NO PM NUMBER WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

HME

13 GT01-PM-RTN-HME-MBV-BR004 202313277 PM GT01 PENGECEKAN VISUAL PIPING MISS ELIMINATOR HME 4/8/2023 Asmar, Burhanudin 2 01:30 03:00
14 GT01-PM-RTN-HME-MBV-BR008 202313278 PM GT01 PENGECEKAN VISUAL PIPING EVAC PUMP HME 4/8/2023 Asmar, Burhanudin 2 01:30 03:00
MAN HOUR REQUARED 42:00
MAN HOUR AVAILABLE 80
% UTILITY 53%

NO PM NUMBER WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

HKI & HLI

25 GT01-PM-RTN-HLI-MBV-GH009 202313264 PM GT01 PENGECEKAN KELISTRIKAN BEARING PUMP BQ HLI-GT 4/8/2023 Ahmad, Rahmanda 2 02:00 04:00
26 GT01-PM-RTN-HKI-MBN-AT008 202313296 PM GT01 PENGECEKAN INSTRUMENT DAN CONTROL PRESSURE FORWARDING PUMPHLI-GT 4/8/2023 Ahmad, Rahmanda 2 01:00 02:00
27 GT01-PM-RTN-HKI-MBN-AT013 202313297 PM GT01 PENGECEKAN INSTRUMENT DAN CONTROL PRESSUURE LOW PRESSURE HLI-GT 4/8/2023 Ahmad, Rahmanda 2 01:00 02:00
28 GT01-PM-RTN-HKI-MBN-AT015 202313298 PM GT01 PENGECEKAN INSTRUMENT DAN CONTROL LIQUID VALVE VC3-1 HLI-GT 4/8/2023 Ahmad, Rahmanda 2 01:00 02:00
29 GT01-PM-RTN-HKI-MBN-BR002 202313299 PM GT01 PENGECEKAN INSTRUMENT DAN CONTROL PIPING MAIN ATOMIZING AIR COMPRESSOR
HLI-GT 4/8/2023 Ahmad, Rahmanda 2 01:00 02:00

MAN HOUR REQUARED 76:00


MAN HOUR AVAILABLE 80
% UTILITY 95%
PEMELIHARAAN RUTIN PLTD SELAYAR NO DOK :

WEEK-31 (31 JULI - 4 AGUSTUS 2023) REV :

PIP UPDK TELLO

NO WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL FEEDBACK

PM PLTD SELAYAR

HME

34 SL07-PM-RTN-HME-MJA-AV001 PEMELIHARAAN P3 [CUMMINS 2] CYLINDER HEAD 1-16 HME 04 August 2023 Marwan, Ishaq 2 01:00 02:00
35 SL07-PM-RTN-HME-MJN-BN001 PEMELIHARAAN P3 [CUMMINS 2] INJECTOR 01-16 HME 04 August 2023 Marwan, Agus 2 01:00 02:00
36 SL07-PM-RTN-HME-MJA-AE001 PEMELIHARAAN P2 [CUMMINS 2] CRANKSHAFT HME 04 August 2023 Marwan, Khareum 2 01:00 02:00
37 SL07-PM-RTN-HME-MJV-AT001 PEMELIHARAAN P2 [CUMMINS 2] LUBE OIL FILTER & BYPASS HME 04 August 2023 Marwan, Samsul 2 01:00 02:00
38 SL07-PM-RTN-HME-MJG-AC001 PEMELIHARAAN P1 [CUMMINS 2] RADIATOR HME 04 August 2023 Marwan, Imran 2 01:00 02:00
39 SL07-PM-RTN-HME-MJN-AT001 PEMELIHARAAN P1 [CUMMINS 2] FUEL FILTER & PIPING HME 04 August 2023 Marwan, Ishaq 2 01:00 02:00
40 SL07-PM-RTN-HME-MJP-AG001 PEMELIHARAAN P1 [CUMMINS 2] ALTERNATOR HME 04 August 2023 Marwan, Agus 2 01:00 02:00
41 SL07-PM-RTN-HME-MJQ-AZ001 PEMELIHARAAN P1 [CUMMINS 2] INTAKE MANIFOLD 01 HME 04 August 2023 Marwan, Khareum 2 01:00 02:00
MAN HOUR REQUARED 112:00 2:48

MAN HOUR AVAILABLE 200


% LOAD BALANCE 56,00%
HLI

15 SL07-PM-RTN-HLI-BBA-GS001 PEMELIHARAAN P2 [CUMMINS 2] SWITCHGEAR EQUIP. (VACUM CIRCUIT BREAKER) HLI 04 August 2023 Fachrul, Engga 2 01:00 02:00
16 SL07-PM-RTN-HLI-BAT-AH001 HLI
PEMELIHARAAN P1 [CUMMINS 2] HEATING, STORAGE EQUIPMENT, TRANFORMER, ISOLATING LV & HV 04 August 2023 Fachrul, Engga, Rizal D 3 01:00 03:00
17 SL07-PM-RTN-HLI-BBT-GD001 HLI
PEMELIHARAAN P1 [CUMMINS 2] EQUPMENT 6,3 KV HV & LV, STATION SERVICE TRAFO 04 August 2023 Fachrul, Engga 2 01:00 02:00
18 SL07-PM-RTN-HLI-BTR-GR001 PEMELIHARAAN P1 [CUMMINS 2] 12 V BATTERY 150 AH SYSTEM FOR CUMMINS #2 HLI 04 August 2023 Fachrul, Engga 2 01:00 02:00
MAN HOUR REQUARED 67:00 4:28

MAN HOUR AVAILABLE 120


% UTILITY 56%
PEMELIHARAAN RUTIN PLTD TELLO NO DOK :

WEEK-31 (31 JULI - 4 AGUSTUS 2023) REV :

PIP UPDK TELLO

NO PM NUMBER WO NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

HLI

15 DT00-PM-RTN-HLI-BTA-GR018 202313302 PEMELIHARAAN P1 110 VDC BATTERY UNIT 1-2 COMMON PLTD SWD D SWD HLI 04 August 2023 Kafrawi, Jabbar 2 02:00 04:00
MAN HOUR REQUARED 60:00
MAN HOUR AVAILABLE 80
% UTILITY 75%

NO WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

HME

MAN HOUR REQUARED 100:00


MAN HOUR AVAILABLE 120
% UTILITY 83%