LAPORAN PROGRESS FISIK MINGGUAN

INSTITUSI : KEMENTERIAN PERHUBUNGAN DIREKTORAT JENDERAL PERHUBUNGAN DARAT Periode


BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH XVIII PROV. SULAWESI TENGGARA Minggu Ke-19
KEGIATAN : PENINGKATAN/REVITALISASI TERMINAL PENUMPANG TIPE A PUUWATU TAHAP II NILAI KONTRAK : Rp. 16.946.870.000,- 18-05-21
NOMOR KONTRAK : KU.003/89/I/BPTD-SULTRA/2021 KONTRAKTOR : PT. GUNAKARYA NUSANTARA s/d
TGL. KONTRAK : 16 FEBRUARI 2021 KONSULTAN : PT. TRI ARTA CONSULINDO 24-05-21

KUANTITAS TERCAPAI PROGRESS TERCAPAI PROGRESS TERTIMBANG


NO URAIAN SATUAN KUANTITAS BOBOT S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
% LALU INI INI LALU INI INI LALU INI INI
A PEKERJAAN PENDAHULUAN
1 Direksi Keet dan Gudang Bahan m2 120.00 1.135 60.84 - 60.84 0.575 - 0.575 50.700 - 50.700
2 Pagar Pengaman Proyek m' 200.00 0.23 40.00 - 40.00 0.046 - 0.046 20.000 - 20.000
3 Pengukuran Awal dan Pemasangan Bowplank m' 184.80 0.12 184.80 - 184.80 0.116 - 0.116 100.000 - 100.000
4 Pengadaan Listrik Kerja ls 1.00 0.46 1.00 - 1.00 0.464 - 0.464 100.000 - 100.000
5 Pengadaan Air Kerja ls 1.00 0.32 1.00 - 1.00 0.321 - 0.321 100.000 - 100.000
6 Pelaporan / Dokumentasi set 1.00 0.18 0.37 - 0.374 0.067 - 0.067 37.447 - 37.447
7 Mobilisasi/Demobilisasi set 1.00 0.93 0.60 - 0.60 0.557 - 0.557 60.000 - 60.000
8 K3 set 1.00 1.70 0.34 - 0.34 0.578 - 0.578 34.043 - 34.043
B PEKERJAAN STRUKTUR
B.1 PEKERJAAN PONDASI
1 Pek. Galian Tanah m3 283.39 0.16 - - - - - - - - -
2 Pek. Urugan Tanah Kembali m3 94.46 0.05 - - - - - - - - -
3 Urugan pasir bawah pondasi t. 10 cm m3 14.35 0.03 - - - - - - - - -
4 Pek. Pondasi Batu Kosong m3 57.40 0.22 - - - - - - - - -
5 Pek. Pondasi Batu Kali 1 : 4 m3 121.17 0.80 - - - - - - - - -
6 Pembuatan Beton Bertulang Pilecap :
6.1 PC-1 (2,2m x 2,2m x 0,4m)
- Beton K-250 m3 38.72 0.32 21.30 5.81 27.11 0.176 0.048 0.224 55.010 15.000 70.010
- Bekesting m2 70.40 0.07 70.40 - 70.40 0.074 - 0.074 100.000 - 100.000
- Pembesian BJTD-32 kg 4,715.78 0.56 4,715.78 - 4,715.78 0.563 - 0.563 100.000 - 100.000
- Lantai Kerja 10 cm m3 9.68 0.06 9.68 - 9.68 0.063 - 0.063 100.000 - 100.000
- Galian m3 270.40 0.15 270.40 - 270.40 0.153 - 0.153 100.000 - 100.000
- Urugan Kembali m3 90.13 0.05 - - - - - - - - -
6.2 PC-2 (1,8m x 1,8m x 0,4m)
- Beton K-250 m3 31.10 0.26 31.10 - 31.10 0.257 - 0.257 100.000 - 100.000
- Bekesting m2 69.12 0.07 69.12 - 69.12 0.072 - 0.072 100.000 - 100.000
- Pembesian BJTD-32 kg 4,116.55 0.49 4,116.55 - 4,116.55 0.491 - 0.491 100.000 - 100.000
- Lantai Kerja 10 cm m3 7.78 0.05 7.78 - 7.78 0.050 - 0.050 100.000 - 100.000
- Galian m3 232.32 0.13 232.32 - 232.32 0.132 - 0.132 100.000 - 100.000
- Urugan Kembali m3 77.44 0.04 - - - - - - - - -
6.3 PC-3 (1,6m x 1,6m x 0,3m)
- Beton K-250 m3 5.83 0.05 5.83 - 5.83 0.048 - 0.048 100.000 - 100.000
- Bekesting m2 12.96 0.01 12.96 - 12.96 0.014 - 0.014 100.000 - 100.000
- Pembesian BJTD-32 kg 646.89 0.08 646.89 - 646.89 0.077 - 0.077 100.000 - 100.000
- Lantai Kerja 10 cm m3 1.94 0.01 1.94 - 1.94 0.013 - 0.013 100.000 - 100.000
- Galian m3 58.08 0.03 58.08 - 58.08 0.033 - 0.033 100.000 - 100.000

