PEMBANGUNAN AKSES
SIMPANG TAK SEBIDANG (STS) MARTADINATA

WEEKLY MEETING
MINGGU – 23
PERIODE 16 JANUARI 2023 – 22 JANUARI 2023
OVERVIEW SAFETY
Jasa Pemborongan Pekerjaan Pembangunan Akses Simpang Tak Sebidang
(STS) Martadinata Jalan Tol Serpong – Cinere
S TAT I S T I K H S E
JUMLAH MANPOWER DAN MANHOURS STATISTIK KECELAKAAN KERJA
JUMLAH TENAGA KERJA DAN JAM KERJA PEKAN LALU MINGGU 23 AKUMULASI KATEGORI PEKAN INI AKUMULASI

Jumlah Personil PT PP 63 63 NEARMISS 0 6


Jumlah Personil Subkontraktor 98 100 FIRST AID CASE 0 3

Jumlah Total Manpower


161 166 MEDICAL TREAMENT 0 0

Jam Kerja PT PP 85.931 5.292 LOST TIME INJURITY 0 0


Jam Kerja Mandor/Subkon 98.716 7.936 FATALITY 0 0
Jumlah Jam Kerja 172.740 13.228 172.740 PROPERTY DAMAGE 0 0
Jumlah Kehilangan Hari Kerja akibat LTI 0 0 0 SAFE MANHOURS 172.740

MONITORING ALAT BERAT MONITORING PERSONIL HSE


ALAT JUMLAH ALAT JUMLAH KETERANGAN JUMLAH
EXCAVATOR PC200 3 UNIT ROTARY DRILLING RIG 1 UNIT HSE ON DUTY 6
TRUCK MOUNTED CRANE 1 UNIT CRAWLER CRANE 1 UNIT PARAMEDIC ON DUTY 1
DUMP TRUCK INDEX 8 2 UNIT EXCAVATOR PC75 (Wheel) 1 UNIT FLAGMAN ON DUTY 6
V I S UA L I SA S I K E G I ATA N H S E

TOOLBOX MEETING HOUSEKEEPING

FIT FOR DUTY PEMBUATAN AKSES PEJALAN KAKI


V I S UA L I SA S I K E G I ATA N H S E

HSE MEETING HSE INDUCTION PEKERJA PENGECATAN PARAPET

INSPEKSI HYGIENE KATERING


V I S UA L I SA S I K E G I ATA N H S E

INSPEKSI EYE WASH FOGGING AREA KANTOR

KEGIATAN JUMAT BERKAH


STOP WORK AUTHORITY

DESKRIPSI SWA

INISIATOR AFIF ALAMSYAH

JABATAN HSE OFFICER

UNSAFE ACTION
KATAGORI
LEVEL 2 (>24 JAM)

TANGGAL 15 JANUARI 2023

CRANE UNTUK
PEMBONGKARAN SEGMEN PCI
DESKRIPSI
GIRDER PT WITON TIDAK
TEMUAN
DILENGKAPI DENGAN
LOAD M0MENT INDICATOR

LOKASI STS MARTADINATA

PEMBONGKARAN SEGMEN PCI


PEKERJAAAN
GIRDER PT WITON
CLOSING STOP WORK AUTHORITY

DESKRIPSI PERBAIKAN
PENDATANGAN UNIT CRANE PENGGANTI
TAHUN 2015 KAPASITAS 50 TON DENGAN
DILENGKAPI LOAD MOMENT IINDICATOR

ESTIMASI BIAYA PERBAIKAN

RP 12.000.000
MONITORING CUACA (PEKAN 23)
SENIN, 23 JANUARI 2023 SELASA 24 JANUARI 2023 RABU, 25 JANUARI 2023 KAMIS, 26 JANUARI 2023
24 24 24 24
23 13 23 13 23 13 23 13
0 0 0 0
11 1 11 1 11 1 11 1
22 14 22 14 22 14 22 14
10 2 10 2 10 2 10 2

21 9 3 15 21 9 3 15 21 9 3 15 21 9 3 15

8 4 8 4 8 4 8 4
20 16 20 16 20 16 20 16
7 5 7 5 7 5 7 5
6 6 6 6
19 17 19 17 19 17 19 17
18 18 18 18

