Pjg x Brt Bsi Pjg x Brt Bsi Ttl brt besi
3 4 5 = (2x4) 6 = (3x4) 7

186.09 0.62 115.3758 115.38 kg/m'

90.65 0.62 56.203 56.20 kg/m'


Begel + Tulangan = 171.58 kg/m'
= 71.49 kg/m3

P x L x T x unit =
4.50 x 8.00 x 0.10 = 3.60 m3
4.50 x 8.00 = 36.00 m2
= 250.98 kg
Pnjg Tulgn+40x Brt Bsi Pjg x Brt Bsi Pjg x Brt Bsi Ttl brt besi
3 4 5 = (2x4) 6 = (3x4) 7

270.99 0.62 168.0138 168.01 kg/m'

133.82 0.62 82.9684 82.97 kg/m'


Begel + Tulangan = 250.98 kg/m'
= 69.72 kg/m3

P x L x T x unit =
18.84 x 0.50 x 0.10 = 0.94 m3
18.84 x 0.50 = 9.42 m2
= 85.75 kg
Pnjg Tulgn+40x Brt Bsi Pjg x Brt Bsi Pjg x Brt Bsi Ttl brt besi
3 4 5 = (2x4) 6 = (3x4) 7

86.34 0.62 53.5308 53.53 kg/m'

51.96 0.62 32.2152 32.22 kg/m'


Begel + Tulangan = 85.75 kg/m'
= 91.22 kg/m3
Analisa Kusen Rest Area

JML
TYPE JML URAIAN SAT
PER UNIT

PJ1 1.00 Kaca Tempred 12mm laminated 3.36 m2


1.00 Kaca Bening 12 mm 9.52 m2
1.00 Ply Wood + Rangka 3.40 m2
1.00 Cat Duco 3.40 m2
1.00 Sticker sandblast 4.51 m2
1.00 Sealent 36.80 m1
1.00 Floor Hing 4.00 set
1.00 Loockcase 1.00 bh
1.00 Handle Stainles 2.00 psng
1.00 Lampu TL 3.00 ttk

PJ2 1.00 Kaca Tempred 12mm laminated 6.72 m2


1.00 Kaca Bening 12 mm 31.00 m2
1.00 Ply Wood + Rangka 6.80 m2
1.00 Cat Duco 6.80 m2
1.00 Sticker sandblast 14.17 m2
1.00 Sealent 69.60 m1
1.00 Floor Hing 8.00 set
1.00 Loockcase 2.00 bh
1.00 Handle Stainles 4.00 psng
1.00 Lampu TL 6.00 ttk

P1 1.00 Kaca Tempred 12mm laminated 3.36 m2


1.00 Ply Wood + Rangka 3.40 m2
1.00 Cat Duco 3.40 m2
1.00 Sticker sandblast 1.47 m2
1.00 Floor Hing 4.00 set
1.00 Loockcase 1.00 bh
1.00 Handle Stainles 2.00 psng
1.00 Lampu TL 3.00 ttk

P2 1.00 Kusen aluminium 4" natural 7.16 m'


1.00 Rangka pintu Alumunium 0.55 m2
1.00 Rangka bouvent aluminium 0.21 m2
1.00 Kaca bening 5 mm 1.40 m2
1.00 Engsel pintu 3.00 bh
1.00 Engsel Jendela 2.00 bh
1.00 Kunci Pintu + Handle 1.00 bh
1.00 Door Stoper 1.00 bh
1.00 Rambuncis 1.00 bh

P3 1.00 Kusen aluminium 4" Colour 7.16 m'


1.00 Rangka pintu Kayu Lapis Double Teakwood 1.68 m2
1.00 Rangka bouvent aluminium 0.21 m2
1.00 Kaca bening 5 mm 0.27 m2
1.00 Engsel pintu 3.00 bh
1.00 Engsel Jendela 2.00 bh
1.00 Kunci Pintu + Handle 1.00 bh
1.00 Rambuncis 1.00 bh

PL 1.00 Kusen aluminium 4" Colour 4.90 m'


1.00 Rangka pintu Kayu Lapis Double Teakwood 1.68 m2
1.00 HPL 1.32 m2
1.00 Krepyak 0.15 m2
1.00 Engsel pintu 3.00 bh
1.00 Kunci Pintu + Handle 1.00 bh

PJ3 1.00 Kusen aluminium 4" Colour 17.90 m'


1.00 Rangka pintu Alumunium 3.46 m2
1.00 Rangka bouvent aluminium 0.21 m2
1.00 Kaca bening 5 mm 1.43 m2
1.00 Engsel pintu 3.00 bh
1.00 Engsel Jendela 2.00 bh
1.00 Kunci Pintu + Handle 1.00 bh
1.00 Rambuncis 1.00 bh
1.00 Sealent 6.68 bh
1.00 Meja Teablok 18 mm 4.64 m2

J1 1.00 Kaca Bening 12 mm 11.83 m2


1.00 Sticker sandblast 4.19 m2
1.00 Sealent 45.50 m1

J2 1.00 Kaca Bening 12 mm 5.72 m2


1.00 Sticker sandblast 2.02 m2
1.00 Sealent 18.80 m1

J3 1.00 Kaca Bening 12 mm 8.84 m2


1.00 Sticker sandblast 3.13 m2
1.00 Sealent 77.52 m1

J4 1.00 Kaca Bening 12 mm 15.42 m2


1.00 Sticker sandblast 5.46 m2
1.00 Sealent 48.26 m1

J5 1.00 Kusen aluminium 4" Colour 10.44 m'


1.00 Rangka Jendela Alumunium 0.48 m'
1.00 Rangka Bouvent Alumunium 0.35 m'
1.00 Engsel Jendela 4.00 bh
1.00 Engsel Bouvent 4.00 bh
1.00 Kaca bening 5mm 1.82 m2
1.00 Rambuncis 2.00 bh

JA 1.00 Kusen aluminium 4" Colour 2.90 m'


1.00 Kaca bening 5mm 1.82 m2
1.00 Sealent 2.90 m1

B1 1.00 Kusen aluminium 4" Colour 2.80 m'


1.00 Rangka Bouvent Alumunium 0.16 m'
1.00 Kaca bening 5mm 0.27 m2
1.00 Rambuncis 1.00 bh

B2 1.00 Kusen aluminium 4" Colour 4.92 m'


1.00 Rangka Bouvent Alumunium 0.33 m'
1.00 Kaca bening 5mm 0.53 m2
1.00 Rambuncis 2.00 bh
HARGA SAT TOTAL HARGA

1,850,000.00 6,216,000.00
300,000.00 2,856,000.00
162,955.00 554,047.00
42,728.25 145,276.05
94,098.75 424,385.36
3,750.00 138,000.00
1,200.00 4,800.00
110,000.00 110,000.00
400,000.00 800,000.00
125,000.00 375,000.00
11,623,508.41

1,850,000.00 12,432,000.00
300,000.00 9,300,000.00
162,955.00 1,108,094.00
42,728.25 290,552.10
94,098.75 1,333,379.29
3,750.00 261,000.00
1,200.00 9,600.00
110,000.00 220,000.00
400,000.00 1,600,000.00
125,000.00 750,000.00
27,304,625.39

1,850,000.00 6,216,000.00
162,955.00 554,047.00
42,728.25 145,276.05
94,098.75 138,325.16
1,200.00 4,800.00
110,000.00 110,000.00
400,000.00 800,000.00
125,000.00 375,000.00
8,343,448.21

108,984.35 780,327.95
521,295.00 286,712.25
521,295.00 109,471.95
141,642.63 198,299.68
37,921.25 113,763.75
23,747.50 47,495.00
200,000.00 200,000.00
52,031.75 52,031.75
50,000.00 50,000.00
1,838,102.33

121,634.35 870,901.95
479,524.70 805,601.50
571,895.00 120,097.95
141,642.63 38,243.51
37,921.25 113,763.75
23,747.50 47,495.00
200,000.00 200,000.00
50,000.00 50,000.00
2,246,103.66

121,634.35 596,008.32
479,524.70 805,601.50
100,000.00 132,000.00
500,000.00 75,000.00
37,921.25 113,763.75
200,000.00 200,000.00
1,922,373.57

121,634.35 2,177,254.87
479,524.70 1,659,155.46
571,895.00 120,097.95
141,642.63 202,548.96
37,921.25 113,763.75
23,747.50 47,495.00
200,000.00 200,000.00
50,000.00 50,000.00
3,750.00 25,050.00
500,000.00 2,320,000.00
6,915,365.99

300,000.00 3,549,000.00
94,098.75 394,273.76
3,750.00 170,625.00
4,113,898.76

300,000.00 1,716,000.00
94,098.75 190,079.48
3,750.00 70,500.00
1,976,579.48

300,000.00 2,652,000.00
94,098.75 294,529.09
3,750.00 290,700.00
3,237,229.09

300,000.00 4,626,000.00
94,098.75 513,779.18
3,750.00 180,975.00
5,320,754.18

121,634.35 1,269,862.61
571,895.00 274,509.60
571,895.00 200,163.25
23,747.50 94,990.00
23,747.50 94,990.00
141,642.63 257,789.59
50,000.00 100,000.00
2,292,305.05

121,634.35 352,739.62
141,642.63 257,789.59
3,750.00 10,875.00

121,634.35 340,576.18
571,895.00 91,503.20
141,642.63 38,243.51
50,000.00 50,000.00
520,322.89

121,634.35 598,441.00
571,895.00 188,725.35
141,642.63 75,070.59
50,000.00 100,000.00
962,236.94
BACK UP PERHITUNGAN VOLUM
KEGIATAN : PENYUSUNAN DED PEMBANGUNAN KAWASAN EXIT TOLL
PEKERJAAN : DED PEMBANGUNAN KAWASAN EXIT TOLL
LOKASI : KAB. PEKALONGAN
TAHUN ANGGARAN : 2017

NO PEKERJAAN PER

PEKERJAAN SCLUPTURE

1 Galian Tanah Area


6.50

2 Urugan Tanah Peninggian Luas Lingkaran


195.97
2.00

3 Urugan Pasir Bawah Footplat p x l


3.00 x 3.00

4 Urugan Pasir Bawah Lantai Luas Lingkaran


284.93

5 Lantai Kerja Bawah lantai p x l


3.00 x 3.00

6 Rolag Batu Bata p x l


22.00 x 0.35

31.40 x 0.35

7 Lantai Kerja Bawah Footplat Luas Lingkaran


284.93

8 Lantai Kerja Bawah Footplat beton a + b


2

3.00 + 1.00
2

besi D19-15 P x Kg besi

6.69 x 2.23

6.42 x 2.23

Begesting p x l
3.00 x 0.20
2.00 x 0.30
9 Beton bertulang sloof 15/20

beton p x l

22.00 x 0.15
31.40 x 0.15

besi 412 P x Kg besi


53.40 x 0.89

besi 10-150 p x Kg besi


0.70 x 0.62

Begesting p x l
53.40 x 0.20
53.40 x 0.15

9 Beton bertulang Kolom Pedestal 100/100

beton p x l

3.60 x 0.80

besi 20 D 19 P x Kg besi
3.60 x 2.23

besi 12-150 p x Kg besi


4.00 x 0.89

Begesting p x l
3.60 x 1.00

Beton bertulang Kolom Pedestal 100/100

beton p x l

21.80 x 0.15

10 Pasang Dinding Batu Bata 1:4 p x l

22.00 x

11 Pasang Plat Landas tebal 10mm p x l

0.70 x 0.70

12 Pasang Plat Sambung tebal 8mm p x l

0.60 x 0.60

13 Angkur besi dia 19 mm p x l


0.70 x

14 Baut bh

72.00

15 Baja IWF 600,300 p x l

8.00 x

16 Baja IWF 500, p x l

6.00 x

17 Pipa hitam 8" t= 4,5 mm p x l

8.10 x

18 Tembaga Motif Luas

Bawah a + b
2

6.00 + 2.00

5.00 + 2.00

Tengah Panjang 3.14


Tinggi 14.00

Luas

p x l
3.14 x

Atas Panjang 3.14


Tinggi 8.10

Luas

p x l
3.14 x

19 Lantai Batu Lempeng L1 p x r


3.14 x 7.90

L2 3.14 x 4.85
l3 1.50 x 5.00

20 Lantai Paving Holland L1 p x r


3.14 x 10.70

p x r
3.14 x 7.90

21 Kansteen Keliling 2.00 x p


2.00 x 3.14

22 Rumput Gajah Mini L1 p x r


3.14 x 4.85

L2 4.15 x 5.00

23 Terucuk Bambu L1 p x l

3.00

1 Tiang pancang Mini pile 32 x 32 x32 (K450)

P3 p x N
12.00 x 3.00

2 Pecah kepala tiang pancang minipile

P3 p x N
x 3.00

3 Lantai kerja bwh pile cap t= 5 cm

P3 Area x N
2.85 x

4 Beton Bertulang Pile cap type P3


Membuat Beton mutu f'c=21,7 MPa Area x l
(K250), Slump(122),w/c=0,58 2.85 x

5 Kolom Pedestal p x l
Membuat Beton mutu f'c=21,7 MPa 0.90 x 0.90
(K250), Slump(122),w/c=0,58
RHITUNGAN VOLUME SCLUPTURE EXIT TOLL

PERHITUNGAN VOLUME VOLUME

x t x Unit = Vol
x 0.90 x 1.00 = 5.85 5.85

x t x Unit = Vol
x 0.30 x 1.00 = 58.79 70.79
x 3.00 x 2.00 12.00

x t x Unit = Vol
x 0.10 x 1.00 = 0.90 0.90

x t x Unit = Vol
x 0.10 x 1.00 = 28.49 28.49

x t x Unit = Vol
x 0.05 x 1.00 = 0.45 0.45

x t x Unit = Vol
x 0.35 x 1.00 = 2.70 6.55

x 0.35 x 1.00 = 3.85

x t x Unit = Vol
x 0.05 x 1.00 = 14.25 14.25

x t x P = Vol

x 0.60 x 3.00 = 3.60 3.60

x bh x Unit = Vol

x 21.00 x 1.00 = 313.29 628.26

x 22.00 x 1.00 = 314.97

x sisi x unit = vol


x 4.00 x 1.00 = 2.40 m2 3.00
x 1.00 x 1.00 = 0.60 m2
x t x Unit = Vol

x 0.20 x 1.00 = 2.22 5.38


x 0.20 x 1.00 = 3.16

x bh x Unit = Vol
x 4.00 x 1.00 = 190.10 345.04

x bh x Unit = Vol
x 357.00 x 1.00 = 154.94

x sisi x unit = vol


x 2.00 x 1.00 = 21.36 m2 37.38
x 2.00 x 1.00 = 16.02 m2

x t x Unit = Vol

x 0.80 x 1.00 = 1.76 1.76

x bh x Unit = Vol
x 12.00 x 1.00 = 96.34 185.34

x bh x Unit = Vol
x 25.00 x 1.00 = 89.00

x sisi x unit = vol


x 4.00 x 1.00 = 14.40 m2 14.40

x t x Unit = Vol

x 0.15 x 1.00 = 1.65 1.65

x t x Unit = Vol

x 0.70 x 1.00 = 15.40 15.40

x kg x Unit = Vol

x 75.00 x 1.00 = 52.50 52.50

x kg x Unit = Vol

x 65.00 x 16.00 = 624.00 624.00

x kg x Unit = Vol
x 2.23 x 8.00 = 12.49 12.49

72.00

x kg x Unit = Vol

x 170.67 x 1.00 = 1365.36 1,365.36

x kg x Unit = Vol

x 89.65 x 1.00 = 537.90 537.90

x kg x Unit = Vol

x 30.11 x 1.00 = 243.89 243.89

x t x Unit = Vol

x 2.00 x 2.00 = 16.00 30.00

x 2.00 x 2.00 = 14.00

x t x Unit = Vol 43.96


14.00 = 43.96

x t x Unit = Vol 25.43


8.10 = 25.43

x r x Unit = Vol
x 7.90 x 1.00 = 195.97 114.61

x 4.85 x 1.00 = 73.86


= 7.50

x r x Unit = Vol
x 10.70 x 1.00 = 359.50 163.53

x r x Unit = Vol
x 7.90 x 1.00 = 195.97

x r x Unit = Vol 67.20


x 10.70 x 1.00 = 67.20

x r x Unit = Vol 53.11


x 4.85 x 1.00 = 73.86

= 20.75

x t x Unit = Vol 48.00

16.00 = 48.00

36.00

x t x Unit = Vol
x 1.00 = 36.00

3.00

x t x Unit = Vol
x 1.00 = 3.00

0.14

x t x Unit = Vol
0.05 x 1.00 = 0.14

x t x Unit = Vol
0.60 x 1.00 = 1.71 1.71

x t x Unit = Vol
3.70 x 1.00 = 3.00 3.00
VOLUME KET

m3

m3

m3

m3

m3

m3

m3

m3

kg

m2
m3

kg

m2

m3

kg

m2

m3

m2

kg

kg
kg

bh

kg

kg

kg

m2

m2

m2

m2
m2

m1

m2

m1

m1

ttk

m3

m3

m3
BACK UP PERHITUNGAN VOLUME
KEGIATAN : PENYUSUNAN DED PEMBANGUNAN KAWASAN EXIT TOL
PEKERJAAN : DED PEMBANGUNAN KAWASAN EXIT TOL
LOKASI : KECAMATAN BOJONG, KABUPATEN PEKALONGAN
TAHUN ANGGARAN : 2017

NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET

I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi awal dan akhir 1.00 Ls
2 Uitzet dan bouwplank 1.00 Ls
3 Air kerja dan listrik kerja 1.00 Ls
4 Papan nama proyek 1.00 Ls
5 Mobilisasi dan demobilisasi 1.00 Ls
6 Pagar sementara dari seng gelombang tinggi 2,00 m - m'
p x l x t x unit = vol

II PEKERJAAN LAVATORY PUBLIK


II. 1. PEKERJAAN TANAH
1 Galian tanah pondasi
p x l x t x unit = vol
- Pondasi Footplat 1.00 x 1.00 x 1.30 x 21.00 = 27.30 m3 174.51 m3
- Pondasi Pasangan Batu Belah
- Arah X 18.00 x 1.00 x 1.15 x 3.00 = 62.10 m3
7.50 x 1.00 x 1.15 x 2.00 = 17.25 m3
6.00 x 1.00 x 1.15 x 1.00 = 6.90 m3
9.00 x 1.00 x 1.15 x 1.00 = 10.35 m3
- Arah Y 6.50 x 1.00 x 1.15 x 2.00 = 14.95 m3
1.50 x 1.00 x 1.15 x 17.00 = 29.33 m3
4.50 x 1.00 x 1.15 x 1.00 = 5.18 m3
1.00 x 1.00 x 1.15 x 1.00 = 1.15 m3

2 Urugan Tanah Kembali


p x l x t x unit = vol
- Galian Tanah Pondasi = 174.51 m3 111.22 m3
Dikurangi :
- Urugan Pasir = -10.24 m3
- Lantai Kerja = -1.05 m3
- Pondasi Footplat = -3.05 m3
- Pondasi Pasangan Batu Belah = -43.52 m3
- Sloof 15x25 = -5.43 m3

3 Urugan Pasir di Bawah Pondasi


p x l x t x unit = vol
- Arah X 18.00 x 0.80 x 0.10 x 3.00 = 4.32 m3 10.24 m3
7.50 x 0.80 x 0.10 x 2.00 = 1.20 m3
6.00 x 0.80 x 0.10 x 1.00 = 0.48 m3
9.00 x 0.80 x 0.10 x 1.00 = 0.72 m3
- Arah Y 6.50 x 0.80 x 0.10 x 2.00 = 1.04 m3
1.50 x 0.80 x 0.10 x 17.00 = 2.04 m3
4.50 x 0.80 x 0.10 x 1.00 = 0.36 m3
1.00 x 0.80 x 0.10 x 1.00 = 0.08 m3

4 Urugan Tanah Peninggian Bangunan


p x l x t x unit = vol
19.20 x 7.90 x 1.30 x 1.00 = 197.18 m3 197.18 m3

5 Terucuk Bambu 3" p x l x t x unit = vol


2.00 x 189.00 = 378.00 m' 378.00 m'

II. 2. PEKERJAAN BETON


1 Beton Lantai Kerja
p x l x t x unit = vol
1.00 x 1.00 x 0.05 x 21.00 = 1.05 m3 1.05 m3

2 Rabat Beton tebal 5 cm


p x l x t x unit = vol
19.20 x 7.90 x 0.05 x 1.00 = 7.58 m3 7.58 m3

3 Beton Pondasi Footplat 80x80 cm


- Beton K-250 p x l x t x unit = vol
0.80 x 0.80 x 0.20 x 21.00 = 2.69 m3 3.05 m3
0.34 x 0.05 x 21.00 = 0.36 m3

- Pembesian p x besi x bh x unit = vol

83/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET
12-150 2.15 x 0.888 x 12.00 x 21.00 = 481.12 kg 481.12 kg

- Bekisting p x l x sisi x unit = vol


0.80 x 0.20 x 4.00 x 21.00 = 13.44 m2 30.24 m2
0.50 x 0.40 x 4.00 x 21.00 = 16.80 m2

4 Beton Sloof 15x25 cm


- Beton K-250 p x l x t x unit = vol
- Arah X 18.00 x 0.15 x 0.25 x 3.00 = 2.03 m3 5.43 m3
7.50 x 0.15 x 0.25 x 2.00 = 0.56 m3
6.00 x 0.15 x 0.25 x 1.00 = 0.23 m3
9.00 x 0.15 x 0.25 x 1.00 = 0.34 m3
- Arah Y 6.50 x 0.15 x 0.25 x 6.00 = 1.46 m3
1.50 x 0.15 x 0.25 x 9.00 = 0.51 m3
4.50 x 0.15 x 0.25 x 1.00 = 0.17 m3
3.50 x 0.15 x 0.25 x 1.00 = 0.13 m3

- Pembesian p x besi x bh x unit = vol


4 12 19.03 x 0.888 x 4.00 x 3.00 = 202.78 kg 954.89 kg
7.57 x 0.888 x 4.00 x 2.00 = 53.78 kg
6.07 x 0.888 x 4.00 x 1.00 = 21.56 kg
9.07 x 0.888 x 4.00 x 1.00 = 32.22 kg
6.57 x 0.888 x 4.00 x 6.00 = 140.02 kg
1.57 x 0.888 x 4.00 x 9.00 = 50.19 kg
4.57 x 0.888 x 4.00 x 1.00 = 16.23 kg
3.57 x 0.888 x 4.00 x 1.00 = 12.68 kg
10-150 0.70 x 0.617 x 121.0 x 3.00 = 156.78 kg
0.70 x 0.617 x 51.00 x 2.00 = 44.05 kg
0.70 x 0.617 x 41.00 x 1.00 = 17.71 kg
0.70 x 0.617 x 61.00 x 1.00 = 26.35 kg
0.70 x 0.617 x 44.00 x 6.00 = 114.02 kg
0.70 x 0.617 x 11.00 x 9.00 = 42.76 kg
0.70 x 0.617 x 31.00 x 1.00 = 13.39 kg
0.70 x 0.617 x 24.00 x 1.00 = 10.37 kg

- Bekisting p x l x sisi x unit = vol


18.00 x 0.25 x 2.00 x 3.00 = 27.00 m2 72.25 m2
7.50 x 0.25 x 2.00 x 2.00 = 7.50 m2
6.00 x 0.25 x 2.00 x 1.00 = 3.00 m2
9.00 x 0.25 x 2.00 x 1.00 = 4.50 m2
6.50 x 0.25 x 2.00 x 6.00 = 19.50 m2
1.50 x 0.25 x 2.00 x 9.00 = 6.75 m2
4.50 x 0.25 x 2.00 x 1.00 = 2.25 m2
3.50 x 0.25 x 2.00 x 1.00 = 1.75 m2

5 Beton Kolom K1 20x20 cm


- Beton K-250 p x l x t x unit = vol
0.20 x 0.20 x 4.84 x 7.00 = 1.36 m3 2.49 m3
0.20 x 0.20 x 4.05 x 7.00 = 1.13 m3

- Pembesian p x besi x bh x unit = vol


4 D12 5.50 x 0.888 x 4.00 x 7.00 = 136.75 kg 438.28 kg
4.71 x 0.888 x 4.00 x 7.00 = 117.11 kg
10-150 0.70 x 0.617 x 33.00 x 7.00 = 99.77 kg
0.70 x 0.617 x 28.00 x 7.00 = 84.65 kg

- Bekisting p x l x sisi x unit = vol


4.84 x 0.20 x 4.00 x 7.00 = 27.10 m2 49.78 m2
4.05 x 0.20 x 4.00 x 7.00 = 22.68 m2

6 Beton Kolom K2 15x20 cm


- Beton K-250 p x l x t x unit = vol
0.15 x 0.20 x 3.45 x 7.00 = 0.72 m3 0.72 m3

- Pembesian p x besi x bh x unit = vol


4 D12 4.11 x 0.888 x 4.00 x 7.00 = 102.19 kg 164.38 kg
10-150 0.60 x 0.617 x 24.00 x 7.00 = 62.19 kg

- Bekisting p x l x sisi x unit = vol


3.45 x 0.15 x 2.00 x 7.00 = 7.25 m2 16.91 m2
3.45 x 0.20 x 2.00 x 7.00 = 9.66 m2

7 Beton Kolom Praktis 15x15 cm


p x l x t x unit = vol

84/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET
2.50 x 35.00 = 87.50 m' 87.50 m'

85/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET
8 Beton Balok 15x20 cm
- Beton K-250 p x l x t x unit = vol
18.00 x 0.15 x 0.20 x 2.00 = 1.08 m3 1.50 m3
2.00 x 0.15 x 0.20 x 7.00 = 0.42 m3

- Pembesian p x besi x bh x unit = vol


4 D13 18.65 x 1.042 x 4.00 x 2.00 = 155.47 kg 545.24 kg
2.13 x 1.042 x 4.00 x 7.00 = 62.14 kg
10-100 0.60 x 0.617 x 92.00 x 2.00 = 68.12 kg
0.60 x 0.617 x 91.00 x 2.00 = 67.38 kg
0.60 x 0.617 x 12.00 x 7.00 = 31.10 kg
0.60 x 0.617 x 11.00 x 7.00 = 28.51 kg
10-150 0.60 x 0.617 x 62.00 x 2.00 = 45.90 kg
0.60 x 0.617 x 61.00 x 2.00 = 45.16 kg
0.60 x 0.617 x 8.00 x 7.00 = 20.73 kg
0.60 x 0.617 x 8.00 x 7.00 = 20.73 kg

- Bekisting p x l x sisi x unit = vol


18.00 x 0.15 x 1.00 x 2.00 = 5.40 m2 27.50 m2
18.00 x 0.20 x 2.00 x 2.00 = 14.40 m2
2.00 x 0.15 x 1.00 x 7.00 = 2.10 m2
2.00 x 0.20 x 2.00 x 7.00 = 5.60 m2

9 Beton Ring Balok 15x20 cm


- Beton K-250 p x l x t x unit = vol
18.00 x 0.15 x 0.20 x 4.00 = 2.16 m3 2.66 m3
1.50 x 0.15 x 0.20 x 8.00 = 0.36 m3
4.50 x 0.15 x 0.20 x 1.00 = 0.14 m3

- Pembesian p x besi x bh x unit = vol


4 12 18.60 x 0.888 x 4.00 x 4.00 = 264.27 kg 606.21 kg
1.62 x 0.888 x 4.00 x 8.00 = 46.03 kg
4.62 x 0.888 x 4.00 x 1.00 = 16.41 kg
10-120 0.60 x 0.617 x 151.0 x 4.00 = 223.60 kg
0.60 x 0.617 x 14.00 x 8.00 = 41.46 kg
0.60 x 0.617 x 39.00 x 1.00 = 14.44 kg

- Bekisting p x l x sisi x unit = vol


18.00 x 0.15 x 1.00 x 4.00 = 10.80 m2 48.68 m2
18.00 x 0.20 x 2.00 x 4.00 = 28.80 m2
1.50 x 0.15 x 1.00 x 8.00 = 1.80 m2
1.50 x 0.20 x 2.00 x 8.00 = 4.80 m2
4.50 x 0.15 x 1.00 x 1.00 = 0.68 m2
4.50 x 0.20 x 2.00 x 1.00 = 1.80 m2

10 Beton Balok Kuda-kuda 15x20 cm


- Beton K-250 p x l x t x unit = vol
6.50 x 0.15 x 0.20 x 7.00 = 1.37 m3 1.37 m3

- Pembesian p x besi x bh x unit = vol


4 D12 6.62 x 0.888 x 4.00 x 7.00 = 164.60 kg 307.13 kg
10-120 0.60 x 0.617 x 55.00 x 7.00 = 142.53 kg

- Bekisting p x l x sisi x unit = vol


6.50 x 0.15 x 1.00 x 7.00 = 6.83 m2 25.03 m2
6.50 x 0.20 x 2.00 x 7.00 = 18.20 m2

11 Beton Plat Atap tebal 10 cm


- Beton K-250 p x l x t x unit = vol
19.00 x 2.30 x 0.10 x 1.00 = 4.37 m3 4.37 m3

- Pembesian p x besi x bh x unit = vol


10-150 19.85 x 0.617 x 127.0 x 1.00 = 1555.43 kg 1,578.63 kg
2.35 x 0.617 x 16.00 x 1.00 = 23.20 kg

- Bekisting p x l x sisi x unit = vol


19.00 x 2.30 x 1.00 x 1.00 = 43.70 m2 47.96 m2
19.00 x 0.10 x 2.00 x 1.00 = 3.80 m2
2.30 x 0.10 x 2.00 x 1.00 = 0.46 m2

86/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET
II. 3. PEKERJAAN PASANGAN
1 Pasangan batu belah 1pc : 4ps p x l x t x unit = vol
- Arah X 18.00 x 0.425 x 0.80 x 3.00 = 18.36 m3 43.52 m3
7.50 x 0.425 x 0.80 x 2.00 = 5.10 m3
6.00 x 0.425 x 0.80 x 1.00 = 2.04 m3
9.00 x 0.425 x 0.80 x 1.00 = 3.06 m3
- Arah Y 6.50 x 0.425 x 0.80 x 2.00 = 4.42 m3
1.50 x 0.425 x 0.80 x 17.00 = 8.67 m3
4.50 x 0.425 x 0.80 x 1.00 = 1.53 m3
1.00 x 0.425 x 0.80 x 1.00 = 0.34 m3

III PEKERJAAN MUSHOLLA


III.1. PEKERJAAN TANAH
1 Galian tanah pondasi
p x l x t x unit = vol
- Pondasi Footplat
- Footplat F1 1.40 x 1.40 x 2.45 x 12.00 = 57.62 m3 289.89 m3
- Footplat F2 1.00 x 1.00 x 1.87 x 10.00 = 18.70 m3
- Pondasi Pasangan Batu Belah
- Arah X 8.25 x 1.31 x 1.52 x 1.00 = 16.43 m3
1.50 x 1.31 x 1.52 x 2.00 = 5.97 m3
3.00 x 1.31 x 1.52 x 2.00 = 11.95 m3
6.00 x 1.31 x 1.52 x 1.00 = 11.95 m3
15.00 x 1.31 x 1.52 x 2.00 = 59.74 m3
- Arah Y 6.00 x 1.31 x 1.52 x 3.00 = 35.84 m3
15.00 x 1.31 x 1.52 x 2.00 = 59.74 m3
3.00 x 1.31 x 1.52 x 2.00 = 11.95 m3

2 Urugan Tanah Kembali


p x l x t x unit = vol
- Galian Tanah Pondasi = 289.89 m3 271.63 m3
Dikurangi :
- Urugan Pasir = -13.10 m3
- Lantai Kerja = -1.18 m3
- Pondasi Footplat = -3.98 m3
- Pondasi Aanstamping
- Pondasi Pasangan Batu Belah = m3
- Sloof 15x25 = m3

3 Urugan Pasir di Bawah Pondasi


p x l x t x unit = vol
- Pondasi Footplat
- Footplat F1 1.20 x 1.20 x 0.10 x 12.00 = 1.73 m3 13.10 m3
- Footplat F2 0.80 x 0.80 x 0.10 x 10.00 = 0.64 m3
- Pondasi Pasangan Batu Belah
- Arah X 8.25 x 1.00 x 0.10 x 1.00 = 0.83 m3
1.50 x 1.00 x 0.10 x 2.00 = 0.30 m3
3.00 x 1.00 x 0.10 x 2.00 = 0.60 m3
6.00 x 1.00 x 0.10 x 1.00 = 0.60 m3
15.00 x 1.00 x 0.10 x 2.00 = 3.00 m3
- Arah Y 6.00 x 1.00 x 0.10 x 3.00 = 1.80 m3
15.00 x 1.00 x 0.10 x 2.00 = 3.00 m3
3.00 x 1.00 x 0.10 x 2.00 = 0.60 m3

4 Urugan Pasir di Bawah Lantai


luas x l x t x unit = vol
506.57 x 0.10 x 1.00 = 50.66 m3 50.66 m3

5 Urugan Tanah Peninggian Bangunan


p x l x t x unit = vol
15.00 x 15.00 x 1.30 x 1.00 = 292.50 m3 304.20 m3
3.00 x 3.00 x 1.30 x 1.00 = 11.70 m3

6 Terucuk Bambu 3" p x l x t x unit = vol


- Footplat F1 2.00 x 108.00 = 216.00 m' 396.00 m'
- Footplat F2 2.00 x 90.00 = 180.00 m'

III. 2. PEKERJAAN BETON


1 Beton Lantai Kerja
p x l x t x unit = vol
- Footplat F1 1.20 x 1.20 x 0.05 x 12.00 = 0.86 m3 1.18 m3
- Footplat F2 0.80 x 0.80 x 0.05 x 10.00 = 0.32 m3

87/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET
2 Rabat Beton tebal 5 cm
luas x l x t x unit = vol
506.57 x 0.05 x 1.00 = 25.33 m3 25.33 m3

88/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET
3 Beton Pondasi Footplat F1 120x120 cm
- Beton K-250 p x l x t x unit = vol
1.20 x 1.20 x 0.15 x 12.00 = 2.59 m3 3.98 m3
0.77 x 0.15 x 12.00 = 1.39 m3

- Pembesian p x besi x bh x unit = vol


D10-20 1.35 x 0.617 x 14.00 x 12.00 = 139.94 kg 511.32 kg
16-20 1.40 x 1.579 x 14.00 x 12.00 = 371.38 kg

- Bekisting p x l x sisi x unit = vol


1.20 x 0.15 x 4.00 x 12.00 = 8.64 m2 25.56 m2
0.75 x 0.47 x 4.00 x 12.00 = 16.92 m2

4 Beton Pondasi Footplat F2 80x80 cm


- Beton K-250 p x l x t x unit = vol
0.80 x 0.80 x 0.15 x 10.00 = 0.96 m3 1.47 m3
0.34 x 0.15 x 10.00 = 0.51 m3

- Pembesian p x besi x bh x unit = vol


D10-200 0.95 x 0.617 x 10.00 x 10.00 = 58.62 kg 222.84 kg
16-200 1.03 x 1.579 x 5.00 x 10.00 = 81.32 kg
1.05 x 1.579 x 5.00 x 10.00 = 82.90 kg

- Bekisting p x l x sisi x unit = vol


0.80 x 0.15 x 4.00 x 10.00 = 4.80 m2 11.28 m2
0.48 x 0.30 x 2.00 x 10.00 = 2.88 m2
0.53 x 0.34 x 2.00 x 10.00 = 3.60 m2

5 Beton Sloof S1 20x30 cm


- Beton K-250 p x l x t x unit = vol
15.00 x 0.20 x 0.30 x 8.00 = 7.20 m3 7.20 m3

- Pembesian p x besi x bh x unit = vol


612 16.08 x 0.888 x 6.00 x 8.00 = 685.39 kg 1,134.07 kg
10-150 0.90 x 0.617 x 101.0 x 8.00 = 448.68 kg

- Bekisting p x l x sisi x unit = vol


15.00 x 0.30 x 2.00 x 8.00 = 72.00 m2 72.00 m2

6 Beton Sloof S2 15x25 cm


- Beton K-250 p x l x t x unit = vol
8.25 x 0.15 x 0.25 x 1.00 = 0.31 m3 1.83 m3
1.50 x 0.15 x 0.25 x 3.00 = 0.17 m3
3.00 x 0.15 x 0.25 x 4.00 = 0.45 m3
6.00 x 0.15 x 0.25 x 4.00 = 0.90 m3

- Pembesian p x besi x bh x unit = vol


412 8.37 x 0.888 x 4.00 x 1.00 = 29.73 kg 323.82 kg
1.62 x 0.888 x 4.00 x 3.00 = 17.26 kg
3.12 x 0.888 x 4.00 x 4.00 = 44.33 kg
6.12 x 0.888 x 4.00 x 4.00 = 86.95 kg
10-150 0.70 x 0.617 x 56.00 x 1.00 = 24.19 kg
0.70 x 0.617 x 11.00 x 3.00 = 14.25 kg
0.70 x 0.617 x 21.00 x 4.00 = 36.28 kg
0.70 x 0.617 x 41.00 x 4.00 = 70.83 kg

- Bekisting p x l x sisi x unit = vol


8.25 x 0.25 x 2.00 x 1.00 = 4.13 m2 24.38 m2
1.50 x 0.25 x 2.00 x 3.00 = 2.25 m2
3.00 x 0.25 x 2.00 x 4.00 = 6.00 m2
6.00 x 0.25 x 2.00 x 4.00 = 12.00 m2

7 Beton Kolom K1 35x35 cm


- Beton K-250 p x l x t x unit = vol
0.35 x 0.35 x 6.91 x 12.00 = 10.16 m3 10.16 m3

- Pembesian p x besi x bh x unit = vol


12D12 7.43 x 0.888 x 12.00 x 12.00 = 950.09 kg 1,308.05 kg
8-120 1.28 x 0.395 x 59.00 x 12.00 = 357.96 kg

- Bekisting p x l x sisi x unit = vol


6.91 x 0.35 x 4.00 x 12.00 = 116.09 m2 116.09 m2

89/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET
8 Beton Kolom K2 L 15x25 cm
- Beton K-250 p x l x t x unit = vol
0.15 x 0.25 x 7.09 x 2.00 = 0.53 m3 1.19 m3
0.15 x 0.10 x 7.09 x 2.00 = 0.21 m3
0.15 x 0.25 x 2.80 x 3.00 = 0.32 m3
0.15 x 0.10 x 2.80 x 3.00 = 0.13 m3

- Pembesian p x besi x bh x unit = vol


512 7.51 x 0.888 x 5.00 x 2.00 = 66.69 kg 159.81 kg
2.92 x 0.888 x 5.00 x 3.00 = 38.89 kg
8-150 0.88 x 0.395 x 48.00 x 2.00 = 33.37 kg
0.88 x 0.395 x 20.00 x 3.00 = 20.86 kg

- Bekisting p x l x sisi x unit = vol


7.09 x 0.25 x 4.00 x 2.00 = 14.18 m2 22.58 m2
2.80 x 0.25 x 4.00 x 3.00 = 8.40 m2

9 Beton Kolom K3 15x25 cm


- Beton K-250 p x l x t x unit = vol
0.15 x 0.25 x 5.51 x 3.00 = 0.62 m3 1.04 m3
0.15 x 0.25 x 2.80 x 4.00 = 0.42 m3

- Pembesian p x besi x bh x unit = vol


412 5.63 x 0.888 x 4.00 x 3.00 = 59.99 kg 185.27 kg
2.92 x 0.888 x 4.00 x 4.00 = 41.49 kg
10-150 0.70 x 0.617 x 38.00 x 3.00 = 49.24 kg
0.70 x 0.617 x 20.00 x 4.00 = 34.55 kg

- Bekisting p x l x sisi x unit = vol


5.51 x 0.15 x 2.00 x 3.00 = 4.96 m2 22.19 m2
5.51 x 0.25 x 2.00 x 3.00 = 8.27 m2
2.80 x 0.15 x 2.00 x 4.00 = 3.36 m2
2.80 x 0.25 x 2.00 x 4.00 = 5.60 m2

10 Beton Kolom Praktis 15x15 cm


p x l x t x unit = vol
5.30 x 11.00 = 58.30 m' 86.30 m'
2.80 x 10.00 = 28.00 m'

11 Beton Balok B1 20x40 cm


- Beton K-250 p x l x t x unit = vol
15.00 x 0.20 x 0.40 x 4.00 = 4.80 m3 5.41 m3
3.80 x 0.20 x 0.40 x 2.00 = 0.61 m3

- Pembesian p x besi x bh x unit = vol


4D16 16.44 x 1.579 x 4.00 x 4.00 = 415.34 kg 1,031.15 kg
3.96 x 1.579 x 4.00 x 2.00 = 50.02 kg
4D12 16.08 x 0.888 x 4.00 x 4.00 = 228.46 kg
3.92 x 0.888 x 4.00 x 2.00 = 27.85 kg
10-150 1.10 x 0.617 x 101.0 x 4.00 = 274.19 kg
1.10 x 0.617 x 26.00 x 2.00 = 35.29 kg

- Bekisting p x l x sisi x unit = vol


15.00 x 0.20 x 1.00 x 4.00 = 12.00 m2 67.60 m2
15.00 x 0.40 x 2.00 x 4.00 = 48.00 m2
3.80 x 0.20 x 1.00 x 2.00 = 1.52 m2
3.80 x 0.40 x 2.00 x 2.00 = 6.08 m2

12 Beton Balok B2 20x40 cm - 20x30 cm


- Beton K-250 p x l x t x unit = vol
5.00 x 0.20 x 0.35 x 8.00 = 2.80 m3 4.76 m3
7.00 x 0.20 x 0.35 x 4.00 = 1.96 m3

- Pembesian p x besi x bh x unit = vol


4D16 5.16 x 1.579 x 4.00 x 8.00 = 260.72 kg 971.09 kg
7.16 x 1.579 x 4.00 x 4.00 = 180.89 kg
4D12 5.12 x 0.888 x 4.00 x 8.00 = 145.49 kg
7.12 x 0.888 x 4.00 x 4.00 = 101.16 kg
10-150 1.10 x 0.617 x 14.00 x 8.00 = 76.01 kg
0.90 x 0.617 x 21.00 x 8.00 = 93.29 kg
1.10 x 0.617 x 14.00 x 4.00 = 38.01 kg
0.90 x 0.617 x 34.00 x 4.00 = 75.52 kg

90/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET

- Bekisting p x l x sisi x unit = vol


5.00 x 0.20 x 1.00 x 8.00 = 8.00 m2 62.40 m2
7.00 x 0.20 x 1.00 x 4.00 = 5.60 m2
2.00 x 0.40 x 2.00 x 8.00 = 12.80 m2
3.00 x 0.40 x 2.00 x 8.00 = 19.20 m2
2.00 x 0.30 x 2.00 x 4.00 = 4.80 m2
5.00 x 0.30 x 2.00 x 4.00 = 12.00 m2

13 Beton Balok B3 20x30 cm


- Beton K-250 p x l x t x unit = vol
22.82 x 0.20 x 0.30 x 1.00 = 1.37 m3 1.37 m3

- Pembesian p x besi x bh x unit = vol


6D12 23.90 x 0.888 x 6.00 x 1.00 = 127.34 kg 212.30 kg
10-150 0.90 x 0.617 x 153.0 x 1.00 = 84.96 kg

- Bekisting p x l x sisi x unit = vol


22.82 x 0.20 x 1.00 x 1.00 = 4.56 m2 18.25 m2
22.82 x 0.30 x 2.00 x 1.00 = 13.69 m2

14 Beton Balok B4 20x25 cm


- Beton K-250 p x l x t x unit = vol
3.70 x 0.20 x 0.25 x 4.00 = 0.74 m3 0.74 m3

- Pembesian p x besi x bh x unit = vol


5D12 3.82 x 0.888 x 5.00 x 4.00 = 67.84 kg 119.17 kg
10-150 0.80 x 0.617 x 26.00 x 4.00 = 51.33 kg

- Bekisting p x l x sisi x unit = vol


3.70 x 0.20 x 1.00 x 4.00 = 2.96 m2 10.36 m2
3.70 x 0.25 x 2.00 x 4.00 = 7.40 m2

15 Beton Balok B5 15x20 cm


- Beton K-250 p x l x t x unit = vol
6.00 x 0.15 x 0.20 x 5.00 = 0.90 m3 1.64 m3
3.00 x 0.15 x 0.20 x 6.00 = 0.54 m3
1.50 x 0.15 x 0.20 x 2.00 = 0.09 m3
3.50 x 0.15 x 0.20 x 1.00 = 0.11 m3

- Pembesian p x besi x bh x unit = vol


212 6.12 x 0.888 x 2.00 x 5.00 = 54.35 kg 342.62 kg
3.12 x 0.888 x 2.00 x 6.00 = 33.25 kg
1.62 x 0.888 x 2.00 x 2.00 = 5.75 kg
3.62 x 0.888 x 2.00 x 1.00 = 6.43 kg
2D13 6.13 x 1.042 x 2.00 x 5.00 = 63.87 kg
3.13 x 1.042 x 2.00 x 6.00 = 39.14 kg
1.63 x 1.042 x 2.00 x 2.00 = 6.79 kg
3.63 x 1.042 x 2.00 x 1.00 = 7.56 kg
10-100 0.60 x 0.617 x 31.00 x 5.00 = 57.38 kg
0.60 x 0.617 x 16.00 x 6.00 = 35.54 kg
0.60 x 0.617 x 9.00 x 2.00 = 6.66 kg
0.60 x 0.617 x 19.00 x 1.00 = 7.03 kg
10-150 0.60 x 0.617 x 21.00 x 1.00 = 7.77 kg
0.60 x 0.617 x 11.00 x 1.00 = 4.07 kg
0.60 x 0.617 x 6.00 x 1.00 = 2.22 kg
0.60 x 0.617 x 13.00 x 1.00 = 4.81 kg