- Urugan Kembali m3 19.36 0.01 - - - - - - - - -


6.4 PC-4 (3,7m x 3,7m x 0,3m)
- Beton K-250 m3 4.11 0.03 - - - - - - - - -
- Bekesting m2 4.44 0.00 2.22 - 2.22 0.002 - 0.002 50.000 - 50.000
- Pembesian BJTD-32 kg 405.29 0.05 405.29 - 405.29 0.048 - 0.048 100.000 - 100.000
- Lantai Kerja 10 cm m3 1.37 0.01 - - - - - - - - -
- Galian m3 25.21 0.01 25.21 - 25.21 0.014 - 0.014 100.000 - 100.000
- Urugan Kembali m3 8.40 0.00 - - - - - - - - -
7 Pek. Beton Bertulang Kolom Pedestal:
7.1 Kolom K1 (55 cm x 55 cm)
- Beton K-250 m3 24.68 0.20 13.61 - 13.61 0.112 - 0.112 55.156 - 55.156
- Bekesting m2 179.52 0.27 127.60 - 127.60 0.193 - 0.193 71.078 - 71.078
- Pembesian BJTD-32 kg 7,353.79 0.88 5,815.34 1,538.45 7,353.79 0.694 0.184 0.878 79.080 20.920 100.000
8 Pek. Beton Bertulang Kolom Pedestal:
8.1 Kolom K1 (50 cm x 20 cm)
- Beton K-250 m3 0.86 0.01 - - - - - - - - -
- Bekesting m2 9.60 0.01 - - - - - - - - -
- Pembesian BJTD-32 kg 240.21 0.03 180.16 - 180.16 0.022 - 0.022 75.000 - 75.000
C PEK. STRUKTUR LANTAI I -
1 Urugan tanah peninggian lantai m3 609.41 0.88 - - - - - - - - -
2 Pek. Urug pasir bawah lantai t. 10cm m3 152.35 0.30 - - - - - - - - -
3 Pek. Beton lantai t. 10 cm -
- Beton K-250 m3 163.16 1.35 - - - - - - - - -
- Pembesian Wiremesh M8 kg 8,892.10 1.04 - - - - - - - - -
4 Pembuatan Beton Bertulang Tie Beam/Sloof
4.1 Tie Beam/Sloof S1 (30cm x 60cm)
- Beton K-250 m3 90.97 0.75 - - - - - - - - -
- Bekesting m2 758.10 0.86 - - - - - - - - -
- Pembesian BJTD-32 kg 17,365.40 2.07 - - - - - - - - -
4.2 Tie Beam/Sloof S2 (30cm x 50cm) -
- Beton K-250 m3 7.91 0.07 - - - - - - - - -
- Bekesting m2 67.20 0.08 - - - - - - - - -
- Pembesian BJTD-32 kg 1,077.04 0.13 - - - - - - - - -
5 Kolom K1 (55 cm x 55 cm)
- Beton K-250 m3 78.05 0.64 - - - - - - - - -
- Bekesting m2 567.60 1.09 - - - - - - - - -
- Pembesian BJTD-32 kg 12,718.81 1.52 - - - - - - - - -
6 Kolom K1 (50 cm x 20 cm) -
- Beton K-250 m3 2.64 0.02 - - - - - - - - -
- Bekesting m2 26.40 0.05 - - - - - - - - -