JUMAT, 27 JANUARI 2023 SABTU, 28 JANUARI 2023 MINGGU, 29 JANUARI 2023


24 24 24
23 13 23 13 23 13
0 0 0
11 1 11 1 11 1
22 14 22 14 22 14
10 2 10 2 10 2

21 9 3 15 21 9 3 15 21 9 3 15

8 4 8 4 8 4
20 16 20 16 20 16
7 5 7 5 7 5
6 6 6
19 17 19 17 19 17
18 18 18
TOTAL JUMLAH GERIMIS/HUJAN DALAM SEMINGGU (PEKAN 23) = 12 JAM
• Pagi – Sore (06:00 – 18:00) : 4 Jam * Kondisi dilapangan tidak dapat dikerjakan pada saat hujan
• Sore – Malam (18:00 – 06:00) : 9 Jam
OVERVIEW QUALITY
Jasa Pemborongan Pekerjaan Pembangunan Akses Simpang Tak Sebidang
(STS) Martadinata Jalan Tol Serpong – Cinere
KJanuary
A L E N D E R R E N2023
C A N A K E R JA JA N UA R I 2 0 2 3
Sunday Monday Tuesday Wednesday Thursday Friday Saturday

1 2 3 4 5 6 7
Inspeksi rutin Inspeksi rutin Inspeksi rutin Uji kuat tekan Inspeksi rutin Inspeksi rutin Inspeksi rutin
lapangan uji kuat lapangan uji kuat lapangan uji kuat beton trial mix BP. lapangan uji kuat lapangan uji kuat lapangan uji kuat
tekan beton harian tekan beton harian tekan beton harian Presisi umur 28 hari tekan beton harian tekan beton harian tekan beton harian

8 9 10 11 12 13 14
Inspeksi rutin Inspeksi rutin Tes mortar DS8 Pengujian PDA A2 Inspeksi rutin Inspeksi rutin Inspeksi rutin
lapangan uji kuat lapangan uji kuat UMUR 14 HARI BP 32 STS lapangan uji kuat lapangan uji kuat lapangan uji kuat
tekan beton harian tekan beton harian tekan beton harian tekan beton harian tekan beton harian

15 16 17 18 19 20 21
Inspeksi rutin Inspeksi rutin Inspeksi rutin Inspeksi rutin inspeksi produksi Trial mix beton BP. Inspeksi rutin
lapangan uji kuat lapangan uji kuat lapangan uji kuat lapangan uji kuat precast Presisi kelas E & P lapangan uji kuat
tekan beton harian tekan beton harian tekan beton harian tekan beton harian MCB/Barrier PT. tekan beton harian
AMB, SUBANG

: Realisasi

: Dibatalkan

: Direncanakan
T E M UA N K E T I DA K S ES UA I A N
TINDAK LANJUT RETAK PERMUKAAN PADA TOPING KOLOM P1 OP BUKIT INDAH

Investigasi retak permukaan pada toping kolom P1 OP Bukit Indah bersama tim aplikator Sika
T E M UA N K E T I DA K S ES UA I A N
TINDAK LANJUT RETAK PERMUKAAN PADA TOPING KOLOM P1 OP BUKIT INDAH

Perbaikan retak permukaan dengan metode gravity menggunakan material sikadur 752
P E N G UJ I A N L A PA N G A N
PENGUJIAN HAMMER BOX CULVERT (OP PONDOK CABE)
PENGUJIAN LAPANGAN
PENGUJIAN REFLECTIVE PENGECATAN MARKA ( MAINROAD TOL SERPONG – CINERE )
P E N G UJ I A N B E TO N
UJI TEKAN BETON BP ADHIMIX KELAS B1, C & E (UMUR 7, 14 & 28 HARI)

LC MAINROAD 12m UMUR 7 HARI KELAS E HEAD WALL A1 BI UMUR 7 HARI KELAS C

DINDING A1 TAHAP 2 UMUR 14 HARI KELAS C KOLOM P1 TAHAP 1 BUKIT INDAH UMUR 28 HARI KELAS B1
P E N G UJ I A N B E TO N
UJI TEKAN BETON BP ADHIMIX KELAS B2 (UMUR 7, 14 & 28 HARI)