- Bekisting p x l x sisi x unit = vol


6.00 x 0.15 x 1.00 x 5.00 = 4.50 m2 29.98 m2
3.00 x 0.15 x 1.00 x 6.00 = 2.70 m2
1.50 x 0.15 x 1.00 x 2.00 = 0.45 m2
3.50 x 0.15 x 1.00 x 1.00 = 0.53 m2
6.00 x 0.20 x 2.00 x 5.00 = 12.00 m2
3.00 x 0.20 x 2.00 x 6.00 = 7.20 m2
1.50 x 0.20 x 2.00 x 2.00 = 1.20 m2
3.50 x 0.20 x 2.00 x 1.00 = 1.40 m2

16 Beton Plat Atap Tebal 10 cm


- Beton K-250 p x l x t x unit = vol
10.30 x 3.75 x 0.10 x 2.00 = 7.73 m3 32.23 m3
6.00 x 6.00 x 0.10 x 1.00 = 3.60 m3
3.00 x 3.00 x 0.10 x 1.00 = 0.90 m3
5.00 x 5.00 x 0.10 x 8.00 = 20.00 m3

91/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET

92/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET
- Pembesian p x besi x bh x unit = vol
10-150 10.40 x 0.617 x 26.00 x 2.00 = 333.67 kg 2,766.99 kg
3.85 x 0.617 x 70.00 x 2.00 = 332.56 kg
6.10 x 0.617 x 41.00 x 1.00 = 154.31 kg
6.10 x 0.617 x 41.00 x 1.00 = 154.31 kg
3.10 x 0.617 x 21.00 x 1.00 = 40.17 kg
3.10 x 0.617 x 21.00 x 1.00 = 40.17 kg
5.10 x 0.617 x 34.00 x 8.00 = 855.90 kg
5.10 x 0.617 x 34.00 x 8.00 = 855.90 kg

- Bekisting p x l x sisi x unit = vol


10.30 x 3.75 x 1.00 x 2.00 = 77.25 m2 327.87 m2
10.30 x 0.10 x 2.00 x 2.00 = 4.12 m2
3.75 x 0.10 x 2.00 x 2.00 = 1.50 m2
6.00 x 6.00 x 1.00 x 1.00 = 36.00 m2
3.00 x 3.00 x 1.00 x 1.00 = 9.00 m2
5.00 x 5.00 x 1.00 x 8.00 = 200.00 m2

III. 3. PEKERJAAN PASANGAN


1 Pasangan Batu Kosong / Aanstamping
p x l x t x unit = vol
8.25 x 1.00 x 0.20 x 1.00 = 1.65 m3 21.75 m3
1.50 x 1.00 x 0.20 x 3.00 = 0.90 m3
3.00 x 1.00 x 0.20 x 4.00 = 2.40 m3
6.00 x 1.00 x 0.20 x 4.00 = 4.80 m3
15.00 x 1.00 x 0.20 x 4.00 = 12.00 m3

2 Pasangan Batu Belah 1pc : 4ps


p x l x t x unit = vol
8.25 x 0.55 x 0.80 x 1.00 = 3.63 m3 47.85 m3
1.50 x 0.55 x 0.80 x 3.00 = 1.98 m3
3.00 x 0.55 x 0.80 x 4.00 = 5.28 m3
6.00 x 0.55 x 0.80 x 4.00 = 10.56 m3
15.00 x 0.55 x 0.80 x 4.00 = 26.40 m3

14 Rollag Bata
p x l x t x unit = vol
3.80 x 0.15 x 0.25 x 4.00 = 0.57 m3 3.50 m3
3.80 x 0.15 x 0.20 x 4.00 = 0.46 m3
3.80 x 0.15 x 0.20 x 4.00 = 0.46 m3
10.30 x 0.15 x 0.25 x 2.00 = 0.77 m3
10.30 x 0.15 x 0.20 x 2.00 = 0.62 m3
10.30 x 0.15 x 0.20 x 2.00 = 0.62 m3

IV PEKERJAAN KAWASAN
1 Urugan Tanah Peninggian
(t1 + t2) / 2 = vol
- Tinggi P0 1.13 + 1.34 / 2.00 = 1.24 m'
- Tinggi P1 0.95 + 1.10 / 2.00 = 1.03 m'
- Tinggi P4 0.77 + 0.94 / 2.00 = 0.86 m'
(t1 + t2 + t3) / 3 = vol
- Tinggi Rata-rata 1.24 + 1.03 + 0.86 / 3.00 = 1.04 m'

luas x l x t x unit = vol


32,000 x 1.04 x 1.00 = 33,280.00 m3 33,280.00 m3

2 Saluran MD 100

Saluran Batu Kali p x Luas


1109.02 x 1.04 = 1153.38 m3

Pasir Urug p x L x T
1109.02 x 1.60 x 0.10 = 177.44 m3

Beton Lantai Kerja p x L x T


1109.02 x 1.60 x 0.05 = 88.72 m3

Plester p x L x T
1109.02 x 3.00 = 3327.06 m2

AciAn = 6654.12 m2

Plat Beton p x L x T

93/451
NO PEKERJAAN PERHITUNGAN VOLUME VOLUME KET
1109.02 x 1.20 x 0.10 = 133.08 m3

Pembesian p n kg
809.02 x 16.00 x 0.40 = 5177.73 kg

3 Saluran MD 50

Saluran Batu Kali p x Luas


161.70 x 0.26 = 42.04 m3

Pasir Urug p x L x T
161.70 x 0.80 x 0.10 = 12.94 m3

Beton Lantai Kerja p x L x T


161.70 x 0.80 x 0.05 = 6.47 m3

Plester p x L x T
161.70 x 1.50 = 242.55 m2

AciAn = 485.10 m2

Galian Tanah Irigasi p x L x T


406.60 x 0.80 x 0.50 = 162.64 m3

Plat Beton p x L x T
161.70 x 0.70 x 0.10 = 11.32 m3

Pembesian p n kg
161.70 x 14.00 x 0.62 = 1403.56 kg

5 Pengaspalan
Volume Area tebal BJ
Penghamparan Aspal 3385.00 x 0.04 x 2.30 = 311.42 m3

LPA Volume Area x Tebal


3385.00 x 0.25 = 846.25 m3
LPB Volume Area x Tebal
3385.00 x 0.2 = 677.00 m3

Lapis Perekat Teak coat Volume Area x Koefisien Liter


3385.00 x 0.3 = 1015.50 LTR
Primecoat 3385.00 X 0.8 = 2708.00 LTR

5 Paving
Luas Area
Pasang Paving 13123.00
Pasir Bawah Paving 13123.00 x 0.10 = 1312.30 m3

Kansteen Panjang
1055.40
m1

5 Pagar Panel

Pagar Panel Panjang


659.02 m1

94/451
REKAPITULASI
RENCANA ANGGARAN BIAYA
KEGIATAN : PENYUSUNAN DED PEMBANGUNAN KAWASAN EXIT TOL
PEKERJAAN : DED PEMBANGUNAN KAWASAN EXIT TOL
LOKASI : KECAMATAN BOJONG, KABUPATEN PEKALONGAN
TAHUN ANGGARAN : 2017

JUMLAH
NO URAIAN PEKERJAAN
HARGA SATUAN (Rp)

I PEKERJAAN PERSIAPAN 50,000,000.00

II PEKERJAAN LAVATORY PUBLIK (2 UNIT) 573,778,217.59


II.1 PEKERJAAN TANAH 44,666,285.31
II.2 PEKERJAAN BETON 159,741,479.46
II.3 PEKERJAAN PASANGAN 106,910,158.41
II.4 PEKERJAAN KUSEN, PINTU & JENDELA 12,130,884.31
II.5 PEKERJAAN PLAFOND 13,433,993.75
II.6 PEKERJAAN PENUTUP LANTAI 37,958,857.62
II.7 PEKERJAAN CAT-CATAN 6,516,520.63
II.8 PEKERJAAN ATAP 76,400,451.52
II.9 PEKERJAAN ELEKTRIKAL 10,450,000.00
II.10 PEKERJAAN PLUMBING & SANITAIR 89,314,416.18
II.11 PEKERJAAN LAIN-LAIN 16,255,170.40

III PEKERJAAN MUSHOLLA


III.1 PEKERJAAN TANAH 77,698,255.45
III.2 PEKERJAAN BETON 388,685,925.45
III.3 PEKERJAAN PASANGAN 129,887,372.00
III.4 PEKERJAAN KUSEN, PINTU & JENDELA 13,540,852.80
III.5 PEKERJAAN PLAFOND 57,284,144.45
III.6 PEKERJAAN PENUTUP LANTAI 85,392,345.65
III.7 PEKERJAAN CAT-CATAN 10,288,661.62
III.8 PEKERJAAN ATAP 317,661,400.00
III.9 PEKERJAAN ELEKTRIKAL 13,144,000.00
III.10 PEKERJAAN PLUMBING & SANITAIR 40,229,736.87
III.11 PEKERJAAN LAIN-LAIN 30,127,020.58

IV PEKERJAAN KAWASAN

V BANGUNAN UTAMA

1 Pondasi 30,865,242.15
2 PEKERJAAN SLOOF 356,579,979.80
3 PEKERJAAN KOLOM 720,950,297.34
4 PEKERJAAN BALOK 476,098,852.94
5 PEKERJAAN PLAT ATAP 158,828,534.37
6 PEKERJAAN TANAH DAN PONDASI 576,164,125.22
7 PEKERJAAN PASANGAN DAN PLESTERAN 569,270,334.36
8 PEKERJAAN PENUTUP LANTAI DAN DINDING 1,183,539,538.10
9 PEKERJAAN KUSEN DAN PINTU JENDELA 376,209,320.03
10 PEKERJAAN PLAFOND 597,618,227.53
11 PEKERJAAN PENGECATAN 167,380,530.74
12 PEKERJAAN SANITAIR 51,523,313.15
13 PEKERJAAN KONSTRUKSI BAJA 89,421,376.27
14 INSTALASI AIR BERSIH 119,160,000.00
15 INSTALASI AIR KOTOR DAN AIR BEKAS 200,332,955.51
16 PEKERJAAN TAMBAH DAYA 33 KVA 62,900,000.00
17 PEKERJAAN TRAFO 87,500,000.00
18 PEKERJAAN PANEL TEGANGAN MENENGAH 215,300,000.00
19 PEKERJAAN PANEL TEGANGAN RENDAH 270,000,000.00
20 PEKERJAAN KABEL FEEDER 486,505,000.00
21 PEKERJAAN INSTALASI LISTRIK 331,599,000.00
22 PEKERJAAAN PENANGKAL PETIR 34,250,000.00
23 PEKERJAAN FIRE ALARM 150,000,000.00
24 PEKERJAAN TELEPON 89,896,000.00
25 PEKERJAAN CCTV 78,000,000.00
26 PEKERJAAN MATV 21,545,000.00
27 PEKERJAAN AC 235,731,500.00
28 PEKERJAAN PENERANGAN KAWASAN 679,656,000.00

V PEKERJAAN RUMAH POWER HOUSE & GROUND WATER TANK

I PEKERJAAN TANAH 25,115,280.78


II PEKERJAAN BETON BERTULANG 336,884,267.86
III PEKERJAAN PASANGAN 103,043,316.11
IV PEKERJAAN KUSEN PINTU & JENDELA 18,800,000.00
V PEKERJAAN PLAFOND 17,612,000.00
VI PEKERJAAN PENGECATAN 17,890,066.63
VII PEKERJAAN MEKANIKAL ELEKTRIKAL 30,170,376.77
VIII PEKERJAAN LAIN-LAIN 16,671,675.00

VI PEKERJAAN TOWER AIR


VI PEKERJAAN SUMUR DALAM
VII PEKERJAAN SCLUPTURE

Jumlah Total I
PPN 10%
Jumlah Total II
Dibulatkan

Terbilang : Dua Puluh Sembilan Milyar Lima Ratus Empat Ribu Rupiah
Terbilang : Dua Puluh Sembilan Milyar Lima Ratus Empat Ribu Rupiah

Kab. Pekalongan , 2
PEJABAT PEMBUAT KOMITMEN PT. DIENG AGUNG

Zaenuri,ST.MT Nanang Indriyanto, ST


NIP. 19721027 200604 1 010 Direktur

Plt. KEPALA DINAS PEKERJAAN UMUM KEPALA BIDANG TATA RUANG


DAN PENATAAN RUANG DPU TARU KABUPATEN PEKALONGA
KABUPATEN PEKALONGAN

Wahyu Kuncoro, ST.MT Sri Lestari, S.IP.


NIP. 19700418 199703 1 004 NIP. 19740511 199803 2 007
REKAPITULASI
NCANA ANGGARAN BIAYA

TOTAL
HARGA SATUAN (Rp)

50,000,000.00

1,147,556,435.18

1,163,939,714.87

10,093,157,331.48

8,416,825,127.51
566,186,983.15

265,093,729.33
217,287,060.00
417,138,969.00

22,337,185,350.52
2,233,718,535.05
24,570,903,885.57
24,570,903,000.00

atus Empat Ribu Rupiah


atus Empat Ribu Rupiah

Kab. Pekalongan , 2017


PT. DIENG AGUNG

Nanang Indriyanto, ST
Direktur

KEPALA BIDANG TATA RUANG


DPU TARU KABUPATEN PEKALONGAN

Sri Lestari, S.IP.


NIP. 19740511 199803 2 007
BACK UP PERHIT
KEGIATAN : PENYUSUNAN DED PEMBANGUNAN KAWASAN EXIT TOLL
PEKERJAAN : DED PEMBANGUNAN KAWASAN EXIT TOLL
LOKASI : KAB. PEKALONGAN
TAHUN ANGGARAN : 2017

NO PEKERJAAN

PEKERJAAN STRUKTUR

1 Tiang pancang Mini pile 32 x 32 x32 (K450) P2

P3

2 Pecah kepala tiang pancang minipile p2

P3

3 Lantai kerja bwh pile cap t= 5 cm p2

P3

4 Beton Bertulang Pile cap type P2


Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 Readymix

5 Beton Bertulang Pile cap type P3


Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 Readymix

6 Sloof S1 30/40
x 381.36
y 214

7 Sloof S1 20/30
x 208
y 170

8 Sloof S 15/20
x 146.5
y 79.5

8 Kolom K1 60/60
9 Kolom K2 50/50

10 Kolom Ka 35/35

11 Kolom Kb 30/40

12 Kolom KP 15/15

13 Balok B1 30/60
x 42
y 52

14 Balok B2 30/40
x 10.88
y 8

15 Balok Ba 45/20
x 24
y 24

16 Balok Bb 40/20
x 4
y 3

17 Balok R1 30/50
x 132
y 160

18 Balok R2 25/40
x 48
Lingkaran 56.52
Lingkaran 18.84

19 Pekerjaan Water Profing Plat Atap


1
2

PEKERJAAN ARSITEKTUR

20 Galian tanah biasa sedalam 1 m


Utama 339.7
x 139
y 79.5

21 Pondasi batu belah campuran 1SP : 4PP


Utama 339.7
x 139
y 79.5
Rolag 460.84

22 Urugan kembali bekas galian tanah


Utama 339.7
x 139
y 79.5

23 Pasir urug bawah Pondasi


Utama 339.7
x 139
y 79.5

Rolag 460.84

24 Urugan tanah peninggian peil lantai

25 Dinding bata merah tebal batu campuran 1SP : 4PP

x 364.28
y 297.6

Penambahan Tinggi Atap 68

Gunungan 1
2
Kurang i

Rolag
LUBANG KUSEN

PJ1
PJ2
P1
P2
P3
PL
PJ3
J1
J2
J3
J4
J5
JA
B1
B2
FG

Lubang Dinding

26 Plesteran 1SP : 4PP tebal 15 mm

27 Plesteran skoning Sudut

28 Urugan pasir bwh keramik t=5 cm

29 Lantai kerja bwh keramik t= 5 cm

30 Pas. Lantai Homogenous tile 60 x 60 cm polish


1811

31 Pas. Lantai Homogenous tile 60 x 60 cm unpolish


1112

32 Lantai keramik 20x20 cm Unpolish


36
36

33 Lantai Rabat Beton K-175 tebal 5 cm


4
40
145.5

34 Dinding keramik 20x25 cm


KM1 7.9
Km2 X 26
Km2 Y 24.25
Km3 X 13.8
Km3 Y 15
KM4 x 12.7
KM4 y 15

36 Tali Air
KM1 7.9
Km2 X 26
Km2 Y 24.25
Km3 X 13.8
Km3 Y 15
KM4 x 12.7
KM4 y 15

37 Rabat Beton K-100


1 111.13
2 70.15
3 199

38 Pas. Gypsum Board Tb. 9mm + Rangka hollow 4/4 dan 2/2

39 Pas. Calsi Board Tb.4,5 mm + Rangka hollow 4/4 dan 2/2

40 Pas. Plafond Spandex Galvalum + Rangka hollow 4/4 dan 2/2

41 List plafond gypsum 10 cm


607.42
556.8
64.8
242

42 Drop ceiling 363

43 Pekerjaan Pintu Type FG


44 Angin Angin Atas FG

45 Pekerjaan Partisi Type PT

46 Balok Lateu Atas Kusen

PJ1 6
PJ2 16
P1 1.6
P2 0.86
P3 0.88
PL 0.75
PJ3 3.5
J1 4.55
J2 2.2
J3 3.48
J4 6.09
J5 1.72
JA 0.65
B1 0.8
B2 1.57
FG 3
46 Tangga Besi WF 200x100

47 Plat tebal 10 mm

48 Rangka Hollow 40x40

49 Papan 2/20
anak tangga
bordes

50 Realing Tangga Stainless steel

51 Saluran buis beton U20 cm


- Pasir urug tebal 5 cm

- Pas. Batu bata 1pc : 3ps

- Buis Beton u20


BACK UP PERHITUNGAN VOLUME REST AREA
UNAN KAWASAN EXIT TOLL
N EXIT TOLL

PERHITUNGAN VOLUME

p x N x t x Unit = Vol
12.00 x 2.00 x 74.00 = 1776.00

p x N x t x Unit = Vol
12.00 x 3.00 x 40.00 = 1440.00

p x N x t x Unit = Vol
x 2.00 x 74.00 = 148.00

p x N x t x Unit = Vol
x 3.00 x 40.00 = 120.00

p x l x t x Unit = Vol
1.00 x 1.00 0.05 x 10.00 = 0.50

Area x N x t x Unit = Vol


2.85 x 0.05 x 40.00 = 5.70

p x l x t x Unit = Vol
2.00 x 1.00 0.60 x 74.00 = 88.80

Area x l x t x Unit = Vol


2.85 x 0.60 x 40.00 = 68.40

p x l x t x Unit = Vol
595.36 x 0.30 0.40 x 1.00 = 71.44

p x l x t x Unit = Vol
378.00 x 0.20 0.30 x 1.00 = 22.68

p x l x t x Unit = Vol
226.00 x 0.15 0.20 x 1.00 = 6.78

p x l x t x Unit = Vol
4.60 x 0.60 0.60 x 42.00 = 69.55

p x l x t x Unit = Vol
5.85 x 0.60 0.60 x 8.00 = 16.85
p x l x t x Unit = Vol
4.60 x 0.50 0.50 x 17.00 = 19.55

p x l x t x Unit = Vol
1.50 x 0.35 0.35 x 35.00 = 6.43

p x l x t x Unit = Vol
1.50 x 0.30 0.40 x 12.00 = 2.16

p x l x t x Unit = Vol
3.65 x 0.15 0.15 x 136.00 = 11.17

p x l x t x Unit = Vol
94.00 x 0.30 0.60 x 1.00 = 16.92

p x l x t x Unit = Vol
18.88 x 0.30 0.40 x 1.00 = 2.27

p x l x t x Unit = Vol
48.00 x 0.45 0.20 x 1.00 = 4.32

p x l x t x Unit = Vol
7.00 x 0.40 0.20 x 1.00 = 0.56

p x l x t x Unit = Vol
292.00 x 0.30 0.50 x 1.00 = 43.80

p x l x t x Unit = Vol
123.36 x 0.25 0.40 x 1.00 = 12.34

Area x l x t x Unit = Vol


228.00 x 1.00 = 228.00
36.00 x 2.00 = 36.00

p x l x t x Unit = Vol
558.20 x 0.80 1.25 x 1.00 = 558.20

p x Area x x Unit = Vol


558.20 x 0.84 x 1.00 = 468.89
p x Area x x Unit = Vol
460.84 x 0.11 x 1.00 = 50.69

p x Area x x Unit = Vol


558.20 x 0.30 x 1.00 = 167.46

p x l x t x Unit = Vol
558.20 x 0.80 x 0.05 x 1.00 = 22.33

p x l x t x Unit = Vol
460.84 x 0.30 x 0.05 x 1.00 = 6.91

p x Area x t x Unit = Vol


x 3000 0.30 x 1.00 = 900.00

p x l x t x Unit = Vol
661.88 x x 3.65 x 1.00 = 2415.86

p x l x t x Unit = Vol
68.00 x x 1.25 x 1.00 = 85.00

p x l : 2.00 x Unit = Vol


16.00 x 6.25 x 2.00 x 2.00 = 100.00
16.00 x 8.66 x 2.00 x 2.00 = 138.56
16.00 x 5.00 x 2.00 x 2.00 = 80.00

10.00 x x 0.30 x 4.00 = 12.00


p x l x t x Unit = Vol
2.60 x 5.40 x x 1.00 = 14.04
2.60 x 15.30 x x 1.00 = 39.78
2.30 x 2.10 x x 1.00 = 4.83
2.78 x 0.86 x x 3.00 = 7.17
2.78 x 0.86 x x 1.00 = 2.39
2.10 x 0.78 x x 12.00 = 19.66
3.52 x 3.00 x x 4.00 = 42.24
1.82 x 7.00 x x 7.00 = 89.18
2.20 x 2.80 x x 1.00 = 6.16
2.44 x 4.00 x x 1.00 = 9.76
2.44 x 7.00 x x 4.00 = 68.32
1.72 x 1.78 x x 5.00 = 15.31
0.88 x 0.65 x x 28.00 = 16.02
0.68 x 0.80 x x 13.00 = 7.07
1.56 x 0.68 x x 6.00 = 6.36
2.62 x 2.40 x x 32.00 = 201.22

36.00 x x 2.65 x 1.00 = 95.40

p x l x t x Unit = Vol
121.00 x x 4.15 x 1.00 = 502.15

p x Area x t x Unit = Vol


x 3000 0.05 x 1.00 = 150.00

p x Area x t x Unit = Vol


x 3000 0.05 x 1.00 = 150.00

p x Area x t x Unit = Vol


x 1811 x 1.00 = 1811.00

p x Area x t x Unit = Vol


x 1112 x 1.00 = 1112.00

p x Area x t x Unit = Vol


x 72 x 1.00 = 72.00

p x Area x t x Unit = Vol


x 190 0.05 x 1.00 = 9.50

p x l x t x Unit = Vol
114.65 x 1.50 x 1.00 = 171.98

p x l x t x Unit = Vol
114.65 x x 1.00 = 114.65

Area x l x t x Unit = Vol


380.28 x 0.05 x 1.00 = 19.01

Area x l x t x Unit = Vol


1981.60 x x 1.00 = 1981.60

Area x l x t x Unit = Vol


224.50 x x 1.00 = 224.50

Area x l x t x Unit = Vol


876.40 x x 1.00 = 876.40

p x l x t x Unit = Vol
1471.02 x x 1.00 = 1471.02

p x l x t x Unit = Vol
363.00 x x 1.00 = 363.00

p x l x t x Unit = Vol
2.62 x 2.40 x 32.00 = 201.22
n x l x t x Unit = Vol
3.00 x x 32.00 = 96.00

p x l x t x Unit = Vol
4.00 x 3.00 x 3.00 = 36.00

p x l x t x Unit = Vol

6.00 x 0.15 x 0.20 x 1.00 = 0.18


16.00 x 0.15 x 0.20 x 1.00 = 0.48
1.60 x 0.15 x 0.20 x 1.00 = 0.05
0.86 x 0.15 x 0.20 x 3.00 = 0.08
0.88 x 0.15 x 0.20 x 1.00 = 0.03
0.75 x 0.15 x 0.20 x 12.00 = 0.27
3.50 x 0.15 x 0.20 x 4.00 = 0.42
4.55 x 0.15 x 0.20 x 7.00 = 0.96
2.20 x 0.15 x 0.20 x 1.00 = 0.07
3.48 x 0.15 x 0.20 x 1.00 = 0.10
6.09 x 0.15 x 0.20 x 4.00 = 0.73
1.72 x 0.15 x 0.20 x 5.00 = 0.26
0.65 x 0.15 x 0.20 x 28.00 = 0.55
0.80 x 0.15 x 0.20 x 13.00 = 0.31
1.57 x 0.15 x 0.20 x 6.00 = 0.28
3.00 x 0.15 x 0.20 x 32.00 = 2.88
p x kg x t x Unit = Vol
12.50 x 25.95 x x 1.00 = 324.38

area x kg x n x Unit = Vol


0.09 x 75.00 x 21.00 x 1.00 = 141.75

area x x t x Unit = Vol


8.21 x x x 1.00 = 8.21

p x l x n x Unit = Vol
1.00 x 0.35 x 20.00 x 1.00 = 7.00
1.00 x 2.20 x 1.00 x 1.00 = 2.20

p x l x n x Unit = Vol
12.00 x 1.00 = 12.00

p x l x t x Unit = Vol
345.00 x 0.50 0.05 1.00 = 8.63

p x l x t x Unit = Vol
345.00 x 0.15 0.40 2.00 = 41.40

p x l x t x Unit = Vol
345.00 x = 345.00
VOLUME KET

3,216.00 m1

268.00 ttk

0.50 m3

88.80 m3

68.40 m3

71.44 m3

22.68 m3

6.78 m3

86.40 m3
19.55 m3

6.43 m3

2.16 m3

11.17 m3

16.92 m3

2.27 m3

4.32 m3

0.56 m3

43.80 m3

12.34 m3

264.00 m3

558.20 m3

519.58 m3
167.46 m3

29.24 m3

900.00 m3

2,026.51 m2

158.56 m2
644.91 m2

4,053.02 m2

502.15 m1

150.00 m3

150.00 m3

1,811.00 m2

1,112.00 m2

72.00 m2
9.50 m3

171.98 m2

114.65 m1

19.01 m2

1,981.60 m2

224.50 m2

876.40 m2

1,471.02 m1

363.00 m1

201.22 m2
96.00 bh

36.00 m2

7.65 m3
324.38 kg

141.75 kg

8.21 m2

9.20 m2

12.00 m1

8.63 m3

41.40 m2

345.00 m1
BACK UP BETON REST AREA
Beton Bertulang Foot Plat
TYPE JUMLAH B H TEBAL V
P2 10.00 1.00 1.00 0.60 6.00 m3

P2
X = Bentang Terpendek
Y = Bentang Terpanjang

X Y tinggi volume
1.00 1.00 0.60 0.60 m3
BESI
diameter jarak panjang panjang
jumlah kg/m' TOTAL
tulangan tulangan tulangan total (m')
D19 0.20 11.00 2.05 22.55 2.25 50.74
D19 0.20 11.00 2.05 22.55 2.25 50.74
D19 0.20 6.00 2.05 12.30 2.25 27.68
D19 0.20 6.00 2.05 12.30 2.25 27.68
jumlah = 156.84
per m3 = 261.40
BEKISTING
kell ( 4 x 1m' tinggi
) (m') volume beton = 1.00 m3
4.00 0.60 2.40 m2 besi = 261.40 kg
per m3 = 4.00 m2/m3 bekesting = 4.00 m2

Beton Bertulang Foot Plat


TYPE JUMLAH B H TEBAL V
p3 40.00 2.00 0.62 0.60 29.76 m3
p3 40.00 1.30 1.30 0.60 40.56 m4
70.32

p3
X = Bentang Terpendek
Y = Bentang Terpanjang

X Y tinggi volume
2.00 0.62 0.60 0.74 m3
BESI
diameter jarak panjang panjang
jumlah kg/m' TOTAL
tulangan tulangan tulangan total (m')
D19 0.20 4.00 1.67 6.68 2.25 15.03
D19 0.20 4.00 1.67 6.68 2.25 15.03
D19 0.20 11.00 3.05 33.55 2.25 75.49
D19 0.20 11.00 3.05 33.55 2.25 75.49
jumlah = 181.04
per m3 = 244.65
BEKISTING
kell ( 4 x 1m' tinggi
) (m') volume beton = 1.00 m3
5.24 0.60 3.14 m2 besi = 244.65 kg
per m3 = 4.24 m2/m3 bekesting = 4.24 m2
p3
X = Bentang Terpendek
Y = Bentang Terpanjang

X Y tinggi volume
1.30 1.30 0.60 1.01 m3
BESI
diameter jarak panjang panjang
jumlah kg/m' TOTAL
tulangan tulangan tulangan total (m')
D19 0.20 6.00 2.35 14.10 2.25 31.73
D19 0.20 6.00 2.35 14.10 2.25 31.73
D19 0.20 6.00 2.35 14.10 2.25 31.73
D19 0.20 6.00 2.35 14.10 2.25 31.73
jumlah = 126.92
per m3 = 125.66
BEKISTING
kell ( 4 x 1m' tinggi
) (m') volume beton = 1.00 m3
5.20 0.60 3.12 m2 besi = 125.66 kg
per m3 = 3.09 m2/m3 bekesting = 3.09 m2

Beton Slof
TYPE L B H V
S1 595.36 0.30 0.40 71.44
S2 378.00 0.20 0.30 22.68
S 226.00 0.15 0.20 6.78
100.90 m3

S1
B H PJG volume
0.30 0.40 1.00 0.12 m3 1.00
BESI TB
diamerter jarak jumlah panjang panjang
kg/m'
tulangan tulangan (btg) tulangan total (m') kg
D16 1.00 6.00 1.00 6.00 1.56 9.36
d10 0.13 7.69 1.34 10.30 0.62 6.39

jumlah = 15.75
per m3 = 131.25

BEKISTING
kell sisi L volume
0.80 1.00 0.80 m2
per m3 = 6.67 m2/m3
beton = 1.00 m3
besi = 131.25 kg/m3
bekisting = 6.67 m2/m3
S2
B H PJG volume
0.20 0.30 1.00 0.06 m3 1.00
BESI TB
diamerter jarak jumlah panjang panjang
kg/m'
tulangan tulangan (btg) tulangan total (m') kg
D16 1.00 4.00 1.00 4.00 1.56 6.24
d10 0.13 7.69 0.94 7.23 0.62 4.48

jumlah = 10.72
per m3 = 178.67

BEKISTING
kell sisi L volume
0.60 1.00 0.60 m2
per m3 = 10.00 m2/m3

beton = 1.00 m3
besi = 178.67 kg/m3
bekisting = 10.00 m2/m3
S
B H PJG volume
0.15 0.20 1.00 0.03 m3 1.00
BESI TB
diamerter jarak jumlah panjang panjang
kg/m'
tulangan tulangan (btg) tulangan total (m') kg
d12 1.00 4.00 1.00 4.00 0.89 3.56
d8 0.15 6.67 0.64 4.27 0.393 1.68

jumlah = 5.24
per m3 = 174.67

BEKISTING
kell sisi L volume
0.40 1.00 0.40 m2
per m3 = 13.33 m2/m3

beton = 1.00 m3
besi = 174.67 kg/m3
bekisting = 13.33 m2/m3

Pekerjaan Kolom
Type Jumlah B H L V
KP1 136.00 0.15 0.15 3.65 11.17 m3
K1 42.00 0.60 0.60 4.60 69.55 m3
8.00 0.60 0.60 5.85 16.85 m3
K2 17.00 0.50 0.50 4.60 19.55 m3
Ka 35.00 0.35 0.35 1.50 6.43 m3
Kb 12.00 0.30 0.40 1.50 2.16 m3
125.71
KP1
B H PJG volume
0.15 0.15 1.00 0.02 m3 1.00
BESI TB
panjang
diamerter jarak jumlah panjang kg/m'
tulangan kg
tulangan tulangan (btg) total (m')
d12 1.00 4.00 1.00 4.00 0.887 3.55
d8 0.15 6.67 0.40 2.67 0.393 1.05
jumlah = 4.60
per m3 = 230.00

BEKISTING
kell sisi tinggi (m') volume
0.60 1.00 0.60 m2
per m3 = 30.00 m2/m3

beton = 1.00 m3
besi = 230.00 kg/m3
bekisting = 30.00 m2/m3
K1
B H PJG volume
0.60 0.60 1.00 0.36 m3 1.00
BESI TB
panjang
diamerter jarak jumlah panjang kg/m'
tulangan kg
tulangan tulangan (btg) total (m')
D25 1.00 25.00 1.00 25.00 3.98 99.50
d10 0.10 10.00 2.20 22.00 0.62 13.64

jumlah = 113.14
per m3 = 314.28

BEKISTING
kell sisi tinggi (m') volume
2.40 1.00 2.40 m2
per m3 = 6.67 m2/m3

beton = 1.00 m3
besi = 314.28 kg/m3
bekisting = 6.67 m2/m3

K2
B H PJG volume
0.50 0.50 1.00 0.25 m3 1.00
BESI TB
panjang
diamerter jarak jumlah panjang kg/m'
tulangan kg
tulangan tulangan (btg) total (m')
D25 1.00 8.00 1.00 8.00 3.98 31.84
d10 0.10 10.00 1.80 18.00 0.62 11.16

jumlah = 43.00
per m3 = 172.00

BEKISTING
kell sisi tinggi (m') volume
2.00 1.00 2.00 m2
per m3 = 8.00 m2/m3

beton = 1.00 m3
besi = 172.00 kg/m3
bekisting = 8.00 m2/m3
Ka
B H PJG volume
0.35 0.35 1.00 0.12 m3 1.00
BESI TB
panjang
diamerter jarak jumlah panjang kg/m'
tulangan kg
tulangan tulangan (btg) total (m')
D25 1.00 4.00 1.00 4.00 3.98 15.92
d10 0.10 10.00 1.20 12.00 0.62 7.44

jumlah = 23.36
per m3 = 194.67

BEKISTING
kell sisi tinggi (m') volume
1.40 1.00 1.40 m2
per m3 = 11.67 m2/m3

beton = 1.00 m3
besi = 194.67 kg/m3
bekisting = 11.67 m2/m3

Kb
B H PJG volume
0.30 0.40 1.00 0.12 m3 1.00
BESI TB
panjang
diamerter jarak jumlah panjang kg/m'
tulangan kg
tulangan tulangan (btg) total (m')
D25 1.00 6.00 1.00 6.00 3.98 23.88
d10 0.10 10.00 1.20 12.00 0.62 7.44

jumlah = 31.32
per m3 = 261.00

BEKISTING
kell sisi tinggi (m') volume
1.40 1.00 1.40 m2
per m3 = 11.67 m2/m3

beton = 1.00 m3
besi = 261.00 kg/m3
bekisting = 11.67 m2/m3

Pekerjaan Balk
Type L B H V
B1 94.00 0.30 0.60 16.92
B2 18.88 0.30 0.40 2.27
Ba 48.00 0.45 0.20 4.32
Bb 7.00 0.40 0.20 0.56
R1 292.00 0.30 0.50 43.80
R2 123.36 0.25 0.40 12.34

80.21 m3
B1
B H PJG volume
0.30 0.60 1 0.180 m3 1.00
BESI TB
panjang
dia jarak jumlah panjang kg/m' kg
tulangan
tulangan (btg) total (m')
D22 1.00 12.00 1.00 12.00 3.04 36.48
d10 0.13 7.69 1.60 12.30 0.62 7.63
44.11
245.06

BEKISTING
kell sisi pjg (m') volume
1.80 1 1.80 m2
per m3 = 10.00 m2/m3

beton = 1.00 m3
besi = 245.06 kg/m3
bekisting = 10.00 m2/m3

B2
B H PJG volume
0.30 0.40 1 0.120 m3 1.00
BESI TB
panjang
dia jarak jumlah panjang kg/m' kg
tulangan
tulangan (btg) total (m')
D22 1.00 10.00 1.00 10.00 3.04 30.40
d10 0.13 7.69 1.20 9.23 0.62 5.72
36.12
301.00

BEKISTING
kell sisi pjg (m') volume
1.40 1 1.40 m2
per m3 = 11.67 m2/m3

beton = 1.00 m3
besi = 301.00 kg/m3
bekisting = 11.67 m2/m3
Ba
B H PJG volume
0.45 0.20 1 0.090 m3 1.00
BESI TB
panjang
dia jarak jumlah panjang kg/m' kg
tulangan
tulangan (btg) total (m')
D19 1.00 11.00 1.00 11.00 2.25 24.75
d10 0.13 7.69 1.10 8.46 0.62 5.25
30.00
333.33

BEKISTING
kell sisi pjg (m') volume
1.30 1 1.30 m2
per m3 = 14.44 m2/m3

beton = 1.00 m3
besi = 333.33 kg/m3
bekisting = 14.44 m2/m3

Bb
B H PJG volume
0.40 0.20 1 0.080 m3 1.00
BESI TB
panjang
dia jarak jumlah panjang kg/m' kg
tulangan
tulangan (btg) total (m')
D16 1.00 11.00 1.00 11.00 1.56 17.16
d10 0.13 7.69 1.00 7.69 0.62 4.77
21.93
274.13

BEKISTING
kell sisi pjg (m') volume
1.20 1 1.20 m2
per m3 = 15.00 m2/m3

beton = 1.00 m3
besi = 274.13 kg/m3
bekisting = 15.00 m2/m3
R1
B H PJG volume
0.30 0.50 1 0.150 m3 1.00
BESI TB
panjang
dia jarak jumlah panjang kg/m' kg
tulangan
tulangan (btg) total (m')
D2 1.00 9.00 1.00 9.00 2.25 20.25
d10 0.13 7.69 1.40 10.77 0.62 6.68
26.93
179.53

BEKISTING
kell sisi pjg (m') volume
1.60 1 1.60 m2
per m3 = 10.67 m2/m3

beton = 1.00 m3
besi = 179.53 kg/m3
bekisting = 10.67 m2/m3

R2
B H PJG volume
0.25 0.40 1 0.100 m3 1.00
BESI TB
panjang
dia jarak jumlah panjang kg/m' kg
tulangan
tulangan (btg) total (m')
D16 1.00 8.00 1.00 8.00 1.56 12.48
d10 0.13 7.69 1.10 8.46 0.62 5.25
17.73
177.30

BEKISTING
kell sisi pjg (m') volume
1.30 1 1.30 m2
per m3 = 13.00 m2/m3

beton = 1.00 m3
besi = 177.30 kg/m3
bekisting = 13.00 m2/m3

Pekerjaan Balk
Type L B H V
Latiu 0.15 0.20 -
Talang 0.50 0.25
Latiu
B H PJG volume
0.15 0.20 1 0.030 m3 1.00
BESI TB
panjang
dia jarak jumlah panjang kg/m' kg
tulangan
tulangan (btg) total (m')
12 1.00 4.00 1.00 4.00 0.887 3.55
d10 0.15 6.67 0.50 3.34 0.62 2.07
5.62
187.33

BEKISTING
kell sisi pjg (m') volume
0.70 1 0.70 m2
per m3 = 23.33 m2/m3

beton = 1.00 m3
besi = 187.33 kg/m3
bekisting = 23.33 m2/m3

Talang
B H PJG volume
0.50 0.25 1 0.125 m3 1.00
BESI TB
panjang
dia jarak jumlah panjang kg/m' kg
tulangan
tulangan (btg) total (m')
12 1.00 4.00 1.00 4.00 0.887 3.55
d10 0.15 6.67 1.30 8.67 0.62 5.38
8.93
71.44

BEKISTING
kell sisi pjg (m') volume
1.50 1 1.50 m2
per m3 = 12.00 m2/m3

beton = 1.00 m3
besi = 71.44 kg/m3
bekisting = 12.00 m2/m3
TOTAL
kg
kg
kg
kg
kg
kg/m3

TOTAL
kg
kg
kg
kg
kg
kg/m3
TOTAL

kg
kg
kg
kg
kg
kg/m3

m3

kg
kg

kg
kg/m3
m3

kg
kg

kg
kg/m3
m3

kg
kg

kg
kg/m3

m3

kg
kg
kg
kg/m3
m3

kg
kg

kg
kg/m3

m3

kg
kg

kg
kg/m3
m3

kg
kg

kg
kg/m3

m3

kg
kg

kg
kg/m3
m3

kg
kg
kg
kg/m3

m3

kg
kg
kg
kg/m3
m3

kg
kg
kg
kg/m3

m3

kg
kg
kg
kg/m3
m3

kg
kg
kg
kg/m3

m3

kg
kg
kg
kg/m3
m3

kg
kg
kg
kg/m3

m3

kg
kg
kg
kg/m3
BACK UP BAJA REST AREA

NO JENIS PEKERJAAN VOLUME SAT POSISI / TYPE

III.2.6 PEKERJAAN PENUTUP ATAP Item Pek.


