PT.

BINA SARANA SUKSES


PLANT DEPARTEMENT SITE PMSS
PLAN PS & PLAN BACKLOG
NO PLAN PS UNIT MODEL HM PS PS TYPE UPDATE HM HM ACTUAL DEVIASI STATUS TGL PS START CLOSE FINISH KETERANGAN
EXTEND AFTER
9 03 Januari 2023 X175 ZX470LC-5G 22250 PS1 03/01/2023 22234,1 -15,9 OPEN
X181 READY
15 04 Januari 2023 HT81076 CMT106 2750 PS1 03/01/2023 2668,4 -81,6 PROGRES

19 05 Januari 2023 X181 ZX470LC-5G 22750 PS1 03/01/2023 22711,9 -38,1 PROGRES

20 05 Januari 2023 DZ270 D85E-SS-2 11250 PS1 03/01/2023 11176,7 -73,3 PROGRES

21 05 Januari 2023 HT81076 CMT106 2750 PS1 03/01/2023 2668,4 -81,6 PROGRES

23 05 Januari 2023 LVTC02 TRITON-4D56 4750 PS1 03/01/2023 4677 -73 OPEN

24 05 Januari 2023 TL755 AM-LTM-4000KS 19000 PS3 03/01/2023 18952,9 -47,1 CLOSE

PLAN PS & PLAN BACKLOG 06 Januari 2023 0 JAM


CLOSE DUR COMPARTMENT PAP
NO TANGGAL UNIT MODEL HM PS PS TYPE UPDATE HM HM ACTUAL DEVIASI STATUS START PS KET DUR PS DUR B/L WELDING TYRE MO BACKLOG DESCRIPTION BACKLOG 0 JAM LOC PS
PS PCR

1 06 Januari 2023 X9338 ZX200-5G 2750 PS1 03/01/2023 2686,2 -63,8 MINUS 3 JAM 0 JAM 0 JAM 0 JAM 0 0 3 JAM

RING,DUST SHANTUI
BUSHING SHANTUI
2 06 Januari 2023 DZ327 DH24-C3 RS 1750 PS1 03/01/2023 1678,4 -71,6 MINUS 3 JAM 0 JAM 0 JAM 0 JAM 130025890 PISTON RING SHANTUI 3 JAM
RING SHANTUI
RETAINER SHANTUI

4 06 Januari 2023 LT021 2642 250 PS1 03/01/2023 188,9 -61,1 MINUS 3 JAM 0 JAM 0 JAM 0 JAM 0 0 3 JAM

PLAN PS & PLAN BACKLOG 07 Januari 2023 0 JAM


CLOSE DUR COMPARTMENT PAP
NO TANGGAL UNIT MODEL HM PS PS TYPE UPDATE HM HM ACTUAL DEVIASI STATUS START PS KET DUR PS DUR B/L WELDING TYRE MO BACKLOG DESCRIPTION BACKLOG 0 JAM LOC PS
PS PCR

1 07 Januari 2023 X9244 ZX200-5G 6500 PS2 03/01/2023 6436,4 -63,6 MINUS 5 JAM 0 JAM 0 JAM 0 JAM 0 0 5 JAM

2 07 Januari 2023 DZ236 D85E-SS-2 22250 PS1 03/01/2023 22175,3 -74,7 MINUS 3 JAM 0 JAM 0 JAM 0 JAM 0 0 3 JAM

4 07 Januari 2023 GS014 NTA855-G1B 20000 PS4(G) 03/01/2023 19941,5 -58,5 MINUS 6 JAM 0 JAM 0 JAM 0 JAM 0 0 6 JAM

SCH REPLACE ELEMENT RACOR 05 Januari 2023


NO TANGGAL UNIT DESCRIPTION

1 05 Januari 2023 HT81176 REPLACE ELEMENT RACOR


2 05 Januari 2023 HT81174 REPLACE ELEMENT RACOR
3 05 Januari 2023 HT81075 REPLACE ELEMENT RACOR
4 05 Januari 2023 GS029 REPLACE ELEMENT RACOR

PREPARED BY ACKNOWLEDGE

Admin/Planner Kabag/Spv PLANT Kabag Logistic Kabag Engineering Kabag Produksi