BP 6 & 11 P1 2 STS UMUR 7 HARI BP 4, 5, 15, 16, 25, 27, 33, 34 & 35 ABT 2 STS UMUR 28 HARI

BP 1, 4, 5, 7, 8, 9, 10, 12, 13, 14, 15, 16, 26, 27, 28, 29 & 30 STS UMUR 14 HARI
P E N C A PA I A N & R E N C A N A K E R JA
PEKAN 16 PEKAN 17 : Realisasi
KEGIATAN
16 17 18 19 20 21 22 23 24 25 26 27 28 29
: Dibatalkan
Pengetesan mortar DS8/8a
umur 28 hari
: Direncanakan
Trial mortar pad material fosroc

Inspeksi Rutin Lapangan dan Uji


Kuat Tekan Beton Harian
U J I K U AT T E K A N B E T O N U M U R 7 & 1 4 H A R I B P. A D H I M I X

Kuat tekan rata-rata 7 Hari : 9,23 (92%) LC PC A2 STS Kuat tekan rata-rata 7 Hari : 23,5 (78%) P1 BP 6 STS Kuat tekan rata-rata 7 Hari : 16,0 (80%) HEAD WALL A1 BI

Kuat tekan rata-rata 14 Hari : 12,6 (126%) LC PC P2 STS Kuat tekan rata-rata 14 Hari: 32 (109%) KOLOM P1 Kuat tekan rata-rata 14 Hari: 30,1 (100,1%) P1 BP 12 STS
U j i K u a t Te k a n B e t o n U m u r 2 8 H a r i B P. A d h i m i x d a n M a r k a

Kuat tekan rata-rata Detour puri marisa : 26,3 (132%) Kuat tekan rata-rata PC P1 BI THP 1 : 22,5 (113%)

Nilai reflektive rata-rata marka putih : 310/216


Tebal rata-rata marka putih : 3,2 mm

Nilai reflektive rata-rata marka kuning : 244/190


Tebal rata-rata marka putih : 3,1 mm

Kuat tekan rata-rata A2 BP 34 STS : 34,6 (115%)


OVERVIEW PELAKSANAAN KONSTRUKSI
Jasa Pemborongan Pekerjaan Pembangunan Akses Simpang Tak Sebidang
(STS) Martadinata Jalan Tol Serpong – Cinere
UPDATE LAHAN S/D DESEMBER
BERITA ACARA SERAH TERIMA LAHAN TAHAP 8
PER TANGGAL 20 DESEMBER 2022

Lahan Sudah Bebas/


No Lokasi Pekerjaan Satuan Kebutuhan Lahan Persentase
Dibayar

1 STS Martadinata M2 26,329 12,570 47.74%

2 OP Bukit Indah M2 3,163 3,163 100.00%

3 OP Cabe Raya M2 1,704 1,704 100.00%

4 Main Road M2 591 591 100.00%


TOTAL 31,787 18,028 56.72%

Note : Pembayaran UGK dilaksanakan tanggal 20 Desember 2022


Dalam surat pernyataan pemilik lahan akan mengosongkan lahan 2 minggu setelah menerima UGK
Pada bidang No. 78 (1440 m2), No. 83 (2065 m2) , 93 (79 m2), dengan total 3584 m2
Realisasi dilapangan tanggal 04 Januari 2023 baru bisa dilakukan pembongkaran
MAPPING LAHAN BEBAS STS s/d TAHAP 8