1. Kuda-Kuda Baja 1

- Kuda - Kuda Baja WF. 200.100. 5,5.8 mm (KB1) = 2916.13 kg Atap 1 IWF 200.100.5,5.8 mm

- Kuda - Kuda Baja WF. 200.100. 5,5.8 mm (KB2) = 1927.32 kg Atap 2 IWF 200.100.5,5.8 mm

- Kuda - Kuda Baja WF. 200.100. 5,5.8 mm (KB3) = 2801.43 kg Atap 3 IWF 200.100.5,5.8 mm

- Kuda - Kuda Baja WF. 200.100. 5,5.8 mm (KB4) = 2558.40 kg Atap 4 IWF 200.100.5,5.8 mm

- Kuda - Kuda Baja 2C 150.65.20.2,3 (KB5) = 748.00 kg Atap 5 2C 150.65.20.2,3 mm

- Kolom Baja WF. 250.125 = 3140.60 kg Atap 5 IWF 250.125.7,5.12,5


- Konsol Baja WF. 200.100. 5,5.8 mm (1./2) = 0.00 kg Atap 1
Atap 2
Atap 3

- Konsol Baja 2C 150.65.20.2,3 = 1986.88 kg Tritisan Atap 5


triitisan

- Plat buhul, t = 10 mm = 96.00 kg Plat buhul, t = 10 mm


Atap 1 Plat buhul, t = 10 mm
Atap 2 Plat buhul, t = 10 mm
Atap 3 Plat buhul, t = 10 mm
Atap 4 Plat buhul, t = 10 mm
Atap 5 Plat buhul, t = 10 mm

- Plat Stifner t = 10 mm = 97.50 kg Plat Stifner t = 10 mm


Atap 1 Plat Stifner t = 10 mm
Atap 2 Plat Stifner t = 10 mm
Atap 3 Plat Stifner t = 10 mm
Atap 4 Plat Stifner t = 10 mm
Atap 5 Plat Stifner t = 10 mm
Konsol Plat Stifner t = 10 mm
Kolom Base Plat t = 10 mm

- Base Plat t = 12 mm = 90.00 kg Base Plat t = 12 mm


Atap 1 Base Plat t = 12 mm
Atap 2 Base Plat t = 12 mm
Atap 3 Base Plat t = 12 mm
Atap 4 Base Plat t = 12 mm
Atap 5 Base Plat t = 12 mm
Kolom Base Plat t = 12 mm

- Angkur Baut 22 L=50 cm = 119.20 kg Angkur Baut 22 L=50 cm


Atap 1 Angkur Baut 22
Atap 2 Angkur Baut 22
Atap 3 Angkur Baut 22
Atap 4 Angkur Baut 22
Atap 5 Angkur Baut 22
Kolom Angkur Baut 19

2. Rangka Atap Baja


- Pasang Gording Canal 150.50.20.3 mm = 13530.00 kg Pasang Gording Canal 150.50.20.3 mm
Atap 1 nal 150.50.20.3 mm
Atap 2 nal 150.50.20.3 mm
Atap 3 nal 150.50.20.3 mm
Atap 4 nal 150.50.20.3 mm

- Pasang Sagrod besi 10mm = 631.88 kg Pasang Sagrod besi 10mm


Atap 1 Sagrod besi 10mm
Atap 2 Sagrod besi 10mm
Atap 3 Sagrod besi 10mm
Atap 4 Sagrod besi 10mm

- Pasang watermore = 96.00 bh Pasang watermore


- Baja siku L.60.60.6 mm ( klos gording ) = 13333.20 kg Baja siku L.60.60.6 mm ( klos gording )
Atap 1 m ( klos gording )
Atap 2 m ( klos gording )
Atap 3 m ( klos gording )
Atap 4 m ( klos gording )

4. Penutup Atap
- Penutup atap genteng keramik glazuur = 2112.83 m2 a. Atap 1 genteng
1) Panjang kemiringan
atap

- Luas atap 1 - 4 sisi


(Persegi)

b. Atap 2 genteng
1) Panjang kemiringan
atap

- Luas atap 1 - 4 sisi


(Trapesium)

c. Atap 3 genteng
1) Panjang kemiringan
atap

- Luas atap 1 - 4 sisi


(Trapesium)
d. Atap 4 onduline
1) Panjang kemiringan
atap

- Luas atap 1 - 4 sisi


(Trapesium)

e. Atap 5 skylight
1) Panjang kemiringan
atap

Luas Lingkaran

e. Tritisan Galvalume

P x

227.00 x
56.00 x

5 - Usuk dan Reng Baja Ringan = 3492.93 m2


6 - Bubungan genteng keramik glazuur = 123.00 m' Bubungan genteng keramik glazuur
7 - Penutup atap bitumen selulosa gelombang = 264.00 m2 Penutup atap bitumen selulosa ge
8 - Listplank woodplank lbr 30 cm tb. 5 mm = 624.60 m' Listplank woodplank lbr 30 cm tb.
9 - Tiang Pipa GIP diameter 4" = 5.74 m1 Tiang Pipa GIP diameter 4"
10 - Penutup Atap Galvalum = 849.75 m2 Penutup Atap Galvalum
PERHITUNGAN VOLUME
/ TYPE
P x L x T x unit =

Pnjang/Lmbr besi Brt Bsi Pjg x Brt Bsi Unit Ttl brt besi
2 3 4 = (2x3) 5 6 = (4x5)

19.54 21.32 416.59 7.00 2,916.13 kg

22.60 21.32 481.83 4.00 1,927.32 kg

14.60 21.32 311.27 9.00 2,801.43 kg

20.00 21.32 426.40 6.00 2,558.40 kg

17.00 5.50 93.50 8.00 748.00 kg

82.00 38.30 3140.60 1.00 3,140.60 kg


36.30 10.66 386.96 7.00 kg
2.60 10.66 27.72 4.00 kg
2.30 10.66 24.52 9.00 kg
- kg

14.00 5.50 77.00 1.00 77.00 kg


347.25 5.50 1909.88 1.00 1,909.88 kg
1,986.88 kg

0.08 75.00 6.00 16.00 96.00 kg


0.24 75.00 18.00 4.00 kg
0.23 75.00 17.25 9.00 kg
0.24 75.00 18.00 6.00 kg
0.02 75.00 1.50 8.00 kg
96.00 kg

0.13 75.00 9.75 10.00 97.50 kg


0.20 75.00 15.00 4.00 kg
0.13 75.00 9.75 9.00 kg
0.18 75.00 13.50 6.00 kg
0.15 75.00 11.25 8.00 kg
0.01 75.00 0.75 7.00 kg
0.10 75.00 7.50 1.00 kg
97.50 kg

0.09 100.00 9.00 10.00 90.00 kg


1.44 100.00 144.00 4.00 kg
1.44 100.00 144.00 9.00 kg
0.48 100.00 48.00 6.00 kg
0.16 100.00 16.00 8.00 kg
0.25 100.00 25.00 1.00 kg
90.00 kg

4.00 2.98 11.92 10.00 119.20 kg


8.00 2.98 23.84 4.00 kg
8.00 2.98 23.84 9.00 kg
8.00 2.98 23.84 6.00 kg
3.20 2.98 9.54 8.00 kg
2.40 2.23 5.35 1.00 kg
` 119.20 kg

al 150.50.20.3 mm
924.00 5.50 5082.00 1.00 5,082.00 kg
432.00 5.50 2376.00 1.00 2,376.00 kg
816.00 5.50 4488.00 1.00 4,488.00 kg
144.00 5.50 792.00 2.00 1,584.00 kg
13,530.00 kg

39.08 0.62 24.23 10.00 242.30 kg


45.20 0.62 28.02 4.00 112.08 kg
29.20 0.62 18.10 9.00 162.90 kg
30.80 0.62 19.10 6.00 114.60 kg
631.88 kg
2.00 x 48.00 = 96.00 bh
mm ( klos gording )
924.00 5.42 5008.08 1.00 5,008.08 kg
432.00 5.42 2341.44 1.00 2,341.44 kg
816.00 5.42 4422.72 1.00 4,422.72 kg
144.00 5.42 780.48 2.00 1,560.96 kg
13,333.20 kg

Cos Sisi dasar 8.00


= = = 0.819 =
35 Sisi miring Sisi miring
8.00 8.00
= Sisi miring = = = 9.77 m1
Cos35 0.819
= 9.770 x ( 44.00 + 0.00 )x 2.00 = 859.76 m2

Cos Sisi dasar 8.00


= = = 0.707 =
45 Sisi miring Sisi miring
8.00 8.00
= Sisi miring = = = 11.32 m1
Cos45 0.707
= 11.320 x ( 24.00 + 20.00 )x 2.00 = 498.08 m2
2

Cos Sisi dasar 6.00


= = = 0.819 =
35 Sisi miring Sisi miring
6.00 6.00
= Sisi miring = = = 7.33 m1
Cos35 0.819
= 7.330 x ( 55.00 + 48.00 )x 2.00 = 754.99 m2
2
Cos Sisi dasar 3.00
= = = 0.500 =
60 Sisi miring Sisi miring
3.00 3.00
= Sisi miring = = = 6.00 m1
Cos60 0.500
= 6.000 x ( 9.00 + 13.00 )x 2.00 = 264.00 m2
2
x 2.00

18.42
=

= 3.14 x r x r
= 3.14 x 9.21 x 9.21
= 266.35 266.35 m2

L =

3.25 = 737.75 849.75 m2


2.00 = 112.00

3492.93 m2

= 123 = 123.00 m'


= = 264.00 m2
= 624.60 = 624.60 m'
= 5.74 = 5.74 m'
= 849.75 = 849.75 m2
NO URAIAN PEKERJAAN

V PEKERJAAN BANGUNAN
V.A PEKERJAAN STRUKTUR

1 Pondasi
Lantai kerja bwh pile cap t= 5 cm
Beton Bertulang Pile cap type P2
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 Readymix
- Pembesian dengan besi ulir
- Bekisting untuk Pondasi 2 x pakai

2 PEKERJAAN KONSTRUKSI BAJA


PORTAL BAJA
- Kolom Baja WF. 250.125
- Plat buhul, t = 10 mm
- Plat Stifner t = 10 mm
- Base Plat t = 12 mm
- Angkur Baut 22 L=50 cm

Total Head

Page 156
JUMLAH TOTAL
HARGA SATUAN
VOLUME SATUAN HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)

0.50 m3 981,676.98 490,838.49

6.00 M3 1,191,415.05 7,148,490.30


1,568.40 Kg 13,680.40 21,456,339.36
24.00 M2 73,732.25 1,769,574.00

Sub Jumlah 30,865,242.15

3,140.60 kg 25,236.75 79,258,537.05


96.00 kg 25,236.75 2,422,728.00
97.50 kg 25,236.75 2,460,583.12
90.00 kg 25,236.75 2,271,307.50
119.20 kg 25,236.75 3,008,220.60

Sub Jumlah 89,421,376.27

120,286,618

Page 157
RENCANA ANGGARAN BIAYA

KEGIATAN : PENYUSUNAN DED PEMBANGUNAN KAWASAN EXIT TOL


PEKERJAAN : DED PEMBANGUNAN KAWASAN EXIT TOL
LOKASI : KECAMATAN BOJONG, KABUPATEN PEKALONGAN
TAHUN ANGGARAN : 2017

NO URAIAN PEKERJAAN VOLUME SATUAN

I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi awal dan akhir 1.00 Ls
2 bowplank 1.00 Ls
3 Mobilisasi dan Demobilisasi 1.00 Ls
4 Pagar sementara dari seng gelombang tinggi 2,00 m 1.00 Ls
5 Sewa Direksi Keet, Gudang dan Barak Kerja 1.00 Ls
6 Bongkaran Bangunan Lama 1.00 Ls

II PEKERJAAN LAVATORY PUBLIK (2 UNIT)


II.1 PEKERJAAN TANAH
1 Galian tanah pondasi 174.51 m3
2 Urugan tanah kembali 111.22 m3
3 Urugan pasir dibawah pondasi 10.24 m3
4 Urugan tanah peninggian bangunan 197.18 m3
5 Terucuk bambu 378.00 m'

II.2 PEKERJAAN BETON


1 Beton lantai kerja K100 1.05 m3
2 Rabat beton tebal 5 cm K100 7.58 m3
3 Beton pondasi footplat 80x80 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 3.05 m3
- Pembesian 481.12 kg
- Bekisting 30.24 m2
4 Beton sloof 15x25 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 5.43 m3
- Pembesian 954.89 kg
- Bekisting 72.25 m2
5 Beton kolom K1 20x20 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 2.49 m3
- Pembesian 438.28 kg
- Bekisting 49.78 m2
6 Beton kolom K2 15x20 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 0.72 m3
- Pembesian 164.38 kg
- Bekisting 16.91 m2
7 Beton kolom praktis 15x15 cm 87.50 m'
8 Beton balok 15x20 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 1.50 m3
- Pembesian 545.24 kg
- Bekisting 27.50 m2
NO URAIAN PEKERJAAN VOLUME SATUAN

9 Beton ring balok 15x20 cm


Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 2.66 m3
- Pembesian 606.21 kg
- Bekisting 48.68 m2
10 Beton balok kuda-kuda 15x20 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 1.37 m3
- Pembesian 307.13 kg
- Bekisting 25.03 m2
11 Beton plat atap tebal 10 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 4.37 m3
- Pembesian 1,578.63 kg
- Bekisting 47.96 m2

II.3 PEKERJAAN PASANGAN


1 Pasangan batu belah 1pc : 4ps 43.52 m3
2 Pasangan roster R0 20.56 m2
3 Pasangan glass block R1 10.04 m2
4 Pasangan batu tempel andesit 58.39 m2
5 Pas. Dinding bata 1/2 batu 1pc : 4ps 196.63 m2
6 Plesteran dinding bata 1pc : 4ps 393.13 m2
7 Plesteran beton 1pc : 3ps 37.57 m2
8 Acian 180.32 m2
9 Plesteran Skoning 13.74 m'

II.4 PEKERJAAN KUSEN, PINTU & JENDELA


1 Pintu P 16.00 unit
2 Jendela boven BV 12.00 unit
3 Jendela boven BV1 1.00 unit
NO URAIAN PEKERJAAN VOLUME SATUAN

II.5 PEKERJAAN PLAFOND


1 Plafond kalsiboard 3,5 mm rangka hollow 47.24 m2
2 Compound plat beton 16.38 m2
3 List tepi profil gypsum 73.96 m'

II.6 PEKERJAAN PENUTUP LANTAI


1 Pas. Keramik lantai 30x30 cm unpolished 139.13 m2
2 Pas. Dinding 40x20 cm 199.59 m2

II.7 PEKERJAAN CAT-CATAN


1 Cat tembok eksterior 83.15 m2
2 Cat tembok interior 125.72 m2
3 Cat plafond 47.24 m2

II.8 PEKERJAAN ATAP


1 Gording C 150x75 2,150.40 kg
2 Pas. Atap PVC gelombang 128.64 m2
3 Talang air PVC 4" 19.20 m'
4 Listplank GRC 51.80 m'
5 Water proofing coating 31.30 m2
6 Roof drain 4" 7.00 bh

II.9 PEKERJAAN ELEKTRIKAL


1 Instalasi titik lampu 26.00 titik
2 Lampu down light E27 LED 4 W 16.00 bh
3 Lampu down light E27 LED 7 W 10.00 bh
4 Saklar tunggal 2.00 bh
5 Saklar ganda 10.00 bh

II.10 PEKERJAAN PLUMBING & SANITAIR


1 Closet duduk 15.00 bh
2 Washtafel 4.00 bh
3 Floor drain 18.00 bh
4 Kaca cermin 2.00 bh
5 Kran air 16.00 bh
6 Urinoir 7.00 bh
7 Septictank 2.00 unit
8 Peresapan 2.00 unit
9 Pipa PVC Class AW 2" air bersih 53.50 m'
10 Pipa PVC Class AW 4" Air Kotor 36.00 m'
11 Pipa PVC Class AW 4" air limbah 41.18 m'
12 Pipa PVC Class AW 4" air hujan 28.70 m'
NO URAIAN PEKERJAAN VOLUME SATUAN

13 Fitting 1.00 Ls

II.11 PEKERJAAN LAIN-LAIN


1 Saluran buis beton U20 cm
- Pasir urug tebal 5 cm 0.40 m3
- Pas. Batu bata 1pc : 3ps 24.00 m2
- Buis beton U20 cm 20.00 m'
- Tutup saluran grill besi 20.00 m'
2 Beton meja washtafel finishing marmer 2.00 unit

Jumlah Total II.11 Pekerjaan Lain-


JUMLAH TOTAL PEKERJAAN LAV
JUMLAH TOTAL PEKERJAAN LAV

III PEKERJAAN MUSHOLLA


III.1 PEKERJAAN TANAH
1 Galian tanah pondasi 289.89 m3
2 Urugan tanah kembali 271.63 m3
3 Urugan pasir dibawah pondasi 13.10 m3
4 Urugan pasir dibawah lantai 50.66 m3
5 Urugan tanah peninggian bangunan 304.20 m3
6 Terucuk bambu 396.00 m'

III.2 PEKERJAAN BETON


1 Beton lantai kerja K100 1.18 m3
2 Rabat beton tebal 5 cm K100 25.33 m3
3 Beton pondasi footplat F1 120x120 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 3.98 m3
- Pembesian 511.32 kg
- Bekisting 25.56 m2
NO URAIAN PEKERJAAN VOLUME SATUAN

4 Beton pondasi footplat F2 80x80 cm


Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 1.47 m3
- Pembesian 222.84 kg
- Bekisting 11.28 m2
5 Beton sloof S1 20x30 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 7.20 m3
- Pembesian 1,134.07 kg
- Bekisting 72.00 m2
6 Beton sloof S2 15x25 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 1.83 m3
- Pembesian 323.82 kg
- Bekisting 24.38 m2
7 Beton kolom K1 35x35 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 10.16 m3
- Pembesian 1,308.05 kg
- Bekisting 116.09 m2
8 Beton kolom K2 L 15x25 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 1.19 m3
- Pembesian 159.81 kg
- Bekisting 22.58 m2
9 Beton kolom K3 15x25 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 1.04 m3
- Pembesian 185.27 kg
- Bekisting 22.19 m2
10 Beton kolom praktis 15x15 cm 86.30 m'
11 Beton balok B1 20x40 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 5.41 m3
- Pembesian 1,031.15 kg
- Bekisting 67.60 m2
12 Beton balok B2 20x40 - 20x30 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 4.76 m3
- Pembesian 971.09 kg
- Bekisting 62.40 m2
13 Beton balok B3 20x30 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 1.37 m3
- Pembesian 212.30 kg
- Bekisting 18.25 m2
14 Beton balok B4 20x25 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 0.74 m3
- Pembesian 119.17 kg
- Bekisting 10.36 m2
15 Beton balok B5 15x20 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 1.64 m3
- Pembesian 342.62 kg
- Bekisting 29.98 m2
16 Beton plat atap tebal 10 cm
Membuat Beton mutu f'c=21,7 MPa (K250) Readymix 32.23 m3
- Pembesian 2,766.99 kg
- Bekisting 327.87 m2

III.3 PEKERJAAN PASANGAN


1 Pasangan batu kosong/Aanstamping 21.75 m3
NO URAIAN PEKERJAAN VOLUME SATUAN

2 Pasangan batu belah 1pc : 4ps 47.85 m3


3 Pasangan glass block R0 9.36 m2
4 Pasangan glass block R1 86.40 m2
5 Pasangan roster R2 46.08 m2
6 Pasangan roster R3 5.76 m2
7 Pasangan roster R4 6.24 m2
8 Pasangan roster R5 2.35 m2
9 Pas. Dinding bata 1/2 batu 1pc : 4ps 108.49 m2
10 Plesteran dinding bata 1pc : 4ps 216.98 m2
11 Plesteran beton 1pc : 3ps 73.39 m2
12 Acian 251.78 m2
13 Plesteran Skoning 4.71 m'
14 Rollag bata 3.50 m3

III.4 PEKERJAAN KUSEN, PINTU & JENDELA


1 Pintu P 4.00 unit
2 Pintu PU 2.00 unit
3 Jendela LB 6.00 unit

III.5 PEKERJAAN PLAFOND


1 Compound plat beton 252.26 m2
2 List tepi profil gypsum 62.03 m'

III.6 PEKERJAAN PENUTUP LANTAI


1 Pas. Keramik lantai 60x120 cm polished 219.30 m2
2 Pas. Keramik lantai 60x60 cm unpolished 38.87 m2
3 Pas. Keramik lantai 30x30 cm unpolished 30.54 m2
4 Pas. Keramik Dinding 20x25 cm 38.59 m2

III.7 PEKERJAAN CAT-CATAN


1 Cat tembok eksterior 140.11 m2
2 Cat tembok interior 111.67 m2
3 Cat plafond 159.04 m2

III.8 PEKERJAAN ATAP


1 Rangka atap 163.98 m2
2 Pas. Atap kubah enamel 163.98 m2
3 Water proofing coating 101.08 m2
4 Roof drain 4" 12.00 bh

III.9 PEKERJAAN ELEKTRIKAL


NO URAIAN PEKERJAAN VOLUME SATUAN

1 Instalasi titik lampu 18.00 titik


2 Lampu down light E27 LED 4 W 7.00 bh
3 Lampu down light E27 LED 11 W 10.00 bh
4 Lampu gantung 1.00 bh
5 Saklar tunggal 1.00 bh
6 Saklar ganda 6.00 bh
7 Stop kontak 6.00 bh

III.10 PEKERJAAN PLUMBING & SANITAIR


1 Closet duduk 4.00 bh
2 Floor drain 6.00 bh
3 Kran air 14.00 bh
4 Septictank 1.00 unit
5 Peresapan 1.00 unit
6 Pipa PVC Class AW 2" air bersih 41.50 m'
7 Pipa PVC Class AW 4" Air Kotor 21.00 m'
8 Pipa PVC Class AW 4" air limbah 14.50 m'
9 Pipa PVC Class AW 4" air hujan 78.00 m'
10 Fitting 1.00 Ls

III.11 PEKERJAAN LAIN-LAIN


1 Saluran buis beton U20 cm
- Pasir urug tebal 5 cm 1.90 m3
- Pas. Batu bata 1pc : 3ps 113.82 m2
- Buis beton U20 cm 94.85 m'
- Tutup saluran grill besi 10.30 m'

IV PEKERJAAN KAWASAN
1 Urugan tanah peninggian 33,280.00 m3
2 Pasangan Batu Kali Saluran MD 100 1,153.38 m3
-Plat Beton Penutup Saluran K-225 133.08 m3
-besi Tulangan Polos 5,177.73 kg
-Pasir Urug 177.44 m3
-Beton Lantai Kerja 5cm 88.72 m3
-Plesteran 1:2 3,327.06 m2
-Acian 6,654.12 m2
3 Pasangan Batu Kali Saluran MD 50 42.04 m3
-Pasir Urug 12.94 m3
-Beton Lantai Kerja 5cm 6.47 m3
-Plesteran 1:2 242.55 m2
-Acian 485.10 m2
-Plat Beton Penutup Saluran K-225 11.32 m3
-besi Tulangan Polos 1,403.56 kg
-Galian Tanah Saluran Irigasi 162.64 m3
4 Pekerjaan Beraspal
- Penghamparan LPB (Lapis Pondasi Bawah) Tebal 20 cm 846.25 M3
NO URAIAN PEKERJAAN VOLUME SATUAN

-Penghamparan LPA (Pondasi Agregrat Kelas A) Tebal 25 cm 846.25 M3


-Prime Coat (Lapis Resap Pengikat) 2,708.00 ltr
Takecoat (Lapis Peresap) 1,015.50 ltr
-Penghamparan AC-WC (Asphalt concrete wearing course) tebal 4,0 cm 311.42 ton
5 Pekerjaan Paving
-Pasir Urug Bawah Paving 1,312.30 m3
-Pasang Paving K300 tebal 8 cm 13,123.00 m2
-Pasang Kansteen 1,055.40 m'
6 -Pagar Panel Keliling 659.02 m1
7 -Pekerjaan Taman
-Pohon ketapang kencana, lingkar batang bawah + 20 cm, tinggi + 5 m, daun
20.00 bh
rimbun
-Penanaman palm putri 15.00 bh
-Penanaman tanaman ornamen 5.00 bh
-Penanaman tanaman perdu berbunga 160.00 bh
-Penanaman rumput gajah mini beserta urugan tanah subur dan pemupukan 3033.00 m2
NCANA ANGGARAN BIAYA

JUMLAH TOTAL
HARGA SATUAN
HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)

5,000,000.00 5,000,000.00
5,000,000.00 5,000,000.00
10,000,000.00 10,000,000.00
15,000,000.00 15,000,000.00
10,000,000.00 10,000,000.00
5,000,000.00 5,000,000.00

Jumlah Total I. Pekerjaan Persiapan 50,000,000.00


JUMLAH TOTAL PEKERJAAN PERSIAPAN 50,000,000.00

62,962.50 10,987,585.87
18,434.50 2,050,285.09
208,322.50 2,133,222.40
105,052.50 20,714,251.95
23,230.00 8,780,940.00

Jumlah Total II.1 Pekerjaan Tanah 44,666,285.31

981,676.98 1,030,760.82
981,676.98 7,441,111.50

1,191,415.05 3,633,815.90
13,680.40 6,581,914.04
147,464.50 4,459,326.48

1,191,415.05 6,469,383.72
13,680.40 13,063,277.15
91,862.00 6,637,029.50

1,191,415.05 2,966,623.47
13,680.40 5,995,845.71
162,955.00 8,111,899.90

1,191,415.05 857,818.83
13,680.40 2,248,784.15
162,955.00 2,755,569.05
59,149.24 5,175,558.50

1,191,415.05 1,787,122.57
13,680.40 7,459,101.29
188,830.00 5,192,825.00
JUMLAH TOTAL
HARGA SATUAN
HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)

1,191,415.05 3,169,164.03
13,680.40 8,293,195.28
188,830.00 9,192,244.40

1,191,415.05 1,632,238.61
13,680.40 4,201,661.25
188,830.00 4,726,414.90

1,191,415.05 5,206,483.76
13,680.40 21,596,289.85
205,505.00 9,856,019.80

Jumlah Total II.2 Pekerjaan Beton 159,741,479.46

841,627.50 36,627,628.80
267,892.50 5,507,869.80
285,000.00 2,861,400.00
197,828.06 11,551,180.42
124,165.50 24,414,662.26
47,895.20 18,829,039.97
49,738.88 1,868,689.72
26,933.00 4,856,558.56
28,612.00 393,128.88

Jumlah Total II.3 Pekerjaan Pasangan 106,910,158.41

415,400.70 6,646,411.20
380,310.18 4,563,722.16
920,750.95 920,750.95

Jumlah Total II.4 Pekerjaan Kusen, Pintu & Jendela 12,130,884.31


JUMLAH TOTAL
HARGA SATUAN
HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)

184,051.75 8,694,604.67
175,000.00 2,866,500.00
25,323.00 1,872,889.08

Jumlah Total II.5 Pekerjaan Plafond 13,433,993.75

123,966.73 17,247,491.14
103,769.56 20,711,366.48

Jumlah Total II.6 Pekerjaan Penutup Lantai 37,958,857.62

34,270.00 2,849,550.50
22,011.00 2,767,222.92
19,046.30 899,747.21

Jumlah Total II.7 Pekerjaan Cat-Catan 6,516,520.63

27,030.75 58,126,924.80
85,036.75 10,939,127.52
73,588.50 1,412,899.20
75,000.00 3,885,000.00
55,000.00 1,721,500.00
45,000.00 315,000.00

Jumlah Total II.8 Pekerjaan Atap 76,400,451.52

235,000.00 6,110,000.00
135,000.00 2,160,000.00
185,500.00 1,855,000.00
25,000.00 50,000.00
27,500.00 275,000.00

Jumlah Total II.9 Pekerjaan Elektrikal 10,450,000.00

2,713,885.00 40,708,275.00
555,105.00 2,220,420.00
40,422.50 727,605.00
175,797.63 351,595.26
71,484.00 1,143,744.00
615,077.50 4,305,542.50
7,500,000.00 15,000,000.00
4,500,000.00 9,000,000.00
43,383.75 2,321,030.62
104,233.13 3,752,392.68
104,233.13 4,292,320.29
104,233.13 2,991,490.83
JUMLAH TOTAL
HARGA SATUAN
HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)
2,500,000.00 2,500,000.00

Jumlah Total II.10 Pekerjaan Plumbing & Sanitair 89,314,416.18

208,322.50 83,329.00
127,298.10 3,055,154.40
130,834.35 2,616,687.00
275,000.00 5,500,000.00
2,500,000.00 5,000,000.00

Jumlah Total II.11 Pekerjaan Lain-lain 16,255,170.40


JUMLAH TOTAL PEKERJAAN LAVATORY PUBLIK 573,778,217.59
JUMLAH TOTAL PEKERJAAN LAVATORY PUBLIK (2 UNIT) 1,147,556,435.18

62,962.50 18,252,199.12
18,434.50 5,007,363.23
208,322.50 2,729,024.75
208,322.50 10,553,617.85
105,052.50 31,956,970.50
23,230.00 9,199,080.00

Jumlah Total III.1 Pekerjaan Tanah 77,698,255.45

981,676.98 1,158,378.83
981,676.98 24,865,877.90

1,191,415.05 4,741,831.89
13,680.40 6,995,062.12
147,464.50 3,769,192.62
JUMLAH TOTAL
HARGA SATUAN
HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)

1,191,415.05 1,751,380.12
13,680.40 3,048,540.33
147,464.50 1,663,399.56

1,191,415.05 8,578,188.36
13,680.40 15,514,531.22
91,862.00 6,614,064.00

1,191,415.05 2,180,289.54
13,680.40 4,429,987.12
91,862.00 2,239,595.56

1,191,415.05 12,104,776.90
13,680.40 17,894,647.22
162,955.00 18,917,445.95

1,191,415.05 1,417,783.90
13,680.40 2,186,264.72
162,955.00 3,679,523.90

1,191,415.05 1,239,071.65
13,680.40 2,534,567.70
162,955.00 3,615,971.45
59,149.24 5,104,579.41

1,191,415.05 6,445,555.42
13,680.40 14,106,544.46
188,830.00 12,764,908.00

1,191,415.05 5,671,135.63
13,680.40 13,284,899.63
188,830.00 11,782,992.00

1,191,415.05 1,632,238.61
13,680.40 2,904,348.92
188,830.00 3,446,147.50

1,191,415.05 881,647.13
13,680.40 1,630,293.26
188,830.00 1,956,278.80

1,191,415.05 1,953,920.68
13,680.40 4,687,178.64
188,830.00 5,661,123.40

1,191,415.05 38,399,307.06
13,680.40 37,853,529.99
205,505.00 67,378,924.35

Jumlah Total III.2 Pekerjaan Beton 388,685,925.45

404,995.50 8,808,652.12
JUMLAH TOTAL
HARGA SATUAN
HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)
841,627.50 40,271,875.87
285,000.00 2,667,600.00
285,000.00 24,624,000.00
267,892.50 12,344,486.40
267,892.50 1,543,060.80
267,892.50 1,671,649.20
267,892.50 629,547.37
124,165.50 13,470,715.09
47,895.20 10,392,300.49
49,738.88 3,650,336.40
26,933.00 6,781,190.74
28,612.00 134,762.52
827,770.00 2,897,195.00

Jumlah Total III.3 Pekerjaan Pasangan 129,887,372.00

415,400.70 1,661,602.80
5,564,625.00 11,129,250.00
125,000.00 750,000.00

Jumlah Total III.4 Pekerjaan Kusen, Pintu & Jendela 13,540,852.80

184,051.75 46,428,894.45
175,000.00 10,855,250.00

Jumlah Total III.5 Pekerjaan Plafond 57,284,144.45

309,916.83 67,964,760.81
247,933.46 9,637,173.59
123,966.73 3,785,943.93
103,769.56 4,004,467.32

Jumlah Total III.6 Pekerjaan Penutup Lantai 85,392,345.65

34,270.00 4,801,569.70
22,011.00 2,457,968.37
19,046.30 3,029,123.55

Jumlah Total III.7 Pekerjaan Cat-Catan 10,288,661.62

1,350,000.00 221,373,000.00
550,000.00 90,189,000.00
55,000.00 5,559,400.00
45,000.00 540,000.00

Jumlah Total III.8 Pekerjaan Atap 317,661,400.00


JUMLAH TOTAL
HARGA SATUAN
HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)
235,000.00 4,230,000.00
135,000.00 945,000.00
215,000.00 2,150,000.00
5,500,000.00 5,500,000.00
25,000.00 25,000.00
27,500.00 165,000.00
21,500.00 129,000.00

Jumlah Total III.9 Pekerjaan Elektrikal 13,144,000.00

2,713,885.00 10,855,540.00
40,422.50 242,535.00
71,484.00 1,000,776.00
7,500,000.00 7,500,000.00
4,500,000.00 4,500,000.00
43,383.75 1,800,425.62
104,233.13 2,188,895.73
104,233.13 1,511,380.38
104,233.13 8,130,184.14
2,500,000.00 2,500,000.00

Jumlah Total III.10 Pekerjaan Plumbing & Sanitair 40,229,736.87

208,322.50 395,812.75
127,298.10 14,489,069.74
130,834.35 12,409,638.09
275,000.00 2,832,500.00

Jumlah Total III.11 Pekerjaan Lain-lain 30,127,020.58


JUMLAH TOTAL PEKERJAAN MUSHOLLA 1,163,939,715

105,052.50 3,496,147,200.00
841,627.50 970,716,325.95
1,107,216.38 147,348,355.85
13,680.40 70,833,417.49
208,322.50 36,964,744.40
981,676.98 87,094,381.66
52,289.12 173,969,039.58
26,933.00 179,215,413.96
841,627.50 35,382,020.10
208,322.50 2,695,693.15
981,676.98 6,351,450.06
52,289.12 12,682,726.05
26,933.00 13,065,198.30
1,107,216.38 12,533,689.42
13,680.40 19,201,262.22
62,962.50 10,240,221.00

802,457.00 679,079,236.25
JUMLAH TOTAL
HARGA SATUAN
HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)
694,881.00 588,043,046.25
11,290.73 30,575,296.84
10,239.00 10,397,704.50
941,453.95 293,187,589.10

29,670.00 38,935,941.00
202,368.92 2,655,687,337.16
120,113.74 126,768,041.19
350,000.00 230,657,000.00

850,000.00 17,000,000.00

450,000.00 6,750,000.00
550,000.00 2,750,000.00
15,000.00 2,400,000.00
45,000.00 136,485,000

JUMLAH TOTAL PEKERJAAN KAWASAN 10,093,157,331.48


No Pekerjaan

IV BANGUNAN UTAMA

A. PEKERJAAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1 Administrasi & Dokumentasi
2 Pagar pengaman dari seng
3 Uitzet dan pengukuran lapangan
4 Direksi Keet , Air Kerja, Gudang

A PEKERJAAN TANAH & PONDASI


I PEKERJAAN TANAH
1 Galian Tanah pondasi
2 Urugan Kembali
3 Urugan Pasir bwh pile cap dan sloof
4 Urugan tanah peninggian peil lantai

II PEKERJAAN TIANG PANCANG DAN PILE CAP


1 Tiang pancang Mini pile 32 x 32 x32
2 Mobilisasi demobilisasi alat pancang hidrolis
3 Pecah kepala tiang pancang minipile
4 Lantai kerja bwh pile cap t= 5 cm
5 Beton Bertulang Pile cap type P1
- Membuat Beton mutu f'c=19,3Mpa (K225), Slump(122),w/c=0,58
- Pembesian dengan besi ulir
- Bekisting untuk Pondasi 2 x pakai

6 Beton Bertulang Pile cap type P2

174
No Pekerjaan

- Membuat Beton mutu f'c=19,3Mpa (K225), Slump(122),w/c=0,58


- Pembesian dengan besi ulir
- Bekisting untuk Pondasi

7 Beton Bertulang Pile cap type P3


- Membuat Beton mutu f'c=19,3Mpa (K225), Slump(122),w/c=0,58
- Pembesian dengan besi ulir
- Bekisting untuk Pondasi

8 Beton Bertulang Pile cap type P4


- Membuat Beton mutu f'c=19,3Mpa (K225), Slump(122),w/c=0,58
- Pembesian dengan besi ulir
- Bekisting untuk Pondasi

III. PEKERJAAN PONDASI BATU KALI


1 Pas. Pondasi Batu Kali 1 PC : 6 Psr
2 Pas. Pondasi Batu Kosong

B PEKERJAAN BETON
1 Lantai kerja bwh sloof t= 5 cm
2 Beton bertulang sloof S1 30x40 cm
- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk Sloof

3 Beton bertulang sloof S2 20x30 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan

175
No Pekerjaan

- Bekisting untuk Sloof

176
No Pekerjaan

4 Beton bertulang sloof praktis 15/20


Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66
Besi tulangan
Bekisting untuk Sloof

5 Beton bertulang kolom K1 60x60


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk Kolom

6 Beton bertulang kolom KT 40x40


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk Kolom

7 Beton bertulang kolom pedestal 25x35


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk Kolom

8 Beton bertulang tangga lt 01 ke Lt atap


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk plat

9 Beton bertulang kolom KP 11x11 cm

10 Beton bertulang balok bordes tangga 25/45 Lt 01


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk balok

177
No Pekerjaan

11 Beton bertulang balok latai 15x20 cm

12 Beton bertulang kolom dan balok gawangan kusen PJ1 11x11 cm

13 Beton bertulang plat leuvel t=10 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk plat

14 Beton bertulang plat meja pantry t=10 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk balok

15 Beton bertulang balok lantai dag B1 30x65 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk balok

16 Beton bertulang balok lantai dag B2 30x50 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk balok

17 Beton bertulang balok lantai dag BA 20x50 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk balok

18 Beton bertulang balok lantai dag B2L 25x50 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk balok

178
No Pekerjaan

19 Beton bertulang balok lantai dag BC 30x60 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk balok

20 Beton bertulang balok latai 15x20 cm

179
No Pekerjaan

21 Beton bertulang balok ring R1 40x60 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk balok

22 Beton bertulang balok ring R2 30x50 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk balok

23 Beton bertulang balok ring praktis 15/20

24 Beton bertulang plat lantai dag t= 12 cm


- Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
- Besi tulangan
- Bekisting untuk lantai

C PEKERJAAN ATAP
I PEKERJAAN RANGKA ATAP
1 Kuda-kuda baja IWF 300 150 6,5 9
2 Gording C 150 50 20 3,2
3 Base plat t= 12 mm
4 Trackstang besi O 16 mm
5 Baja siku 50 50 5 dudukan gording
6 Sagrod besi O 12 mm
7 Angkur baut O 19 L= 40 cm
8 Walter moor

180
No Pekerjaan

II PEKERJAAN PENUTUP ATAP


1 Penutup atap genteng keramik glassur
2 Bubungan genteng keramik glassur
3 Lapisan atap aluminium foil dobel sided
4 Lisplank kayu Bengkirai

D PEKERJAAN PASANGAN DAN PLESTERAN

1 Pas. Batu Bata tb. 1/2 bata 1 PC : 3 Psr


2 Pas. Batu Bata tb. 1/2 bata 1 PC : 6 Psr
3 Pas. Roolag batu bata tb. 1/2 bata 1 PC : 3 Psr
4 Plesteran 1 PC : 3 Psr tb. 1,5 cm
5 Plesteran 1 PC : 6 Psr tb. 1,5 cm
6 Sponengan sudut
7 Pekerjaan Acian

E PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Urugan pasir bwh keramik t=5 cm
2 Lantai kerja bwh keramik t= 5 cm
3 Pas. Lantai Homogenous tile 60 x 60 cm
4 Pas. Lantai Homogenous tile 60 x 60 cm unpolish
5 Pas. Lantai tangga granit tile 60x60 cm lt 1 ke lt balkon
6 Pas. Lantai Homogenous tile 60 x 60 cm lantai balkon
7 Pas. Lantai Keramik uk. 20x20 cm
8 Keramik dinding 20/25

181
No Pekerjaan

F PEKERJAAN KUSEN, PINTU, JENDELA DAN RAILING


1 Pekerjaan pintu type PJ1
2 Pekerjaan pintu type PJ2
3 Pekerjaan pintu type PJ3
Pekerjaan pintu type P1
4 Pekerjaan pintu type P2
1 Pekerjaan pintu type P3
5 Pekerjaan pintu type PL
2 Pekerjaan jendela type J1
3 Pekerjaan jendela type J2
4 Pekerjaan jendela type J3
5 Pekerjaan jendela type J4
6 Pekerjaan bouvent B1
7 Pekerjaan bouvent B2
8 Partisi PT
9 Folding gate type FG 32 bh
10 Railing tangga stainless steel Lt 01 s/d Lt 02
11 Railing atap stainless steel

G PEKERJAAN PLAFOND
1 Pas. Langit-langit Gypsum Board Tb. 9mm
2 Plafond spandex
3 Pas. Langit-langit calsiboard t=3,5 mm
4 Drop ceiling
5 Pas. Lis Langit-langit plafond gypsum profil

H PEKERJAAN CAT
1 Pengecatan dinding eksterior

182
No Pekerjaan

2 Pengecatan dinding interior


3 Pengecatan plafond
4 Waterproofing membran plat atap

I PEKERJAAN SANITAIR
1 Closet duduk washdown+assesories
2 Wastafel+assesories
3 Urinoir
4 Sekat urinoir
5 Kran air
6 Floor drain
7 Kitchen zink
8 Kaca cermin

J PEKERJAAN LANSEKAP
I PEKERJAAN PERKERASAN HALAMAN
1 Urugan pasir bwh paving
2 Pasang paving blok
3 Pasang kanstin

II. PEKERJAAN SALURAN


1 Saluran U-20
2 Bak kontrol
3 Pasangan batu kosong bwh bak kontrol
4 Saluran pipa PVC O 4"
5 Plat beton penutup saluran t= 10cm
- Beton K-225

183
No Pekerjaan

- Besi tulangan polos

184
No Pekerjaan

III. PEKERJAAN TAMAN DAN VEGETASI


1 Pasang kanstin
2 Pohon ketapang kencana, lingkar batang bawah + 20 cm, tinggi + 5 m, daun rimbun
3 Penanaman palm putri
4 Penanaman tanaman ornamen
5 Penanaman tanaman perdu berbunga
6 Penanaman rumput gajah mini beserta urugan tanah subur dan pemupukan

IV. PEKERJAAN GROUNDTANK


1 Galian tanah
2 Lantai kerja beton K-100 t= 5 cm
3 Lantai beton bertulang t= 20 cm
- Beton K-225
- Besi tulangan ulir
4 Dinding beton bertulang t- 20 cm
- Beton K-225
- Besi tulangan ulir
- Begesting dinding 2x pakai
5 Tutup beton bertulang t= 20 cm
- Beton K-225
- Besi tulangan
- Begesting lantai
6 Tutup manhole
7 Pasangan keramik 40x40 cm

K PEKERJAAN PLUMBING
I. PEKERJAAN AIR BERSIH

185
No Pekerjaan

Peralatan Utama
1 Ground Water Tank Utama kap. 120 m3
2 Pompa Transfer dari Ground Water Utama menuju Roof tank :
Jenis Pompa
Kapasitas
Total Head
Lengkap dengan Panel Control, WLC
dan Pengkabelan dari Panel ke Pompa
3 Roof Tank
Pengadaan, Pemasangan Roof Tank
Type
Kapasitas
Lengkap dengan instalasi, WLC dan accessories lainnya
Pemipaan Lengkap, accessories + Fitting
4 Pengadaan dan pemasangan packaged booster pump
Jenis Pompa
Kapasitas
Total Head
Lengkap dengan Panel Control, WLC
dan Pengkabelan dari Panel ke Pompa
5 Dudukan Frame Stud Support Tanki Air Atas
6 Pipa Header Roof Tank
PPR PN-10 : Dia. 4" (Lengkap dengan innstalasi)
8 Pipa transfer dari GWT
PPR PN-10 : Dia. 2"
9 Pipa drain dari roof tank
PVC AW : Dia. 2"
Pekerjaan Instalasi
Pemipaan air bersih
PPR PN-10
PPR PN-10
PPR PN-10

186
No Pekerjaan

PPR PN-10
PPR PN-10
PPR PN-10
PPR PN-10

187
No Pekerjaan

II. PEKERJAAN AIR KOTOR DAN AIR BEKAS


INSTALASI UTAMA
Pipa induk air kotor & air bekas menuju bak penampung
1 Pipa PVC AW dia 8"
2 Galian pipa
3 Bak kontrol
Pipa menuju IPAL Existing
1 Pipa PVC AW 4"
2 Bak penampung
3 Pompa sumpit (transfer dari bak penampung ke ipal existing)
b. INSTALASI DALAM GEDUNG
Pipa riser
7 Grease trape

III. PEKERJAAN AIR HUJAN


Pemipaan air hujan dari roof tank
Pipa PVC AW
Roff drain

L PEKERJAAN ELEKTRIKAL
I. PEKERJAAN PASANG BARU 197 KVA
Bp (Biaya Penyambungan)
Ujl (Uang Jaminan Langganan)
Materai

SLO

188
No Pekerjaan

SJI BTL
Pengurusan Penyalaan

II. PEKERJAAN TRAFO


Transformator, kapasitas 250 kVA
- Phasa / Freq : 3 Phasa / 50 Hz
- Primer : 20 KV
- Secunder : 380 / 400 V
- Pendingin : Olie ( ONAN )
- Accessories : DGPT2, Conservator, Elastimold
- Transportasi, akomodasi, pemasangan
Grounding System
Material Bantu

III. PEKERJAAN GENSET


Genset kapasitas 250 kVA,3,50 Hz,380V
Silent Type, Stand by, Gen Set lengkap terpasang + Panel Kontrol Genset
Pentanahan Body Genset dengan BC 50 mm2
Pentanahan Netral Genset dengan BC 50 mm2
Tangki solar harian / BBM Kap.1.000 liter
Pemipaan Elektrik & Manual Pump Solar
Perijinan ke Instansi terkait
Fuel Electric Pump c/w Panel Control
Pekerjaan Ducting Radiator System
Instalasi Gas Buang Knalpot
Sound proofing ruang genset, Rock Wall 80 Kg/m3
Material & Peralatan Bantu
Solar test

189
No Pekerjaan

190
No Pekerjaan

IV. PEKERJAAN PANEL TEGANGAN RENDAH


LVMDP
CAPASITOR BANK 12x25 KVAR
SDP
PP-POMPA
PP-ATAP
PP/LP-1
PP/LP-2
PP/LP-3
PP,AC-1
PP,AC-2
PP,AC-3
Grounding elektrikal max 2 ohm (Trafo, Panel TM, LVMDP)
Grounding elektronika max 1 ohm

V. PEKERJAAN KABEL FEEDER


Kabel dari LVMDP ke SDP-1 :
NYY 4x120mm2 + BC 95mm2
Kabel dari LVMDP ke SDP-2 :
NYY 4x120mm2 + BC 95mm2
Kabel dari LVMDP ke PP-POMPA :
NYY 4x6mm2 + BC 4mm2
Kabel dari LVMDP ke PP/LP-Power House :
NYY 4x4mm2 + BC 4mm2
Kabel dari SDP-1 ke PP/LP-1 :
NYY 4x10mm2 + BC 6mm2
NYY 4x16mm2 + BC 10mm2
Kabel dari SDP-1 ke PP/LP-4 :
NYY 4x16mm2 + BC 10mm2
Kabel dari SDP-1 ke PP-ATAP.1 :

191
No Pekerjaan

NYY 4x16mm2 + BC 10mm2


Kabel dari SDP-2 ke PP.AC-1 :
NYY 4x25mm2 + BC 16mm2
Kabel dari PP-ATAP.1 ke PC-BOSTER PUMP :
NYY 4x4mm2 + BC 4mm2
Kabel dari PP-ATAP.1 ke JET PUMP :
NYY 3x4mm2 + BC 4mm2

VI. PEKERJAAN INSTALASI LISTRIK


Pengadaan ,pemasangan, kabel,konduit
lampu, rak,bobokan, penggantung, klem
armature, perapihan, training dan tes commissioning

Titik lampu,kabel NYM 3x2,5mm2 dalam conduit 20mm2


Titik stop kontak,kabel NYM 3x2,5mm2 dalam conduit 20mm2
Lampu RM 300 TL Led 2x19 W ACR
Lampu RM 300 TL Led 2x10 W ACR
Down Light E27 Led 7 W
Baret Circle E27 Led 7 W
Stop kontak, 1ph. 16A
Saklar tunggal
Saklar ganda
Saklar hotel
Kabel tray 400x100 mm berikut fitting, dan accessories lainnya
Kabel tray 300x100 mm berikut fitting, dan accessories lainnya

Lampu PJU Led 3x23 W tiang tinggi 9m, berikut pondasi dan accessories lainnya
Kabel intalasi Lampu PJU NYFGbY 3x4 mm2

192
No Pekerjaan

VII. PEKERJAAAN PENANGKAL PETIR


Air Terminal Electro Static (non radio aktif), Radius Proteksi min 80 Meter,
berikut tiang dan accessories
Obstruction Light led 5 w
Lighting strike counter
Conductor Cable, BC 50 mm2 dalam conduit
Cable Clamp, support dan accessories lainnya
Bak Kontrol berikut grounding max 1 ohm
Material bantu
Ijin Depnaker

M PEKERJAAN ELEKTRONIKA
I. PEKERJAAN FIRE ALARM
Pengadaan dan pemasangan lengkap peralatan
instalasi kabel, dudukan dan penggantung, training dan
tes commissioning

PERALATAN UTAMA
MCFA ( Conventional ) 20 Zone c/w battery & charge
Annunciator

Lantai 1
Titik fire alarm,kabel NYA 2x1.5mm2 + conduit 20 mm2
ROR Detector
Smoke Detector
Manual Push Button
Alarm Bell
Indikator Lamp
End of Line

193
No Pekerjaan

Terminal box
Kabel dari Terminal Box ke MDF

II. PEKERJAAN TELEPON & WIFI


Pengadaan dan pemasangan lengkap peralatan
instalasi kabel, dudukan dan penggantung, training dan
tes commissioning

PERALATAN UTAMA
PABX 1-8 line 104 ext berikut setting, accessories lainnya
Penyambungan telephone
Server

Titik telephone,kabel UTP cat 6 + pipa conduit 20mm2


Titik wifi,kabel UTP cat 6 + pipa conduit 20mm2
Socket outlet telepon
Wifi
Terminal box

III. PEKERJAAN CCTV


Pengadaan dan pemasangan lengkap peralatan
instalasi kabel, dudukan dan penggantung, training dan
tes commissioning

PERALATAN UTAMA
DVR 8 Chanel (central cctv)
LED Monitor 32"
Rack for CCTV berikut intslasi dan material bantu

194
No Pekerjaan

Fixed Dome Colour Camera


Instalasi Audio, Video, & Power dalam Konduit yang Terpisah

195
No Pekerjaan

IV. PEKERJAAN TATA SUARA


Pengadaan dan pemasangan lengkap peralatan
instalasi kabel, dudukan dan penggantung, training dan
tes commissioning

PERALATAN UTAMA
CD/MMC/USB player
AM/FM Tuner
Paging Microphone
Cabinet Rack
Mixer Pre Amplifier
fire dome speaker
Power amplifier 240 W
Speaker Selector
Emergency massage (evac mix)

Ceiling speaker 6 W
Volume Control 3 - 6 W
Instalasi speaker kabel NYMHY 3x1.5mm2 dalam pipa conduit 20 mm2
Terminal box
Kabel dari terminal box ke central terminal box NYM 3x2.5mm2 dalam pipa conduit 20mm2

V. PEKERJAAN MATV
Pengadaan dan pemasangan lengkap peralatan
instalasi kabel, dudukan dan penggantung, training dan
tes commissioning

PERALATAN UTAMA
Parabola 16 Feet, Lengkap dengan Dudukan

196
No Pekerjaan

Antena Yagi ( UHF ) Termasuk Tiang


Power Divider
Channel Amplifier (10 chanel)
Decoder
Modulator
Passive Combiner
Booster
Cabinet Rack
Instalasi + Material Bantu
PERALATAN UTAMA TV BERLANGGANAN
Parabola , Lengkap dengan Dudukan, receiver, modulator dan accessories.

Spliter
Kabel Tuvur, Coaxial RG 6 dalam conduit 20 mm2
Taff off
Outlet TV
Titik Instalasi Outlet TV Coaxial RG 6 dalam pipa conduit 20 mm2

197
No Pekerjaan

VI. PEKERJAAN AC
Pengadaan dan pemasangan air conditioning (AC) lengkap dengan
pipa kabel daya, refrigerant berisolasi, pipa kondensat
dan perlengkapannya beserta pengetesan sistem dan instalasi.

Pekerjaan Unit AC / Digital Scroll system, termasuk dudukan Unit dan remote wireless
1 Indoor Unit , Cassette type kap : 19,100 BTU/h
2 Indoor Unit IU, Wall type kap : 9,600 BTU/h

3 Pemipaan Refrigrant berisolasi


9.52mm x t0.8
12.7mm x t0.8
15.88mm x t1.0
19.05mm x t1.0
4 Pemipaan Drain / PVC AW berisolasi
5 Fitting-Fitting
6 Refnet Joint
MDS-Y1-A
MDS-Y2-A
11 Titik Instalasi daya AC
kabel power indoor
kabel power outdoor
14 Testing and Commisioning

198
Pekerjaan Volume

PERSIAPAN
JAAN PERSIAPAN
strasi & Dokumentasi 1.00
pengaman dari seng 1.00
an pengukuran lapangan 1.00
Keet , Air Kerja, Gudang 1.00

SUB JUMLAH - I
SUB TOTAL PEKERJAAN PERSIAPAN

JAAN TANAH & PONDASI


JAAN TANAH
Tanah pondasi 664.14
72.99
Pasir bwh pile cap dan sloof 223.84
tanah peninggian peil lantai 3,838.90

SUB JUMLAH - I

JAAN TIANG PANCANG DAN PILE CAP


ancang Mini pile 32 x 32 x32 2,544.00
asi demobilisasi alat pancang hidrolis 1.00
kepala tiang pancang minipile 468.00
kerja bwh pile cap t= 5 cm 10.61
Bertulang Pile cap type P1
embuat Beton mutu f'c=19,3Mpa (K225), Slump(122),w/c=0,58 96.00
embesian dengan besi ulir 6,035.33
ekisting untuk Pondasi 2 x pakai 199.68

Bertulang Pile cap type P2

199
Pekerjaan Volume

embuat Beton mutu f'c=19,3Mpa (K225), Slump(122),w/c=0,58 24.99


embesian dengan besi ulir 2,191.12
ekisting untuk Pondasi 71.47

Bertulang Pile cap type P3


embuat Beton mutu f'c=19,3Mpa (K225), Slump(122),w/c=0,58 14.06
embesian dengan besi ulir 1,304.84
ekisting untuk Pondasi 44.99

Bertulang Pile cap type P4


embuat Beton mutu f'c=19,3Mpa (K225), Slump(122),w/c=0,58 24.00
embesian dengan besi ulir 2,256.17
ekisting untuk Pondasi 96.00

SUB JUMLAH - II

JAAN PONDASI BATU KALI


ondasi Batu Kali 1 PC : 6 Psr 253.51
ondasi Batu Kosong 92.19

SUB JUMLAH - III

SUB TOTAL PEKERJAAN TIANG PANCANG DA

JAAN BETON
kerja bwh sloof t= 5 cm 6.05
bertulang sloof S1 30x40 cm
n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 54.24
8,684.26
sting untuk Sloof 361.78

bertulang sloof S2 20x30 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 22.50
4,799.99

200
Pekerjaan Volume

sting untuk Sloof 225.00

201
Pekerjaan Volume

bertulang sloof praktis 15/20


n mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66 6.84
1,134.07
sting untuk Sloof 91.18

bertulang kolom K1 60x60


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 96.77
18,869.44
sting untuk Kolom 645.12

bertulang kolom KT 40x40


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 3.07
971.56
sting untuk Kolom 30.72

bertulang kolom pedestal 25x35


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 3.07
971.56
sting untuk Kolom 30.72

bertulang tangga lt 01 ke Lt atap


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 5.13
768.98
sting untuk plat 51.27

bertulang kolom KP 11x11 cm 336.00

bertulang balok bordes tangga 25/45 Lt 01


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.82
143.65
sting untuk balok 8.34

202
Pekerjaan Volume

bertulang balok latai 15x20 cm 62.50

bertulang kolom dan balok gawangan kusen PJ1 11x11 cm 20.40

bertulang plat leuvel t=10 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.90
1,477.82
sting untuk plat 108.96

bertulang plat meja pantry t=10 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 1.11
150.55
sting untuk balok 22.20

ertulang balok lantai dag B1 30x65 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 13.85
4,202.06
sting untuk balok 113.60

ertulang balok lantai dag B2 30x50 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 29.51
9,043.98
sting untuk balok 255.71

ertulang balok lantai dag BA 20x50 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 3.58
1,085.66
sting untuk balok 42.96

ertulang balok lantai dag B2L 25x50 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.31
1,236.99
sting untuk balok 43.05

203
Pekerjaan Volume

ertulang balok lantai dag BC 30x60 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.70
801.94
sting untuk balok 22.50

bertulang balok latai 15x20 cm 75.60

204
Pekerjaan Volume

ertulang balok ring R1 40x60 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 32.64
7,390.01
sting untuk balok 217.60

ertulang balok ring R2 30x50 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 17.40
4,426.72
sting untuk balok 150.80

ertulang balok ring praktis 15/20 55.45

ertulang plat lantai dag t= 12 cm


n mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 91.78
13,202.84
sting untuk lantai 764.85

SUB TOTAL PEKERJAAN BETON

JAAN ATAP
ERJAAN RANGKA ATAP
a-kuda baja IWF 300 150 6,5 9 22,779.69
ding C 150 50 20 3,2 25,635.65
e plat t= 12 mm 1,439.90
kstang besi O 16 mm 1,243.87
siku 50 50 5 dudukan gording 175.50
od besi O 12 mm 314.29
kur baut O 19 L= 40 cm 432.00
104.00

SUB JUMLAH - I

205
Pekerjaan Volume

ERJAAN PENUTUP ATAP


utup atap genteng keramik glassur 3,792.26
ungan genteng keramik glassur 87.68
san atap aluminium foil dobel sided 3,792.26
ank kayu Bengkirai 397.10

SUB JUMLAH - II
SUB TOTAL PEKERJAAN ATAP

JAAN PASANGAN DAN PLESTERAN

Batu Bata tb. 1/2 bata 1 PC : 3 Psr 276.08


Batu Bata tb. 1/2 bata 1 PC : 6 Psr 1,860.48
Roolag batu bata tb. 1/2 bata 1 PC : 3 Psr 139.26
teran 1 PC : 3 Psr tb. 1,5 cm 331.30
teran 1 PC : 6 Psr tb. 1,5 cm 3,720.96
nengan sudut 733.40
erjaan Acian 3,357.27

SUB TOTAL PEKERJAAN PASANGAN DAN PLESTERAN

RJAAN PENUTUP LANTAI DAN DINDING


an pasir bwh keramik t=5 cm 147.65
ai kerja bwh keramik t= 5 cm 147.65
Lantai Homogenous tile 60 x 60 cm 1,769.00
Lantai Homogenous tile 60 x 60 cm unpolish 1,121.38
Lantai tangga granit tile 60x60 cm lt 1 ke lt balkon 14.17
Lantai Homogenous tile 60 x 60 cm lantai balkon 260.45
Lantai Keramik uk. 20x20 cm 62.62
mik dinding 20/25 363.69

SUB TOTAL PEKERJAAN PENUTUP LANTAI DAN DIND

206
Pekerjaan Volume

ERJAAN KUSEN, PINTU, JENDELA DAN RAILING


erjaan pintu type PJ1 1.00
erjaan pintu type PJ2 1.00
erjaan pintu type PJ3 4.00
erjaan pintu type P1 1.00
erjaan pintu type P2 3.00
erjaan pintu type P3 1.00
erjaan pintu type PL 12.00
erjaan jendela type J1 7.00
erjaan jendela type J2 1.00
erjaan jendela type J3 1.00
erjaan jendela type J4 4.00
erjaan bouvent B1 4.00
erjaan bouvent B2 4.00
3.00
ng gate type FG 32 bh 201.22
ng tangga stainless steel Lt 01 s/d Lt 02 9.70
ng atap stainless steel 54.55

SUB TOTAL PEKERJAAN KUSEN, PINTU, JENDELA DAN

ERJAAN PLAFOND
Langit-langit Gypsum Board Tb. 9mm 1,857.07
ond spandex 804.35
Langit-langit calsiboard t=3,5 mm 560.80
363.00
Lis Langit-langit plafond gypsum profil 1,189.77

SUB TOTAL PEKERJAAN PLAFOND

ERJAAN CAT

catan dinding eksterior 1,175.04

207
Pekerjaan Volume

catan dinding interior 2,855.45

catan plafond 2,417.87

rproofing membran plat atap 215.58

SUB TOTAL PEKERJAAN CAT

ERJAAN SANITAIR
et duduk washdown+assesories 10.00
tafel+assesories 9.00
3.00
2.00
19.00
12.00
4.00
4.00

SUB TOTAL PEKERJAAN SANITAIR

ERJAAN LANSEKAP
ERJAAN PERKERASAN HALAMAN
an pasir bwh paving 251.00
ang paving blok 2,510.00
ang kanstin 305.16

SUB JUMLAH - I

ERJAAN SALURAN
134.45
10.00
angan batu kosong bwh bak kontrol 1.08
ran pipa PVC O 4" 71.85
beton penutup saluran t= 10cm
Beton K-225 4.10

208
Pekerjaan Volume

Besi tulangan polos 555.74

SUB JUMLAH - II

209
Pekerjaan Volume

ERJAAN TAMAN DAN VEGETASI


ang kanstin 305.16

n ketapang kencana, lingkar batang bawah + 20 cm, tinggi + 5 m, daun rimbun 18.00
anaman palm putri 12.00
anaman tanaman ornamen 4.00
anaman tanaman perdu berbunga 160.00
anaman rumput gajah mini beserta urugan tanah subur dan pemupukan 632.00

SUB JUMLAH - III

ERJAAN GROUNDTANK
13.82
ai kerja beton K-100 t= 5 cm 1.15
ai beton bertulang t= 20 cm
Beton K-225 1.15
Besi tulangan ulir 168.04
ing beton bertulang t- 20 cm
Beton K-225 4.22
Besi tulangan ulir 616.13
Begesting dinding 2x pakai 42.24
p beton bertulang t= 20 cm
Beton K-225 0.80
Besi tulangan 116.69
Begesting lantai 8.00
p manhole 1.00
angan keramik 40x40 cm 21.20

SUB JUMLAH - IV
SUB TOTAL PEKERJAAN LANSEKAP

ERJAAN PLUMBING
JAAN AIR BERSIH

210
Pekerjaan Volume

Water Tank Utama kap. 120 m3 1.00

ransfer dari Ground Water Utama menuju Roof tank : 1.00


: Centryfugal type
: 120 Liter/Menit
: 30 m

dengan Panel Control, WLC


gkabelan dari Panel ke Pompa
8.00

an, Pemasangan Roof Tank


: Tangki Fiber
: 3 x 2000 liter
dengan instalasi, WLC dan accessories lainnya
n Lengkap, accessories + Fitting
an dan pemasangan packaged booster pump 1.00

: Vertical inline multistage


: 200 Liter/Menit
: 30 m
dengan Panel Control, WLC
gkabelan dari Panel ke Pompa
Frame Stud Support Tanki Air Atas 1.00

der Roof Tank


10 : Dia. 4" (Lengkap dengan innstalasi) 1.00

sfer dari GWT


10 : Dia. 2" 35.00

n dari roof tank


22.00

5.00
5.00
30.00

211
Pekerjaan Volume

15.00
54.00
86.00
26.00

SUB JUMLAH - I

212
Pekerjaan Volume

AN AIR KOTOR DAN AIR BEKAS

air kotor & air bekas menuju bak penampung


AW dia 8" 86.00
86.00
6.00
ju IPAL Existing
100.00
1.00
mpit (transfer dari bak penampung ke ipal existing) 1.00
I DALAM GEDUNG

1.00

SUB JUMLAH - II

AN AIR HUJAN
air hujan dari roof tank
: Dia. 4" 40.00
: Dia. 4" 6.00

SUB JUMLAH - III


SUB TOTAL PEKERJAAN PLUMBING

ERJAAN ELEKTRIKAL
AN PASANG BARU 197 KVA
Penyambungan) 197,000.00
Jaminan Langganan) 197,000.00
1.00

197,000.00

213
Pekerjaan Volume

197,000.00
n Penyalaan 197,000.00

SUB JUMLAH - I

AN TRAFO
ator, kapasitas 250 kVA 1.00
sa / Freq : 3 Phasa / 50 Hz
er : 20 KV
under : 380 / 400 V
dingin : Olie ( ONAN )
ssories : DGPT2, Conservator, Elastimold
sportasi, akomodasi, pemasangan
1.00
1.00

SUB JUMLAH - II

JAAN GENSET
kapasitas 250 kVA,3,50 Hz,380V 1.00
ype, Stand by, Gen Set lengkap terpasang + Panel Kontrol Genset
ahan Body Genset dengan BC 50 mm2 1.00
ahan Netral Genset dengan BC 50 mm2 1.00
olar harian / BBM Kap.1.000 liter 1.00
an Elektrik & Manual Pump Solar 1.00
n ke Instansi terkait 1.00
ctric Pump c/w Panel Control 1.00
an Ducting Radiator System 1.00
Gas Buang Knalpot 1.00
proofing ruang genset, Rock Wall 80 Kg/m3 1.00
& Peralatan Bantu 1.00
500.00

214
Pekerjaan Volume

SUB JUMLAH - III

215
Pekerjaan Volume

JAAN PANEL TEGANGAN RENDAH


1.00
TOR BANK 12x25 KVAR 1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
ng elektrikal max 2 ohm (Trafo, Panel TM, LVMDP) 3.00
ng elektronika max 1 ohm 1.00

SUB JUMLAH - IV

JAAN KABEL FEEDER


ari LVMDP ke SDP-1 : 40.00
120mm2 + BC 95mm2
ari LVMDP ke SDP-2 : 40.00
120mm2 + BC 95mm2
ari LVMDP ke PP-POMPA : 22.00
6mm2 + BC 4mm2
ari LVMDP ke PP/LP-Power House : 15.00
4mm2 + BC 4mm2
ari SDP-1 ke PP/LP-1 : 10.00
10mm2 + BC 6mm2
16mm2 + BC 10mm2
ari SDP-1 ke PP/LP-4 : 25.00
16mm2 + BC 10mm2
ari SDP-1 ke PP-ATAP.1 : 30.00

216
Pekerjaan Volume

16mm2 + BC 10mm2
ari SDP-2 ke PP.AC-1 : 9.00
25mm2 + BC 16mm2
ari PP-ATAP.1 ke PC-BOSTER PUMP : 21.00
4mm2 + BC 4mm2
ari PP-ATAP.1 ke JET PUMP : 22.00
4mm2 + BC 4mm2

SUB JUMLAH - V

JAAN INSTALASI LISTRIK


aan ,pemasangan, kabel,konduit
ak,bobokan, penggantung, klem
e, perapihan, training dan tes commissioning

pu,kabel NYM 3x2,5mm2 dalam conduit 20mm2 133.00


p kontak,kabel NYM 3x2,5mm2 dalam conduit 20mm2 78.00
RM 300 TL Led 2x19 W ACR 38.00
RM 300 TL Led 2x10 W ACR 21.00
ght E27 Led 7 W 60.00
rcle E27 Led 7 W 14.00
ntak, 1ph. 16A 78.00
40.00
6.00
10.00
ay 400x100 mm berikut fitting, dan accessories lainnya 57.00
ay 300x100 mm berikut fitting, dan accessories lainnya 57.00

PJU Led 3x23 W tiang tinggi 9m, berikut pondasi dan accessories lainnya 6.00
talasi Lampu PJU NYFGbY 3x4 mm2 332.00

SUB JUMLAH - VI

217
Pekerjaan Volume

JAAAN PENANGKAL PETIR


minal Electro Static (non radio aktif), Radius Proteksi min 80 Meter, 3.00
iang dan accessories
tion Light led 5 w 3.00
strike counter 3.00
tor Cable, BC 50 mm2 dalam conduit 120.00
lamp, support dan accessories lainnya 1.00
ntrol berikut grounding max 1 ohm 3.00
1.00
1.00

SUB JUMLAH - VII


SUB TOTAL PEKERJAAN E

AAN ELEKTRONIKA
JAAN FIRE ALARM
aan dan pemasangan lengkap peralatan
i kabel, dudukan dan penggantung, training dan
mmissioning

ATAN UTAMA
Conventional ) 20 Zone c/w battery & charge 1.00
2.00

e alarm,kabel NYA 2x1.5mm2 + conduit 20 mm2 61.00


33.00
16.00
Push Button 3.00
3.00
3.00
3.00

218
Pekerjaan Volume

1.00
ari Terminal Box ke MDF 1.00

SUB JUMLAH - I

JAAN TELEPON & WIFI


aan dan pemasangan lengkap peralatan
i kabel, dudukan dan penggantung, training dan
mmissioning

ATAN UTAMA
1-8 line 104 ext berikut setting, accessories lainnya 1.00
mbungan telephone 1.00
1.00

ephone,kabel UTP cat 6 + pipa conduit 20mm2 20.00


i,kabel UTP cat 6 + pipa conduit 20mm2 7.00
outlet telepon 20.00
7.00
1.00

SUB JUMLAH - II

JAAN CCTV
aan dan pemasangan lengkap peralatan
i kabel, dudukan dan penggantung, training dan
mmissioning

ATAN UTAMA
Chanel (central cctv) 3.00
3.00
r CCTV berikut intslasi dan material bantu 1.00

219
Pekerjaan Volume

Dome Colour Camera 7.00


si Audio, Video, & Power dalam Konduit yang Terpisah 7.00

SUB JUMLAH - III

220
Pekerjaan Volume

JAAN TATA SUARA


aan dan pemasangan lengkap peralatan
i kabel, dudukan dan penggantung, training dan
mmissioning

ATAN UTAMA
C/USB player 1.00
1.00
Microphone 2.00
1.00
re Amplifier 1.00
me speaker 2.00
amplifier 240 W 5.00
r Selector 1.00
ency massage (evac mix) 1.00

speaker 6 W 12.00
Control 3 - 6 W 1.00
si speaker kabel NYMHY 3x1.5mm2 dalam pipa conduit 20 mm2 12.00
1.00
ari terminal box ke central terminal box NYM 3x2.5mm2 dalam pipa conduit 20mm2 12.00

SUB JUMLAH - IV

JAAN MATV
aan dan pemasangan lengkap peralatan
i kabel, dudukan dan penggantung, training dan
mmissioning

ATAN UTAMA
bola 16 Feet, Lengkap dengan Dudukan 1.00

221
Pekerjaan Volume

na Yagi ( UHF ) Termasuk Tiang 2.00


4.00
nnel Amplifier (10 chanel) 2.00
8.00
8.00
sive Combiner 3.00
1.00
1.00
lasi + Material Bantu 1.00
ATAN UTAMA TV BERLANGGANAN
bola , Lengkap dengan Dudukan, receiver, modulator dan accessories. 1.00

1.00
el Tuvur, Coaxial RG 6 dalam conduit 20 mm2 10.00
2.00
8.00
Instalasi Outlet TV Coaxial RG 6 dalam pipa conduit 20 mm2 8.00

SUB JUMLAH - V

222
Pekerjaan Volume

daan dan pemasangan air conditioning (AC) lengkap dengan


abel daya, refrigerant berisolasi, pipa kondensat
rlengkapannya beserta pengetesan sistem dan instalasi.

an Unit AC / Digital Scroll system, termasuk dudukan Unit dan remote wireless
Unit , Cassette type kap : 19,100 BTU/h 1.00
Unit IU, Wall type kap : 9,600 BTU/h 6.00

an Refrigrant berisolasi
88.00
45.00
38.00
35.00
an Drain / PVC AW berisolasi 1.00
1.00

7.00
14.00
talasi daya AC
ower indoor 37.00
ower outdoor 2.00
and Commisioning 1.00

SUB JUMLAH - V.
SUB TOTAL PEKERJAAN E

223
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

Ls - -
Ls - -
Ls - -
Ls - -

AAN PERSIAPAN -

m3 A.2.3.1.1-KBPKL 56,005.00 37,195,160.70


m3 A.2.3.1.9-KBPKL 18,434.50 1,345,534.16
m3 A.2.3.1.11-KBPKL 208,322.50 46,630,908.40
m3 A.2.3.1.14-KBPKL 105,052.50 403,286,042.25

488,457,645.51

m' 270,000.00 686,880,000.00


ls 15,000,000.00 15,000,000.00
ttk 35,000.00 16,380,000.00
m3 A.4.1.1.9 808,888.96 8,582,311.87
-
M3 A.4.1.1.12.3-KBPKL 1,191,415.05 114,375,844.80
Kg A.4.1.1.17-KBPKL 13,680.40 82,565,728.53
M2 A.4.1.1.20-KBPKL 147,464.50 29,445,711.36
-
-

224
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
M3 A.4.1.1.12.3-KBPKL 1,191,415.05 29,773,462.10
Kg A.4.1.1.17-KBPKL 13,680.40 29,975,398.05
M2 A.4.1.1.20-KBPKL 147,464.50 10,539,287.82
-
-
M3 A.4.1.1.12.3-KBPKL 1,191,415.05 16,751,295.60
Kg A.4.1.1.17-KBPKL 13,680.40 17,850,733.14
M2 A.4.1.1.20-KBPKL 147,464.50 6,634,427.86
-
-
M3 A.4.1.1.12.3-KBPKL 1,191,415.05 28,593,961.20
Kg A.4.1.1.17-KBPKL 13,680.40 30,865,308.07
M2 A.4.1.1.20-KBPKL 147,464.50 14,156,592.00

1,138,370,062.40

m3 A.3.2.1.4 789,463.50 200,136,891.89


m3 A.3.2.1.9-KBPKL 404,995.50 37,336,535.15

237,473,427.04

RJAAN TIANG PANCANG DAN PILE CAP 1864301134.95

m3 A.4.1.1.4 919,187.07 5,561,081.77

M3 A.4.1.1.8 1,191,415.05 64,622,352.31


Kg A.4.1.1.17-KBPKL 13,680.40 118,804,150.50
M2 A.4.1.1.21.1-KBPKL 91,862.00 33,233,834.36

M3 A.4.1.1.12.1-KBPKL 1,191,415.05 26,806,838.63


Kg A.4.1.1.21.1-KBPKL 13,680.40 65,665,783.20

225
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
M2 A.4.1.1.21.1-KBPKL 91,862.00 20,668,950.00

226
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

M3 A.4.1.1.8 1,191,415.05 8,149,278.94


Kg A.4.1.1.17-KBPKL 13,680.40 15,514,531.23
M2 A.4.1.1.21.1-KBPKL 91,862.00 8,375,977.16

M3 A.4.1.1.8 1,191,415.05 115,293,234.39


Kg A.4.1.1.17-KBPKL 13,680.40 258,141,486.98
M2 A.4.1.1.22.2.1-KBPKL 118,450.00 76,414,464.00

M3 A.4.1.1.8 1,191,415.05 3,657,644.20


Kg A.4.1.1.17-KBPKL 13,680.40 13,291,329.42
M2 A.4.1.1.22.2.1-KBPKL 118,450.00 3,638,784.00

M3 A.4.1.1.8 1,191,415.05 3,657,644.20


Kg A.4.1.1.17-KBPKL 13,680.40 13,291,329.42
M2 A.4.1.1.22.2.1-KBPKL 118,450.00 3,638,784.00

-
M3 A.4.1.1.8 1,191,415.05 6,111,959.21
Kg A.4.1.1.17-KBPKL 13,680.40 10,519,953.99
M2 A.4.1.1.26-KBPKL 135,297.50 6,936,702.83

m' A.4.1.1.35 61,694.16 20,729,237.76

M3 A.4.1.1.8 1,191,415.05 976,960.34


Kg A.4.1.1.17-KBPKL 13,680.40 1,965,189.46
M2 A.4.1.1.23.2-KBPKL 188,830.00 1,574,842.20
-

227
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
m' A.4.1.1.36 83,621.18 5,226,323.75
-
m' A.4.1.1.35 61,694.16 1,258,560.86
-

M3 A.4.1.1.8 1,191,415.05 12,986,424.05


Kg A.4.1.1.17-KBPKL 13,680.40 20,217,168.73
M2 A.4.1.1.24.2-KBPKL 211,427.50 23,037,140.40
-

M3 A.4.1.1.8 1,191,415.05 1,322,470.71


Kg A.4.1.1.17-KBPKL 13,680.40 2,059,584.22
M2 A.4.1.1.23.2-KBPKL 152,030.00 3,375,066.00

-
M3 A.4.1.1.8 1,191,415.05 16,501,098.44
Kg A.4.1.1.17-KBPKL 13,680.40 57,485,861.62
M2 A.4.1.1.23.2-KBPKL 152,030.00 17,270,608.00
-

M3 A.4.1.1.8 1,191,415.05 35,158,658.13


Kg A.4.1.1.17-KBPKL 13,680.40 123,725,263.99
M2 A.4.1.1.23.2-KBPKL 152,030.00 38,875,591.30

M3 A.4.1.1.8 1,191,415.05 4,265,265.88


Kg A.4.1.1.17-KBPKL 13,680.40 14,852,263.06
M2 A.4.1.1.23.2-KBPKL 152,030.00 6,531,208.80

M3 A.4.1.1.8 1,191,415.05 5,134,998.87


Kg A.4.1.1.17-KBPKL 13,680.40 16,922,518.00
M2 A.4.1.1.23.2-KBPKL 152,030.00 6,544,891.50

228
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

M3 A.4.1.1.8 1,191,415.05 3,216,820.64


Kg A.4.1.1.17-KBPKL 13,680.40 10,970,859.98
M2 A.4.1.1.23.2-KBPKL 152,030.00 3,420,675.00

m' A.4.1.1.36 83,621.18 6,321,761.21

229
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
-

M3 A.4.1.1.8 1,191,415.05 38,887,787.23


Kg A.4.1.1.17-KBPKL 13,680.40 101,098,292.80
M2 A.4.1.1.23.2-KBPKL 152,030.00 33,081,728.00

M3 A.4.1.1.8 1,191,415.05 20,730,621.87


Kg A.4.1.1.17-KBPKL 13,680.40 60,559,300.29
M2 A.4.1.1.23.2-KBPKL 152,030.00 22,926,124.00

m' A.4.1.1.36 83,621.18 4,636,794.43

-
M3 A.4.1.1.8 1,191,415.05 109,348,073.29
Kg A.4.1.1.17-KBPKL 13,680.40 180,620,132.34
M2 A.4.1.1.24.2-KBPKL 211,427.50 161,710,323.38

RJAAN BETON 2,077,522,585.27

-
kg A.4.2.1.2 25,236.75 574,885,341.61
kg A.4.2.1.2 25,236.75 646,960,490.14
kg A.4.2.1.2 25,236.75 36,338,396.33
kg A.4.2.1.2 25,236.75 31,391,236.22
kg A.4.2.1.2 25,236.75 4,429,049.63
kg A.4.2.1.2 25,236.75 7,931,658.16
bh A.4.2.1.2 25,236.75 10,902,276.00
bh 50,000.00 5,200,000.00

1,318,038,448.09

230
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

-
m2 A.4.5.2.3 182,154.25 690,776,276.11
m2 A.4.5.2.4 217,879.00 19,103,630.72
m2 A.4.5.2.42 27,904.75 105,822,067.24
m' A.4.6.1.22.1-KBPKL 182,907.50 72,632,568.25

888,334,542.32

AAN ATAP 2,206,372,990.41

m2 A.4.4.1.8 127,298.10 35,144,459.45


m2 A.4.4.1.11 121,433.10 225,923,853.89
m2 A.4.4.1.8 127,298.10 17,727,533.41
m2 A,4,4,2.3-KBPKL 49,738.88 16,478,490.94
m2 A,4,4,2.6-KBPKL 46,206.08 171,930,975.44
m' A,4,4,2.20-KBPKL 28,612.00 20,984,040.80
m2 A,4,4,2.27-KBPKL 26,933.00 90,421,352.91

AAN PASANGAN DAN PLESTERAN 578,610,706.84

m3 A.2.3.1.11-KBPKL 208,322.50 30,758,817.13


m3 A.4.1.1.4 919,187.07 135,717,970.89
m2 A.4.4.3.35.9-KBPKL 324,377.92 573,824,540.48
m2 A.4.4.3.35.9-KBPKL 324,377.92 363,750,911.93
m2 A.4.4.3.35.9-KBPKL 324,377.92 4,596,435.13
m2 A.4.4.3.35.9-KBPKL 324,377.92 84,484,229.26
m2 A.4.4.3.36.2-KBPKL 126,999.56 7,952,712.45
m2 A.4.4.3.50-KBPKL 125,918.56 45,795,321.09
-

AAN PENUTUP LANTAI DAN DINDING 1,246,880,938.36

231
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

unit 31,950,000.00 31,950,000.00


unit 31,950,000.00 31,950,000.00
unit 19,170,000.00 76,680,000.00
unit 11,182,500.00 11,182,500.00
unit 4,676,203.34 14,028,610.02
unit 4,676,203.34 4,676,203.34
unit 2,907,293.07 34,887,516.84
unit 4,685,989.01 32,801,923.07
unit 2,243,809.80 2,243,809.80
unit 3,748,791.21 3,748,791.21
unit 4,217,390.11 16,869,560.44
unit 571,380.58 2,285,522.32
unit 475,074.45 1,900,297.80
unit 13,662,000.00 40,986,000.00
m2 A.4.2.1.8 600,737.00 120,880,299.14
m' 750,000.00 7,275,000.00
m' 750,000.00 40,912,500.00
-

AAN KUSEN, PINTU, JENDELA DAN RAILING 475,258,533.98

m2 A.4.5.1.7.2-KBPKL 179,865.75 334,023,288.35


m2 140,000.00 112,609,000.00
m2 A.4.5.1.7.3-KBPKL 184,051.75 103,216,221.40
m' 110,000.00 39,930,000.00
m' A.4.5.1.11-KBPKL 25,323.00 30,128,545.71

AAN PLAFOND 619,907,055.46

m2 A.4.7.1.10.3-KBPKL 34,270.00 40,268,620.80

232
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
m2 A.4.7.1.10.1-KBPKL 22,011.00 62,851,309.95
m2 A.4.7.1.11.3-KBPKL 19,046.30 46,051,477.38
A.4.7.1.11.6-KBPKL 63,451.25 13,678,820.48

162,850,228.61

bh A.5.1.1.1.2-KBPKL 2,713,885.00 27,138,850.00


bh A.5.1.1.5-KBPKL 555,105.00 4,995,945.00
bh A.5.1.1.4-KBPKL 615,077.50 1,845,232.50
bh 300,000.00 600,000.00
bh A.5.1.1.19 71,484.00 1,358,196.00
bh A.5.1.1.14 40,422.50 485,070.00
bh A.5.1.1.12 391,517.50 1,566,070.00
bh 250,000.00 1,000,000.00

AAN SANITAIR 38,989,363.50

m3 A.2.3.1.11-KBPKL 29,670.00 7,447,170.00


m2 A.4.4.3.64.8-KBPKL 162,118.92 406,918,489.20
m' A.4.4.3.64.12-KBPKL 120,113.74 36,653,908.90

451,019,568.10

m' A.9.1.1.8-KBPKL 130,472.92 17,542,084.09


bh A.5.1.1.15 417,438.50 4,174,385.00
m3 A.3.2.1.9-KBPKL 404995.5 437,395.14
m' A.5.1.1.32 104,233.13 7,489,150.39
-
m3 A.4.1.1.7 1,107,216.38 4,539,587.16

233
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
kg A.4.1.1.17-KBPKL 13,680.40 7,602,745.50

41,785,347.28

234
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

m' 65,000.00 19,835,400.00


bh 850,000.00 15,300,000.00
bh 450,000.00 5,400,000.00
bh 550,000.00 2,200,000.00
bh 10,000.00 1,600,000.00
m2 45,000.00 28,440,000.00

72,775,400.00

m3 A.2.3.1.1-KBPKL 56,005.00 773,989.10


m3 A.4.1.1.4 919,187.07 1,057,065.13
-
m3 A.4.1.1.7 1,107,216.38 1,273,298.84
kg A.4.1.1.17-KBPKL 13,680.40 2,298,854.42
-
m3 A.4.1.1.10 1,154,746.90 4,873,031.92
kg A.4.1.1.20-KBPKL 13,680.40 8,428,904.85
m2 A.4.1.1.25-KBPKL 198,030.00 8,364,787.20
-
m3 A.4.1.1.12.2-KBPKL 1,233,700.51 986,960.41
kg A.4.1.1.22.2-KBPKL 13,680.40 1,596,365.88
m2 A.4.1.1.24.2-KBPKL 211,427.50 1,691,420.00
bh 500,000.00 500,000.00
m2 A.4.4.3.35.6-KBPKL 122,575.92 2,598,609.50

34,443,287.25

AAN LANSEKAP 600,023,602.63

235
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

unit
unit 8,600,000.00 8,600,000.00
-
-
-
-
-
unit 1,750,000.00 14,000,000.00
-
-
-
-
-
set 12,000,000.00 12,000,000.00
-
-
-
-
-
ls 1,250,000.00 1,250,000.00
-
bh 1,435,500.00 1,435,500.00
-
m 105,000.00 3,675,000.00
-
m 36,000.00 792,000.00
-
-
m 206,000.00 1,030,000.00
m 146,000.00 730,000.00
m 105,000.00 3,150,000.00

236
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
m 67,000.00 1,005,000.00
m 33,000.00 1,782,000.00
m 23,000.00 1,978,000.00
m 19,000.00 494,000.00

51,921,500.00

237
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

m 219,000.00 18,834,000.00
m 125,000.00 10,750,000.00
bh 535,000.00 3,210,000.00
-
m 70,000.00 7,000,000.00
bh 2,500,000.00 2,500,000.00
unit 6,800,000.00 6,800,000.00
-
-
unit 650,000.00 650,000.00
-

49,744,000.00

m 70,000.00 2,800,000.00
bh 225,000.00 1,350,000.00

4,150,000.00

AAN PLUMBING 105,815,500.00

va 631.00 124,307,000.00
va 225.00 44,325,000.00
bh 6,000.00 6,000.00
-
va 35.00 6,895,000.00

238
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
va 33.00 6,501,000.00
va 25.00 4,925,000.00

186,959,000.00

unit 50,025,000.00 50,025,000.00

titik 3,500,000.00 3,500,000.00


ls 1,500,000.00 1,500,000.00

55,025,000.00

unit 518,656,128.00 518,656,128.00


-
titik 3,500,000.00 3,500,000.00
titik 3,500,000.00 3,500,000.00
unit 11,357,000.00 11,357,000.00
unit 4,500,000.00 4,500,000.00
lot 4,000,000.00 4,000,000.00
unit 10,000,000.00 10,000,000.00
lot 9,000,000.00 9,000,000.00
lot 7,500,000.00 7,500,000.00
ls 5,000,000.00 5,000,000.00
ls 11,671,400.00 11,671,400.00
Liter 10,000.00 5,000,000.00

239
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
593,684,528.00

240
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

buah 47,838,000.00 47,838,000.00


buah 35,617,500.00 35,617,500.00
buah 10,430,000.00 10,430,000.00
buah 7,739,000.00 7,739,000.00
buah 5,960,000.00 5,960,000.00
buah 8,107,000.00 8,107,000.00
buah 9,620,000.00 9,620,000.00
buah 9,620,000.00 9,620,000.00
buah 7,386,000.00 7,386,000.00
buah 7,356,000.00 7,356,000.00
buah 7,356,000.00 7,356,000.00
titik 6,000,000.00 18,000,000.00
titik 6,000,000.00 6,000,000.00

181,029,500.00

m 781,000.00 31,240,000.00
-
m 781,000.00 31,240,000.00
-
m 53,000.00 1,166,000.00
-
m 41,000.00 615,000.00
-
m 82,000.00 820,000.00
-
-
m 112,000.00 2,800,000.00
-
m 112,000.00 3,360,000.00

241
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
-
m 125,000.00 1,125,000.00
-
m 41,000.00 861,000.00
-
m 38,000.00 836,000.00

74,063,000.00

titik 251,000.00 33,383,000.00


titik 315,000.00 24,570,000.00
buah 2,423,250.00 92,083,500.00
buah 1,758,000.00 36,918,000.00
buah 439,000.00 26,340,000.00
buah 738,000.00 10,332,000.00
buah 54,000.00 4,212,000.00
buah 30,000.00 1,200,000.00
buah 42,000.00 252,000.00
buah 34,000.00 340,000.00
m 399,000.00 22,743,000.00
m 339,750.00 19,365,750.00
-
buah 14,678,000.00 88,068,000.00
m 40,000.00 13,280,000.00

373,087,250.00

242
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

unit 12,500,000.00 37,500,000.00


-
bh 3,754,300.00 11,262,900.00
bh 2,750,000.00 8,250,000.00
m 96,600.00 11,592,000.00
ls 4,000,000.00 4,000,000.00
set 1,250,000.00 3,750,000.00
ls 2,000,000.00 2,000,000.00
ls 5,000,000.00 5,000,000.00

83,354,900.00
PEKERJAAN ELEKTRIKAL 1,547,203,178.00

-
-

bh 27,319,000.00 27,319,000.00
bh 8,069,000.00 16,138,000.00
-
-
titik 199,000.00 12,139,000.00
bh 293,000.00 9,669,000.00
bh 878,000.00 14,048,000.00
bh 493,000.00 1,479,000.00
bh 339,000.00 1,017,000.00
bh 216,000.00 648,000.00
bh 108,000.00 324,000.00

243
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
bh 807,000.00 807,000.00
ls 2,500,000.00 2,500,000.00
-
86,088,000.00

-
-

unit 34,430,000.00 34,430,000.00


ls 10,000,000.00 10,000,000.00
unit by owner -
-
titik 421,000.00 8,420,000.00
titik 421,000.00 2,947,000.00
bh 76,000.00 1,520,000.00
bh 842,000.00 5,894,000.00
bh 807,000.00 807,000.00

64,018,000.00

-
-

unit 42,626,000.00 127,878,000.00


unit 6,529,000.00 19,587,000.00
ls 4,419,000.00 4,419,000.00
-

244
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
bh 8,161,000.00 57,127,000.00
titik 1,046,000.00 7,322,000.00

216,333,000.00

245
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

-
-

buah 3,279,600.00 3,279,600.00


buah 5,320,000.00 5,320,000.00
buah 6,030,450.00 12,060,900.00
lot 18,374,400.00 18,374,400.00
set 24,518,700.00 24,518,700.00
buah 694,000.00 1,388,000.00
buah 3,750,000.00 18,750,000.00
buah 3,600,000.00 3,600,000.00
buah 7,286,400.00 7,286,400.00
-
buah 112,000.00 1,344,000.00
buah 146,500.00 146,500.00
titik 230,000.00 2,760,000.00
unit 807,000.00 807,000.00
m 104,001.50 1,248,018.00
-

100,883,518.00

-
-

Unit 1,750,000.00 1,750,000.00

246
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp
Buah 500,000.00 1,000,000.00
Buah 355,000.00 1,420,000.00
Buah 475,000.00 950,000.00
Buah 2,100,000.00 16,800,000.00
Buah 2,150,000.00 17,200,000.00
Buah 2,250,000.00 6,750,000.00
Unit 2,500,000.00 2,500,000.00
Unit 1,750,000.00 1,750,000.00
Ls 2,000,000.00 2,000,000.00
-
Ls By owner -
-
buah 275,000.00 275,000.00
m 15,000.00 150,000.00
buah 225,000.00 450,000.00
buah 80,000.00 640,000.00
titik 215,000.00 1,720,000.00
-

247
Harga Jumlah
Sat Kode Analisa Satuan Harga
Rp Rp

-
-

-
Unit 9,268,400.00 9,268,400.00
Unit 4,284,000.00 25,704,000.00
-
-
m 21,120.00 1,858,560.00
m 38,120.69 1,715,431.05
m 53,103.45 2,017,931.10
m 82,133.33 2,874,666.55
ls 2,000,000.00 2,000,000.00
bh 3,538,283.26 3,538,283.26
-
bh 798,000.00 5,586,000.00
bh 364,000.00 5,096,000.00
-
titik 250,000.00 9,250,000.00
titik 680,000.00 1,360,000.00
lot 15,000,000.00 15,000,000.00

85,269,271.96
PEKERJAAN ELEKTRONIKA 580,269,289.96

248
JUMLAH TOTAL
HARGA SATUAN
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)

V PEKERJAAN RUMAH POWER HOUSE & GROUND WATER TANK

I PEKERJAAN TANAH
1 Galian Tanah 236.00 m3 62,962.50 14,859,150.00
2 Urugan Tanah Kembali 78.67 m3 18,434.50 1,450,242.11
3 Buangan tanah sisa galian 157.34 m3 27,600.00 4,342,584.00
4 Urugan Pasir 11.73 m3 208,322.50 2,443,622.92
5 Urugan Sirtu 9.55 m3 211,485.00 2,019,681.75

Sub Total 25,115,280.78

II PEKERJAAN BETON BERTULANG


1 Lantai Kerja Beton K-100 3.16 m3 981,676.98 3,102,099.25
2 Rabat Beton Lantai K-100 5.80 m3 919,187.07 5,331,285.00
3 Beton Pondasi Foot Plat K-250
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 0.64 m3 1,121,700.88 717,888.56
- Pembesian 108.31 kg 13,680.40 1,481,724.12
- Bekisting 3.20 m2 147,464.50 471,886.40
4 Beton Sloof K-250 type S1 40x30
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 1.20 m3 1,121,700.88 1,346,041.05
- Pembesian 131.22 kg 13,680.40 1,795,142.08
- Bekisting 6.00 m2 123,314.50 739,887.00
5 Beton Sloof K-250 type S2 15x20
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 0.60 m3 1,121,700.88 673,020.52
- Pembesian 108.95 kg 13,680.40 1,490,479.58
- Bekisting 8.00 m2 123,314.50 986,516.00
6 Beton Kolom K-250 type K 30x40
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 3.26 m3 1,121,700.88 3,656,744.86
- Pembesian 447.37 kg 13,680.40 6,120,200.54
- Bekisting 38.03 m2 162,380.00 6,175,311.40
7 Beton Kolom K-250type K 20x20
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 0.46 m3 1,121,700.88 515,982.40
- Pembesian 96.54 kg 13,680.40 1,320,705.81
- Bekisting 9.20 m2 162,380.00 1,493,896.00
8 Beton Kolom K-50 type K 30x40 GWT
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 2.05 m3 1,121,700.88 2,299,486.80
- Pembesian 376.11 kg 13,680.40 5,145,335.24
- Bekisting 23.92 m2 162,380.00 3,884,129.60
9 Beton Kolom K-250 type K 25x30 GWT
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 0.43 m3 1,121,700.88 482,331.37
- Pembesian 81.08 kg 13,680.40 1,109,206.83
- Bekisting 6.31 m2 162,380.00 1,024,617.80
10 Beton Balok K-250 type BU 20x40 (Atap)
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 2.56 m3 1,121,700.88 2,871,554.25
- Pembesian 539.00 kg 13,680.40 7,373,735.60
- Bekisting 32.00 m2 188,830.00 6,042,560.00
11 Beton Balok K-250 type BP 20x30 (Atap)
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 2.70 m3 1,121,700.88 3,028,592.37
- Pembesian 473.77 kg 13,680.40 6,481,363.10
- Bekisting 36.00 m2 188,830.00 6,797,880.00
12 Beton Plat Dak Atap K-275 tebal 10 cm
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 10.06 m3 1,121,700.88 11,284,310.85
- Pembesian 1339.63 kg 13,680.40 18,326,674.25
- Bekisting 100.60 m2 205,505.00 20,673,803.00
13 Beton K-250 Listplank
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 1.47 m3 1,121,700.88 1,648,900.29
- Pembesian 123.85 kg 13,680.40 1,694,317.54
- Bekisting 38.22 m2 102,752.50 3,927,200.55
14 Beton Balok K-250 type 30x40 (GWT)
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 3.60 m3 1,121,700.88 4,038,123.16
- Pembesian 583.87 kg 13,680.40 7,987,575.14
- Bekisting 33.00 m2 188,830.00 6,231,390.00
15 Beton Balok K-250 type 25x40 (GWT)
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 0.60 m3 1,121,700.88 673,020.52
- Pembesian 84.69 kg 13,680.40 1,158,593.07
- Bekisting 6.30 m2 188,830.00 1,189,629.00
16 Beton Plat Lantai Dasar K-250 tebal 25 cm (GWT)
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 12.25 m3 1,121,700.88 13,740,835.78
- Pembesian 2227.21 kg 13,680.40 30,469,123.68
- Bekisting 0.57 m2 147,464.50 84,054.76
17 Beton Dinding K-250 (GWT)
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 9.00 m3 1,121,700.88 10,095,307.92
- Pembesian 2037.93 kg 13,680.40 27,879,697.57
- Bekisting 120.00 m2 198,030.00 23,763,600.00
18 Beton Plat Tutup K-250 tebal 15 cm (GWT)
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 5.33 m3 1,121,700.88 5,978,665.69
- Pembesian 1615.11 kg 13,680.40 22,095,350.84
- Bekisting 35.53 m2 205,505.00 7,301,592.65