LAHAN BEBAS 47.74 %

LAHAN BELUM BEBAS

LAHAN SUDAH BEBAS SUDAH DIBONGKAR

LAHAN SUDAH BEBAS BELUM DIBONGKAR

LAHAN BEBAS MASIH DIHUNI

PEMBEBASAN LAHAN LAMA


MAPPING LAHAN BEBAS STS s/d TAHAP 8

LAHAN BEBAS 100 %

LAHAN BELUM BEBAS

LAHAN SUDAH BEBAS SUDAH DIBONGKAR

LAHAN SUDAH BEBAS BELUM DIBONGKAR

LAHAN BEBAS MASIH DIHUNI

PEMBEBASAN LAHAN LAMA


PROGRES PEKERJAAN S/D 22 JANUARI 2023
JANGKA WAKTU PELAKSANAAN = 395 HARI

TAHUN 2022 TAHUN 2023


BOBOT
PEMBAYARAN ITEM PEKERJAAN KETERANGAN
(%)
AGUSTUS '22 SEPTEMBER '22 OCTOBER '22 NOVEMBER '22 DESEMBER '22 JANUARI '23 FEBRUARI '23 MARET '23 APRIL '23 MEI '23 JUNI '23 JULI '23 AGUSTUS '23 SEPTEMBER '23

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57

BAB 1 UMUM 2.590 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.037 0.037 0.037 0.037 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.084 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.060 0.048 0.048 0.048 0.048 0.048 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 100%

BAB 2 PEMBERSIHAN TEMPAT KERJA 0.744 0.018 0.018 0.018 0.018 0.015 - - - - - - 0.001 0.001 0.001 - 0.011 0.011 0.011 0.011 0.014 0.014 0.014 0.014 0.012 0.012 0.012 0.012 0.012 - - - - - - -
I - - - - - - - - - - - - - - - - - - - - -

BAB 3 PEMBONGKARAN 0.920 - - - 0.024 0.024 - - 0.029 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.168 0.168 0.174 0.174 0.171 0.171 0.188 0.188 0.166 0.014 0.014 0.014 0.014 - - - - - - -
D - - - - - - - - - - - - - - - - - - - - -

BAB 4 PERKERJAAN TANAH 10.648 - - 0.001 0.001 0.001 0.001 - - - - - 0.002 0.002 0.002 0.027 0.200 0.200 0.173 0.173 0.173 0.173 0.173 0.173 - 0.041 0.041 0.505 0.505 0.505 0.561 0.561 0.561 0.527 0.527 0.471
U 0.471 0.422 0.422 0.422 0.422 0.418 0.418 - - - - - - - - - - - - - -

BAB 5 GALIAN STRUKTUR 0.241 - - 0.002 0.002 0.002 0.002 - - - - 0.014 0.017 0.017 0.003 - - - - - - - - - 0.028 0.028 0.028 0.041 0.041 0.028 0.028 0.028 - - - -
L - - - - - - - - - - - - - - - - - - - - - 75%

BAB 6 DRAINASE 4.096 - - - - - - - - - - - 0.009 0.009 0.009 0.009 0.009 0.009 0.143 0.143 0.109 0.043 0.009 0.009 0.009 0.009 0.009 0.009 - - 0.098 0.098 0.098 0.437 0.437 0.437 0.261 0.261 0.162 0.162 0.259 0.162 0.151 0.157 0.169 0.169 0.177 0.177 0.177 0.020 0.009 0.009 0.009 0.009 - - -