Page 249
19 Beton Plat Lantai Dudukan Genset K-300 tebal 20 cm
- Beton K-300 0.95 m3 1,154,746.90 1,097,009.55
- Pembesian 60.72 kg 13,680.40 830,673.88
- Bekisting 1.85 m2 147,464.50 272,809.32
20 Waterproofing membrane untuk GWT 86.07 m2 100,000.00 8,607,000.00
21 Waterproofing membrane untuk Dak atap + screed 2 cm 122.13 m2 179,115.74 21,875,405.32

Sub Total 336,884,267.86

III PEKERJAAN PASANGAN


1 Aanstampeng 6.00 m3 404,995.50 2,429,973.00
2 Pasangan Batu Belah 1 Pc : 5 Ps 14.65 m3 810,991.50 11,881,025.47
3 Pasangan dinding batu bata 1/2 batu 1 Pc : 5 Ps 215.54 m2 122,205.90 26,340,259.68
4 Plesteran dinding batu bata 1 Pc : 5 Ps 348.52 m2 46,989.92 16,376,926.91
5 Plesteran beton 1 Pc : 3 Ps 117.58 m2 49,738.88 5,848,297.51
6 Acian 466.10 m2 26,933.00 12,553,471.30
7 Sponengan Sudut 1 Pc : 3 Ps 654.05 m' 28,612.00 18,713,678.60
8 Kolom praktis 11x11 71.25 m' 81,664.99 5,818,630.53
9 Balok latiu 10x15 31.00 m' 99,388.81 3,081,053.11

Sub Total 103,043,316.11

IV PEKERJAAN KUSEN PINTU & JENDELA


1 Pintu PD1 1.00 bh 3,400,000.00 3,400,000.00
2 Pintu PD2 1.00 bh 4,412,500.00 4,412,500.00
3 Pintu PD3 1.00 bh 3,912,500.00 3,912,500.00
4 Jendela BVJ1 1.00 bh 1,725,000.00 1,725,000.00
5 Jendela BVJ2 2.00 bh 1,212,500.00 2,425,000.00
6 Jendela BVK 1.00 bh 1,912,500.00 1,912,500.00
7 Tutup GWT 1.00 bh 1,012,500.00 1,012,500.00

Sub Total 18,800,000.00

V PEKERJAAN PLAFOND
1 Pasang Plafond Beton Expose 100.64 m2 175,000.00 17,612,000.00

Sub Total 17,612,000.00

VI PEKERJAAN PENGECATAN
1 Cat Dinding 466.10 m2 34,270.00 15,973,247.00
2 Cat Plafond 100.64 m2 19,046.30 1,916,819.63

Sub Total 17,890,066.63

VII PEKERJAAN MEKANIKAL ELEKTRIKAL


1 Titik lampu,kabel NYM 3x2,5mm2 dalam conduit 20mm2 6.00 titik 235,000.00 1,410,000.00
2 Titik stop kontak,kabel NYM 3x2,5mm2 dalam conduit 20mm2 4.00 titik 250,000.00 1,000,000.00
3 Lampu TL Balk 1x18 Watt 6.00 buah 250,000.00 1,500,000.00
4 Stop kontak, 1ph. 16A 4.00 buah 21,500.00 86,000.00
5 Saklar tunggal 3.00 buah 25,000.00 75,000.00
6 Panel Penerangan 1.00 unit 500,000.00 500,000.00
7 Exhaust fan 200 cfm 6.00 buah 850,000.00 5,100,000.00
8 Roof Drain 8.00 buah 225,000.00 1,800,000.00
9 Pipa PVC 3" Torong talang 4.80 m' 60,000.00 288,000.00
10 Pipa PVC 4" Sparing Kabel 2.40 m' 69,000.00 165,600.00
11 Saluran Keliling U-20 33.82 m' 368,277.29 12,455,137.94
12 Saluran Keliling Buis beton O-20 17.03 m' 230,808.59 3,930,670.28
13 Bak Kontrol 5.00 bh 371,993.71 1,859,968.55

Sub Total 30,170,376.77

VIII PEKERJAAN LAIN-LAIN


1 Pagar BRC pada R. Trafo 3.00 m' 250,000.00 750,000.00
2 Pintu BRC pada R. Trafo 1.00 unit 2,220,000.00 2,220,000.00
3 Tutup Besi siku & plat bordes (saluran tempat intalasi kabel) 14.88 m2 850,000.00 12,648,000.00
4 Tangga Pipa GIP 1" 7.00 bh 150,525.00 1,053,675.00

Sub Total 16,671,675.00

JUMLAH TOTAL 566,186,983

Page 250
NO URAIAN PEKERAJAAN

VI PEKERJAAN TOWER AIR


1 Galian Tanah pondasi
2 Lantai kerja bwh pile cap t= 7 cm
3 Pondasi sumuran O 80
- Beton cyclop
- Besi tulangan
- Buis beton O 80
4 Beton bertulang pondasi plat 500x500 cm
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58
- Besi tulangan
- Begesting
5 Beton bertulang sloof 20/40
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58
- Besi tulangan
- Begesting
6 Beton bertulang kolom 50/50
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58
- Besi tulangan
- Begesting
6 Beton bertulang balok ring BR2 25/40
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58
- Besi tulangan
- Begesting
7 Beton bertulang plat elv. +4.60 t= 12 cm
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58
- Besi tulangan
- Begesting
7 Beton bertulang balok atap B1 30/75
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58
- Besi tulangan
- Begesting
8 Beton bertulang balok atap BR1 20/50
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58

251
- Besi tulangan
- Begesting
8 Beton bertulang balok atap BC 30x50/75
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58
- Besi tulangan
- Begesting
8 Beton bertulang plat lantai el. + 12.60 t= 14 cm
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58
- Besi tulangan
- Begesting
9 Pasangan batu bata 1Pc:6Ps
10 Plesteran 1Pc:6Ps
11 Acian
12 Tangga besi
13 Tandon air kap 8 m3
14 Besi hollow 40x40x1,2 mm
15 Wiremesh M6

SUB JUMLAH - VI

VII PEKERJAAN SUMUR DALAM


1 persiapan
- Mobilisasi/Demobilisasi
- Persiapan lapangan, rigging up dll
- Pembuatan spull bak dan kanal

2 Pekerjaan Pemboran Sumur


Pengeboran lubang pandu 6" sedalam 120 meter
- dari 0 meter s/d 50 meter
- dari 50 meter s/d 100 meter
- dari 110 meter s/d 120 meter

252
3 Bore hole logging
Reaming hole dia. 6" ke dia. 8"
- dari 0 meter s/d 50 meter
- dari 50 meter s/d 100 meter
- dari 110 meter s/d 120 meter

4 Pengadaan dan pemasangan pipa konstruksi


- Pipa jambang dan pipa naik GIP medium A dia. 4"
- Saringan (Screen) stainless steel dia. 4" (sesuai logging)
- Cone bottom
- Well cover / tutup sumur
- Gate valve dia. 2"
- Check valve dia. 2"
- Air valve
- Manometer

5 Penyempurnaan sumur
- Gravel Pack 2 mm - 10 mm dia. 2"
- Graouting 1 pc : 1 ps
- Development / pencucian sumur
- Apron beton 1 : 3 : 5
Pumping test
Analisa air

6 Pengadaan dan pemasangan pompa dan panel


- Pompa Submersible 1,5 KW, 220 Volt, 1 Phase, Head 67 m, Q = 5 m3/jam
- Panel pompa 1,5 KW, 220 Volt, 1 Phase, Double WLC
- Kabel pompa NYY 3x2,5 mm2
- Kabel WLC NYYHY 3x1,5 mm2
- Elektroda massa
- Pipa hisap GIP medium A dia. 2"
Bak pelindung sumur
Laporan akhir pengeboran dan dokumentasi
7 Test dan comissioning
8 Penyelidikan mata air geo listrik

253
SUB JUMLAH - VII

254
harga satuan JUMLAH TOTAL
VOLUME SAT (RP) HARGA SATUAN HARGA SATUAN
(RP) (RP)

35.55 m3 62,962.50 2,238,316.87


1.82 m3 981,676.98 1,786,652.10

7.54 m3 603,164.00 4,547,856.56


781.02 kg 13,680.40 10,684,666.00
5.00 bh 143,000.00 715,000.00

25.00 m3 1,121,700.88 28,042,522.00


3,520.95 kg 13,680.40 48,168,004.38
20.00 m2 147,464.50 2,949,290.00

0.64 m3 1,121,700.88 717,888.56


156.05 kg 13,680.40 2,134,826.42
6.40 m2 91,862.00 587,916.80

13.60 m3 1,121,700.88 15,255,131.96


1,840.21 kg 13,680.40 25,174,808.88
108.80 m2 162,955.00 17,729,504.00
-
1.60 m3 1,121,700.88 1,794,721.40
246.21 kg 13,680.40 3,368,251.28
16.80 m2 188,830.00 3,172,344.00

1.19 m3 1,121,700.88 1,334,824.04


146.73 kg 13,680.40 2,007,325.09
9.92 m2 205,505.00 2,038,609.60

1.80 m3 1,121,700.88 2,019,061.58


279.69 kg 13,680.40 3,826,271.07
14.40 m2 188,830.00 2,719,152.00

1.57 m3 1,121,700.88 1,761,070.38

255
360.64 kg 13,680.40 4,933,699.45
18.84 m2 188,830.00 3,557,557.20

2.06 m3 1,121,700.88 2,310,703.81


379.71 kg 13,680.40 5,194,584.68
17.03 m2 207,014.40 3,525,455.23

2.93 m3 1,121,700.88 3,286,583.57


361.27 kg 13,680.40 4,942,318.10
20.93 m2 205,505.00 4,301,219.65
66.84 m2 46,206.08 3,088,414.38
136.04 m2 46,206.08 6,285,875.12
136.04 m2 26,933.00 3,663,965.32
3.78 m2 750,000.00 2,835,000.00
2.00 unit 12,000,000.00 24,000,000.00
263.24 kg 21,294.40 5,605,537.85
79.68 m2 35,000.00 2,788,800.00

265,093,729.33

1.00 ls 3,500,000.00 3,500,000.00


1.00 ls 500,000.00 500,000.00
1.00 ls 400,000.00 400,000.00

50.00 m 232,600.00 11,630,000.00


50.00 m 260,700.00 13,035,000.00
20.00 m 286,770.00 5,735,400.00

256
120.00 m 17,900.00 2,148,000.00

50.00 m 213,800.00 10,690,000.00


50.00 m 225,700.00 11,285,000.00
20.00 m 248,270.00 4,965,400.00

102.00 m 229,500.00 23,409,000.00


18.00 m 1,269,800.00 22,856,400.00
1.00 bh 250,000.00 250,000.00
1.00 set 250,000.00 250,000.00
2.00 bh 400,000.00 800,000.00
1.00 bh 450,000.00 450,000.00
1.00 bh 300,000.00 300,000.00
1.00 bh 120,000.00 120,000.00

3.00 m3 385,700.00 1,157,100.00


1.00 m3 475,000.00 475,000.00
1.00 ls 4,800,000.00 4,800,000.00
1.00 ls 500,000.00 500,000.00
24.00 jam 123,365.00 2,960,760.00
1.00 cth 300,000.00 300,000.00

3.00 unit 17,130,000.00 51,390,000.00


3.00 unit 2,000,000.00 6,000,000.00
100.00 m 26,000.00 2,600,000.00
100.00 m 11,500.00 1,150,000.00
6.00 bh 75,000.00 450,000.00
66.00 m 105,000.00 6,930,000.00
1.00 ls 750,000.00 750,000.00
1.00 ls 500,000.00 500,000.00
1.00 ls 2,500,000.00 2,500,000.00
3.00 ttk 7,500,000.00 22,500,000.00

257
217,287,060.00

258
NO URAIAN PEKERJAAN VOLUME SATUAN

VII PEKERJAAN SCLUPTURE

1 MINIPILE CONCRETE
Tiang pancang Mini pile 32 x 32 x32 (K450) 36.00 m'
Pekerjaan Pemancangan system hydraulic jacking 36.00 m'
Pecah kepala tiang pancang minipile 3.00 ttk
Lantai kerja bwh pile cap t= 5 cm 0.14 m3
Beton Bertulang Pile cap type P3
Membuat
- Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 1.71 M3
Pembesian
- dengan besi ulir 633.23 Kg
Bekisting
- untuk Pondasi 2 x pakai 12.53 M2
Kolom K1 80/80
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 3.00 M3
- Pembesian dengan besi ulir 942.84 Kg
- Bekisting untuk Kolom 2x Pakai 20.01 M2
Kolom Praktis
- Membuat Beton mutu f'c=21,7 MPa (K250), Slump(122),w/c=0,58 1.65 M3
- Pembesian dengan besi ulir 379.50 Kg
- Bekisting untuk Kolom 2x Pakai 49.50 M2

2 Galian Tanah 5.85 m3


3 Urugan Tanah Peninggian 70.79 m3
4 Urugan Pasir Bawah Lantai t = 10 cm 28.49 m3
5 Lantai Kerja Bawah Lantai t = 5 cm 0.45 m3
6 Pasangan Rolag Batu Bata 1:2 6.55 m2
7 Pasang dinding Batu Bata 1:4 15.40 m2
8 Plesteran dinding bata 1pc : 4ps 30.80 m2
9 Plat landas t= 10 mm 52.50 kg
10 Plat Sambungan t= 8 mm 624.00 kg
11 Angkur besi 19mm 12.49 kg
12 baut 12 mm 72.00 bh
13 Baja IWF 600.300.12.20 1365.36 kg
14 Baja IWF 500.200.10.16 537.90 kg
15 Pipa hitam 8" t= 4,5 mm 243.89 kg
16 Tembaga Motif Polos 43.96 m2
17 Tembaga Motif batik Semen 25.43 m2
18 GRC Motif Batik Jlamprang 30.00 m2
19 Lantai Batu paros / Lempeng 114.61 m2
20 Pasang Paving Holland 163.53 m2
21 Pasang Kansteen 67.20 m1
22 Tanam Rumput Gajah Mini 53.11 m2
23 Terucuk Bambu 3" 48.00 m1
JUMLAH TOTAL
HARGA SATUAN
HARGA SATUAN HARGA SATUAN
(Rp) (Rp) (Rp)

270,000.00 9,720,000
75,000.00 2,700,000
35,000.00 105,000
981,676.98 137,435

1,191,415.05 2,037,320
13,680.40 8,662,840
73,732.25 923,865

1,191,415.05 3,574,245
13,680.40 12,898,428
81,477.50 1,630,365

1,191,415.05 1,965,835
13,680.40 5,191,712
81,477.50 4,033,136

62,962.50 368,331
105,052.50 7,436,666
208,322.50 5,935,108
981,676.98 441,755
827,770.00 5,421,894
124,165.50 1,912,149
47,895.20 1,475,172
25,236.75 1,324,929
25,236.75 15,747,732
13,680.40 170,868
22,000.00 1,584,000
25,236.75 34,457,249
25,236.75 13,574,848
25,236.75 6,154,991
2,000,000.00 87,920,000
3,000,000.00 76,290,000
1,200,000.00 36,000,000
197,828.06 22,673,074
202,368.92 33,093,389
120,113.74 8,071,643
45,000.00 2,389,950
23,230.00 1,115,040

Sub Total 417,138,969.00


DAFTAR HARGA SATUAN PEKERJAAN
DAERAH BAWAH
SUMBER DATA
D A E R A H

NO. KODE URAIAN PEKERJAAN

I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


1 A.2.2.1.2-KBPKL Pagar Sementara dari Seng Gelombang Tinggi 2,00 m
2 A.2.2.1.4-KBPKL Pengukuran dan Pemasangan Bouwplank
3 A.2.2.1.5-KBPKL Pembuatan Kantor Sementara dg Lantai Plesteran
4 A.2.2.1.7-KBPKL Pembuatan Gudang Semen dan Peralatan
5 A.2.2.1.9 Membersihkan Lapangan dan Perataan/Pengembalian pekerjaan minor
6 A.2.2.1.10.1-KBPKL Pembuatan Steger/Perancah dari Bambu
7 A.2.2.1.10.2-KBPKL Steger/Scafolding (sewa)
8 A.2.2.1.11-KBPKL Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm
9 A.2.2.1.13.1-KBPKL Bongkaran Beton Bertulang tebal diatas 40 cm
10 A.2.2.1.13.2-KBPKL Bongkaran Beton Bertulang tebal dibawah 40 cm
11 A.2.2.1.14-KBPKL Bongkaran Dinding Tembok Bata Merah
12 A.2.2.1.15-KBPKL Bongkaran Plesteran Dinding
13 A.2.2.1.16-KBPKL Bongkaran Pasangan Batu
14 A.2.2.1.17-KBPKL Lansiran material (lepas/agregat) manual untuk daerah sulit dijangkau
15 A.2.2.1.18-KBPKL Lansiran material manual untuk daerah sulit dijangkau
16 A.2.2.1.19-KBPKL Kisdam pasir/tanah
17 A.2.2.1.20-KBPKL Sewa pompa air

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1-KBPKL Menggali Tanah Biasa Sedalam 1 m
2 A.2.3.1.2-KBPKL Menggali Tanah Biasa Sedalam 2 m
3 A.2.3.1.3-KBPKL Menggali Tanah Biasa Sedalam 3 m
4 A.2.3.1.4-KBPKL Menggali Tanah Keras Sedalam 1 m
5 A.2.3.1.5-KBPKL Menggali Tanah Cadas Sedalam 1 m
6 A.2.3.1.6-KBPKL Menggali Tanah Lumpur Sedalam 1 m
7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m
8 A.2.3.1.8 MembuangTanah sejauh 30 m'
9 A.2.3.1.9-KBPKL Pengurugan Kembali
10 A.2.3.1.10-KBPKL Pemadatan (per 20 cm)
11 A.2.3.1.11-KBPKL Urugan Pasir
13 A.2.3.1.12 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan

370472593.xlsx 261/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

14 A.2.3.1.13 Mengurug Sirtu Padat


A.2.3.1.13--KBPKL Mengurug Sirtu
15 A.2.3.1.14-KBPKL Mengurug tanah baru padat
0 A.2.3.1.15-KBPKL Mengurug tanah baru

III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP
2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP
2.a A.3.2.1.2.a Pemasangan Pondasi Batu 1SP : 4 PP (30 % Blondos : 70 % Belah)
3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP
4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP
4.a A.3.2.1.4.a Pemasangan Pondasi Batu 1SP : 6 PP (30 % Blondos : 70 % Belah)
5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP
6 A.3.2.1.9-KBPKL Pemasang Batu Kosong/Anstamping
7 A.3.2.1.10 Pasang Pondasi Siklop, 60% Beton Camp. 1PC : 2PB : 3KR & 40% Batu B
8 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm
9 A.3.2.1.12-KBPKL Pasang Trucuk Bambu
10 A.3.2.1.13-KBPKL Tiang Pancang Kayu Gelondongan
11 A.3.2.1.14-KBPKL Tiang Pancang Baja Pipa atau Kotak
12 A.3.2.1.15-KBPKL Tiang Pancang Beton Bertulang (25 x 25 cm)
13 A.3.2.1.16-KBPKL Tiang Pancang Beton Bertulang (30 x 30 cm)
14 A.3.2.1.17-KBPKL Tiang Pancang Beton Bertulang (40 x 40 cm)

IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

1 A.4.4.1.1 Pemasangan Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp

2 A.4.4.1.2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Cam

3 A.4.4.1.3 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Cam

4 A.4.4.1.4 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Cam

5 A.4.4.1.5 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Cam

6 A.4.4.1.7 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Cam

7 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Cam

8 A.4.4.1.9 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Cam

9 A.4.4.1.10 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Cam

10 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Cam

11 A.4.4.1.12 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Cam

12 A.4.4.1.20-KBPKL Pemasangan Dinding Bata Ringan tebal 75 mm

13 A.4.4.1.21 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP


14 A.4.4.1.22 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP :
15 A.4.4.1.23 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP :

370472593.xlsx 262/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A,4,4,2.1-KBPKL Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm
2 A,4,4,2.2-KBPKL Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm
3 A,4,4,2.3-KBPKL Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm
4 A,4,4,2.4-KBPKL Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm
5 A,4,4,2.5-KBPKL Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm
6 A,4,4,2.6-KBPKL Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm
7 A,4,4,2.7-KBPKL Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm
8 A,4,4,2.8-KBPKL Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm
13 A,4,4,2.13-KBPKL Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm
14 A,4,4,2.14-KBPKL Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm
15 A,4,4,2.15-KBPKL Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm
16 A,4,4,2.16-KBPKL Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm
17 A,4,4,2.17-KBPKL Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm
19 A,4,4,2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm
20 A,4,4,2.20-KBPKL Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm
21 A,4,4,2.23-KBPKL Pemasangan Plesteran Ciprat 1Pc : 2 Pp
22 A,4,4,2.24 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (=20 m')
23 A,4,4,2.25 Pemasangan Finishing Siar Pasangan Dinding Conblock ekspose (=8 m')
24 A,4,4,2.26-KBPKL Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp
25 A,4,4,2.27-KBPKL Pemasangan Acian

VI A.4.6.1 HARGA SATUAN PEKERJAAN KAYU DAN DINDING PEMISAH


1 A.4.6.1.1-KBPKL Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu Jati
2 A.4.6.1.2-KBPKL Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu Bengkirai
3 A.4.6.1.3-KBPKL Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu Kampas
4 A.4.6.1.3 Pembuatan & Pemasangan Pintu KlampStandard Kayu Kampas
5 A.4.6.1.4 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Kampas
6 A.4.6.1.5.1-KBPKL Pembuatan & Pemasangan Daun Pintu Panel, Kayu Jati
7 A.4.6.1.5.2-KBPKL Pembuatan & Pemasangan Daun Pintu Panel, Kayu Bengkirai
8 A.4.6.1.5.3-KBPKL Pembuatan & Pemasangan Daun Pintu Panel, Kayu Kampas
9 A.4.6.1.5.4-KBPKL Pembuatan & Pemasangan Daun Pintu Panel, Kayu Lokal Keras
10 A.4.6.1.6.1-KBPKL Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Jati
11 A.4.6.1.6.2-KBPKL Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Bengkirai
12 A.4.6.1.6.3-KBPKL Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Kampas
13 A.4.6.1.6.4-KBPKL Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Lokal Keras
14 A.4.6.1.7.1-KBPKL Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Jati
15 A.4.6.1.7.2-KBPKL Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Bengkirai

370472593.xlsx 263/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

16 A.4.6.1.7.3-KBPKL Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Kampas

17 A.4.6.1.7.4-KBPKL Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Lokal keras

18 A.4.6.1.8.1-KBPKL Pembuatan&Pemasangan Pintu kayu lapis Rangkap rangka tertutup Kayu Jati

19 A.4.6.1.8.2-KBPKL Pembuatan&Pemasangan Pintu kayu lapis Rangkap rangka tertutup Kayu


20 A.4.6.1.8.3-KBPKL Pembuatan&Pemasangan Pintu kayu lapis Rangkap rangka tertutup Kayu
21 A.4.6.1.8.4-KBPKL Pembuatan&Pemasangan Pintu kayu lapis Rangkap rangka tertutup Kayu
22 A.4.6.1.9.1-KBPKL Pembuatan&Pemasangan Pintu Plywood rangkap, rangka expose kayu ja
23 A.4.6.1.9.2-KBPKL Pembuatan&Pemasangan Pintu Plywood rangkap, rangka expose kayu Be
24 A.4.6.1.9.3-KBPKL Pembuatan&Pemasangan Pintu Plywood rangkap, rangka expose kayu Ka
25 A.4.6.1.10.1-KBPKL Pembuatan & Pemasangan Jalusi mati Kosen Kayu Jati
26 A.4.6.1.10.2-KBPKL Pembuatan & Pemasangan Jalusi mati Kosen Kayu Bengkirai
27 A.4.6.1.10.3-KBPKL Pembuatan & Pemasangan Jalusi mati Kosen Kayu Kampas
28 A.4.6.1.10.4-KBPKL Pembuatan & Pemasangan Jalusi mati Kosen Kayu Lokal keras
29 A.4.6.1.11.1-KBPKL Pembuatan & Pemasangan Pintu Teakwood Rangkap, Rangka Expose Ka
30 A.4.6.1.11.2-KBPKL Pembuatan & Pemasangan Pintu Teakwood Rangkap, Rangka Expose Kayu Beng

31 A.4.6.1.11.3-KBPKL Pembuatan & Pemasangan Pintu Teakwood Rangkap, Rangka Expose Kayu Kamp

32 A.4.6.1.12.1-KBPKL Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis Formika,Rangka expose


33 A.4.6.1.12.2-KBPKL Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis Formika,Rangk
34 A.4.6.1.12.3-KBPKL Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis Formika,Rangk
35 A.4.6.1.13.1-KBPKL Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu Jati
36 A.4.6.1.13.2-KBPKL Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu Bengk
37 A.4.6.1.13.3-KBPKL Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu Kampa
38 A.4.6.1.14.1-KABPKL Pembuatan&Pemasangan Konstruksi Kuda-kuda Expose, Kayu Jati
39 A.4.6.1.14.2-KABPKL Pembuatan&Pemasangan Konstruksi Kuda-kuda Expose, Kayu Bengkirai
40 A.4.6.1.14.3-KABPKL Pembuatan&Pemasangan Konstruksi Kuda-kuda Expose, Kayu Kampas
41 A.4.6.1.15.1-KBPKL Pemasangan konstruksi Gording, Kayu Jati
42 A.4.6.1.15.2-KBPKL Pemasangan konstruksi Gording, Kayu Bengkirai
43 A.4.6.1.15.3-KBPKL Pemasangan konstruksi Gording, Kayu Kampas
44 A.4.6.1.16.1-KBPKL Pemasangan Rangka Atap (reng 2/3, kaso 5/7), Kayu Kampas
45 A.4.6.1.16.2-KBPKL Pemasangan Rangka Atap (reng 3/4, kaso 5/7), Kayu Kampas
46 A.4.6.1.16.3-KBPKL Pemasangan Rangka Atap (reng 2/3, kaso 5/7) untuk genteng plentong ke
47 A.4.6.1.16.4-KBPKL Pemasangan Rangka Atap (reng 2/3, kaso 5/7) untuk genteng plentong ke
48 A.4.6.1.16.5-KBPKL Pemasangan Rangka Atap (reng 2/3, kaso 5/7) untuk genteng plentong ke
49 A.4.6.1.16.6-KBPKL Pemasangan Rangka Atap (reng 3/4, kaso 5/7) untuk genteng plentong be
50 A.4.6.1.16.7-KBPKL Pemasangan Rangka Atap (reng 3/4, kaso 5/7) untuk genteng plentong be
51 A.4.6.1.16.8-KBPKL Pemasangan Rangka Atap (reng 3/4, kaso 5/7) untuk genteng plentong be
52 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Kampas
53 A.4.6.1.19.1-KBPKL Pemasangan Rangka Langit-langit (50x1,00) m, kayu Bengkirai
54 A.4.6.1.19.2-KBPKL Pemasangan Rangka Langit-langit (50x1,00) m, kayu Kampas

370472593.xlsx 264/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

55 A.4.6.1.19.3-KBPKL Pemasangan Rangka Langit-langit (50x1,00) m, kayu Lokal keras


56 A.4.6.1.20.1-KBPKL Pemasangan Rangka Langit-langit (60x60) cm, kayu Bengkirai
57 A.4.6.1.20.2-KBPKL Pemasangan Rangka Langit-langit (60x60) cm, kayu Kampas
58 A.4.6.1.20.3-KBPKL Pemasangan Rangka Langit-langit (60x60) cm, kayu Lokal keras
59 A.4.6.1.21.1-KBPKL Pemasangan Listplank Uk. (3x20)cm Kayu Bengkirai
60 A.4.6.1.21.2-KBPKL Pemasangan Listplank Uk. (3x20)cm Kayu Kampas
61 A.4.6.1.21.3-KBPKL Pemasangan Listplank Uk. (3x20)cm Kayu Lokal keras
62 A.4.6.1.22.1-KBPKL Pemasangan Listplank Uk. (3x30)cm Kayu Bengkirai
63 A.4.6.1.22.2-KBPKL Pemasangan Listplank Uk. (3x30)cm Kayu Kampas
64 A.4.6.1.22.3-KBPKL Pemasangan Listplank Uk. (3x30)cm Kayu Lokal keras
65 A.4.6.1.23.1-KBPKL Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu Bengkirai
66 A.4.6.1.23.2-KBPKL Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu Kampas
67 A.4.6.1.23.3-KBPKL Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu Lokal keras
68 A.4.6.1.24.1-KBPKL Pemasangan Dinding Pemisah Teakwood Rangkap Rangka Kayu Bengkira
69 A.4.6.1.24.2-KBPKL Pemasangan Dinding Pemisah Teakwood Rangkap Rangka Kayu Kampas
70 A.4.6.1.24.3-KBPKL Pemasangan Dinding Pemisah Teakwood Rangkap Rangka Kayu Lokal ke
71 A.4.6.1.25.1-KBPKL Pemasangan Dinding Pemisah Plywood Rangkap Rangka Kayu Bengkirai
72 A.4.6.1.25.2-KBPKL Pemasangan Dinding Pemisah Plywood Rangkap Rangka Kayu Kampas
73 A.4.6.1.25.3-KBPKL Pemasangan Dinding Pemisah Plywood Rangkap Rangka Kayu Lokal kera
74 A.4.6.1.28-KBPKL Pemasangan Dinding Bilik, Rangka Kayu Kampas
75 A.4.6.1.29-KBPKL Pemasangan Dinding Pemisah Gypsum, Rangka Holllow/Baja ringan profi
76 A.4.6.1.30-KBPKL Pemasangan Dinding Pemisah GRC-Board, Rangka Holllow/Baja ringan p
77 A.4.6.1.31-KBPKL Pemasangan Dinding Pemisah Multiplek lapis tachonsheet, Rangka Holllo
78 A.4.6.1.32-KBPKL Pemasangan Allumunium Composite Panel (ACP), Rangka Holllow
79 A.4.6.1.32-KBPKL Pemasangan Allumunium Composite Panel (ACP) cutting/motif, Rangka H
80 A.4.6.1.33-KBPKL Pemasangan Papan Suri Kayu Kampas

VII A.4.1.1 HARGA SATUAN PEKERJAAN BETON


1 A.4.1.1.1 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (122)cm, w/c = 0,87
2 A.4.1.1.2 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (122)cm, w/c = 0,78
3 A.4.1.1.3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (122)cm, w/c = 0,72
4 A.4.1.1.4 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c
5 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66
6 A.4.1.1.6 Membuat Beton mutu f'c=16,9 MPa (K200), slum (122)cm, w/c = 0,61
7 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58
8 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56
9 A.4.1.1.9 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (122)cm, w
10 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (122)cm, w/c = 0,52
11 A.4.1.1.11 Membuat Beton mutu f'c=28,8 MPa (K325), slum (122)cm, w/c = 0,49

370472593.xlsx 265/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

12 A.4.1.1.12 Membuat Beton mutu f'c=31,2 MPa (K350), slum (122)cm, w/c = 0,48
13 A.4.1.1.12.1-KBPKL Membuat Beton menggunakan Readymix K-350
14 A.4.1.1.12.2-KBPKL Membuat Beton menggunakan Readymix K-300
15 A.4.1.1.12.3-KBPKL Membuat Beton menggunakan Readymix K-250
16 A.4.1.1.12.4-KBPKL Membuat Beton menggunakan Readymix K-225
17 A.4.1.1.12.5-KBPKL Membuat Beton menggunakan Readymix K-200
18 A.4.1.1.12.6-KBPKL Membuat Beton menggunakan Readymix K-175
19 A.4.1.1.12.7-KBPKL Membuat Beton menggunakan Readymix K-125
20 A.4.1.1.12.6-KBPKL Sewa concrete pump
21 A.4.1.1.17-KBPKL Pembesian dg Besi Polos atau Besi Ulir
22 A.4.1.1.18-KBPKL Kabel Presstresed Polos/strand
23 A.4.1.1.19-KBPKL Jaring Kawat baja/Wire Mesh
24 A.4.1.1.20-KBPKL Memasang Bekisting untuk Pondasi
25 A.4.1.1.21-KBPKL Memasang Bekisting untuk Sloof
26 A.4.1.1.21.1-KBPKL Memasang Bekisting untuk Sloof (2 kali pakai)
27 A.4.1.1.22.1-KBPKL Memasang Bekisting untuk Kolom menggunakan plywood/multiplek
28 A.4.1.1.22.2-KBPKL Memasang Bekisting untuk Kolom
29 A.4.1.1.22.2.1-KBPKL Memasang Bekisting untuk Kolom (2 kali pakai)
30 A.4.1.1.23.1-KBPKL Memasang Bekisting untuk Balok menggunakan plywood/multiplek
31 A.4.1.1.23.2-KBPKL Memasang Bekisting untuk Balok
32 A.4.1.1.23.2.1-KBPKL Memasang Bekisting untuk Balok (2 kali pakai)
33 A.4.1.1.24.3-KBPKL Memasang Bekisting untuk Lantai menggunakan plywood/multiplek
34 A.4.1.1.24.2-KBPKL Memasang Bekisting untuk Lantai
35 A.4.1.1.25-KBPKL Memasang Bekisting untuk Dinding
36 A.4.1.1.26-KBPKL Memasang Bekisting untuk Tangga
37 A.4.1.1.27-KBPKL Memasang Jembatan Cor

VIII A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil
2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur
3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar
4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong
5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur
6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar
7 A.4.5.2.9 Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5 mm
8 A.4.5.2.10 Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5 mm
9 A.4.5.2.12 Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4 mm
10 A.4.5.2.15 Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4 mm
11 A.4.5.2.16-KBPKL Pemasangan bubung stel Gelombang

370472593.xlsx 266/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

12 A.4.5.2.30 Pemasangan Atap Genteng Beton


13 A.4.5.2.32-KBPKL Pemasangan Atap Genteng Metal butir pasir
14 A.4.5.2.33-KBPKL Pemasangan Atap Bitumen
15 A.4.5.2.34 Pemasangan Nok Genteng Beton
16 A.4.5.2.36-KBPKL Pemasangan Nok Genteng Metal butir pasir
17 A.4.5.2.37-KBPKL Pemasangan Nok Genteng bitumen
18 A.4.5.2.38 Pemasangan Atap Seng Gelombang
19 A.4.5.2.39 Pemasangan Atap Nok Seng
20 A.4.5.2.42 Pasang Allumunium Foil / Sisalation

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 A.4.5.1.1.1-KBPKL Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm
2 A.4.5.1.1.2-KBPKL Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 5 mm
3 A.4.5.1.1.3-KBPKL Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 6 mm
4 A.4.5.1.2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm
5 A.4.5.1.3 Pemasangan Langit-langit Akustik Ukuran (30x60) cm
6 A.4.5.1.4 Pemasangan Langit-langit Akustik Ukuran (60x120) cm
7 A.4.5.1.5.1-KBPKL Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm
8 A.4.5.1.5.2-KBPKL Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 4 mm
9 A.4.5.1.5.3-KBPKL Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 6 mm
10 A.4.5.1.6 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm
11 A.4.5.1.7 Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm
12 A.4.5.1.7.1-KBPKL Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm rangka
13 A.4.5.1.7.2-KBPKL Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm rangka
14 A.4.5.1.7.3-KBPKL Memasang Langit-langit GRC Board, Uk (120x240) tebal 4 mm rangka hol
15 A.4.5.1.9 Memasang Langit-langit Akustik Uk (60x120) cm & Rangka Allumunium
16 A.4.5.1.10 List Langit-Langit Kayu Profil
17 A.4.5.1.11-KBPKL List Langit-Langit gypsum

X A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


1 A.5.1.1.1.1-KBPKL Memasang Closet Duduk / Mono Blok
2 A.5.1.1.1.2-KBPKL Memasang Closet Duduk Washdown + aksessories
3 A.5.1.1.2-KBPKL Memasang Closet Jongkok Porselen
4 A.5.1.1.4-KBPKL Memasang Urinoir
5 A.5.1.1.5-KBPKL Memasang Wastafel
6 A.5.1.1.6-KBPKL Pemasangan Bathcuip porselen
7 A.5.1.1.7.1-KBPKL Pemasangan Bak Fibreglass vol.1 m3
8 A.5.1.1.7.2-KBPKL Pemasangan Bak Fibreglass vol.0,3 m3
9 A.5.1.1.8-KBPKL Memasang Bak Mandi Batu Bata Vol. 0,30 m3

370472593.xlsx 267/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

10 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell


11 A.5.1.1.14 Pemasangan Floor Drain
12 A.5.1.1.15 Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm
13 A.5.1.1.16 Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm
14 A.5.1.1.17 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm
15 A.5.1.1.18 Pemasangan Pipa Galvanis "
16 A.5.1.1.19 Pemasangan Kran " atau "
17 A.5.1.1.20 Pemasangan Pipa Galvanis "
18 A.5.1.1.21 Pemasangan Pipa Galvanis 1"

19 A.5.1.1.22 Pemasangan Pipa Galvanis 1 "

20 A.5.1.1.23 Pemasangan Pipa Galvanis 3"

21 A.5.1.1.24 Pemasangan Pipa Galvanis 4"

370472593.xlsx 268/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

22 A.5.1.1.25 Pemasangan Pipa PVC tipe AW "


23 A.5.1.1.26 Pemasangan Pipa PVC tipe AW "
24 A.5.1.1.27 Pemasangan Pipa PVC tipe AW 1"
25 A.5.1.1.28 Pemasangan Pipa PVC tipe AW 1"
26 A.5.1.1.29 Pemasangan Pipa PVC tipe AW 2"
27 A.5.1.1.31 Pemasangan Pipa PVC tipe AW 3"
28 A.5.1.1.32 Pemasangan Pipa PVC tipe AW 4"
29 A.5.1.1.33 Pemasangan Pipa Air Limbah Jenis Pipa Tanah 20 cm
30 A.5.1.1.34 Pemasangan Pipa Air Limbah Jenis Pipa Tanah 15 cm
31 A.5.1.1.35 Pemasangan Pipa Beton 20 cm
32 A.5.1.1.35.1-KBPKL Pemasangan Pipa Beton 30 cm
33 A.5.1.1.35.2-KBPKL Pemasangan Pipa Beton 40 cm
34 A.5.1.1.35.3-KBPKL Pemasangan Pipa Beton 50 cm
34 A.5.1.1.35.4-KBPKL Pemasangan Pipa Beton 60 cm
35 A.5.1.1.36-KBPKL Pemasangan Pipa Beton 80 cm
36 A.5.1.1.37-KBPKL Pemasangan U-DITCH (30.30.120 TEBAL 7CM)
37 A.5.1.1.38-KBPKL Pemasangan U-DITCH (40.40.120 TEBAL 7CM)
38 A.5.1.1.39-KBPKL Pemasangan U-DITCH (40.60.120 TEBAL 7CM)
39 A.5.1.1.40-KBPKL Pemasangan U-DITCH (60.60.120 TEBAL 8CM)
40 A.5.1.1.41-KBPKL Pemasangan U-DITCH (80.100.120 TEBAL 10CM)
41 A.5.1.1.42-KBPKL Pemasangan TUTUP U-DITCH (30.120 TEBAL 7CM)
42 A.5.1.1.43-KBPKL Pemasangan TUTUP U-DITCH (40.120 TEBAL 7CM)
43 A.5.1.1.44-KBPKL Pemasangan TUTUP U-DITCH (60.120 TEBAL 10CM)
44 A.5.1.1.45-KBPKL Pemasangan TUTUP U-DITCH (80.120 TEBAL 10CM)

XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 Pemasangan Besi Profil
2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF
3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja)
4 A.4.2.1.4 Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku
5 A.4.2.1.5-KBPKL Pengerjaan Pengelasan dengan Las Listrik
6 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi
7 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door)
8 A.4.2.1.9 Pemasangan Sunscreen Allumunium
9 A.4.2.1.10 Pemasangan Rolling Door Allumunium
10 A.4.2.1.11.1-KBPKL Pemasangan Kusen Pintu/jendela Allumunium polos
11 A.4.2.1.11.2-KBPKL Pemasangan Kusen Pintu/jendela Allumunium warna
12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm
13 A.4.2.1.13.1-KBPKL Pemasangan Pintu / jendela Kaca Rangka Allumunium polos
14 A.4.2.1.13.2-KBPKL Pemasangan Pintu/jendela Kaca Rangka Allumunium warna
15 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds

370472593.xlsx 269/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

16 A.4.2.1.15 Pemasangan Terali Besi Strip (2x3) cm


17 A.4.2.1.16 Pemasangan Kawat Nyamuk
18 A.4.2.1.17 Pemasangan Jendela Nako & Tralis
19 A.4.2.1.18 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm
20 A.4.2.1.19 Pemasangan Talang 1/2 Lingkaran 15 cm, Seng Plaat BJLS 30 Lebar 45
21 A.4.2.1.20-KBPKL Pemasangan 1 m2 atap pelana baja ringan profil C/Z bentang <7m
22 A.4.2.1.21-KBPKL Pemasangan 1 m2 atap pelana baja ringan profil C/Z bentang 7-10m
23 A.4.2.1.22-KBPKL Pemasangan 1 m2 atap pelana baja ringan profil C/Z bentang >10m
24 A.4.2.1.23-KBPKL Pemasangan 1 m2 atap limas/jurai baja ringan profil C/Z bentang <7m
24 A.4.2.1.24-KBPKL Pemasangan 1 m2 atap limas/jurai baja ringan profil C/Z bentang 7-10m
24 A.4.2.1.25-KBPKL Pemasangan 1 m2 atap limas/jurai baja ringan profil C/Z bentang >10m

370472593.xlsx 270/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA


1 A.4.6.2.1 Pemasangan Kunci Tanam Antik
2 A.4.6.2.2 Pemasangan Kunci Tanam Biasa
3 A.4.6.2.3 Pemasangan Kunci Kamar Mandi
4 A.4.6.2.4 Pemasangan Kunci Selinder
5 A.4.6.2.5 Pemasangan Engsel Pintu
6 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu
7 A.4.6.2.7 Pemasangan Engsel Angin
8 A.4.6.2.9 Pemasangan Kait Angin
9 A.4.6.2.10 Pasang Door Closer
10 A.4.6.2.11 Pemasangan Kunci Selot
11 A.4.6.2.13 Pemasangan Door Stop
12 A.4.6.2.14 Pemasangan Rel Pintu Dorong
13 A.4.6.2.15 Pemasangan Kunci Lemari
14 A.4.6.2.16 Pemasangan Kaca tebal 3 mm
15 A.4.6.2.17 Pemasangan Kaca tebal 5 mm
16 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm
17 A.4.6.2.19-KBPKL Pemasangan Pintu KM Allumunium
18 A.4.6.2.20-KBPKL Pemasangan Pintu KM Fiber
19 A.4.6.2.21-KBPKL Pemasangan Pintu KM PVC

XIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING

1 A.4.4.3.35.1-KBPKL Pemasangan Lantai Keramik 30 x 30 cm Polos Sekualitas Platinum

2 A.4.4.3.35.2-KBPKL Pemasangan Lantai Keramik 30 x 30 cm Polos Sekualitas Mulia/Asiatile

3 A.4.4.3.35.3-KBPKL Pemasangan Lantai Keramik 30 x 30 cm Motif Sekualitas Platinum

4 A.4.4.3.35.4-KBPKL Pemasangan Lantai Keramik 30 x 30 cm Motif Sekualitas Mulia/Asiatile

5 A.4.4.3.35.5-KBPKL Pemasangan Lantai Keramik 40 x 40 cm Polos Sekualitas Platinum

6 A.4.4.3.35.6-KBPKL Pemasangan Lantai Keramik 40 x 40 cm Polos Sekualitas Mulia/Asiatile

7 A.4.4.3.35.7-KBPKL Pemasangan Lantai Keramik 40 x 40 cm Motif Sekualitas Platinum

8 A.4.4.3.35.8-KBPKL Pemasangan Lantai Keramik 40 x 40 cm Motif Sekualitas Mulia/Asiatile

9 A.4.4.3.35.9-KBPKL Pemasangan Lantai Granite Tile KW A

10 A.4.4.3.35.10-KBPKL Pemasangan Lantai Granite Tile KW B

11 A.4.4.3.36.1-KBPKL Pemasangan Lantai Keramik 20 x 20 cm polos

12 A.4.4.3.36.2-KBPKL Pemasangan Lantai Keramik 20 x 20 cm motif

13 A.4.4.3.36.3-KBPKL Pemasangan Lantai Keramik 25 x 25 cm polos

14 A.4.4.3.36.4-KBPKL Pemasangan Lantai Keramik 25 x 25 cm motif

15 A.4.4.3.36.5-KBPKL Pemasangan Lantai Keramik Outdoor/anti slip 20 x 20 cm

370472593.xlsx 271/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

16 A.4.4.3.36.7-KBPKL Pemasangan Lantai Keramik Outdoor/anti slip 30 x 30 cm

17 A.4.4.3.36.8-KBPKL Pemasangan Lantai Keramik Outdoor/anti slip 40 x 40 cm

18 A.4.4.3.37-KBPKL Pemasangan Lantai Keramik uk.10 x 33 cm, untuk variasi / border

19 A.4.4.3.39-KBPKL Pemasangan Plint Keramik Ukuran 10x20 cm

20 A.4.4.3.40-KBPKL Pemasangan Plint Keramik Ukuran 10x25 cm

21 A.4.4.3.41-KBPKL Pemasangan Plint Keramik Ukuran 5x20 cm

22 A.4.4.3.43-KBPKL Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm

23 A.4.4.3.44 Pemasangan Lantai Karpet

24 A.4.4.3.46 Pemasangan Lantai Parquet Jati

25 A.4.4.3.49-KBPKL Pemasangan Dinding Keramik 10x20 cm,

26 A.4.4.3.50-KBPKL Pemasangan Dinding Keramik 20x20 cm,

27 A.4.4.3.53-KBPKL Pemasangan Dinding Keramik 10x25 cm,

28 A.4.4.3.54-KBPKL Pemasangan Dinding Keramik 25x25 cm,

29 A.4.4.3.55-KBPKL Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm

30 A.4.4.3.58-KBPKL Pemasangan Dinding Batu Paros / Batu Tempel Hitam

31 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm

32 A.4.4.3.64.1-KBPKL Pemasangan Paving Block t=8cm K-300

33 A.4.4.3.64.2-KBPKL Pemasangan Paving Block t=8cm K-300 warna

34 A.4.4.3.64.3-KBPKL Pemasangan Paving Block t=6 cm K-250

35 A.4.4.3.64.4-KBPKL Pemasangan Paving Block t=6 cm K-250 warna

36 A.4.4.3.64.8-KBPKL Pemasangan Paving Block t=6cm K-200

37 A.4.4.3.64.9-KBPKL Pemasangan Paving Block t=6cm K-200 warna

38 A.4.4.3.64.10-KBPKL Pemasangan Paving Block t=6cm K-175

39 A.4.4.3.64.11-KBPKL Pemasangan Paving Block t=6cm K-175 warna

40 A.4.4.3.64.12-KBPKL Pemasangan kansteen beton 10,15,30,50 atau 15,20,30,50

41 A.4.4.3.64.13-KBPKL Pemasangan kansteen beton dengan cor beton (K.175)

XIV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.1 Pengikisan / pengerokan Permukaan Cat Tembok Lama

2 A.4.7.1.2 Pencucian Bidang Permukaan Tembok yang Pernah dicat

3 A.4.7.1.3 Pengerokan Karat Cat Lama permukaan Baja dg cara manual

4 A.4.7.1.4.1-KBPKL Pengecatan Bidang Kayu lama Kw A

5 A.4.7.1.4.2-KBPKL Pengecatan Bidang Kayu lama KW B

370472593.xlsx 272/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

6 A.4.7.1.4.3-KBPKL Pengecatan Bidang Kayu Baru (1 lp Plamir, 1 lp Cat dasar, 2 Lp Cat Penut

7 A.4.7.1.4.4-KBPKL Pengecatan Bidang Kayu Baru (1 lp Plamir, 1 lp Cat dasar, 2 Lp Cat Penut

8 A.4.7.1.5.1-KBPKL Pengecatan Bidang Kayu Baru (1 lp Plamir, 1 lp Cat dasar, 3 Lp Cat Penut

9 A.4.7.1.5.2-KBPKL Pengecatan Bidang Kayu Baru (1 lp Plamir, 1 lp Cat dasar, 3 Lp Cat Penut

10 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil

11 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur

12 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter

13 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis

14 A.4.7.1.10.1-KBPKL Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) In

15 A.4.7.1.10.2-KBPKL Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) In

A.4.7.1.10.3-KBPKL Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) e

A.4.7.1.10.4-KBPKL Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) e

16 A.4.7.1.11.1-KBPKL Pengecatan Tembok Lama (1lap.Cat dasar, 2lap Cat Penutup) Kw A

17 A.4.7.1.11.2-KBPKL Pengecatan Tembok Lama (1lap.Cat dasar, 2lap Cat Penutup) Kw B

18 A.4.7.1.11.3-KBPKL Pengecatan Langit-Langit (1lap.Cat dasar, 1lap Cat Penutup)

19 A.4.7.1.11.4-KBPKL Pengecatan genteng (2lap Cat Penutup) Kw A

20 A.4.7.1.11.5-KBPKL Pengecatan genteng (2lap Cat Penutup) Kw B

21 A.4.7.1.11.6-KBPKL Pengecatan Coating Batu Alam (2lap Cat Penutup)

22 A.4.7.1.11.7-KBPKL Pemasangan 1 m' wall papper, lebar 50 cm

23 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium

24 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih

25 A.4.7.1.14 Pelaburan Tembok lama dengan Kapur Sirih (pemeliharaan)

26 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi

27 A.4.7.1.17-KBPKL Pengecatan Permukaan Baja dg Meni Besi & Perancah

XV A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA

1 A.8.4.1.1-KBPKL Pemasangan 1 m pipa PVC 63 mm (SNI / RRJ 10 BAR) + accessories

2 A.8.4.1.2-KBPKL Pemasangan 1 m pipa PVC 90 mm (SNI / RRJ 10 BAR) + accessories

3 A.8.4.1.3-KBPKL Pemasangan 1 m pipa PVC 110 mm (SNI / RRJ 10 BAR) + accessories

4 A.8.4.1.4-KBPKL Pemasangan 1 m pipa PVC 150 mm (SNI / RRJ 10 BAR) + accessories

5 A.8.4.1.5-KBPKL Pemasangan 1 m pipa PVC 200 mm (SNI / RRJ 10 BAR) + accessories

6 A.8.4.1.6-KBPKL Pemasangan 1 m pipa PVC 250 mm (SNI / RRJ 10 BAR) + accessories

7 A.8.4.1.7-KBPKL Pemasangan 1 m pipa PVC 300 mm (SNI / RRJ 10 BAR) + accessories

370472593.xlsx 273/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

8 A.8.4.1.8-KBPKL Pemasangan 1 m pipa PVC 32 mm (SNI / MOF 10 BAR) + accessories

9 A.8.4.1.9-KBPKL Pemasangan 1 m pipa PVC 50 mm (SNI / MOF 10 BAR) + accessories

10 A.8.4.1.10-KBPKL Pemasangan 1 m pipa PVC 63 mm (SNI / MOF 10 BAR) + accessories

11 A.8.4.1.11-KBPKL Pemasangan 1 m pipa PVC 90 mm (SNI / MOF 10 BAR) + accessories

12 A.8.4.1.12-KBPKL Pemasangan 1 m pipa PVC 110 mm (SNI / MOF 10 BAR) + accessories

13 A.8.4.1.13-KBPKL Pemasangan 1 m pipa PVC 150 mm (SNI / MOF 10 BAR) + accessories

14 A.8.4.1.17-KBPKL Pemasangan 1 m pipa PVC 110 mm (SNI / Limbah / SDR 41) + accesso

15 A.8.4.1.18-KBPKL Pemasangan 1 m pipa PVC 150 mm (SNI / Limbah / SDR 41) + accesso

16 A.8.4.1.19-KBPKL Pemasangan 1 m pipa PVC 200 mm (SNI / Limbah / SDR 41) + accesso

17 A.8.4.1.20-KBPKL Pemasangan 1 m pipa PVC 250 mm (SNI / Limbah / SDR 41) + accesso

18 A.8.4.1.21-KBPKL Pemasangan 1 m pipa PVC 300 mm (SNI / Limbah / SDR 41) + accesso

19 A.8.4.1.22-KBPKL Pemasangan 1 m pipa HDPE 63 mm + accessories

20 A.8.4.1.23-KBPKL Pemasangan 1 m pipa HDPE 90 mm + accessories

21 A.8.4.1.24-KBPKL Pemasangan 1 m pipa HDPE 110 mm + accessories

22 A.8.4.1.25-KBPKL Pemasangan 1 m pipa HDPE 150 mm + accessories

23 A.8.4.1.26-KBPKL Pemasangan 1 m pipa HDPE 200 mm + accessories

24 A.8.4.1.27-KBPKL Pemasangan 1 m pipa HDPE 250 mm + accessories

25 A.8.4.1.28-KBPKL Pemasangan 1 m pipa HDPE 300 mm + accessories

26 A.8.4.1.29-KBPKL Pemasangan 1 m pipa GIP 32 mm

27 A.8.4.1.30-KBPKL Pemasangan 1 m pipa GIP 50 mm

28 A.8.4.1.31-KBPKL Pemasangan 1 m pipa GIP 63 mm

29 A.8.4.1.32-KBPKL Pemasangan 1 m pipa GIP 90 mm

30 A.8.4.1.33-KBPKL Pemasangan 1 m pipa GIP 110 mm

31 A.8.4.1.34-KBPKL Pemasangan 1 m pipa GIP 150 mm

32 A.8.4.1.35-KBPKL Pemasangan 1 m pipa GIP 200 mm

35 A.8.4.1.1N-KBPKL Pemasangan 1 m pipa PVC 63 mm (SNI / RRJ 10 BAR)

36 A.8.4.1.2N-KBPKL Pemasangan 1 m pipa PVC 90 mm (SNI / RRJ 10 BAR)

37 A.8.4.1.3N-KBPKL Pemasangan 1 m pipa PVC 110 mm (SNI / RRJ 10 BAR)

38 A.8.4.1.4N-KBPKL Pemasangan 1 m pipa PVC 150 mm (SNI / RRJ 10 BAR)

39 A.8.4.1.5N-KBPKL Pemasangan 1 m pipa PVC 200 mm (SNI / RRJ 10 BAR)

370472593.xlsx 274/451 sat.pekerjaan


NO. KODE URAIAN PEKERJAAN

40 A.8.4.1.6N-KBPKL Pemasangan 1 m pipa PVC 250 mm (SNI / RRJ 10 BAR)

41 A.8.4.1.7N-KBPKL Pemasangan 1 m pipa PVC 300 mm (SNI / RRJ 10 BAR)

42 A.8.4.1.8N-KBPKL Pemasangan 1 m pipa PVC 32 mm (SNI / MOF 10 BAR)

43 A.8.4.1.9N-KBPKL Pemasangan 1 m pipa PVC 50 mm (SNI / MOF 10 BAR)

44 A.8.4.1.10N-KBPKL Pemasangan 1 m pipa PVC 63 mm (SNI / MOF 10 BAR)

45 A.8.4.1.11N-KBPKL Pemasangan 1 m pipa PVC 90 mm (SNI / MOF 10 BAR)

46 A.8.4.1.12N-KBPKL Pemasangan 1 m pipa PVC 110 mm (SNI / MOF 10 BAR)

47 A.8.4.1.13N-KBPKL Pemasangan 1 m pipa PVC 150 mm (SNI / MOF 10 BAR)

48 A.8.4.1.14N-KBPKL Pemasangan 1 m pipa PVC 200 mm (SNI / MOF 10 BAR)

49 A.8.4.1.15N-KBPKL Pemasangan 1 m pipa PVC 250 mm (SNI / MOF 10 BAR)

50 A.8.4.1.16N-KBPKL Pemasangan 1 m pipa PVC 300 mm (SNI / MOF 10 BAR)

51 A.8.4.1.17N-KBPKL Pemasangan 1 m pipa PVC 110 mm (SNI / Limbah / SDR 41)

52 A.8.4.1.18N-KBPKL Pemasangan 1 m pipa PVC 150 mm (SNI / Limbah / SDR 41)

53 A.8.4.1.19-KBPKL Pemasangan 1 m pipa PVC 200 mm (SNI / Limbah / SDR 41)

54 A.8.4.1.20N-KBPKL Pemasangan 1 m pipa PVC 250 mm (SNI / Limbah / SDR 41)

55 A.8.4.1.21N-KBPKL Pemasangan 1 m pipa PVC 300 mm (SNI / Limbah / SDR 41)

56 A.8.4.3.1-KBPKL Upah pemasangan aksessories pipa (bila tersendiri)

57 A.8.4.3.2-KBPKL Upah pemasangan pengelasan aksessories pipa (bila tersendiri)

58 A.8.4.5.1-KBPKL Pengetesan pipa

XVI A.9.1.1 HARGA SATUAN PEKERJAAN LAIN-LAIN

1 A.9.1.1.1-KBPKL Pemasangan pagar BRC 90 A2

2 A.9.1.1.2-KBPKL Pemasangan pagar BRC 120 A2

3 A.9.1.1.3-KBPKL Pemasangan pintu single BRC SG 90 T1

4 A.9.1.1.4-KBPKL Pemasangan pintu single BRC SG 120 T1

5 A.9.1.1.5-KBPKL Pekerjaan sumur gali kedalaman 7 m

6 A.9.1.1.6-KBPKL Pekerjaan Septicktank sederhana (SP-1)

7 A.9.1.1.7-KBPKL Pekerjaan Peresapan sederhana (PR-1)

8 A.9.1.1.8-KBPKL Pemasangan got type U 20 cm termasuk pasangan dinding

9 A.9.1.1.9-KBPKL Pemasangan got type U 30 cm termasuk pasangan dinding

370472593.xlsx 275/451 sat.pekerjaan


AFTAR HARGA SATUAN PEKERJAAN GEDUNG
DAERAH BAWAH
PASARAN BEBAS
KABUPATEN PEKALONGAN
EDISI SEMESTER I 2017

HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)

AAN PERSIAPAN
eng Gelombang Tinggi 2,00 m m' 193,539.25
angan Bouwplank m' 78,418.50
entara dg Lantai Plesteran m2 1,185,132.50
men dan Peralatan m2 969,047.50
n dan Perataan/Pengembalian pekerjaan minor m2 13,225.00
ncah dari Bambu m2 75,852.85
) m2 37,645.25
an ukuran 40cmx50cmx25cm bh 223,054.00
ang tebal diatas 40 cm m3 747,500.00
ang tebal dibawah 40 cm m3 560,625.00
bok Bata Merah m2 54,510.00
nding m2 10,120.00
tu m3 168,072.50
/agregat) manual untuk daerah sulit dijangkau m3 161,000.00
al untuk daerah sulit dijangkau kg 402.50
bh 16,974.00
jam 21,533.75

m3 56,005.00
m3 62,962.50
m3 85,675.00
m3 72,680.00
m3 90,850.00
m3 72,680.00
m2 4,542.50
m3 27,600.00
m3 18,434.50
m3 29,670.00
m3 208,322.50
juk tebal 10 cm unt Bidang Resapan m2 58,477.50

370472593.xlsx 276/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
m3 243,512.50
m3 211,485.00
m3 105,052.50
m3 75,497.50

JAAN PONDASI
m3 885,787.50
m3 841,627.50
Batu 1SP : 4 PP (30 % Blondos : 70 % Belah) m3 827,758.50
m3 810,991.50
m3 789,463.50
Batu 1SP : 6 PP (30 % Blondos : 70 % Belah) m3 774,053.50
m3 759,931.50
m3 404,995.50
, 60% Beton Camp. 1PC : 2PB : 3KR & 40% Batu Belah m3 2,427,604.00
m3 849,924.75
m 23,230.00
m 169,502.36
m 841,594.78
m 409,742.70
m 492,485.20
m 777,390.69

ERJAAN PASANGAN DINDING


Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP m2 274,965.00
Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP m2 263,442.00
Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP m2 255,162.00
Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP m2 251,643.00
Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP m2 252,057.00
Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP m2 133,066.50
Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP m2 127,298.10
Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP m2 124,165.50
Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP m2 122,205.90
Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 121,433.10
Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP m2 119,197.50
m2 111,280.90
HB/CB 10, speci camp. 1SP : 4PP m2 263,724.90
Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 2PP m2 271,204.50
Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP m2 267,892.50

370472593.xlsx 277/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)

m2 58,471.52
m2 52,289.12
m2 49,738.88
m2 47,895.20
m2 46,989.92
m2 46,206.08
m2 45,819.68
m2 45,433.28
1 Pc : 2 Pp Tebal 20 mm m2 69,159.16
m2 57,181.60
1 Pc : 4 Pp Tebal 20 mm m2 63,208.60
m2 62,093.56
m2 60,956.44
m2 35,052.92
Skoning 1 Pc : 2Pp, lebar 10 mm m' 28,612.00
m2 35,620.10
Siar Pasangan Dinding Bata Merah (=20 m') m2 25,012.04
Siar Pasangan Dinding Conblock ekspose (=8 m') m2 11,937.00
Siar Pas.Batu Kali Adukan 1Pc : 2Pp m2 35,180.80
m2 26,933.00

ERJAAN KAYU DAN DINDING PEMISAH


ngan Kosen Pintu & Jendela Kayu Jati m3 21,898,875.00
ngan Kosen Pintu & Jendela Kayu Bengkirai m3 17,690,450.00
ngan Kosen Pintu & Jendela Kayu Kampas m3 10,017,650.00
ngan Pintu KlampStandard Kayu Kampas m2 421,440.50
ngan Daun Pintu Klamp Sederhana Kayu Kampas m2 421,440.50
ngan Daun Pintu Panel, Kayu Jati m2 1,104,057.50
ngan Daun Pintu Panel, Kayu Bengkirai m2 966,057.50
ngan Daun Pintu Panel, Kayu Kampas m2 690,057.50
ngan Daun Pintu Panel, Kayu Lokal Keras m2 552,057.50
ngan Pintu & Jendela Kaca Kayu Jati m2 748,535.00
ngan Pintu & Jendela Kaca Kayu Bengkirai m2 665,735.00
ngan Pintu & Jendela Kaca Kayu Kampas m2 500,135.00
ngan Pintu & Jendela Kaca Kayu Lokal Keras m2 417,335.00
ngan Pintu & Jendela Jalusi Kayu Jati m2 1,523,750.00
an Pintu & Jendela Jalusi Kayu Bengkirai m2 1,302,950.00

370472593.xlsx 278/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
an Pintu & Jendela Jalusi Kayu Kampas m2 861,350.00
an Pintu & Jendela Jalusi Kayu Lokal keras m2 640,550.00
n Pintu kayu lapis Rangkap rangka tertutup Kayu Jati m2 790,636.50
gan Pintu kayu lapis Rangkap rangka tertutup Kayu Bengkirai m2 704,386.50
gan Pintu kayu lapis Rangkap rangka tertutup Kayu Kampas m2 531,886.50
gan Pintu kayu lapis Rangkap rangka tertutup Kayu Lokal keras m2 445,636.50
gan Pintu Plywood rangkap, rangka expose kayu jati m2 842,329.00
gan Pintu Plywood rangkap, rangka expose kayu Bengkirai m2 754,009.00
gan Pintu Plywood rangkap, rangka expose kayu Kampas m2 577,369.00
ngan Jalusi mati Kosen Kayu Jati m2 1,246,427.50
ngan Jalusi mati Kosen Kayu Bengkirai m2 1,039,427.50
ngan Jalusi mati Kosen Kayu Kampas m2 625,427.50
ngan Jalusi mati Kosen Kayu Lokal keras m2 418,427.50
ngan Pintu Teakwood Rangkap, Rangka Expose Kayu jati m2 829,449.00
an Pintu Teakwood Rangkap, Rangka Expose Kayu Bengkirai m2 743,199.00
an Pintu Teakwood Rangkap, Rangka Expose Kayu Kampas m2 570,699.00
n Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Jati m2 968,139.00
gan Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Bengkirai m2 881,889.00
gan Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Kampas m2 709,389.00
g Konstruksi Kuda-kuda Konvensional Kayu Jati m3 20,887,105.00
g Konstruksi Kuda-kuda Konvensional Kayu Bengkirai m3 15,827,105.00
g Konstruksi Kuda-kuda Konvensional Kayu Kampas m3 8,793,705.00
gan Konstruksi Kuda-kuda Expose, Kayu Jati m3 23,728,352.50
gan Konstruksi Kuda-kuda Expose, Kayu Bengkirai m3 18,208,352.50
gan Konstruksi Kuda-kuda Expose, Kayu Kampas m3 10,535,552.50
m3 20,189,745.00
si Gording, Kayu Bengkirai m3 15,129,745.00
m3 8,096,345.00
Atap (reng 2/3, kaso 5/7), Kayu Kampas m2 133,048.10
Atap (reng 3/4, kaso 5/7), Kayu Kampas m2 140,555.30
Atap (reng 2/3, kaso 5/7) untuk genteng plentong kecil, Kayu Bengkirai m2 200,042.50
Atap (reng 2/3, kaso 5/7) untuk genteng plentong kecil, Kayu Kampas m2 110,526.50
Atap (reng 2/3, kaso 5/7) untuk genteng plentong kecil, Kayu Lokal keras m2 63,192.50
Atap (reng 3/4, kaso 5/7) untuk genteng plentong besar, Kayu Bengkirai m2 222,812.50
Atap (reng 3/4, kaso 5/7) untuk genteng plentong besar, Kayu Kampas m2 121,787.30
Atap (reng 3/4, kaso 5/7) untuk genteng plentong besar, Kayu Lokal keras m2 68,367.50
m2 203,251.00
Langit-langit (50x1,00) m, kayu Bengkirai m2 250,182.50
Langit-langit (50x1,00) m, kayu Kampas m2 151,714.90

370472593.xlsx 279/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
Langit-langit (50x1,00) m, kayu Lokal keras m2 99,647.50
Langit-langit (60x60) cm, kayu Bengkirai m2 259,555.00
Langit-langit (60x60) cm, kayu Kampas m2 155,332.80
Langit-langit (60x60) cm, kayu Lokal keras m2 100,222.50
Uk. (3x20)cm Kayu Bengkirai m' 180,837.50
Uk. (3x20)cm Kayu Kampas m' 106,317.50
Uk. (3x20)cm Kayu Lokal keras m' 69,057.50
Uk. (3x30)cm Kayu Bengkirai m' 182,907.50
Uk. (3x30)cm Kayu Kampas m' 107,007.50
Uk. (3x30)cm Kayu Lokal keras m' 69,057.50
Dinding Pemisah (60x120) cm Kayu Bengkirai m2 418,335.50
Dinding Pemisah (60x120) cm Kayu Kampas m2 239,303.50
Dinding Pemisah (60x120) cm Kayu Lokal keras m2 144,635.50
Pemisah Teakwood Rangkap Rangka Kayu Bengkirai m2 479,814.50
Pemisah Teakwood Rangkap Rangka Kayu Kampas m2 300,782.50
Pemisah Teakwood Rangkap Rangka Kayu Lokal keras m2 206,114.50
Pemisah Plywood Rangkap Rangka Kayu Bengkirai m2 485,944.00
Pemisah Plywood Rangkap Rangka Kayu Kampas m2 306,912.00
Pemisah Plywood Rangkap Rangka Kayu Lokal keras m2 212,244.00
Bilik, Rangka Kayu Kampas m2 54,554.85
Pemisah Gypsum, Rangka Holllow/Baja ringan profil C (2 muka/sisi) m2 193,223.00
Pemisah GRC-Board, Rangka Holllow/Baja ringan profil C (2 muka/sisi) m2 201,595.00
Pemisah Multiplek lapis tachonsheet, Rangka Holllow (2 muka/sisi) m2 379,500.00
um Composite Panel (ACP), Rangka Holllow m2 454,221.25
um Composite Panel (ACP) cutting/motif, Rangka Holllow m2 791,171.25
m' 43,188.25

c=7,4 Mpa (K100), slum (122)cm, w/c = 0,87 m3 981,676.98


c=9,8 Mpa (K125), slum (122)cm, w/c = 0,78 m3 1,011,433.63
c=12,2 Mpa (K150), slum (122)cm, w/c = 0,72 m3 1,034,841.67
Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 m3 919,187.07
c=14,5 MPa (K175), slum (122)cm, w/c = 0,66 m3 1,061,528.35
c=16,9 MPa (K200), slum (122)cm, w/c = 0,61 m3 1,088,501.38
c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 m3 1,107,216.38
c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 1,121,700.88
Beton mutu f'c=24,0 MPa (K275), slum (122)cm, w/c = 0,53 m3 1,147,006.32
c=26,4 MPa (K300), slum (122)cm, w/c = 0,52 m3 1,154,746.90
c=28,8 MPa (K325), slum (122)cm, w/c = 0,49 m3 1,230,434.93

370472593.xlsx 280/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
c=31,2 MPa (K350), slum (122)cm, w/c = 0,48 m3 1,240,743.84
m3 1,273,490.45
m3 1,233,700.51
m3 1,191,415.05
m3 1,176,930.55
m3 1,158,215.55
m3 1,131,242.52
m3 1,080,768.30
unit/hari 4,192,256.00
kg 13,680.40
kg 13,210.05
kg 17,210.85
m2 147,464.50
m2 123,314.50
m2 91,862.00
ntuk Kolom menggunakan plywood/multiplek m2 162,955.00
m2 162,380.00
m2 118,450.00
ntuk Balok menggunakan plywood/multiplek m2 188,830.00
m2 152,030.00
m2 113,275.00
ntuk Lantai menggunakan plywood/multiplek m2 205,505.00
m2 211,427.50
m2 198,030.00
m2 135,297.50
m2 111,170.50

KERJAAN PENUTUP ATAP


m2 72,846.75
m2 87,279.25
teng Plentong Super / Besar m2 93,604.25
m' 102,879.00
m' 97,129.00
m' 97,129.00
es Gelombang (2,25x0,92 m) x 5 mm m2 78,654.25
es Gelombang (2,00x0,92 m) x 5 mm m2 71,737.00
es Gelombang (3,00x1,05 m) x 4 mm m2 52,106.50
es Gelombang (2,10x1,05 m) x 4 mm m2 43,912.75
m2 62,209.25

370472593.xlsx 281/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
m2 81,604.00
m2 99,285.25
m2 218,500.00
m' 103,086.00
m' 72,030.25
m' 89,516.00
m2 56,557.00
m' 30,383.00
m2 27,904.75

ERJAAN LANGIT-LANGIT
ngit Asbes (1,00x1,00) m, tebal 4 mm m2 35,914.50
ngit Asbes (1,00x1,00) m, tebal 5 mm m2 38,444.50
ngit Asbes (1,00x1,00) m, tebal 6 mm m2 47,299.50
ngit Akustik Ukuran (30x30) cm m2 106,881.00
ngit Akustik Ukuran (30x60) cm m2 116,897.50
ngit Akustik Ukuran (60x120) cm m2 71,932.50
t Tripleks Uk (120x240) cm, Tebal 3 mm m2 38,881.50
t Tripleks Uk (120x240) cm, Tebal 4 mm m2 43,625.25
t Tripleks Uk (120x240) cm, Tebal 6 mm m2 47,506.50
t Lambriziring Kayu Jati, tebal 6 mm m2 414,828.00
t Gypsum Board, Uk (120x240) tebal 9 mm m2 43,199.75
t Gypsum Board, Uk (120x240) tebal 9 mm rangka kayu Kampas m2 152,185.25
t Gypsum Board, Uk (120x240) tebal 9 mm rangka hollow m2 179,865.75
t GRC Board, Uk (120x240) tebal 4 mm rangka hollow m2 184,051.75
t Akustik Uk (60x120) cm & Rangka Allumunium m2 194,493.75
m1 23,218.50
m1 25,323.00

KERJAAN SANITASI DALAM GEDUNG


Unit 996,935.00
uk Washdown + aksessories Unit 2,713,885.00
Unit 247,710.00
Unit 615,077.50
Unit 555,105.00
Unit 1,141,973.00
Unit 738,300.00
Unit 609,500.00
Unit 1,070,061.72

370472593.xlsx 282/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
buah 391,517.50
buah 40,422.50
rol Pas.Batu Bata 30x30 tinggi 35 cm bh 417,438.50
rol Pas.Batu Bata 45 x 45 tinggi 50 cm bh 629,901.00
rol Pas.Batu Bata 60x60 tinggi 60 cm bh 748,983.50
m' 38,737.75
bh 71,484.00
m' 41,708.58
m' 48,541.50
m' 77,157.33
m' 141,887.00
m' 168,624.50

370472593.xlsx 283/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
m' 18,227.50
m' 19,787.19
m' 24,911.88
m' 36,365.16
m' 43,383.75
m' 70,037.16
m' 104,233.13
Limbah Jenis Pipa Tanah 20 cm m' 201,083.25
Limbah Jenis Pipa Tanah 15 cm m' 135,993.25
m' 130,834.35
m' 156,134.35
m' 187,759.35
m' 234,818.62
m' 294,019.35
m' 641,284.85
(30.30.120 TEBAL 7CM) m' 415,605.41
(40.40.120 TEBAL 7CM) m' 506,282.91
(40.60.120 TEBAL 7CM) m' 620,822.91
(60.60.120 TEBAL 8CM) m' 840,357.91
(80.100.120 TEBAL 10CM) m' 1,651,682.91
U-DITCH (30.120 TEBAL 7CM) m' 199,295.00
U-DITCH (40.120 TEBAL 7CM) m' 227,930.00
U-DITCH (60.120 TEBAL 10CM) m' 342,470.00
U-DITCH (80.120 TEBAL 10CM) m' 449,374.00

ERJAAN BESI & ALLUMUNIUM


Kg 27,030.75
kg 25,236.75
Perakitan (Kuda-kuda Baja) 1 kg 1,806.65
Plat Baja tebal 2 mm rangkap, rangka baja Siku m2 778,929.50
1 cm 4,004.88
m2 796,421.00
m2 600,737.00
m2 89,654.00
m2 879,175.00
ntu/jendela Allumunium polos m' 108,984.35
ntu/jendela Allumunium warna m' 121,634.35
munium Strip Lebar 8 cm m2 479,524.70
ndela Kaca Rangka Allumunium polos m2 521,295.00
dela Kaca Rangka Allumunium warna m2 571,895.00
m2 181,263.00

370472593.xlsx 284/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
m2 335,801.29
m2 45,656.43
m2 76,003.50
atar/Jurai , Seng BJLS 28 Lebar 90 cm m' 179,377.00
2 Lingkaran 15 cm, Seng Plaat BJLS 30 Lebar 45 cm m' 73,588.50
p pelana baja ringan profil C/Z bentang <7m m2 167,095.23
p pelana baja ringan profil C/Z bentang 7-10m m2 170,728.37
p pelana baja ringan profil C/Z bentang >10m m2 181,593.50
p limas/jurai baja ringan profil C/Z bentang <7m m2 201,842.68
p limas/jurai baja ringan profil C/Z bentang 7-10m m2 205,989.94
p limas/jurai baja ringan profil C/Z bentang >10m m2 216,855.07

370472593.xlsx 285/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)

ERJAAN KUNCI dan KACA


m Antik Buah 143,347.50
m Biasa Buah 131,847.50
ar Mandi Buah 50,111.25
der Buah 130,611.25
tu set 37,921.25
dela Kupu-kupu set 23,747.50
gin set 46,339.25
Buah 29,923.00
Buah 99,158.75
t Buah 35,063.50
Buah 52,031.75
Dorong Buah 260,440.50
ari Buah 38,084.55
3 mm m2 112,547.63
5 mm m2 141,642.63
in tebal 5 mm m2 175,797.63
Allumunium unit 697,150.70
Fiber unit 398,150.70
PVC unit 415,400.70

ERJAAN PENUTUP LANTAI dan DINDING

eramik 30 x 30 cm Polos Sekualitas Platinum m2 113,596.31

eramik 30 x 30 cm Polos Sekualitas Mulia/Asiatile m2 111,156.19

eramik 30 x 30 cm Motif Sekualitas Platinum m2 117,256.48

eramik 30 x 30 cm Motif Sekualitas Mulia/Asiatile m2 112,376.25

eramik 40 x 40 cm Polos Sekualitas Platinum m2 123,204.56

eramik 40 x 40 cm Polos Sekualitas Mulia/Asiatile m2 122,575.92

eramik 40 x 40 cm Motif Sekualitas Platinum m2 129,114.00

eramik 40 x 40 cm Motif Sekualitas Mulia/Asiatile m2 124,461.92

m2 324,377.92

m2 233,799.60

m2 126,999.56

m2 126,999.56

m2 112,992.56

m2 112,992.56

eramik Outdoor/anti slip 20 x 20 cm m2 126,999.56

370472593.xlsx 286/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
eramik Outdoor/anti slip 30 x 30 cm m2 123,966.73

eramik Outdoor/anti slip 40 x 40 cm m2 119,775.43

eramik uk.10 x 33 cm, untuk variasi / border m2 256,908.16

m' 51,764.95

m' 20,053.70

m' 38,166.20

armer Ukuran 1.00x1.00 cm m2 468,894.56

m2 195,224.00

m2 327,554.50

m2 128,368.06

m2 125,918.56

m2 114,579.56

m2 103,769.56

Marmer Ukuran 1.00x1.00 cm m2 465,783.94

Batu Paros / Batu Tempel Hitam m2 197,828.06

m' 44,321.00

m2 202,368.92

m2 213,868.92

m2 185,118.92

m2 196,618.92

m2 162,118.92

m2 167,868.92

m2 144,868.92

m2 186,527.90

beton 10,15,30,50 atau 15,20,30,50 m 120,113.74

beton dengan cor beton (K.175) m 441,496.39

KERJAAN PENGECATAN

an Permukaan Cat Tembok Lama m2 13,075.50

mukaan Tembok yang Pernah dicat m2 12,989.25

Lama permukaan Baja dg cara manual m2 13,506.75

m2 31,653.75

m2 29,698.75

370472593.xlsx 287/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
yu Baru (1 lp Plamir, 1 lp Cat dasar, 2 Lp Cat Penutup) Kw A m2 42,728.25

yu Baru (1 lp Plamir, 1 lp Cat dasar, 2 Lp Cat Penutup) Kw B m2 39,738.25

yu Baru (1 lp Plamir, 1 lp Cat dasar, 3 Lp Cat Penutup) Kw A m2 57,229.75

yu Baru (1 lp Plamir, 1 lp Cat dasar, 3 Lp Cat Penutup) Kw B m2 53,204.75

m2 33,959.50

m2 51,957.00

m2 10,733.81

m2 35,759.25

(1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) Interior Kw A m2 22,011.00

(1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) Interior, Kw B m2 17,346.60

(1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) exterior Kw A m2 34,270.00

(1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) exterior, Kw B m2 30,383.00

ama (1lap.Cat dasar, 2lap Cat Penutup) Kw A m2 16,226.50

ama (1lap.Cat dasar, 2lap Cat Penutup) Kw B m2 12,997.30

git (1lap.Cat dasar, 1lap Cat Penutup) m2 19,046.30

m2 58,577.55

m2 50,111.25

atu Alam (2lap Cat Penutup) m2 63,451.25

m2 94,098.75

m2 7,417.50

m2 15,082.25

a dengan Kapur Sirih (pemeliharaan) m2 8,423.75

m2 23,615.25

an Baja dg Meni Besi & Perancah m2 81,805.25

ERJAAN PEMASANGAN PIPA

PVC 63 mm (SNI / RRJ 10 BAR) + accessories m 39,810.70

PVC 90 mm (SNI / RRJ 10 BAR) + accessories m 71,341.40

PVC 110 mm (SNI / RRJ 10 BAR) + accessories m 100,936.08

PVC 150 mm (SNI / RRJ 10 BAR) + accessories m 200,549.08

PVC 200 mm (SNI / RRJ 10 BAR) + accessories m 310,432.15

PVC 250 mm (SNI / RRJ 10 BAR) + accessories m 479,090.00

PVC 300 mm (SNI / RRJ 10 BAR) + accessories m 749,364.15

370472593.xlsx 288/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
PVC 32 mm (SNI / MOF 10 BAR) + accessories m 18,555.83

PVC 50 mm (SNI / MOF 10 BAR) + accessories m 31,830.85

PVC 63 mm (SNI / MOF 10 BAR) + accessories m 38,842.98

PVC 90 mm (SNI / MOF 10 BAR) + accessories m 70,772.15

PVC 110 mm (SNI / MOF 10 BAR) + accessories m 98,602.15

PVC 150 mm (SNI / MOF 10 BAR) + accessories m 196,678.18

PVC 110 mm (SNI / Limbah / SDR 41) + accessories m 78,564.55

PVC 150 mm (SNI / Limbah / SDR 41) + accessories m 140,265.50

PVC 200 mm (SNI / Limbah / SDR 41) + accessories m 215,879.73

PVC 250 mm (SNI / Limbah / SDR 41) + accessories m 336,948.28

PVC 300 mm (SNI / Limbah / SDR 41) + accessories m 510,165.30

HDPE 63 mm + accessories m 68,005.25

HDPE 90 mm + accessories m 133,618.50

HDPE 110 mm + accessories m 208,845.75

HDPE 150 mm + accessories m 411,695.40

HDPE 200 mm + accessories m 642,326.75

HDPE 250 mm + accessories m 997,515.75

HDPE 300 mm + accessories m 1,577,443.50

m 52,819.50

m 72,204.67

m 89,282.17

m 123,740.00

m 147,579.50

m 246,579.17

m 540,224.00

PVC 63 mm (SNI / RRJ 10 BAR) m 37,202.50

PVC 90 mm (SNI / RRJ 10 BAR) m 66,021.50

PVC 110 mm (SNI / RRJ 10 BAR) m 93,075.25

PVC 150 mm (SNI / RRJ 10 BAR) m 183,787.25

PVC 200 mm (SNI / RRJ 10 BAR) m 284,567.50

370472593.xlsx 289/451 sat.pekerjaan


HARGA SATUAN
URAIAN PEKERJAAN PEKERJAAN
SAT
(Rp)
PVC 250 mm (SNI / RRJ 10 BAR) m 438,725.00

PVC 300 mm (SNI / RRJ 10 BAR) m 684,894.00

PVC 32 mm (SNI / MOF 10 BAR) m 17,681.25

PVC 50 mm (SNI / MOF 10 BAR) m 29,854.00

PVC 63 mm (SNI / MOF 10 BAR) m 36,322.75

PVC 90 mm (SNI / MOF 10 BAR) m 65,504.00

PVC 110 mm (SNI / MOF 10 BAR) m 90,953.50

PVC 150 mm (SNI / MOF 10 BAR) m 180,268.25

PVC 200 mm (SNI / MOF 10 BAR) m 25,921.00

PVC 250 mm (SNI / MOF 10 BAR) m 35,075.00

PVC 300 mm (SNI / MOF 10 BAR) m 40,192.50

PVC 110 mm (SNI / Limbah / SDR 41) m 72,737.50

PVC 150 mm (SNI / Limbah / SDR 41) m 128,984.00

PVC 200 mm (SNI / Limbah / SDR 41) m 198,610.75

PVC 250 mm (SNI / Limbah / SDR 41) m 309,505.25

PVC 300 mm (SNI / Limbah / SDR 41) m 467,440.50

essories pipa (bila tersendiri) bh 7,371.50

ngelasan aksessories pipa (bila tersendiri) cm 21,844.25

m 1,423.93

m 205,258.33

m 243,217.53

bh 456,700.25

bh 530,300.25

unit 9,374,618.45

unit 4,160,856.25

unit 950,207.77

U 20 cm termasuk pasangan dinding m' 130,472.92

U 30 cm termasuk pasangan dinding m' 151,978.34

370472593.xlsx 290/451 sat.pekerjaan


DAFTAR UPAH PEKERJA

SUMBER DATA : PASARAN BEBAS


D A E R A H : KABUPATEN PEKALONGAN
EDISI SEMESTER I 2017

HARGA
NO. JENIS BAHAN SATUAN KET.
(Rp)
1 Pekerja Hr 70,000.00

2 Mandor Hr 90,000.00

3 Tukang listrik Hr 80,000.00

4 Tukang kayu Hr 85,000.00

5 Kep. tk. kayu Hr 100,000.00

6 Tukang batu Hr 80,000.00

7 Kep. tk. batu Hr 100,000.00

8 Tukang besi Hr 80,000.00

9 Kep. tk. besi Hr 100,000.00

10 T u k a n g c a t Hr 80,000.00

11 K e p . t k . c a t Hr 100,000.00

12 T u k a n g p l i t u r Hr 80,000.00

13 T u k a n g j a l a n Hr 100,000.00

14 T u k a n g g a l i Hr 70,000.00

15 Tukang masak aspal Hr 125,000.00

16 T k . P i p a Hr 80,000.00

17 M a s i n i s Hr 125,000.00

18 P e m b . M a s i n i s Hr 80,000.00

19 P e n j a g a a p i Hr 70,000.00

20 P e n j a g a m a l a m Hr 70,000.00

21 Sopir Hr 125,000.00

22 Pembantu Sopir Hr 70,000.00

370472593.xlsx 451 daftar upah tenaga kerja


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KABUPATEN PEKALONGAN
EDISI SEMESTER I 20

NO. J E N I S B A H A N SATUAN HARGA 2016

(Rp)

VII . B A H A N P I P A
1 Pipa PVC SNI 10 BAR MOF (setara wavin safe)
Pipa PVC 32 ( 1" ) m 7,605.00
Pipa PVC 50 ( 1" ) m 17,190.00
Pipa PVC 63 ( 2" ) m 21,915.00
Pipa PVC 90 ( 3" ) m 45,810.00
Pipa PVC 110 ( 4" ) m 66,510.00
Pipa PVC 150 ( 6" ) m 142,695.00

2 Pipa PVC SNI 10 BAR RRJ (setara wavin lok)


Pipa PVC 63 ( 2" ) m 22,680.00
Pipa PVC 90 ( 3" ) m 46,260.00
Pipa PVC 110 ( 4" ) m 68,355.00
Pipa PVC 150 ( 6" ) m 145,755.00
Pipa PVC 200 ( 8" ) m 224,910.00
Pipa PVC 250 ( 10" ) m 351,000.00
Pipa PVC 300 ( 12" ) m 560,610.00

3 Pipa PVC SNI LIMBAH SDR 41


Pipa PVC SDR 110 ( 4" ) m 50,670.00
Pipa PVC SDR 150 ( 6" ) m 98,100.00
Pipa PVC SDR 200 ( 8" ) m 150,165.00
Pipa PVC SDR 250 ( 10" ) m 238,635.00
Pipa PVC SDR 300 ( 12" ) m 371,520.00

4 Pipa PVC SNI HDPE


Pipa PVC HDPE 32 ( 1" ) m 13,200.00
Pipa PVC HDPE 40 ( 1" ) m 31,650.00
Pipa PVC HDPE 63 ( 2" ) m 50,050.00
Pipa PVC HDPE 90 ( 3" ) m 101,300.00
Pipa PVC HDPE 110 ( 4" ) m 160,150.00
Pipa PVC HDPE 150 ( 6" ) m 318,760.00
Pipa PVC HDPE 200 ( 8" ) m 496,750.00
Pipa PVC HDPE 250 ( 10" ) m 774,150.00
Pipa PVC HDPE 300 ( 12" ) m 1,228,600.00

5 Pipa Medium B Galvanis - SII

370472593.xlsx 294/451 daftar harga pipa


NO. J E N I S B A H A N SATUAN HARGA 2016

(Rp)
Pipa Medium B Galvanis DN " m 12,500.00
Pipa Medium B Galvanis DN 25 ( " ) m 14,166.67
Pipa Medium B Galvanis DN 32 ( 1" ) m 18,000.00
Pipa Medium B Galvanis DN 50 ( 1 " ) m 27,666.67
Pipa Medium B Galvanis DN 63 ( 2" ) m 36,666.67
Pipa Medium B Galvanis DN 2" m 50,000.00
Pipa Medium B Galvanis DN 90 ( 3" ) m 60,000.00
Pipa Medium B Galvanis DN 110 ( 4" ) m 75,000.00
Pipa Medium B Galvanis DN 150 ( 6" ) m 154,166.67
Pipa Medium B Galvanis DN 200 ( 8" ) m 375,000.00
Pipa Medium B Galvanis DN 250 ( 10") m -

370472593.xlsx 295/451 daftar harga pipa


RGA SATUAN BAHAN BANGUNAN

EDISI SEMESTER I 2017

KETERANGAN

panjang 4 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m

panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m

panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m

370472593.xlsx 296/451 daftar harga pipa


KETERANGAN

panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m

370472593.xlsx 297/451 daftar harga pipa


DAFTAR HARGA SATUAN BAHAN BANGUNAN

DAERAH BAWAH

SUMBER DATA : PASARAN BEBAS

D A E R A H : KABUPATEN PEKALONGAN

NO. J E N I S B A H A N SATUAN

I BAHAN DASAR
I BATU KALI Bulat Utuh m3

Bulat Belah m3

Pecah 10/15 m3

Pecah 5/7 m3

Pecah 3/5 m3

2 KERIKIL Timbun m3

Sawur / Koral m3

Beton 0,5/1 m3

Beton ,1/2 m3

Beton ,2/3 m3

Biasa m3

Abu batu m3
3 BATU BATA ex lokal bh
bata ringan /m3 = 111 bh bh

4 PASIR Urug m3

Pasang m3

Beton m3

5 TANAH Padas m3

Liat m3
6 KAPUR Pasang m3
Semen Merah m3
7 PORTLAND CEMENT
40 kg zak
50 kg zak
Semen Putih 40 kg zak
Semen Putih 50 kg zak

370472593.xlsx 298/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

Semen warna kg
8 Beton Readymix mutu K-350 m3
mutu K-300 m3
mutu K-250 m4
mutu K-200 m5
mutu K-175 m6
mutu K-125 m7