BAB 7 SUBGRADE 0.132 - - - - - - - - - - - 0.001 0.001 - - - - - - - 0.001 0.001 0.001 0.001 - - 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.007 0.007 0.003 0.003 0.003 - - - - - - - - - - - - - - - -
F
BAB 8 LAPIS PONDASI AGREGAT DAN LAPIS FONDASI AGREGAT SEMEN 0.622 - - - - - - - - - - - - 0.008 0.008 - - - - - - - - 0.028 0.028 0.028 0.028 - - - - - - - - - 0.028 0.028 0.115 0.190 0.190 0.190 0.190 0.115 0.082 0.082 - - - - - - - - - - -
I
BAB 9 PERKERASAN 8.571 - - - - - - - - - - - - - - - - - - - 0.093 0.064 - - - - - - - - 0.011 0.011 0.011 0.011 0.011 0.011 0.334 0.474 1.058 0.817 0.834 0.603 0.499 0.499 0.499 0.369 0.369 0.369 0.369 0.369 0.509 0.812 0.812 0.812 - - -
T
BAB 10 STRUKTUR BETON 44.424 - - - - - 0.638 0.627 0.152 0.152 0.205 0.165 0.340 0.326 0.326 0.517 0.646 0.646 0.495 0.510 0.696 0.738 0.812 1.300 1.420 1.225 2.044 2.040 1.388 1.014 1.343 1.018 1.429 1.373 1.230 1.446 1.134 1.284 1.208 1.211 0.930 1.111 1.003 0.973 1.061 0.799 0.856 0.784 0.819 0.639 0.633 0.437 0.437 0.437 0.345 0.345 0.026 50%
R
BAB 11 PEKERJAAN BAJA STRUKTURAL 0.073 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.037 0.037 - - - 0.021 0.021 - - - - 0.013 0.013 0.013 0.013 0.013 0.013 - - - - - - - - -
I
BAB 12 PEKERJAAN LAIN-LAIN 24.167 0.151 0.151 0.151 0.151 0.152 0.152 0.152 0.229 0.278 0.272 0.272 0.376 0.350 0.376 0.376 0.376 0.449 0.441 0.447 0.499 0.487 0.487 0.515 0.682 0.870 0.815 0.801 0.806 0.497 0.442 0.477 0.528 0.578 0.543 0.543 0.552 0.624 0.488 0.453 0.491 0.729 0.596 0.584 0.530 0.370 0.322 0.322 0.351 0.310 0.316 0.314 0.373 0.122 0.420 0.420 0.079

BAB 13 PENCAHAYAAN, LAMPU LALU LINTAS DAN PEKERJAAN LISTRIK 2.330 - - 0.006 0.006 0.006 0.006 0.006 0.021 - - - - - 0.025 0.025 - - - - 0.018 - - - 0.008 0.008 - - 0.015 0.015 - - - - - - - - 0.008 - 0.015 0.015 - 0.109 0.109 0.109 0.197 0.248 0.248 0.250 0.237 0.209 0.209 0.126 - - -
2
BAB 14 PLAZA TOL 0.000
0
BAB 15 PENGALIHAN DAN PERLINDUNGAN UTILITAS YANG ADA 0.442 - - - - - - - - - - - - - - - - - - - 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 - - - - - - - 25%

BAB 16 KANTOR DAN FASILITAS TOL 0.000


2
BAB 17 PEKERJAAN HARIAN 0.000
3
TOTAL 100.000

GRAND TOTAL 0.214 0.214 0.224 0.248 0.246 0.845 0.831 0.467 0.470 0.517 0.491 0.810 0.778 0.814 1.018 1.471 1.544 1.498 1.518 1.872 1.767 1.760 2.304 2.430 2.310 3.067 3.502 2.860 2.138 2.562 2.310 2.743 3.003 2.826 2.986 - 2.882 3.196 3.541 3.334 3.208 3.291 2.932 2.512 2.525 1.949 1.973 1.952 2.003 1.627 1.727 1.805 1.864 1.531 0.789 0.789 0.129

KUMULATIF RENCANA ADDENDUM 1 - 0.287 0.601 0.801 1.683 2.069 2.418 2.611 3.077 3.547 4.063 4.554 5.364 6.142 6.956 7.973 9.444 10.989 12.486 14.005 15.876 17.643 19.402 21.707 24.137 26.447 29.514 33.015 35.875 38.013 40.575 42.884 45.628 48.631 51.457 54.443 54.443 57.325 60.521 64.061 67.396 70.603 73.895 76.827 79.339 81.864 83.813 85.785 87.737 89.739 91.366 93.093 94.899 96.763 98.294 99.083 99.871 100.00

REALISASI KUMULATIF ADDENDUM 1 - 0.287 0.541 0.801 1.683 2.059 2.616 3.098 3.683 4.527 4.986 5.324 5.705 6.021 7.474 9.245 11.160 12.869 14.481 15.825 17.221 18.333 19.823 22.272

DEVIASI 0.073 0.113 0.149 0.783 0.912 0.625 0.275 0.606 0.980 0.923 0.770 0.341 - 0.121 0.518 1.272 1.716 1.880 1.995 1.820 1.345 0.690 0.421 0.565