370472593.xlsx 299/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak

2 GENTENG BETON Genteng Beton Warna standard bh


Genteng Beton Warna Special bh
Genteng Beton Warna Khusus bh
Kerpus Beton Warna Standard bh
Kerpus Beton Warna Special bh
Kerpus Beton Warna Khusus bh
3 GENTENG TANAH LIAT
plentong kecil bh
Kodok bh
Kodok Glasur bh
Nok kerpus Kodok bh
Nok kerpus Kodok Glasur bh
Plentong super besar 18 bh/m2 bh
Nok kerpus plentong super bh
5 ASBES GELOMBANG BESAR
. 225 cm X 102 cm X 5 mm bh

. 250 cm X 102 cm X 5 mm bh

. 200 cm X 102 cm X 6 mm bh

. 225 cm X 102 cm X 6 mm bh

. 250 cm X 102 cm X 6 mm bh

Asbes Gelombang Kecil

. 180 cm X 105 cm X 4 mm bh

. 210 cm X 105 cm X 4 mm bh

. 240 cm X 105 cm X 4 mm bh

. 270 cm X 105 cm X 4 mm bh

. 300 cm X 105 cm X 4 mm bh

. 180 cm X 105 cm X 3 mm bh

NOK Jabes nok

370472593.xlsx 300/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

. Kerpus Genteng bh
. Stel Besar bh
. Paten Besar bh
Nokstel gelombang harflex
. Stel Besar bh
. Patent Besar bh
. Plat besar bh
genteng metal butir pasir M1
genteng bitumen m1

370472593.xlsx 301/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh
. 100cm X 100 cm X 4 mm bh
. 100cm X 100 cm X 5 mm bh
. 100cm X 100 cm X 6 mm bh
. 50 cm X 200 cm X 3 mm bh
. 40 cm X 200 cm X 3 mm bh

7 FIBRE GLASS (JABES)


180 X 92 cm bh
200 X 92 cm bh
250 X 92 cm bh
180 X 105 cm bh
210 X 105 cm bh
250 X 105 cm bh
8 SENG PLAT
BJLS 0,18 lebar 55 cm m'
BJLS 0,20 lebar 55 cm m'
BJLS 0,28 lebar 55 cm m'
BJLS 0,30 lebar 55 cm m'
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr
BJLS 0,20 panjang 180 cm lbr
BJLS 0,30 panjang 180 cm lbr
BJLS 0,40 panjang 180 cm lbr
10 Genteng metal pasir m2

Genteng bitumen/PVC m2

III . B A H A N K A Y U
1 JATI Papan m3

Balok/pesagen m3

2 KAMPAS Papan m3

370472593.xlsx 302/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

Balok/pesagen m3

3 KRUING Papan m3

Balok/pesagen m3

4 MERANTI Papan m3

Balok/pesagen m3

370472593.xlsx 303/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

5 LOKAL KERAS Papan m3


Balok/pesagen m3

6 BENGKIRAI Papan m3
Balok/pesagen m3

7 DOLKEN Sedang 8 x 10 x 400 cm bt


Kecil 6 x 7 x 400 cm bt
Besar 10 x 12 x 400 cm bt
Kayu cetakan m3
Kayu bakar m3
Bambu bt

IV . BAHAN PENUTUP DINDING / LANTAI


5 MOZAIK PORSELIN

10 X 20 cm m2

15 X 15 cm m2

20 X 20 cm m2

20 X 25 cm m2

6 Keramik 30 X 30 cm polos Kw 1 m2
50 30 X 30 cm Motif Kw 1 m2
30 X 30 cm polos Kw 2 m2
30 X 30 cm Motif Kw 2 m2
20 X 20 cm polos m2
20 X 20 cm Motif m2
33 x 33 cm m2
25 x 25 cm m2
15 x 20 cm m2
40 x 40 cm polos Kw 1 m2

40 x 40 cm Motif Kw 1 m2

40 x 40 cm polos Kw 2 m2

40 x 40 cm Motif Kw 2 m2

370472593.xlsx 304/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

20 X 20 cm anti slip/tekstur m2
30 X 30 cm anti slip/tekstur m2
40 x 40 cm anti slip/tekstur m2
10 X 20 cm bh

10 X 25 cm bh

5 X 20 cm bh
7 Parquet Jati m2

370472593.xlsx 305/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

8 Batu Paros m2

9 Batu Tempel Hitam/andesit m2

10 Granite Tile kw A m2

kw B m2

11 Marmer m2
V.BAHAN CETAK
1 BUIS BETON 10 cm - 100 cm bh

20 cm - 100 cm bh
30 cm - 100 cm bh
40 cm - 100 cm bh
60 cm - 100 cm bh
80 cm - 100 cm bh
U 20 cm - 100 cm bh
U 30 cm - 100 cm bh
U 50 cm - 100 cm bh
2 U-DITCH

30.30.120 TEBAL 7CM bh

40.40.120 TEBAL 7CM bh

40.60.120 TEBAL 7CM bh

60.60.120 TEBAL 8CM bh

80.100.120 TEBAL 10CM bh

2 TUTUP U-DITCH

30.120 TEBAL 7CM bh

40.120 TEBAL 7CM bh

60.120 TEBAL 10CM bh

80.120 TEBAL 10CM bh

3 LUBANG ANGIN (ROSTER) PC + PASIR


10 X 20 cm bh

370472593.xlsx 306/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

20 X 20 cm bh
25 X 25 cm bh
30 X 30 cm bh
15 X 25 cm bh
15 X 30 cm bh

370472593.xlsx 307/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

4 TIANG PANCANG BETON


25 X 25 cm m

30 X 30 cm m

40 X 40 cm m

dia 25 cm m

dia 30 cm m

dia 40 cm m

VI . B A H A N B E S I
1 BESI BETON besi beton polos kg
besi beton ulir kg

2 BESI PLAT Besi Strip kg

3 BESI PROFIL Besi Profil kg

4 JARING - JARING BAJA


Diameter 4 - 15 kg
Diameter 6 - 15 kg
Kawat Bronjong kg
5 BESI SIKU L 40 X 40 X 6 btg
L 50 X 50 X 6 btg
L 60 X 60 X 6 btg

6 KAWAT - Ikat beton/bendrat kg


- Harmonika 12 X 45 mm m2
- Harmonika 12 X 24 mm m2
- Harmonika 14 X 30 mm m2
- Harmonika 14 X 35 mm m2
- Kawat Nyamuk Nylon m2
- Kawat Kasa m2
- Saringan pasir m2
- Kawat loket m2

370472593.xlsx 308/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

- Kawat duri rol


- Kawat bronjong kg
- Kawat las listrik kg
- Kawat Jaring Baja kg

Rangka hollow m

370472593.xlsx 309/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

VII . B A H A N P I P A
1 Pipa PVC SII SCJ
Pipa PVC DN 20 ( " ) AW JIS btg
Pipa PVC DN 25 ( " ) AW JIS btg

Pipa PVC DN 32 ( 1" ) AW JIS btg


Pipa PVC DN 40 ( 1" ) btg
Pipa PVC DN 63 ( 2" ) btg
Pipa PVC DN 90 ( 3" ) btg
Pipa PVC DN 110 ( 4" ) btg
Pipa PVC DN 160 ( 6" ) btg
Pipa PVC DN 200 ( 8" ) btg
Pipa PVC DN 250 ( 10" ) btg
Pipa PVC DN 315 ( 12" ) btg

3 Pipa Medium B Galvanis - SII


Pipa Medium B Galvanis DN " btg
Pipa Medium B Galvanis DN 25 ( " ) btg
Pipa Medium B Galvanis DN 32 ( 1" ) btg
Pipa Medium B Galvanis DN 50 ( 1 " ) btg
Pipa Medium B Galvanis DN 63 ( 2" ) btg
Pipa Medium B Galvanis DN 2" btg
Pipa Medium B Galvanis DN 90 ( 3" ) btg
Pipa Medium B Galvanis DN 110 ( 4" ) btg
Pipa Medium B Galvanis DN 160 ( 6" ) btg
Pipa Medium B Galvanis DN 200 ( 8" ) btg
Pipa Medium B Galvanis DN 250 ( 10") btg

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr
30 X 60 lbr
60 X 120 lbr
List Kayu Profil m'
2 SOFT BOARD-uk: 4'X 8'

370472593.xlsx 310/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

Gypsum tebal 9 mm lbr


3 HARD BOARD-uk: tebal 4mm lbr
list gypsum m
tepung gypsum kg

370472593.xlsx 311/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr
. 120 X 240 X 3 mm lbr
. 90 X 210 X 4 mm lbr
. 90 X 210 X 9 mm lbr
. 90 X 210 X 12 mm lbr
. 90 X 210 X 15 mm lbr
. 90 X 210 X 18 mm lbr
Tripleks
. 120 X 240 X 3 mm lbr
. 120 X 240 X 4 mm lbr
. 120 X 240 X 6 mm lbr
Multipleks
. 120 X 240 X 9 mm lbr
. 120 X 240 X 12 mm lbr
. 120 X 240 X 15 mm lbr
. 120 X 240 X 18 mm lbr
Formika ukuran pintu lbr

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg
Dempul plamur kg
Ambril/amplas lbr
Batu Apung kg
Cat dasar kg
. Emco kg
. Yunior 66 (nippon paint) kg
- Koas bh

. Deculux kg
. Siralax ons
. Spiritus ltr

370472593.xlsx 312/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

. Plitur jadi ltr

2 TEMBOK
Kalkarium kg
Kapur sirih kg
Plamur kg
Cat Tembok klas B exterior kg

370472593.xlsx 313/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

Cat Tembok klas A exterior kg


Cat Tembok klas B interior kg
Cat Tembok klas A interior kg
Cat Genteng A kg

Cat Genteng B kg

Cat Batu Alam kg

Cat Kayu B kg

Cat Kayu A kg
Sintex 5 kg
Danabride 5 kg
Catylac 5 kg
Mowilex 5 kg

3 BESI
Menie kg
Cat mengkilat kg
Cat kg
Thinner A ltr
Minyak cat ltr
Thinner Super ltr
Residu (teer/aspal) drum
4 Fibre glass (tanki air)
kapasitas 550 liter. bh
kapasitas 1100 liter. bh
Lem Aica Aibon kg

X.BAHAN KACA
1 POLOS 3 mm m2
5 mm m2

2 ES KABUR 3 mm m2
5 mm m2

370472593.xlsx 314/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

3 RAY BAND 3 mm m2
5 mm m2

370472593.xlsx 315/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m'
SPLN LMK 1 X 2 1/2 mm2 m'
. 1X4 mm2 m'
1X6 mm2 m'
NYY :. 2 X 1 1/2 mm2 m'
PRIMA 2 X 2 1/2 mm2 m'
. 2X4 mm2 m'
2X6 mm2 m'
3 X 1 1/2 mm2 m'
3 X 2 1/2 mm2 m'
3X4 mm2 m'
3X6 mm2 m'
NYM :. 2 X 1 1/2 mm2 m'
PRIMA 2 X 2 1/2 mm2 m'
. 2X4 mm2 m'
3 X 1 1/2 mm2 m'
3 X 2 1/2 mm2 m'
3X4 mm2 m'
3X6 mm2 m'

2 SAKLAR
Out bauw . Seri bh
. Engkel bh
In bauw . Seri bh
. Engkel bh

6 STOP KONTAK - Arde Outbow putih bh

Arde Outbow hitam bh

Arde IB bh

Arde Putar bh

370472593.xlsx 316/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh

2 X slag bh

Yale : 1 X slag bh

2 X slag bh

Kuda : 1 X slag bh

2 X slag bh

370472593.xlsx 317/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

2 ENGSEL DAN GERENDEL

Engsel Angin bh

Kupu-kupu biasa bh

Nylon kupu-kupu bh

Espagnoled - dalam negeri bh

Grendel Tanam luar negeri bh

Grendel biasa bh

Kait Angin bh

Door Stop bh

handel kunci bh
XIII . BAHAN SANITAIR
1 KLOSET DUDUK bh

2 KLOSET DUDUK WASHDOWN bh

3 KLOSET JONGKOK bh

5 WASTAFEL MEJA OVAL bh

6 WASTAFEL GANTUNG BULAT bh

8 WASTAFEL GANTUNG SUDUT KECIL bh

9 WASTAFEL BAK CUCI bh

10 TEMPAT SABUN GANTUNG bh

11 TEMPAT SABUN TANAM bh

12 SEPTIC TANK(BIO FILL)

5 Pemakai 1850 liter unit

10 Pemakai 3.000 liter unit

13 LAIN - LAIN

Kran Air bh

Seal tape bh

Floor drain bh

XIV . ALAT PENGIKAT KAYU


1 PAKU - ukuran 1" s/d 4" kg

2 PAKU - payung kg

3 PAKU - sekrup kg

4 PAKU - beton kg

370472593.xlsx 318/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

5 MUR BAUT (kuda-kuda) kg

6 ANGKUR BAUT bh

7 LEM KAYU bh

8 Tali Ijuk kg

370472593.xlsx 319/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

XV . POMPA AIR.
1 POMPA AIR LISTRIK

Sanyo 100 watt bh

Fuji 250 watt bh

Shimizu . 100 watt bh

. 90 watt bh

Dab . 125 watt bh

X VI . PAVING BLOCK
1 K-300 Abu-abu tbl 8 cm m2

Merah/hitam tbl 8 cm m2

2 K-250 Abu-abu tbl 6 cm m2

Merah/hitam tbl 6 cm m2

3 K-225 Abu-abu tbl 6 cm m2

Merah/hitam tbl 6 cm m2

4 K-200 Abu-abu tbl 6 cm m2

Merah/hitam tbl 6 cm m2

5 K-175 Abu-abu tbl 6 cm m2

Merah/hitam tbl 6 cm m2

12 BATACO BH

13 KANSTEEN m'
XVII. L A I N - L A I N
1 KREI 25 MM m2

2 Sliding Pintu J4 bh

3 Naco per Daun bh

4 Rolling door Besi m2

Rolling door Almunium m2

5 Awning Galvalum m2

6 Kusen Almunium 4" natural, Kw. B m'

7 Kusen Almunium 4" warna, Kw. B m'

8 Kusen Almunium 4" natural, Kw. A m'

9 Kusen Almunium 4" warna, Kw. A m'

10 profil Almunium natural m'

370472593.xlsx 320/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

11 profil Almunium warna m'

12 WIDE FLANGE BEAM

150 X 75 X 5 X 7 X 12 btg

8 ASPAL.

Aspal Ex Pertamina isi Net 155 kg drum

370472593.xlsx 321/451 daftar harga bahan


NO. J E N I S B A H A N SATUAN

10 K A C A

Cermin tebal 5 mm m2

11 PAGAR BRC. Pagar BRC 90 A2 /lb

Pagar BRC 120 A2 /lb

12 LAIN-LAIN

Minyak Beton & bekisting ltr

Pintu Lipat Besi m2

Sunscreen Allumunim m2

Allumunium Foil m2

Soda api kg

Sabun kg

Air m3

Koas Alang-alang ikat

Solar (Industri) Pertamina Dex ltr

Premium (Industri) Pertamax ltr

Pelumas ltr
Vynil 30x30 bh

Scafolding set-sewa

Karung plastik/bagor bh

Tali pengikat/nylon m

Hollow m

Paku Sekrup hollow bh

Tachosheet m2

Roof light fiberglass lbr

Atap galvalum m2

ACP m2

ACP cutting/motif m2

Sealent kg

Pintu KM Alluminium unit

Pintu KM Fiber unit

Pintu KM PVC unit

Wallpapper m2

370472593.xlsx 322/451 daftar harga bahan


R HARGA SATUAN BAHAN BANGUNAN

DAERAH BAWAH

PASARAN BEBAS

KABUPATEN PEKALONGAN
EDISI SEMESTER I 2017

HARGA 2017 SEM I

KETERANGAN

(Rp)

160,000.00

193,500.00

225,000.00

238,000.00

238,000.00

160,000.00

160,000.00

225,000.00

225,000.00

225,000.00

100,000.00

240,000.00

750.00

7,000.00

155,000.00

240,000.00

390,000.00

55,000.00

55,000.00

175,000.00

180,000.00

54,000.00

60,000.00

85,000.00

90,000.00

370472593.xlsx 323/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

10,000.00

1,012,000.00

964,000.00

915,000.00

874,000.00

850,000.00

735,000.00

370472593.xlsx 324/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

180,000.00

4,200.00

5,800.00

6,000.00

5,600.00

8,100.00

11,600.00

1,800.00

2,300.00

4,500.00

4,000.00

10,000.00

3,500.00

5,000.00

78,000.00

88,000.00

85,000.00

93,000.00

100,000.00

33,000.00

37,500.00

42,000.00

70,000.00

75,000.00

370472593.xlsx 325/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

4,000.00

22,500.00

39,700.00

30,000.00

26,500.00

48,000.00

45,000.00

56,000.00

370472593.xlsx 326/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

18,000.00

20,000.00

22,000.00

29,000.00

18,000.00

16,000.00

57,000.00

70,000.00

80,000.00

70,000.00

80,000.00

90,000.00

18,000.00

19,000.00

20,000.00

27,500.00

39,000.00

49,000.00

49,000.00

49,000.00

70,000.00

160,000.00

15,000,000.00

15,000,000.00

6,000,000.00

370472593.xlsx 327/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

5,440,000.00

6,000,000.00

5,382,000.00

4,500,000.00

3,900,000.00

370472593.xlsx 328/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

3,000,000.00

2,500,000.00

12,000,000.00

11,000,000.00

24,700.00

21,000.00

33,700.00

150,000.00

15,000.00

54,500.00

53,500.00

53,500.00

55,000.00

38,500.00 3,500
41,500.00 3,773
36,500.00 3,318
37,500.00 3,409
50,000.00 2,000
50,000.00 2,000
55,000.00 5,500
60,000.00 3,000

45,000.00

45,000.00 7,500

49,700.00 8,283

44,500.00 7,417

46,000.00 7,667

370472593.xlsx 329/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

50,000.00 2,000

47,000.00 4,230

77,500.00 12,400

5,300.00

3,000.00

230,000.00

370472593.xlsx 330/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

120,000.00

110,000.00

205,000.00

138,500.00

330,000.00

53,000.00

73,000.00

98,000.00

182,000.00

450,000.00

47,000.00

61,500.00

305,000.00

400,000.00

520,000.00

750,000.00

1,600,000.00

180,000.00

210,000.00

330,000.00

442,000.00

6,000.00

370472593.xlsx 331/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

7,000.00

10,000.00

12,000.00

8,750.00

10,250.00

370472593.xlsx 332/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

285,000.00

350,000.00

550,000.00

285,000.00

325,000.00

400,000.00

10,000.00

10,000.00

10,500.00

10,500.00

14,200.00

15,700.00

13,750.00

60,000.00

132,000.00

160,000.00

16,000.00

27,500.00

27,500.00

58,000.00

58,000.00

15,000.00

20,000.00

15,000.00

18,000.00

370472593.xlsx 333/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

65,000.00

12,500.00

30,000.00

14,198.00

25,000.00

370472593.xlsx 334/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

20,000.00 panjang 4 m

23,500.00 panjang 4 m

35,000.00 panjang 4 m

50,250.00 panjang 4 m

66,000.00 panjang 4 m

110,250.00 panjang 4 m

213,000.00 panjang 4 m

300,000.00 panjang 4 m

500,000.00 panjang 4 m

820,000.00 panjang 4 m

1,150,000.00 panjang 4 m

75,000.00 panjang 6 m

85,000.00 panjang 6 m

108,000.00 panjang 6 m

166,000.00 panjang 6 m

220,000.00 panjang 6 m

300,000.00 panjang 6 m

360,000.00 panjang 6 m

450,000.00 panjang 6 m

925,000.00 panjang 6 m

2,250,000.00 panjang 6 m
panjang 6 m

6,000.00

14,500.00

30,000.00

11,000.00

370472593.xlsx 335/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

65,000.00

75,000.00

12,500.00

2,500.00

370472593.xlsx 336/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

45,000.00

42,000.00

55,000.00

112,000.00

149,500.00

187,000.00

224,000.00

44,000.00

55,000.00

64,000.00

100,000.00

115,000.00

142,500.00

178,000.00

210,000.00

22,500.00

22,500.00

3,500.00

19,000.00

40,000.00

74,000.00

55,000.00

11,000.00

58,000.00

10,000.00

8,000.00

370472593.xlsx 337/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

55,000.00

4,400.00

2,000.00

12,000.00

63,000.00

370472593.xlsx 338/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

76,000.00

19,400.00

35,000.00

60,450.00

40,000.00

104,000.00

47,000.00

57,000.00

110,000.00

87,000.00

260,000.00

96,000.00

26,000.00

49,000.00

51,000.00

20,000.00

12,000.00

25,000.00

102,500.00

925,000.00

1,550,000.00

15,000.00

12,500.00

75,000.00

98,000.00

80,000.00

100,000.00

370472593.xlsx 339/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

85,000.00

110,000.00

370472593.xlsx 340/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

2,000.00

2,900.00

3,600.00

5,300.00

5,500.00

14,000.00

21,000.00

28,500.00

8,000.00

17,000.00

22,300.00

31,400.00

7,000.00

11,750.00

14,625.00

9,400.00

10,800.00

17,500.00

33,700.00

3,500.00

13,000.00

11,000.00

14,800.00

12,000.00

13,000.00

11,000.00

15,500.00

12,000.00

370472593.xlsx 341/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

70,000.00

80,000.00

75,000.00

370472593.xlsx 342/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

14,250.00

10,000.00

17,000.00

35,000.00

83,000.00

10,000.00

10,000.00

35,000.00

163,000.00

600,000.00

2,000,000.00

157,000.00

160,000.00

350,000.00

300,000.00

182,000.00

68,000.00

30,000.00

9,600,000.00

13,600,000.00

25,000.00

4,000.00

25,000.00

575,000.00

12,000.00

25,000.00

45,000.00

60,000.00

370472593.xlsx 343/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

22,000.00

17,500.00

11,000.00

6,500.00

370472593.xlsx 344/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

385,000.00

975,000.00

400,000.00

360,000.00

298,000.00

120,000.00

130,000.00

105,000.00

115,000.00

95,000.00

100,000.00

85,000.00

90,000.00

70,000.00

75,000.00

3,000.00

80,000.00

55,000.00

165,000.00

15,000.00

500,000.00

600,000.00

270,000.00

75,000.00

85,000.00

120,000.00

150,000.00

90,000.00

370472593.xlsx 345/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

100,000.00

1,590,000.00

1,121,488.00

370472593.xlsx 346/451 daftar harga bahan


HARGA 2017 SEM I

KETERANGAN

(Rp)

125,000.00

270,000.00

334,000.00

7,000.00

450,000.00

7,900.00

12,000.00

10,500.00

4,100.00

3,000.00

8,500.00

8,050.00

35,000.00

6,000.00

3,000.00

1,000.00

11,000.00

300.00

65,000.00

90,000.00

100,000.00

243,000.00

293,000.00

37,500.00

432,500.00

172,500.00

187,500.00

50,000.00

370472593.xlsx 347/451 daftar harga bahan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

10 A.4.2.1.11.1-KBPKL 1 m2 Pemasangan 1 m2 atap pelana baja ringan profil C/Z bentang <

A Tenaga

L.01 0.1468 OH Pekerja

L.02 0.1468 OH Tukang Besi

L.03 0.0146 OH Kepala Tukang

L.04 0.0074 OH Mandor

B Bahan

3.065 kg Baja ringan profil C/Z jarak 1 m kuda kuda pelana

C PERALATAN

10 % Peralatan

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

10 A.4.2.1.11.1-KBPKL 1 m2 Pemasangan 1 m2 atap pelana baja ringan profil C/Z bentang 7

A Tenaga

L.01 0.1468 OH Pekerja

L.02 0.1468 OH Tukang Besi

L.03 0.0146 OH Kepala Tukang

L.04 0.0074 OH Mandor

B Bahan

3.171 kg Baja ringan profil C/Z jarak 1 m kuda kuda pelana

C PERALATAN

10 % Peralatan

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

10 A.4.2.1.11.1-KBPKL 1 m2 Pemasangan 1 m2 atap pelana baja ringan profil C/Z bentang >

A Tenaga

L.01 0.1468 OH Pekerja

370472593.xlsx 451/348 BAJA RINGAN


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

L.02 0.1468 OH Tukang Besi

L.03 0.0146 OH Kepala Tukang

L.04 0.0074 OH Mandor

B Bahan

3.488 kg Baja ringan profil C/Z jarak 1 m kuda kuda pelana

C PERALATAN

10 % Peralatan

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

10 A.4.2.1.11.1-KBPKL 1 m2 Pemasangan 1 m2 atap limas/jurai baja ringan profil C/Z bentan

A Tenaga

L.01 0.152 OH Pekerja

L.02 0.152 OH Tukang Besi

L.03 0.0152 OH Kepala Tukang

L.04 0.0076 OH Mandor

B Bahan

4.05 kg Baja ringan profil C/Z jarak 1 m kuda kuda limas/jurai

C PERALATAN

10 % Peralatan

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/349 BAJA RINGAN


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

10 A.4.2.1.11.1-KBPKL 1 m2 Pemasangan 1 m2 atap limas/jurai baja ringan profil C/Z bentan

A Tenaga

L.01 0.152 OH Pekerja

L.02 0.152 OH Tukang Besi

L.03 0.0152 OH Kepala Tukang

L.04 0.0076 OH Mandor

B Bahan

4.171 kg Baja ringan profil C/Z jarak 1 m kuda kuda limas/jurai

C PERALATAN

10 % Peralatan

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

10 A.4.2.1.11.1-KBPKL 1 m2 Pemasangan 1 m2 atap limas/jurai baja ringan profil C/Z bentan

A Tenaga

L.01 0.152 OH Pekerja

L.02 0.152 OH Tukang Besi

L.03 0.0152 OH Kepala Tukang

L.04 0.0076 OH Mandor

B Bahan

4.488 kg Baja ringan profil C/Z jarak 1 m kuda kuda limas/jurai

C PERALATAN

10 % Peralatan

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/350 BAJA RINGAN


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
atap pelana baja ringan profil C/Z bentang <7m 167,095.23

24,146.00

70,000.00 10,276.00

80,000.00 11,744.00

100,000.00 1,460.00

90,000.00 666.00

91,350.00

29,804.24 91,350.00

29,804.20

2,980.42 29,804.20

145,300.20

15% 21,795.03

167,095.23

atap pelana baja ringan profil C/Z bentang 7-10m 170,728.37

24,146.00

70,000.00 10,276.00

80,000.00 11,744.00

100,000.00 1,460.00

90,000.00 666.00

94,509.25

29,804.24 94,509.25

29,804.20

2,980.42 29,804.20

148,459.45

15% 22,268.92

170,728.37

atap pelana baja ringan profil C/Z bentang >10m 181,593.50

24,146.00

70,000.00 10,276.00

370472593.xlsx 451/351 BAJA RINGAN


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
80,000.00 11,744.00

100,000.00 1,460.00

90,000.00 666.00

103,957.19

29,804.24 103,957.19

29,804.20

2,980.42 29,804.20

157,907.39

15% 23,686.11

181,593.50

atap limas/jurai baja ringan profil C/Z bentang <7m 201,842.68

25,004.00

70,000.00 10,640.00

80,000.00 12,160.00

100,000.00 1,520.00

90,000.00 684.00

120,707.17

Z jarak 1 m kuda kuda limas/jurai 29,804.24 120,707.17

29,804.20

2,980.42 29,804.20

175,515.37

15% 26,327.31

201,842.68

370472593.xlsx 451/352 BAJA RINGAN


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

atap limas/jurai baja ringan profil C/Z bentang 7-10m 205,989.94

25,004.00

70,000.00 10,640.00

80,000.00 12,160.00

100,000.00 1,520.00

90,000.00 684.00

124,313.49

Z jarak 1 m kuda kuda limas/jurai 29,804.24 124,313.49

29,804.20

2,980.42 29,804.20

179,121.69

15% 26,868.25

205,989.94

atap limas/jurai baja ringan profil C/Z bentang >10m 216,855.07

25,004.00

70,000.00 10,640.00

80,000.00 12,160.00

100,000.00 1,520.00

90,000.00 684.00

133,761.43

Z jarak 1 m kuda kuda limas/jurai 29,804.24 133,761.43

29,804.20

2,980.42 29,804.20

188,569.63

15% 28,285.44

216,855.07

370472593.xlsx 451/353 BAJA RINGAN


DAFTAR ANALISA PEKER

SUMBER DATA : PASARAN BEBAS


D A E R A H : KABUPATEN PEKALONGAN

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

1 A.2.2.1.2-KBPKL 1 m' Pagar Sementara dari Seng Gelombang Ting


A TENAGA
L.01 0.2 OH Pekerja
L.02 0.4 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.02 OH Mandor
B BAHAN
1.00 bt Bambu
2.5 Kg Portland Semen
1.2 Lbr Seng Gelombang 3" - 5"
0.005 m3 Pasir Beton
0.009 m3 Koral Beton
0.014 m3 Kayu 5/7X4m Kayu lokal keras
0.06 Kg Paku Biasa 2" - 5"

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit

2 A.2.2.1.4-KBPKL 1 m' Pengukuran dan Pemasangan Bouwplank


A Tenaga
L.01 0.1 OH Pekerja
L.02 0.1 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
0.012 m3 Kayu 5/7x 4m Kayu lokal keras
0.02 Kg Paku Biasa 2" - 5"
0.007 m3 Kayu Papan 3/20 kayu lokal keras

370472593.xlsx abk 1-14-354


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx abk 1-14-355


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

3 A.2.2.1.5-KBPKL 1 m2 Pembuatan Kantor Sementara dg Lantai Ples


A Tenaga
L.01 1.5 OH Pekerja
L.02 1 OH Tukang Kayu
L.02 1 OH Tukang Batu
L.03 0.3 OH Kepala Tukang
L.04 0.05 OH Mandor
B Bahan
1.25 Btg Kayu Dolken 8 - 10 / 4 m
0.18 m3 Kayu
0.85 Kg Paku Biasa 2" - 5"
1.1 Kg Besi Strip
35 Kg Portland Sement
0.15 m3 Pasir pasang
0.1 m3 Pasir Beton
0.15 m3 Koral Beton
30 buah Batu bata Merah
0.25 Lbr Seng Plat
2 buah Jendela Naco
0.08 m2 Kaca Polos
0.15 buah Kunci Tanam
0.3 buah Engsel
0.06 Lbr Plywood 4 mm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

4 A.2.2.1.7-KBPKL 1 m2 Pembuatan Gudang Semen dan Peralatan


A Tenaga
L.01 1 OH Pekerja
L.02 1 OH Tukang Kayu
L.03 0.2 OH Kepala Tukang
L.04 0.05 OH Mandor
B Bahan
1.7 Btg Bambu
0.21 m3 Kayu

370472593.xlsx abk 1-14-356


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.3 Kg Paku Biasa 2" - 5"


10.5 Kg Portland Semen
0.03 m3 Pasir Beton
0.05 m3 Koral Beton
1.5 Lbr Seng Gelombang BJLS 32
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx abk 1-14-357


ANALISA P E K E R JAAN

PASARAN BEBAS
KABUPATEN PEKALONGAN EDISI SEMESTER I 2017

HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

HARGA SATUAN PEKERJAAN PERSIAPAN


Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 193,539.25
51,800.00
70,000.00 14,000.00
85,000.00 34,000.00
100,000.00 2,000.00
90,000.00 1,800.00
116,495.00
15,000.00 15,000.00
1,200.00 3,000.00
49,000.00 58,800.00
390,000.00 1,950.00
225,000.00 2,025.00
Kayu 5/7X4m Kayu lokal keras 2,500,000.00 35,000.00
12,000.00 720.00

168,295.00
15% 25,244.25
Harga Satuan Pekerjaan (D+E) 193,539.25

Pengukuran dan Pemasangan Bouwplank 78,418.50


16,950.00
70,000.00 7,000.00
85,000.00 8,500.00
100,000.00 1,000.00
90,000.00 450.00
51,240.00
Kayu 5/7x 4m Kayu lokal keras 2,500,000.00 30,000.00
12,000.00 240.00
Kayu Papan 3/20 kayu lokal keras 3,000,000.00 21,000.00

370472593.xlsx abk 1-14-358


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

68,190.00
15% 10,228.50
Harga Satuan Pekerjaan (D+E) 78,418.50

370472593.xlsx abk 1-14-359


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
Pembuatan Kantor Sementara dg Lantai Plesteran 1,185,132.50
309,500.00
70,000.00 105,000.00
85,000.00 85,000.00
85,000.00 85,000.00
100,000.00 30,000.00
90,000.00 4,500.00
721,050.00
Kayu Dolken 8 - 10 / 4 m 15,000.00 18,750.00
2,500,000.00 450,000.00
12,000.00 10,200.00
10,500.00 11,550.00
1,200.00 42,000.00
240,000.00 36,000.00
390,000.00 39,000.00
225,000.00 33,750.00
750.00 22,500.00
18,000.00 4,500.00
15,000.00 30,000.00
75,000.00 6,000.00
70,000.00 10,500.00
10,000.00 3,000.00
55,000.00 3,300.00

1,030,550.00
15% 154,582.50
Harga Satuan Pekerjaan (D+E) 1,185,132.50

Pembuatan Gudang Semen dan Peralatan 969,047.50


179,500.00
70,000.00 70,000.00
85,000.00 85,000.00
100,000.00 20,000.00
90,000.00 4,500.00
663,150.00
15,000.00 25,500.00
2,500,000.00 525,000.00

370472593.xlsx abk 1-14-360


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
12,000.00 3,600.00
1,200.00 12,600.00
390,000.00 11,700.00
225,000.00 11,250.00
49,000.00 73,500.00

842,650.00
15% 126,397.50
Harga Satuan Pekerjaan (D+E) 969,047.50

370472593.xlsx abk 1-14-361


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

Overhead & Profit


2 A.2.3.1.2-KBPKL 1 m3 Menggali Tanah Biasa Sedalam 2 m
A TENAGA
L.01 0.75 OH Pekerja
L.04 0.025 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

9 A.2.3.1.9-KBPKL 1 m3 Pengurugan Kembali


Pengurugan Kembali di hitung dari 1/3 kali koefisien Pekerjaan
A TENAGA
L.01 0.22 OH Pekerja
L.04 0.007 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

11 A.2.3.1.11-KBPKL 1 m3 Urugan Pasir


A TENAGA
L.01 0.25 OH Pekerja
L.04 0.01 OH Mandor
B BAHAN
1.05 m3 Pasir Urug
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

14.A
A.2.3.1.13--KBPKL 1 m3 Mengurug Sirtu
A TENAGA
L.01 0.10 OH Pekerja

370472593.xlsx 451/362 abk 2-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

L.04 0.010 OH Mandor


B BAHAN
1.1 m3 Sirtu
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

15 A.2.3.1.14-KBPKL 1 m3 Mengurug tanah baru padat


A TENAGA
L.01 0.33 OH Pekerja
L.04 0.025 OH Mandor
B BAHAN
1.2 m3 Tanah urug baru
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

15A A.2.3.1.15-KBPKL 1 m3 Mengurug tanah baru


A TENAGA
L.01 0.10 OH Pekerja
L.04 0.010 OH Mandor
B BAHAN
1.05 m3 Tanah urug baru
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/363 abk 2-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

62,962.50
54,750.00
70,000.00 52,500.00
90,000.00 2,250.00

54,750.00
15% 8,212.50
62,962.50

18,434.50
ali di hitung dari 1/3 kali koefisien Pekerjaan galian
16,030.00
70,000.00 15,400.00
90,000.00 630.00

16,030.00
15% 2,404.50
18,434.50

208,322.50
18,400.00
70,000.00 17,500.00
90,000.00 900.00
162,750.00
155,000.00 162,750.00

181,150.00
15% 27,172.50
208,322.50

211,485.00
7,900.00
70,000.00 7,000.00

370472593.xlsx 451/364 abk 2-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
90,000.00 900.00
176,000.00
160,000.00 176,000.00

183,900.00
15% 27,585.00
211,485.00

105,052.50
25,350.00
70,000.00 23,100.00
90,000.00 2,250.00
66,000.00
55,000.00 66,000.00

91,350.00
15% 13,702.50
105,052.50

75,497.50
7,900.00
70,000.00 7,000.00
90,000.00 900.00
57,750.00
55,000.00 57,750.00

65,650.00
15% 9,847.50
75,497.50

370472593.xlsx 451/365 abk 2-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAA

III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


Overhead & Profit

2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP


A TENAGA
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor
B BAHAN
1.2 m3 Batu Belah 15/20
163 Kg Portland Sement
0.52 m3 Pasir Pasang
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

2.1 A.3.2.1.2.a 1 m3 Pemasangan Pondasi Batu 1SP : 4 PP (30 % Bl


A TENAGA
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor
B BAHAN
0.84 m3 Batu Belah 15/20
0.36 m3 Batu Blondos
163 Kg Portland Sement
0.52 m3 Pasir Pasang
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

4.a A.3.2.1.4.a 1 m3 Pemasangan Pondasi Batu 1SP : 6 PP (30 % B


A TENAGA
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor

370472593.xlsx 451/366 abk 3-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAA

B BAHAN
0.8 m3 Batu Belah 15/20
0.4 m3 Batu bulat
117 Kg Portland Sement
0.561 m3 Pasir Pasang
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

6 A.3.2.1.9-KBPKL 1 m3 Pemasang Batu Kosong/Anstamping


A Tenaga
L.01 0.78 OH Pekerja
L.02 0.39 OH Tukang Batu
L.03 0.039 OH Kepala Tukang
L.04 0.039 OH Mandor
B Bahan
1.2 m3 Batu Blonos
0.432 m3 Pasir Urug
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/367 abk 3-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
A SATUAN PEKERJAAN PONDASI

angan Pondasi Batu Belah 1SP : 4 PP 841,627.50


179,250.00
70,000.00 105,000.00
80,000.00 60,000.00
100,000.00 7,500.00
90,000.00 6,750.00
552,600.00
193,500.00 232,200.00
1,200.00 195,600.00
240,000.00 124,800.00

731,850.00
15% 109,777.50
Satuan Pekerjaan (D+E) 841,627.50

angan Pondasi Batu 1SP : 4 PP (30 % Blondos : 70 % Belah) 827,758.50


179,250.00
70,000.00 105,000.00
80,000.00 60,000.00
100,000.00 7,500.00
90,000.00 6,750.00
540,540.00
193,500.00 162,540.00
160,000.00 57,600.00
1,200.00 195,600.00
240,000.00 124,800.00

719,790.00
15% 107,968.50
Satuan Pekerjaan (D+E) 827,758.50

angan Pondasi Batu 1SP : 6 PP (30 % Blondos : 70 % Belah) 774,053.50


179,250.00
70,000.00 105,000.00
80,000.00 60,000.00
100,000.00 7,500.00
90,000.00 6,750.00

370472593.xlsx 451/368 abk 3-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
493,840.00
193,500.00 154,800.00
160,000.00 64,000.00
1,200.00 140,400.00
240,000.00 134,640.00

673,090.00
15% 100,963.50
Satuan Pekerjaan (D+E) 774,053.50

ang Batu Kosong/Anstamping 404,995.50


93,210.00
70,000.00 54,600.00
80,000.00 31,200.00
100,000.00 3,900.00
90,000.00 3,510.00
258,960.00
160,000.00 192,000.00
155,000.00 66,960.00

352,170.00
15% 52,825.50
Satuan Pekerjaan (D+E) 404,995.50

370472593.xlsx 451/369 abk 3-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

7 A.4.4.1.8 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal

A Tenaga

L.01 0.30 OH Pekerja

L.02 0.1 OH Tukang Batu

L.03 0.01 OH Kepala Tukang

L.04 0.015 OH Mandor

B Bahan

70 Buah Bata Merah 5 x 11 x 22

14.37 Kg Portland Semen

0.04 m3 Pasir Pasang

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

8 A.4.4.1.9 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal

A Tenaga

L.01 0.30 OH Pekerja

L.02 0.1 OH Tukang Batu

L.03 0.01 OH Kepala Tukang

L.04 0.015 OH Mandor

B Bahan

70 Buah Bata Merah 5 x 11 x 22

11.50 Kg Portland Semen

0.043 m3 Pasir Pasang

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/370 abk 4-14


JUMLAH
URAIAN PAKERJAAN HARGA BAHAN/UPAH
Rp Rp

RJAAN PASANGAN DINDING

ata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP 127,298.10

31,350.00

70,000.00 21,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 1,350.00

79,344.00

750.00 52,500.00

1,200.00 17,244.00

240,000.00 9,600.00

110,694.00

15% 16,604.10

127,298.10

ata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP 124,165.50

31,350.00

70,000.00 21,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 1,350.00

76,620.00

750.00 52,500.00

1,200.00 13,800.00

240,000.00 10,320.00

107,970.00

15% 16,195.50

124,165.50

370472593.xlsx 451/371 abk 4-14


file:///conversion/tmp/scratch/370472593.xlsx

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


4 A,4,4,2.4-KBPKL 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm
A Tenaga
L.01 0.2 OH Pekerja
L.02 0.15 OH Tukang batu
L.03 0.015 OH Kepala Tukang
L.04 0.010 OH Mandor
B Bahan
6.240 Kg Portland Semen
0.024 m3 Pasir Pasang
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

20 A,4,4,2.20-KBPKL 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm


A Tenaga
L.01 0.080 OH Pekerja
L.02 0.140 OH Tukang batu
L.03 0.040 OH Kepala Tukang
L.04 0.004 OH Mandor
B Bahan
0.5 Kg Portland Semen
0.013 m3 Pasir Pasang
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

25
A,4,4,2.27-KBPKL 1 m2 Pemasangan Acian
Tenaga

L.01 0.14 OH Pekerja

L.02 0.10 OH Tukang batu

L.03 0.010 OH Kepala Tukang

L.04 0.008 OH Mandor


Bahan
3.25 Kg Portland Semen
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/372 abk 5-14


file:///conversion/tmp/scratch/370472593.xlsx

HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

47,895.20
28,400.00
70,000.00 14,000.00
80,000.00 12,000.00
100,000.00 1,500.00
90,000.00 900.00
13,248.00
1,200.00 7,488.00
240,000.00 5,760.00

41,648.00
15% 6,247.20
47,895.20

ran Skoning 1 Pc : 2Pp, lebar 10 mm 28,612.00


21,160.00
70,000.00 5,600.00
80,000.00 11,200.00
100,000.00 4,000.00
90,000.00 360.00
3,720.00
1,200.00 600.00
240,000.00 3,120.00

24,880.00
15% 3,732.00
28,612.00

26,933.00
19,520.00
70,000.00 9,800.00
80,000.00 8,000.00
100,000.00 1,000.00
90,000.00 720.00
3,900.00
1,200.00 3,900.00

23,420.00
15% 3,513.00
26,933.00

370472593.xlsx 451/373 abk 5-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

VII A.4.1.1 HARGA SATUAN PEKERJAAN BETON

1 A.4.1.1.1 1 m3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (122)cm, w/c
A Tenaga
L.01 1.65 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor
B Bahan
247 Kg Portland Semen
869 Kg Pasir Beton
999 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit
2 A.4.1.1.2 1 m3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (122)cm, w/c
A Tenaga
L.01 1.65 OH Pekerja
L.02 0.28 OH Tukang Batu
L.03 0.03 OH Kepala Tukang
L.04 0.08 OH Mandor
B Bahan
276 Kg Portland Semen
828 kg Pasir Beton
1,012 kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

5 A.4.1.1.5 1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/


A Tenaga
L.01 1.65 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor

370472593.xlsx 451/374 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

B Bahan
326 Kg Portland Semen
760 Kg Pasir Beton
1,029 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

8 A.4.1.1.8 1 m3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/


A Tenaga
L.01 1.650 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor
B Bahan
384 Kg Portland Semen
692 Kg Pasir Beton
1,039 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/375 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

12 A.4.1.1.12 1 m3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (122)cm, w/


A Tenaga
L.01 2.1 OH Pekerja
L.02 0.35 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.105 OH Mandor
B Bahan
448 Kg Portland Semen
667 Kg Pasir Beton
1,000 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

13 A.4.1.1.12.1-KBPKL 1 m3 Membuat Beton menggunakan Readymix K-350


A Tenaga
L.01 0.80 jam Pekerja
L.02 1.807 jam Tukang
L.04 0.100 jam Mandor

B Bahan
448 Kg Portland Semen
667 Kg Pasir Beton
1,000 Kg Kerikil (maksimum 30 mm)
215 ltr Air

C PERALATAN
(E43) 0.10 jam Con. Pan. Mixer
(E49) 0.25 jam Truck Mixer

D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

15 A.4.1.1.12.3-KBPKL 1 m3 Membuat Beton menggunakan Readymix K-250


A Tenaga

370472593.xlsx 451/376 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

L.01 0.80 jam Pekerja


L.02 1.104 jam Tukang
L.04 0.100 jam Mandor

B Bahan
384 Kg Portland Semen
692 Kg Pasir Beton
1,039 Kg Kerikil (maksimum 30 mm)
215 ltr Air

C PERALATAN
(E43) 0.10 jam Con. Pan. Mixer
(E49) 0.25 jam Truck Mixer

D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/377 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

21 A.4.1.1.17-KBPKL 1 Kg Pembesian dg Besi Polos atau Besi Ulir


A Tenaga
L.01 0.0070 OH Pekerja
L.02 0.0070 OH Tukang Besi
L.03 0.0007 OH Kepala Tukang
L.04 0.0004 OH Mandor
B Bahan
1.050 Kg Besi Beton (polos/ulir)
0.015 Kg Kawat Beton
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

24 A.4.1.1.20-KBPKL 1 m2 Memasang Bekisting untuk Pondasi


A Tenaga
L.01 0.171 OH Pekerja
L.02 0.240 OH Tukang Kayu
L.03 0.024 OH Kepala Tukang
L.04 0.024 OH Mandor
B Bahan
0.029 m3 Kayu Klas III (Terentang)
0.300 Kg Paku Biasa 2" - 5"
0.100 Ltr Minyak Bekisting
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