PROGRESS MINGGU INI (PEKAN 23) PROGRESS SAMPAI DENGAN MINGGU INI WAKTU PELAKSANAAN
KETERANGAN PROSENTASE KETERANGAN PROSENTASE KETERANGAN HARI
RENCANA MINGGU INI 2.304 % RENCANA S/D PEKAN 23 21.707 % TOTAL WAKTU PELAKSANAAN 395 Hari

REALISASI MINGGU INI 2.452 % REALISASI S/D PEKAN 23 22.275 % WAKTU TERPAKAI 158 Hari

DEVIASI + 0.148 % DEVIASI + 0.569 % SISA WAKTU PELAKSANAAN 237 Hari


RENCANA ACTION PLAN MINGGU - 24
No Item Pekerjaan Satuan Vol ume Bobot KETERANGAN

9.08 (1a) Perkerasan Beton Semen M3 25.00 0.029% MAINROAD 12M

10.02 (4) Batang Baja Tulangan Sirip BJTS-420B Kg 38,535.00 0.423% PILE CAP A2 STS, PIERHEAD P1

10.01 (10) Beton Struktur Kelas C-1 (Abutments, Telapak Pier, Dinding Penahan Tanah, Pelat Injak, Kotak Tanaman) M3 277.10 0.381% PILECAP A2 STS

10.07 (1) Tiang Cor Beton Cast-in-Place D=80cm dengan Pemantauan Ultrasonik M1 286.00 0.588% 11 TITIK P1 OP CABE RAYA

10.03 (16b1) Gelagar PC-I bentang nominal 39,0m to 41.0m, H=2.10m, penyediaan Buah 5.00 0.352% STRESING GIRDER OP BUKIT
10.03 (12c1) Gelagar PC-I bentang nominal 14,60m s/d 16.00m,H= 0.90m, penyediaan Buah - 0.000% INDAH

Box Culvert 1x1m M1 25.00 0.116% SALURAN CABE RAYA

Rambu Petunjuk Tipe C-1 Buah 1.00 0.069% RAMBU BATAS WILAYAH

SK-1.12.15 (4) Half Movable Concrete Barrier tinggi 1,2 M Buah 14.00 0.017% HALF MCB (ULF)

SK-1.12.15 (5) Movable Concrete Barrier tinggi 1,2 M Buah 54.00 0.075%

Pembersihan Beton Struktur ± 4m M2 2,100.00 0.032%

Pengecetan beton struktur M2 1,925.00 0.137%

SK.12.17(52) Irigasi Otomatis M1 70.00 0.005%

SK.12.17(53) Media Resapan Karung 94.26 0.001%


MAINROAD SERPONG - CINERE
SK.12.17(55) Rambatan A M2 125.00 0.017%

SK.12.17(65) Planter Box Tipe A Buah 175.00 0.238%

SK.12.17(67) Tanah Tanam M3 115.00 0.015%

SK.12.17(68) Bogenvil Bentukan Buah 125.00 0.008%

Action Plan Pekan ke -24 2.504%

Master Schedule Pekan ke -24 2.430%


MAPPING REALISASI BOREDPILE STS MARTADINATA
LAHAN BELUM BEBAS SUDAH DIBAYAR

A1 ( 33 Titik ) PILE SLAB 46 Titik P1 ( 30 Titik ) A2 ( 40 Titik )

A1 PS 1 PS 2 PS 3 PS 4 PS 5 PS 6 PS 7 PS 8 PS 9 P1 A2

LOKASI REALISASI BOR (SISA BOR)

A2 40 / 40 Titik
Elv. Eksisting
P1 30 / 30 Titik
Cor Pilecap
A1 0 / 33 Titik
Bobok Boredpile
PS 0 / 46Titik