26 A.4.1.1.21.1-KBPKL 1 m2 Memasang Bekisting untuk Sloof (2 kali pakai)


A Tenaga
L.01 0.171 OH Pekerja
L.02 0.240 OH Tukang Kayu
L.03 0.024 OH Kepala Tukang
L.04 0.024 OH Mandor
B Bahan
0.013 m3 Kayu Klas III (Terentang)
0.300 Kg Paku Biasa 2" - 5"

370472593.xlsx 451/378 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.050 Ltr Minyak Bekisting


C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

27 A.4.1.1.22.1-KBPKL 1 m2 Memasang Bekisting untuk Kolom menggunakan plywood/m


A Tenaga
L.01 0.240 OH Pekerja
L.02 0.300 OH Tukang Kayu
L.03 0.030 OH Kepala Tukang
L.04 0.030 OH Mandor
B Bahan
0.400 Kg Paku Biasa 2" - 5"
0.200 Ltr Minyak Bekisting
0.015 m3 Balok Kayu Klas III
0.350 Lbr Plywood tebal 9mm
1.000 Btg Bambu
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/379 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

30 A.4.1.1.23.1-KBPKL 1 m2 Memasang Bekisting untuk Balok menggunakan plywood/mu


A Tenaga
L.01 0.240 OH Pekerja
L.02 0.300 OH Tukang Kayu
L.03 0.030 OH Kepala Tukang
L.04 0.030 OH Mandor
B Bahan
0.400 Kg Paku Biasa 2" - 5"
0.200 Ltr Minyak Bekisting
0.018 m3 Balok Kayu Klas III
0.350 Lbr Plywood tebal 9mm
2.000 Btg bambu
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

33 A.4.1.1.24.3-KBPKL 1 m2 Memasang Bekisting untuk Lantai menggunakan plywood/mu


A Tenaga
L.01 0.20 OH Pekerja
L.02 0.25 OH Tukang Kayu
L.03 0.025 OH Kepala Tukang
L.04 0.025 OH Mandor
B Bahan
0.4 Kg Paku Biasa 2" - 5"
0.2 Ltr Minyak Bekisting
0.015 m3 Balok Kayu Klas III
0.35 Lbr Plywood tebal 9mm
4 Btg bambu
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/380 abk 7-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

utu f'c=7,4 Mpa (K100), slum (122)cm, w/c = 0,87 981,676.98


147,770.00
70,000.00 115,500.00
80,000.00 22,000.00
100,000.00 2,800.00
90,000.00 7,470.00
705,862.16
1,200.00 296,400.00
278.57 242,077.33
166.67 166,503.33
4.10 881.50

853,632.16
15% 128,044.82
981,676.98
10%
utu f'c=9,8 Mpa (K125), slum (122)cm, w/c = 0,78 1,011,433.63
148,100.00
70,000.00 115,500.00
80,000.00 22,400.00
100,000.00 3,000.00
90,000.00 7,200.00
731,407.50
1,200.00 331,200.00
278.57 230,655.96
166.67 168,670.04
4.10 881.50

879,507.50
15% 131,926.13
1,011,433.63

utu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66 1,061,528.35


147,770.00
70,000.00 115,500.00
80,000.00 22,000.00
100,000.00 2,800.00
90,000.00 7,470.00

370472593.xlsx 451/381 abk 7-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
775,298.13
1,200.00 391,200.00
278.57 211,713.20
166.67 171,503.43
4.10 881.50

923,068.13
15% 138,460.22
1,061,528.35

utu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 1,121,700.88


147,770.00
70,000.00 115,500.00
80,000.00 22,000.00
100,000.00 2,800.00
90,000.00 7,470.00
827,622.07
1,200.00 460,800.00
278.57 192,770.44
166.67 173,170.13
4.10 881.50

975,392.07
15% 146,308.81
1,121,700.88

370472593.xlsx 451/382 abk 7-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
utu f'c=31,2 MPa (K350), slum (122)cm, w/c = 0,48 1,240,743.84
187,950.00
70,000.00 147,000.00
80,000.00 28,000.00
100,000.00 3,500.00
90,000.00 9,450.00
890,957.69
1,200.00 537,600.00
278.57 185,806.19
166.67 166,670.00
4.10 881.50

1,078,907.69
15% 161,836.15
1,240,743.84

1,273,490.45
29,937.14
10,000.00 8,000.00
11,428.57 20,651.43
12,857.14 1,285.71

890,957.69
1,200.00 537,600.00
278.57 185,806.19
166.67 166,670.00
4.10 881.50

186,488.17
664,957.91 66,495.79
479,969.50 119,992.38

1,107,383.00
15% 166,107.45
1,273,490.45

1,191,415.05
21,902.85

370472593.xlsx 451/383 abk 7-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
10,000.00 8,000.00
11,428.57 12,617.14
12,857.14 1,285.71

827,622.07
1,200.00 460,800.00
278.57 192,770.44
166.67 173,170.13
4.10 881.50

186,488.17
664,957.91 66,495.79
479,969.50 119,992.38

1,036,013.09
15% 155,401.96
1,191,415.05

370472593.xlsx 451/384 abk 7-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
13,680.40
1,156.00
70,000.00 490.00
80,000.00 560.00
100,000.00 70.00
90,000.00 36.00
10,740.00
10,000.00 10,500.00
16,000.00 240.00

11,896.00
15% 1,784.40
13,680.40

147,464.50
36,930.00
70,000.00 11,970.00
85,000.00 20,400.00
100,000.00 2,400.00
90,000.00 2,160.00
91,300.00
3,000,000.00 87,000.00
12,000.00 3,600.00
7,000.00 700.00

128,230.00
15% 19,234.50
147,464.50

91,862.00
36,930.00
70,000.00 11,970.00
85,000.00 20,400.00
100,000.00 2,400.00
90,000.00 2,160.00
42,950.00
3,000,000.00 39,000.00
12,000.00 3,600.00

370472593.xlsx 451/385 abk 7-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
7,000.00 350.00

79,880.00
15% 11,982.00
91,862.00

ng untuk Kolom menggunakan plywood/multiplek 162,955.00


48,000.00
70,000.00 16,800.00
85,000.00 25,500.00
100,000.00 3,000.00
90,000.00 2,700.00
93,700.00
12,000.00 4,800.00
7,000.00 1,400.00
2,500,000.00 37,500.00
100,000.00 35,000.00
15,000.00 15,000.00

141,700.00
15% 21,255.00
162,955.00

370472593.xlsx 451/386 abk 7-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
ng untuk Balok menggunakan plywood/multiplek 188,830.00
48,000.00
70,000.00 16,800.00
85,000.00 25,500.00
100,000.00 3,000.00
90,000.00 2,700.00
116,200.00
12,000.00 4,800.00
7,000.00 1,400.00
2,500,000.00 45,000.00
100,000.00 35,000.00
15,000.00 30,000.00

164,200.00
15% 24,630.00
188,830.00

ng untuk Lantai menggunakan plywood/multiplek 205,505.00


40,000.00
70,000.00 14,000.00
85,000.00 21,250.00
100,000.00 2,500.00
90,000.00 2,250.00
138,700.00
12,000.00 4,800.00
7,000.00 1,400.00
2,500,000.00 37,500.00
100,000.00 35,000.00
15,000.00 60,000.00

178,700.00
15% 26,805.00
205,505.00

370472593.xlsx 451/387 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

VIII A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur

A Tenaga

L.01 0.15 OH Pekerja

L.02 0.075 OH Tukang Kayu

L.03 0.008 OH Kepala Tukang

L.04 0.008 OH Mandor

B Bahan

25 Buah Genteng Kodok / Glasur

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur

A Tenaga

L.01 0.4 OH Pekerja

L.02 0.2 OH Tukang Kayu

L.03 0.02 OH Kepala Tukang

L.04 0.002 OH Mandor

B Bahan

5 Buah Genteng Bubung Kodok / Glasur

8 Kg Portland Semen

0.032 m3 Pasir Pasang

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

14 A.4.5.2.33-KBPKL 1 m2 Pemasangan Atap Bitumen

370472593.xlsx 451/388 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A Tenaga

L.01 0.2 OH Pekerja

L.02 0.1 OH Tukang Kayu

L.03 0.01 OH Kepala Tukang

L.04 0.01 OH Mandor

B Bahan

1.02 m2 Atap bitumen

0.20 Kg Paku sekrup

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/389 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

18 A.4.5.2.38 1 m2 Pemasangan Atap Seng Gelombang

A Tenaga

L.01 0.12 OH Pekerja

L.02 0.06 OH Tukang Kayu

L.03 0.006 OH Kepala Tukang

L.04 0.006 OH Mandor

B Bahan

0.7 Lbr Seng Gelombang BJLS 30

0.02 Kg Paku Biasa 1/2" - 1"

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

20 A.4.5.2.42 1 m2 Pasang Allumunium Foil / Sisalation

A Tenaga

L.01 0.15 OH Pekerja

L.02 0.05 OH Tukang Kayu

L.03 0.005 OH Kepala Tukang

L.04 0.008 OH Mandor

B Bahan

1.05 m2 Sisalation / Allumunium Foil

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/390 abk 8-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

PEKERJAAN PENUTUP ATAP

87,279.25

18,395.00

70,000.00 10,500.00

85,000.00 6,375.00

100,000.00 800.00

90,000.00 720.00

57,500.00

2,300.00 57,500.00

75,895.00

15% 11,384.25

87,279.25

97,129.00

47,180.00

70,000.00 28,000.00

85,000.00 17,000.00

100,000.00 2,000.00

90,000.00 180.00

37,280.00

4,000.00 20,000.00

1,200.00 9,600.00

240,000.00 7,680.00

84,460.00

15% 12,669.00

97,129.00

218,500.00

370472593.xlsx 451/391 abk 8-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
24,400.00

70,000.00 14,000.00

85,000.00 8,500.00

100,000.00 1,000.00

90,000.00 900.00

165,600.00

160,000.00 163,200.00

12,000.00 2,400.00

190,000.00

15% 28,500.00

218,500.00

370472593.xlsx 451/392 abk 8-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
56,557.00

14,640.00

70,000.00 8,400.00

85,000.00 5,100.00

100,000.00 600.00

90,000.00 540.00

34,540.00

49,000.00 34,300.00

12,000.00 240.00

49,180.00

15% 7,377.00

56,557.00

27,904.75

15,970.00

70,000.00 10,500.00

85,000.00 4,250.00

100,000.00 500.00

90,000.00 720.00

8,295.00

7,900.00 8,295.00

24,265.00

15% 3,639.75

27,904.75

370472593.xlsx 451/393 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAA

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

11 A.4.5.1.7 1 m2 Memasang Langit-langit Gypsum Board, Uk (12

A Tenaga

L.01 0.1 OH Pekerja

L.02 0.05 OH Tukang Kayu

L.03 0.005 OH Kepala Tukang

L.04 0.005 OH Mandor

B Bahan

0.364 Lbr Gypsum Board

0.11 Kg Paku Sekrup

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

13 A.4.5.1.7.2-KBPKL 1 m2 Memasang Langit-langit Gypsum Board, Uk (12

A Tenaga

L.01 0.125 OH Pekerja

L.02 0.170 OH Tukang Kayu

L.03 0.013 OH Kepala Tukang

L.04 0.003 OH Mandor

B Bahan

0.364 Lbr Gypsum Board

4.10 m Rangka hollow

0.15 kg Kawat 4 mm

12.00 bh Paku Sekrup

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/394 abk 9-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAA

14 A.4.5.1.7.3-KBPKL 1 m2 Memasang Langit-langit GRC Board, Uk (120x2

A Tenaga

L.01 0.125 OH Pekerja

L.02 0.170 OH Tukang Kayu

L.03 0.013 OH Kepala Tukang

L.04 0.003 OH Mandor

B Bahan

0.364 Lbr GRC Board

4.10 m Rangka hollow

0.15 kg Kawat 4 mm

12.00 bh Paku Sekrup

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/395 abk 9-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAA

17 A.4.5.1.11-KBPKL 1 m1 List Langit-Langit gypsum

A Tenaga

L.01 0.05 OH Pekerja

L.02 0.05 OH Tukang Kayu

L.03 0.005 OH Kepala Tukang

L.04 0.003 OH Mandor

B Bahan

1.05 m1 List gypsum

0.15 Kg tepung gypsum

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

1 A.4.5.1.7.2-KBPKL 1 m2 Memasang Partisi 2x Gypsum Board, Uk (120x2

A Tenaga

L.01 0.250 OH Pekerja

L.02 0.340 OH Tukang Kayu

L.03 0.025 OH Kepala Tukang

L.04 0.005 OH Mandor

B Bahan

0.728 Lbr Gypsum Board

4.100 m Rangka hollow


0.300 kg Kawat 4 mm
24.000 bh Paku Sekrup
C PERALATAN
D Jumlah A+B+C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/396 abk 9-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

SATUAN PEKERJAAN LANGIT-LANGIT

ang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm 43,199.75

12,200.00

70,000.00 7,000.00

85,000.00 4,250.00

100,000.00 500.00

90,000.00 450.00

25,365.00

65,000.00 23,660.00

15,500.00 1,705.00

37,565.00

15% 5,634.75

atuan Pekerjaan (D+E) 43,199.75

ang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm rangka hollow 179,865.75

24,770.00

70,000.00 8,750.00

85,000.00 14,450.00

100,000.00 1,300.00

90,000.00 270.00

131,635.00

65,000.00 23,660.00

25,000.00 102,500.00

12,500.00 1,875.00

300.00 3,600.00

156,405.00

15% 23,460.75

atuan Pekerjaan (D+E) 179,865.75

370472593.xlsx 451/397 abk 9-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

ang Langit-langit GRC Board, Uk (120x240) tebal 4 mm rangka hollow 184,051.75

24,770.00

70,000.00 8,750.00

85,000.00 14,450.00

100,000.00 1,300.00

90,000.00 270.00

135,275.00

75,000.00 27,300.00

25,000.00 102,500.00

12,500.00 1,875.00

300.00 3,600.00

160,045.00

15% 24,006.75

atuan Pekerjaan (D+E) 184,051.75

370472593.xlsx 451/398 abk 9-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
git-Langit gypsum 25,323.00

8,520.00

70,000.00 3,500.00

85,000.00 4,250.00

100,000.00 500.00

90,000.00 270.00

13,500.00

12,500.00 13,125.00

2,500.00 375.00

22,020.00

15% 3,303.00

atuan Pekerjaan (D+E) 25,323.00

ang Partisi 2x Gypsum Board, Uk (120x240) tebal 9 mm rangka Metal 241,638.00

49,350.00

70,000.00 17,500.00

85,000.00 28,900.00

100,000.00 2,500.00

90,000.00 450.00

160,770.00

65,000.00 47,320.00

25,000.00 102,500.00
12,500.00 3,750.00
300.00 7,200.00

210,120.00
15% 31,518.00
atuan Pekerjaan (D+E) 241,638.00

370472593.xlsx 451/399 abk 9-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

X A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

2 A.5.1.1.1.2-KBPKL 1 Unit Memasang Closet Duduk Washdown + aksessories

A Tenaga

L.01 2.0 OH Pekerja

L.02 1.1 OH Tukang Batu

L.03 0.11 OH Kepala Tukang

L.04 0.01 OH Mandor

Buah Bahan

1 Buah Kloset Duduk washdown

0.06 Kelengkapan 6% dari harga Kloset

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

4 A.5.1.1.4-KBPKL 1 Unit Memasang Urinoir

A Tenaga

L.01 0.50 OH Pekerja

L.02 0.50 OH Tukang Batu

L.03 0.10 OH Kepala Tukang

L.04 0.10 OH Mandor

B Bahan

1.00 Buah Urinoir

0.15 - Perlengkapan 15% Harga Urinoir

6.00 Kg Portland Semen

0.01 m3 Pasir Pasang

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

5 A.5.1.1.5-KBPKL 1 Unit Memasang Wastafel

A Tenaga

370472593.xlsx451/400 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

L.01 0.500 OH Pekerja

L.02 0.145 OH Tukang Batu

L.03 0.150 OH Kepala Tukang

L.04 0.100 OH Mandor

B Bahan

1.00 Buah Wastafel

0.15 - Perlengkapan 15% Harga Wastafel

6.00 Kg Portland Semen

0.01 m3 Pasir Pasang

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx451/401 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

11 A.5.1.1.14 1 buah Pemasangan Floor Drain

A Tenaga

L.01 0.010 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.005 OH Mandor

B Bahan

1 bh Floor Drain

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

16 A.5.1.1.19 1 bh Pemasangan Kran " atau "


A Tenaga

L.01 0.010 OH Pekerja

L.02 0.400 OH Tukang Batu

L.03 0.040 OH Kepala Tukang

L.04 0.005 OH Mandor

B Bahan

1.00 bh Kran Air

0.0025 bh Sealtape

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

21 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis 4"


A Tenaga

L.01 0.135 OH Pekerja

L.02 0.225 OH Tukang Batu

L.03 0.023 OH Kepala Tukang

L.04 0.007 OH Mandor

370472593.xlsx451/402 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

B Bahan

1.20 m' Pipa Galvanis 4"

0.35 Ls Perlengkapan 35% x pipa

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

26 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW 2"


A Tenaga

L.01 0.054 OH Pekerja

L.02 0.090 OH Tukang Batu

L.03 0.009 OH Kepala Tukang

L.04 0.003 OH Mandor

B Bahan

1.20 m' Pipa PVC 2"

0.35 Ls Perlengkapan 35% x pipa

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx451/403 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

27 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW 3"


A Tenaga

L.01 0.081 OH Pekerja

L.02 0.135 OH Tukang Batu

L.03 0.0135 OH Kepala Tukang

L.04 0.004 OH Mandor

B Bahan

1.20 m' Pipa PVC 3"

0.35 Ls Perlengkapan 35% x pipa

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

28 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW 4"


A Tenaga

L.01 0.036 OH Pekerja

L.02 0.060 OH Tukang Batu

L.03 0.006 OH Kepala Tukang

L.04 0.002 OH Mandor

B Bahan

1.20 m' Pipa PVC 4"

0.35 Ls Perlengkapan 35% x pipa

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

31 A.5.1.1.35 1 m' Pemasangan Pipa Beton 20 cm


A Tenaga

L.01 0.140 OH Pekerja

L.02 0.070 OH Tukang Batu

L.03 0.007 OH Kepala Tukang

L.04 0.007 OH Mandor

370472593.xlsx451/404 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

B Bahan

1.10 bh pipa beton

0.03 m3 Batu Bata

3.920 kg Semen Portlan

0.056 m3 Pasir Pasang

0.024 m3 Pasir Urug

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx451/405 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

36 A.5.1.1.37-KBPKL 1 m' Pemasangan U-DITCH (30.30.120 TEBAL 7CM)


A Tenaga

L.01 0.200 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.010 OH Mandor

B Bahan

0.83 bh U-Ditch30.30.120 TEBAL 7CM

3.920 kg Semen Portlan

0.056 m3 Pasir Pasang

0.024 m3 Pasir Urug

C PERALATAN

0.1666667 jam Mobilisasi

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

1 A.5.1.1.38-KBPKL 1 m' Pemasangan U-DITCH (40.40.120 TEBAL 7CM)


A Tenaga

L.01 0.200 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.010 OH Mandor

B Bahan

0.83 bh U-Ditch40.40.120 TEBAL 7CM

3.920 kg Semen Portlan

0.056 m3 Pasir Pasang

0.024 m3 Pasir Urug

C PERALATAN

0.1666667 jam Mobilisasi

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx451/406 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1 A.5.1.1.39-KBPKL 1 m' Pemasangan U-DITCH (40.60.120 TEBAL 7CM)


A Tenaga

L.01 0.200 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.010 OH Mandor

B Bahan

0.83 bh U-Ditch40.60.120 TEBAL 7CM

3.920 kg Semen Portlan

0.056 m3 Pasir Pasang

0.024 m3 Pasir Urug

C PERALATAN

0.1666667 jam Mobilisasi

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx451/407 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1 A.5.1.1.40-KBPKL 1 m' Pemasangan U-DITCH (60.60.120 TEBAL 8CM)


A Tenaga

L.01 0.200 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.010 OH Mandor

B Bahan

0.83 bh U-Ditch60.60.120 TEBAL 8CM

3.920 kg Semen Portlan

0.056 m3 Pasir Pasang

0.024 m3 Pasir Urug

C PERALATAN

0.1666667 jam Mobilisasi

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

1 A.5.1.1.41-KBPKL 1 m' Pemasangan U-DITCH (80.100.120 TEBAL 10CM)


A Tenaga

L.01 0.200 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.010 OH Mandor

B Bahan

0.83 bh U-Ditch80.100.120 TEBAL 10CM

3.920 kg Semen Portlan

0.056 m3 Pasir Pasang

0.024 m3 Pasir Urug

C PERALATAN

0.1666667 jam Mobilisasi

D Jumlah A+B+C

E Overhead & Profit

370472593.xlsx451/408 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

F Harga Satuan Pekerjaan (D+E)

1 A.5.1.1.42-KBPKL 1 m' Pemasangan TUTUP U-DITCH (30.120 TEBAL 7CM)


A Tenaga

L.01 0.200 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.010 OH Mandor

B Bahan

0.83 bh Tutup U-Ditch30.120 TEBAL 7CM

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx451/409 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1 A.5.1.1.43-KBPKL 1 m' Pemasangan TUTUP U-DITCH (40.120 TEBAL 7CM)


A Tenaga

L.01 0.200 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.010 OH Mandor

B Bahan

0.83 bh Tutup U-Ditch40.120 TEBAL 7CM

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

1 A.5.1.1.44-KBPKL 1 m' Pemasangan TUTUP U-DITCH (60.120 TEBAL 10CM)


A Tenaga

L.01 0.200 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.010 OH Mandor

B Bahan

0.83 bh Tutup U-Ditch60.120 TEBAL 10CM

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

1 A.5.1.1.45-KBPKL 1 m' Pemasangan TUTUP U-DITCH (80.120 TEBAL 10CM)


A Tenaga

L.01 0.200 OH Pekerja

L.02 0.100 OH Tukang Batu

L.03 0.010 OH Kepala Tukang

L.04 0.010 OH Mandor

B Bahan

0.83 bh Tutup U-Ditch80.120 TEBAL 10CM

370472593.xlsx451/410 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx451/411 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

PEKERJAAN SANITASI DALAM GEDUNG

Duduk Washdown + aksessories 2,713,885.00

239,900.00

70,000.00 140,000.00

80,000.00 88,000.00

100,000.00 11,000.00

90,000.00 900.00

2,120,000.00

2,000,000.00 2,000,000.00

2,000,000.00 120,000.00

2,359,900.00

15% 353,985.00

2,713,885.00

615,077.50

94,000.00

70,000.00 35,000.00

80,000.00 40,000.00

100,000.00 10,000.00

90,000.00 9,000.00

440,850.00

375,000.00 375,000.00

375,000.00 56,250.00

1,200.00 7,200.00

240,000.00 2,400.00

534,850.00

15% 80,227.50

615,077.50

555,105.00

70,600.00

370472593.xlsx451/412 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
70,000.00 35,000.00

80,000.00 11,600.00

100,000.00 15,000.00

90,000.00 9,000.00

412,100.00

350,000.00 350,000.00

350,000.00 52,500.00

1,200.00 7,200.00

240,000.00 2,400.00

482,700.00

15% 72,405.00

555,105.00

370472593.xlsx451/413 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

40,422.50
10,150.00

70,000.00 700.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 450.00
25,000.00

25,000.00 25,000.00

35,150.00

15% 5,272.50

40,422.50

71,484.00

37,150.00

70,000.00 700.00

80,000.00 32,000.00

100,000.00 4,000.00

90,000.00 450.00

25,010.00

25,000.00 25,000.00

4,000.00 10.00

62,160.00

15% 9,324.00

71,484.00

168,624.50

30,380.00

70,000.00 9,450.00

80,000.00 18,000.00

100,000.00 2,300.00

90,000.00 630.00

370472593.xlsx451/414 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
116,250.00

75,000.00 90,000.00

75,000.00 26,250.00

146,630.00

15% 21,994.50

168,624.50

43,383.75

12,150.00

70,000.00 3,780.00

80,000.00 7,200.00

100,000.00 900.00

90,000.00 270.00

25,575.00

16,500.00 19,800.00

16,500.00 5,775.00

37,725.00

15% 5,658.75

43,383.75

370472593.xlsx451/415 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
70,037.16

18,180.00

70,000.00 5,670.00

80,000.00 10,800.00

100,000.00 1,350.00

90,000.00 360.00

42,721.88

27,562.50 33,075.00

27,562.50 9,646.88

60,901.88

15% 9,135.28

70,037.16

104,233.13

8,100.00

70,000.00 2,520.00

80,000.00 4,800.00

100,000.00 600.00

90,000.00 180.00

82,537.50

53,250.00 63,900.00

53,250.00 18,637.50

90,637.50

15% 13,595.63

104,233.13

130,834.35

16,730.00

70,000.00 9,800.00

80,000.00 5,600.00

100,000.00 700.00

90,000.00 630.00

370472593.xlsx451/416 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
97,039.00

53,000.00 58,300.00

562,500.00 16,875.00

1,200.00 4,704.00

240,000.00 13,440.00

155,000.00 3,720.00

113,769.00

15% 17,065.35

130,834.35

370472593.xlsx451/417 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
415,605.41

23,900.00

70,000.00 14,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 900.00

275,014.00

305,000.00 253,150.00

1,200.00 4,704.00

240,000.00 13,440.00

155,000.00 3,720.00

62,482.01

374,892.06 62,482.01

361,396.01

15% 54,209.40

415,605.41

506,282.91

23,900.00

70,000.00 14,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 900.00

353,864.00

400,000.00 332,000.00

1,200.00 4,704.00

240,000.00 13,440.00

155,000.00 3,720.00

62,482.01

374,892.06 62,482.01

440,246.01

15% 66,036.90

506,282.91

370472593.xlsx451/418 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

620,822.91

23,900.00

70,000.00 14,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 900.00

453,464.00

520,000.00 431,600.00

1,200.00 4,704.00

240,000.00 13,440.00

155,000.00 3,720.00

62,482.01

374,892.06 62,482.01

539,846.01

15% 80,976.90

620,822.91

370472593.xlsx451/419 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
840,357.91

23,900.00

70,000.00 14,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 900.00

644,364.00

750,000.00 622,500.00

1,200.00 4,704.00

240,000.00 13,440.00

155,000.00 3,720.00

62,482.01

374,892.06 62,482.01

730,746.01

15% 109,611.90

840,357.91

1,651,682.91

23,900.00

70,000.00 14,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 900.00

1,349,864.00

1,600,000.00 1,328,000.00

1,200.00 4,704.00

240,000.00 13,440.00

155,000.00 3,720.00

62,482.01

374,892.06 62,482.01

1,436,246.01

15% 215,436.90

370472593.xlsx451/420 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
1,651,682.91

P U-DITCH (30.120 TEBAL 7CM) 199,295.00

23,900.00

70,000.00 14,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 900.00

149,400.00

180,000.00 149,400.00

173,300.00

15% 25,995.00

199,295.00

370472593.xlsx451/421 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

P U-DITCH (40.120 TEBAL 7CM) 227,930.00

23,900.00

70,000.00 14,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 900.00

174,300.00

210,000.00 174,300.00

198,200.00

15% 29,730.00

227,930.00

P U-DITCH (60.120 TEBAL 10CM) 342,470.00

23,900.00

70,000.00 14,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 900.00

273,900.00

330,000.00 273,900.00

297,800.00

15% 44,670.00

342,470.00

P U-DITCH (80.120 TEBAL 10CM) 449,374.00

23,900.00

70,000.00 14,000.00

80,000.00 8,000.00

100,000.00 1,000.00

90,000.00 900.00

366,860.00

442,000.00 366,860.00

370472593.xlsx451/422 abk 10-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

390,760.00

15% 58,614.00

449,374.00

370472593.xlsx451/423 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM

2 A.4.2.1.2 1 kg Pemasangan Rangka Kuda-kuda Baja IWF

A Tenaga

L.01 0.06 OH Pekerja

L.02 0.06 OH Tukang Besi

L.03 0.006 OH Kepala Tukang

L.04 0.003 OH Mandor

B Bahan

1.15 kg Besi Baja IWF

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

10 A.4.2.1.11.1-KBPKL 1 m' Pemasangan Kusen Pintu/jendela Allumunium polos

A Tenaga

L.01 0.043 OH Pekerja

L.02 0.043 OH Tukang Besi

L.03 0.0043 OH Kepala Tukang

L.04 0.0021 OH Mandor

B Bahan

1.1 m' Profil Allumunium

2 buah Skrup Fixer

0.06 Tube Sealant

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

11 A.4.2.1.11.2-KBPKL 1 m' Pemasangan Kusen Pintu/jendela Allumunium warna

A Tenaga

370472593.xlsx 451/424 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

L.01 0.043 OH Pekerja

L.02 0.043 OH Tukang Besi

L.03 0.0043 OH Kepala Tukang

L.04 0.0021 OH Mandor

B Bahan

1.1 m' Profil Allumunium warna

2 buah Skrup Fixer

0.06 Tube Sealant

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/425 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

12 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm

A Tenaga

L.01 0.085 OH Pekerja

L.02 0.085 OH Tukang Besi

L.03 0.0085 OH Kepala Tukang

L.04 0.0042 OH Mandor

B Bahan

4.4 m' Profil Allumunium

14.6 m' Allumunium Strip

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

13 A.4.2.1.13.1-KBPKL 1 m2 Pemasangan Pintu / jendela Kaca Rangka Allumunium polos

A Tenaga

L.01 0.085 OH Pekerja

L.02 0.085 OH Tukang Besi

L.03 0.009 OH Kepala Tukang

L.04 0.005 OH Mandor

B Bahan

4.4 m' Pintu/jendela Allumunium

4.5 m' Profil Kaca

0.27 tube Sealant

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

14 A.4.2.1.13.2-KBPKL 1 m2 Pemasangan Pintu/jendela Kaca Rangka Allumunium warna

A Tenaga

370472593.xlsx 451/426 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

L.01 0.085 OH Pekerja

L.02 0.085 OH Tukang Besi

L.03 0.009 OH Kepala Tukang

L.04 0.005 OH Mandor

B Bahan

4.4 m' Pintu/jendela Allumunium warna

4.5 m' Profil Kaca

0.27 tube Sealant

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

16 A.4.2.1.15 1 m2 Pemasangan Terali Besi Strip (2x3) cm

A Tenaga

L.01 1.67 OH Pekerja

L.02 1.67 OH Tukang Las

L.03 0.167 OH Kepala Tukang

L.04 0.083 OH Mandor

B Bahan

6.177 m' Besi Strip 2x3

27.08 cm Pengelasan

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/427 abk 11-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

PEKERJAAN BESI & ALLUMUNIUM

25,236.75

9,870.00

70,000.00 4,200.00

80,000.00 4,800.00

100,000.00 600.00

90,000.00 270.00

12,075.00

10,500.00 12,075.00

21,945.00

15% 3,291.75

25,236.75

en Pintu/jendela Allumunium polos 108,984.35

7,069.00

70,000.00 3,010.00

80,000.00 3,440.00

100,000.00 430.00

90,000.00 189.00

87,700.00

75,000.00 82,500.00

800.00 1,600.00

60,000.00 3,600.00

94,769.00

15% 14,215.35

108,984.35

en Pintu/jendela Allumunium warna 121,634.35

7,069.00

370472593.xlsx 451/428 abk 11-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
70,000.00 3,010.00

80,000.00 3,440.00

100,000.00 430.00

90,000.00 189.00

98,700.00

85,000.00 93,500.00

800.00 1,600.00

60,000.00 3,600.00

105,769.00

15% 15,865.35

121,634.35

370472593.xlsx 451/429 abk 11-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
479,524.70

13,978.00

70,000.00 5,950.00

80,000.00 6,800.00

100,000.00 850.00

90,000.00 378.00

403,000.00

75,000.00 330,000.00

5,000.00 73,000.00

416,978.00

15% 62,546.70

479,524.70

u / jendela Kaca Rangka Allumunium polos 521,295.00

14,100.00

70,000.00 5,950.00

80,000.00 6,800.00

100,000.00 900.00

90,000.00 450.00

439,200.00

90,000.00 396,000.00

6,000.00 27,000.00

60,000.00 16,200.00

453,300.00

15% 67,995.00

521,295.00

u/jendela Kaca Rangka Allumunium warna 571,895.00

14,100.00

370472593.xlsx 451/430 abk 11-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
70,000.00 5,950.00

80,000.00 6,800.00

100,000.00 900.00

90,000.00 450.00

483,200.00

100,000.00 440,000.00

6,000.00 27,000.00

60,000.00 16,200.00

497,300.00

15% 74,595.00

571,895.00

335,801.29

274,670.00

70,000.00 116,900.00

80,000.00 133,600.00

100,000.00 16,700.00

90,000.00 7,470.00

17,331.12

1,050.00 6,485.85

400.49 10,845.27

292,001.12

15% 43,800.17

335,801.29

370472593.xlsx 451/431 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA

16 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm

A Tenaga

L.01 0.015 OH Pekerja

L.02 0.15 OH Tukang Kayu

L.03 0.015 OH Kepala Tukang

L.04 0.00075 OH Mandor

B Bahan

1.1 m2 Kaca Cermin

C PERALATAN

D Jumlah A+B+C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/432 abk 12-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

PEKERJAAN KUNCI dan KACA

175,797.63

15,367.50

70,000.00 1,050.00

85,000.00 12,750.00

100,000.00 1,500.00

90,000.00 67.50

137,500.00

125,000.00 137,500.00

152,867.50

15% 22,930.13

175,797.63

370472593.xlsx 451/433 abk 12-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

XIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING

1 A.4.4.3.32-KBPKL 1 m2 Pemasangan Lantai Keramik 10x 20 cm

A Tenaga

L.01 0.25 OH Pekerja

L.02 0.17 OH Tukang Batu

L.03 0.017 OH Kepala Tukang

L.04 0.017 OH Mandor

B Bahan

53.00 Buah Keramik 10 x 20 cm

6.912 Kg Portland Semen

0.691 Kg Semen warna

0.035 m3 Pasir Pasang

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

2 A.4.4.3.33-KBPKL 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm

A Tenaga

L.01 0.25 OH Pekerja

L.02 0.17 OH Tukang Batu

L.03 0.017 OH Kepala Tukang

L.04 0.017 OH Mandor

B Bahan

106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm

6.912 Kg Portland Semen

0.691 Kg Semen warna

0.035 m3 Pasir Pasang

C PERALATAN

D Jumlah A + B + C

370472593.xlsx 451/434 abk 13-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

3 A.4.4.3.34-KBPKL 1 m2 Pemasangan Lantai Keramik 33 x 33 cm

A Tenaga

L.01 0.25 OH Pekerja

L.02 0.17 OH Tukang Batu

L.03 0.017 OH Kepala Tukang

L.04 0.017 OH Mandor

B Bahan

10 Buah Ubin Keramik 33 x 33 cm

6.912 Kg Portland Semen

0.035 m3 Pasir Pasang

0.691 Kg Semen Warna

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/435 abk 13-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

9 A.4.4.3.35.9-KBPKL 1 m2 Pemasangan Lantai Granite Tile KW A

A Tenaga

L.01 0.25 OH Pekerja

L.02 0.17 OH Tukang Batu

L.03 0.017 OH Kepala Tukang

L.04 0.017 OH Mandor

B Bahan

6.56 Buah Granite tile motif KW A

6.912 Kg Portland Semen

0.035 m3 Pasir Pasang

0.691 Kg Semen Warna

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

12 A.4.4.3.36.2-KBPKL 1 m2 Pemasangan Lantai Keramik 20 x 20 cm motif

A Tenaga

L.01 0.25 OH Pekerja

L.02 0.17 OH Tukang Batu

L.03 0.017 OH Kepala Tukang

L.04 0.017 OH Mandor

B Bahan

26.25 Buah Ubin Keramik 20 x 20 cm

6.912 Kg Portland Semen

0.691 Kg Semen Warna

0.035 m3 Pasir Pasang

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/436 abk 13-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

28 A.4.4.3.54-KBPKL 1 m2 Pemasangan Dinding Keramik 25x25 cm,

A Tenaga

L.01 0.25 OH Pekerja

L.02 0.17 OH Tukang Batu

L.03 0.017 OH Kepala Tukang

L.04 0.017 OH Mandor

B Bahan

17 Buah Keramik

6.912 Kg Portland Semen

0.018 m3 Pasir Pasang

0.691 Kg Semen Warna

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/437 abk 13-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

PEKERJAAN PENUTUP LANTAI dan DINDING

133,060.06

34,330.00

70,000.00 17,500.00

80,000.00 13,600.00

100,000.00 1,700.00

90,000.00 1,530.00

81,374.40

1,090.00 57,770.00

1,200.00 8,294.40

10,000.00 6,910.00

240,000.00 8,400.00

115,704.40

15% 17,355.66

133,060.06

i Keramik Uk. 10 x 10 cm / 5 x 20 cm 133,060.06

34,330.00

70,000.00 17,500.00

80,000.00 13,600.00

100,000.00 1,700.00

90,000.00 1,530.00

81,374.40

545.00 57,770.00

1,200.00 8,294.40

10,000.00 6,910.00

240,000.00 8,400.00

115,704.40

370472593.xlsx 451/438 abk 13-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
15% 17,355.66

133,060.06

136,902.33

34,330.00

70,000.00 17,500.00

80,000.00 13,600.00

100,000.00 1,700.00

90,000.00 1,530.00

84,715.50

6,111.11 61,111.10

1,200.00 8,294.40

240,000.00 8,400.00

10,000.00 6,910.00

119,045.50

15% 17,856.83

136,902.33

370472593.xlsx 451/439 abk 13-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
324,377.92

34,330.00

70,000.00 17,500.00

80,000.00 13,600.00

100,000.00 1,700.00

90,000.00 1,530.00

247,737.76

34,166.67 224,133.36

1,200.00 8,294.40

240,000.00 8,400.00

10,000.00 6,910.00

282,067.76

15% 42,310.16

324,377.92

126,999.56

34,330.00

70,000.00 17,500.00

80,000.00 13,600.00

100,000.00 1,700.00

90,000.00 1,530.00

76,104.40

2,000.00 52,500.00

1,200.00 8,294.40

10,000.00 6,910.00

240,000.00 8,400.00

110,434.40

15% 16,565.16

126,999.56

370472593.xlsx 451/440 abk 13-14


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
103,769.56

34,330.00

70,000.00 17,500.00

80,000.00 13,600.00

100,000.00 1,700.00

90,000.00 1,530.00

55,904.40

2,140.00 36,380.00

1,200.00 8,294.40

240,000.00 4,320.00

10,000.00 6,910.00

90,234.40

15% 13,535.16

103,769.56

370472593.xlsx 451/441 abk 13-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

XIV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

14 A.4.7.1.10.1-KBPKL 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap

A Tenaga

L.01 0.02 OH Pekerja

L.02 0.063 OH Tukang Cat

L.03 0.0063 OH Kepala Tukang

L.04 0.0030 OH Mandor

B Bahan

0.1 Kg Plamir

0.1 Kg Cat Dasar

0.26 Kg Cat A Penutup 2 kali

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

15 A.4.7.1.10.2-KBPKL 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap

A Tenaga

L.01 0.02 OH Pekerja

L.02 0.063 OH Tukang Cat

L.03 0.0063 OH Kepala Tukang

L.04 0.0030 OH Mandor

B Bahan

0.1 Kg Plamir

0.1 Kg Cat Dasar

0.26 Kg Cat Penutup 2 kali

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/442 abk 14-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.7.1.10.3-KBPKL 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap

A Tenaga

L.01 0.02 OH Pekerja

L.02 0.063 OH Tukang Cat

L.03 0.0063 OH Kepala Tukang

L.04 0.0030 OH Mandor

B Bahan

0.1 Kg Plamir

0.1 Kg Cat Dasar

0.26 Kg Cat A Penutup 2 kali

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/443 abk 14-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.7.1.10.4-KBPKL 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap

A Tenaga

L.01 0.02 OH Pekerja

L.02 0.063 OH Tukang Cat

L.03 0.0063 OH Kepala Tukang

L.04 0.0030 OH Mandor

B Bahan

0.1 Kg Plamir

0.1 Kg Cat Dasar

0.26 Kg Cat Penutup 2 kali

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

18 A.4.7.1.11.3-KBPKL 1 m2 Pengecatan Langit-Langit (1lap.Cat dasar, 1lap Cat Penu

A Tenaga

L.01 0.060 OH Pekerja

L.02 0.080 OH Tukang Cat

L.03 0.0040 OH Kepala Tukang

L.04 0.0030 OH Mandor

B Bahan

0.12 Kg Cat Dasar

0.18 Kg Cat Penutup

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/444 abk 14-14


JUMLAH
URAIAN PAKERJAAN HARGA BAHAN/UPAH
Rp Rp

ATUAN PEKERJAAN PENGECATAN

Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) Interior Kw A 22,011.00

7,340.00

70,000.00 1,400.00

80,000.00 5,040.00

100,000.00 630.00

90,000.00 270.00

11,800.00

12,000.00 1,200.00

15,000.00 1,500.00

35,000.00 9,100.00

19,140.00

15% 2,871.00

22,011.00

Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) Interior, Kw B 17,346.60

7,340.00

70,000.00 1,400.00

80,000.00 5,040.00

100,000.00 630.00

90,000.00 270.00

7,744.00

12,000.00 1,200.00

15,000.00 1,500.00

19,400.00 5,044.00

15,084.00

15% 2,262.60

17,346.60

370472593.xlsx 451/445 abk 14-14


JUMLAH
URAIAN PAKERJAAN HARGA BAHAN/UPAH
Rp Rp

Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) exterior Kw A 34,270.00

7,340.00

70,000.00 1,400.00

80,000.00 5,040.00

100,000.00 630.00

90,000.00 270.00

22,460.00

12,000.00 1,200.00

15,000.00 1,500.00

76,000.00 19,760.00

29,800.00

15% 4,470.00

34,270.00

370472593.xlsx 451/446 abk 14-14


JUMLAH
URAIAN PAKERJAAN HARGA BAHAN/UPAH
Rp Rp
Tembok Baru (1lap.Plamir, 1lap Cat Dasar,2 lap. Cat Penutup) exterior, Kw B 30,383.00

7,340.00

70,000.00 1,400.00

80,000.00 5,040.00

100,000.00 630.00

90,000.00 270.00

19,080.00

12,000.00 1,200.00

15,000.00 1,500.00

63,000.00 16,380.00

26,420.00

15% 3,963.00

30,383.00

an Langit-Langit (1lap.Cat dasar, 1lap Cat Penutup) 19,046.30

11,270.00

70,000.00 4,200.00

80,000.00 6,400.00

100,000.00 400.00

90,000.00 270.00

5,292.00

15,000.00 1,800.00

19,400.00 3,492.00

16,562.00

15% 2,484.30

19,046.30

370472593.xlsx 451/447 abk 14-14


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

XV A.8.4.1 HARGA SATUAN PEKERJAAN PEMASAN

36 A.8.4.1.36-KBPKL 1 m Pemasangan 1 m pipa GIP 250 mm

A Tenaga

L.01 0.949 OH Pekerja

L.02 0.475 OH Tukang pipa

L.04 0.095 OH Mandor

B Bahan

1.00 m Pipa GIP 250 mm

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

51 A.8.4.1.14N-KBPKL 1 m Pemasangan 1 m pipa PVC 200 mm (SN

A Tenaga

L.01 0.189 OH Pekerja

L.02 0.095 OH Tukang pipa

L.04 0.019 OH Mandor

B Bahan

1.00 m Pipa PVC 200 mm

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

52 A.8.4.1.15N-KBPKL 1 m Pemasangan 1 m pipa PVC 250 mm (SN

A Tenaga

L.01 0.256 OH Pekerja

L.02 0.128 OH Tukang pipa

L.04 0.026 OH Mandor

370472593.xlsx 451/448 abk 15-35


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

B Bahan

1.00 m Pipa PVC 250 mm

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

53 A.8.4.1.16N-KBPKL 1 m Pemasangan 1 m pipa PVC 300 mm (SN

A Tenaga

L.01 0.294 OH Pekerja

L.02 0.147 OH Tukang pipa

L.04 0.029 OH Mandor

B Bahan

1.00 m Pipa PVC 300 mm

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit

F Harga Satuan Pekerjaan (D+E)

370472593.xlsx 451/449 abk 15-35


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

HARGA SATUAN PEKERJAAN PEMASANGAN PIPA

Pemasangan 1 m pipa GIP 250 mm

112,980.00

70,000.00 66,430.00

80,000.00 38,000.00

90,000.00 8,550.00

0.00 -

112,980.00

15% 16,947.00

Harga Satuan Pekerjaan (D+E) 129,927.00

Pemasangan 1 m pipa PVC 200 mm (SNI / MOF 10 BAR) 25,921.00

22,540.00

70,000.00 13,230.00

80,000.00 7,600.00

90,000.00 1,710.00

0.00 -

22,540.00

15% 3,381.00

Harga Satuan Pekerjaan (D+E) 25,921.00

Pemasangan 1 m pipa PVC 250 mm (SNI / MOF 10 BAR) 35,075.00

30,500.00

70,000.00 17,920.00

80,000.00 10,240.00

90,000.00 2,340.00

370472593.xlsx 451/450 abk 15-35


HARGA JUMLAH
URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
-

0.00 -

30,500.00

15% 4,575.00

Harga Satuan Pekerjaan (D+E) 35,075.00

Pemasangan 1 m pipa PVC 300 mm (SNI / MOF 10 BAR) 40,192.50

34,950.00

70,000.00 20,580.00

80,000.00 11,760.00

90,000.00 2,610.00

0.00 -

34,950.00

15% 5,242.50

Harga Satuan Pekerjaan (D+E) 40,192.50

370472593.xlsx 451/451 abk 15-35

Anda mungkin juga menyukai