= SUDAH DICOR = BELUM DICOR JUMLAH TARGET BOREDPILE = 70/146 Titik


PEMBONGKARAN KLINIK
DOKUMENTASI STS MARTADINATA

GALIAN & BOBOK BOREDPILE PERSIAPAN PENGECORAN PILECAP


DOKUMENTASI STS MARTADINATA

RELOKASI PAGAR PIU

PAGAR PIU
MAPPING REALISASI OP BUKIT INDAH

A-1 P-1 P-2 A-2


16.9 M 41.8 M 16.9 M
V V

IV IV
IV IV

III III
II I I II
CINERE SERPONG
II II
Elv. Eksisting II II

I
I

= SUDAH DICOR = BELUM DICOR = PEMBESIAN


DOKUMENTASI OP BUKIT INDAH

SISI UTARA SISI SELATAN


MAPPING REALISASI DI LOKASI MAINROAD 12M

DPT KIRI
CL DPT KANAN
3310

300 1020 150 250 150 1020 3000


10,300 Bahu Luar Jalur Lalin Bahu Bahu Bahu Luar
Dalam Jalur Lalin
Dalam

8,560

WET LEAN CONCRETE RIGID PAVEMENT

Rigid Pavement 30 cm
Lean Concrete 10 cm TANAH EKSISTING
Agregate Base A 15 cm

= SUDAH DICOR/DIKERJAKAN = BELUM DICOR


DOKUEMENTASI MAINROAD 12M

BESI ULIR DENGAN


COR KELAS C 10 CM

PASANGAN BATU KALI

PEKERJAAN PASANGAN BATU KALI PEKERJAAN RIGID


MAPPING REALISASI PEKERJAAN OP CABE RAYA (16 Januari 2023)

JEMBATAN RENCANA

A1 A2
A1 ( 25 Titik ) REAL 3 TITK A2 ( 25 Titik )

GALIAN PILECAP

= SUDAH DICOR = BELUM DICOR/ TARGET DI COR S.D DESEMBER


KONDISI LAPANGAN OVERPAS CABE RAYA

PEMBONGKARAN SPBU
KONDISI LAPANGAN OVERPAS CABE RAYA A1
KONDISI LAPANGAN OVERPAS CABE RAYA A2

RELOKASI UTILITAS
KM. KM
JALUR B JALUR A

PLANTER BOX
Rambatan

Rambatan
RAMBATANB
RAMBATANA

MEDIAN BARIER A

A
A

MEDIAN BARIER B

BADAN JALAN
BADAN JALAN
25+000 25+000
25+200 25+200
25+400 25+400
25+600 25+600
25+800 25+800
26+000 26+000
26+200 26+200
26+400 26+400
26+600 26+600
26+800 26+800
27+000 27+000
27+200 27+200
27+400 27+400
27+600 27+600
27+800 27+800
28+000 28+000
28+200 28+200
28+400 28+400
28+600 28+600
28+800 28+800
29+000 29+000
29+200 29+200
29+400 29+400
29+600 29+600
29+800 29+800
30+000 30+000
30+200 30+200
MEDIAN
MEDIAN

30+400 30+400
BADAN JALAN
BADAN JALAN

30+600 30+600
30+800 30+800
31+000 31+000
31+200 31+200
31+400 31+400
31+600 31+600
31+800 31+800
32+000 32+000
32+200 32+200
32+400 32+400
32+600 32+600
32+800 32+800
33+000 33+000
33+200 33+200
33+400 33+400
33+600 33+600
STRIP MAP PEKERJAAN PLANTER BOX MEDIAN & BOUGENVILE, RAMBATAN A

33+800 33+800
34+000 34+000
34+200 34+200
34+400 34+400
34+600 34+600
34+800 34+800
35+000 35+000
35+200 35+200
MEDIAN
Vol. Real

789 Buah
2.263 m2
1.605 M2
PLANTER BOX RAMBATAN A
VOL REALISASI

13.195
BENTUKAN
BOUGENVIL

: REALISASI PEKERJAAN BOUGENVILE, RAMBATAN A


11.935 Buah
Buah
PEKERJAAN LANDSCAPE BEAUTIFIKASI

LEK KUAN YU KEMBANG MERAK

AIR MATA PENGANTIN


LEK KWAN YEW
PEKERJAAN LANDSCAPE BEAUTIFIKASI
PEKERJAAN LANDSCAPE BEAUTIFIKASI

THUMBERGIA THUMBERGIA

MELATI BELANDA MELATI BELANDA


PEKERJAAN LANDSCAPE BEAUTIFIKASI

MELATI BELANDA
BOHEMIA BOHEMIA

ALAMANDA ALAMANDA
SCHEDULE PEKERJAAN LANDSCAPE BEAUTIFIKASI
SCHEDULE SCHEDULE
Task Name Jan-23 Feb-23 Mar-23 Task Name Jan-23 Feb-23 Mar-23
23-29 30-5 6-12 13-19 20-26 27-5 6-12 13-19 20-26
BAUTIFIKASI
23-29 30-5 6-12 13-19 20-26 27-5 6-12 13-19 20-26
BAUTIFIKASI
Pem berihan Beton Struktur Ketinggian > 4m
Bam bu Jepang
SERPONG JUNCTION 1
INTERCHANGE PAMULANG 1 Seksi 1 Jalur A 1 1
DPT KEMIRI 1 Seksi 1 Jalur B 1 1
OVER PASS & JPO 1 1 1 Air Mata Pengantin
Pengecatan Beton Struktur Ketinggian > 4m
Seksi 1 Jalur A 1 1
SERPONG JUNCTION 1 1
INTERCHANGE PAMULANG 1 1
Seksi 1 Jalur B 1 1
DPT KEMIRI 1 1 1 Seksi 2 Jalur A 1 1
OVER PASS & JPO 1 1 1 1 1 Seksi 2 Jalur B 1
Kem bang Merak (Caesalpinia pulcherrim a) Alam anda (Allam anda Cathartica)
Seksi 1 Jalur A 1 1 1 Seksi 1 Jalur A 1
Seksi 1 Jalur B 1 1 1 1 Seksi 1 Jalur B 1
Seksi 2 Jalur A FINISH
Seksi 2 Jalur B (Sisa KM 34) 1
Seksi 2 Jalur A 1
Interchange Serpong 1 1 1
Seksi 2 Jalur B 1
KM 25+700-GT Serpong 7 1 1 Lek Kuan Yu
Interchange Pamulang FINISH Seksi 2 Jalur A 1 1
Irigasi Otom atis Seksi 2 Jalur B 1 1
KM 25+250 - 35+250 1 1 1 1 1 1 1 1 1 Planter Box Tipe A
Media Resapan
Seksi 1 Jalur A 1 1
KM 25+250 - 35+250 1 1 1 1 1 1
Bougenville bentukan
Seksi 1 Jalur B 1 1
KM 25+450 - 35+250 1 1 1 1 Seksi 2 Jalur A 1 1
Bogenvil Pagaran Seksi 2 Jalur B 1 1 1
KM 25+450 - 35+250 1 1 Planter Box Tipe B
Ram batan A
Seksi 1 Jalur A 1 1
Seksi 1 Jalur A 1 1
Seksi 1 Jalur B 1
Seksi 1 Jalur B 1 1
Seksi 2 Jalur A 1 1
Seksi 2 Jalur A 1
Seksi 2 Jalur B 1 1 1 Seksi 2 Jalur B 1
Ram batan B Tanah Tanam
Seksi 2 Jalur A 1 1 1 KM 25+450 - 35+250 (Median) 1 1 1 1 1 1 1
Seksi 2 Jalur B 1 1 1 KM 25+450 - 35+250 (Planter Box A & B) 1 1
Kem bang Telang
Kana (Canna Indica)
Seksi 1 Jalur A 1
Seksi 1 Jalur B 1
Akses GT Serpong 5 1 1 1
Seksi 2 Jalur A 1 Cem ara Lilin
Seksi 2 Jalur B 1 Akses GT Serpong 5 1 1 1
DOKUMENTASI PEKERJAAN THREEBEAM STS MARTADINATA
DOKUMENTASI ULF

HALF MCB SALURAN DS 10 –DS 8


DOKUMENTASI PEKERJAAN PENGECATAN BETON STRUKTUR

SEBELUM

SESUDAH
MONITORING PEKERJAAN ULF

19-Jan-23
MONITORING PEKERJAAN ULF

26 Januari 2023

selesai selesai

selesai selesai 19-Jan-23

selesai selesai
MONITORING PEKERJAAN ULF

selesai selesai

selesai selesai

19-Jan-23

selesai selesai
VIDEO PEKAN 23
TERIMA KASIH