- Pembesian BJTD-32 kg 525.66 0.06 - - - - - - - - -
7 Pembuatan Beton Bertulang Tangga
- Beton K-250 m3 16.31 0.13 - - - - - - - - -
- Bekesting m2 135.85 0.20 - - - - - - - - -
- Pembesian BJTD-40 kg 2,821.77 0.34 - - - - - - - - -
8 Kolom Kanopi (HB 200.200.8.12) -
- Base Plat t. 20 mm kg 153.69 0.04 - - - - - - - - -
- Baut M-20 bh 96.00 0.02 - - - - - - - - -
- H-Beam 200.200.8.12 kg 2,195.60 0.52 - - - - - - - - -
D PEK. STRUKTUR LANTAI II ( Elev. +5.50)
1 Balok B1 (35 cm x 65 cm)
- Beton K-250 m3 60.52 0.50 - - - - - - - - -
- Bekesting m2 375.06 0.73 - - - - - - - - -
- Pembesian BJTD-32 kg 13,679.00 1.63 - - - - - - - - -
2 Balok B2 (35 cm x 65 cm)
- Beton K-250 m3 54.46 0.45 - - - - - - - - -
- Bekesting m2 337.55 0.66 - - - - - - - - -
- Pembesian BJTD-32 kg 9,360.47 1.12 - - - - - - - - -
3 Balok B3 (25 cm x 50 cm) -
- Beton K-250 m3 56.51 0.47 - - - - - - - - -
- Bekesting m2 456.62 0.89 - - - - - - - - -
- Pembesian BJTD-32 kg 12,008.86 1.43 - - - - - - - - -
4 Balok B4 (25 cm x 50 cm)
- Beton K-250 m3 1.39 0.01 - - - - - - - - -
- Bekesting m2 11.21 0.02 - - - - - - - - -
- Pembesian BJTD-32 kg 233.11 0.03 - - - - - - - - -
5 Balok B5 (25 cm x 50 cm)
- Beton K-250 m3 0.61 0.01 - - - - - - - - -
- Bekesting m2 6.45 0.01 - - - - - - - - -
- Pembesian BJTD-32 kg 69.04 0.01 - - - - - - - - -
6 Balok BK1 (35 cm x 65 cm)
- Beton K-250 m3 19.82 0.16 - - - - - - - - -
- Bekesting m2 25.55 0.05 - - - - - - - - -
- Pembesian BJTD-32 kg 56.51 0.007 - - - - - - - - -
7 Balok BK2 (35 cm x 65 cm)
- Beton K-250 m3 5.14 0.04 - - - - - - - - -
- Bekesting m2 37.94 0.07 - - - - - - - - -
- Pembesian BJTD-32 kg 806.51 0.10 - - - - - - - - -
8 Balok BK3 (25 cm x 50 cm)
- Beton K-250 m3 0.72 0.006 - - - - - - - - -
- Bekesting m2 7.20 0.01 - - - - - - - - -
- Pembesian BJTD-32 kg 146.16 0.02 - - - - - - - - -
9 Pek. Beton bertulang lantai t. 12cm
- Beton K-250 m3 191.04 1.58 - - - - - - - - -
- Bondeks m2 1,592.01 4.08 - - - - - - - - -
- Pembesian Wiremesh M8 kg 17,352.86 2.02 - - - - - - - - -
10 Kolom K1 (55 cm x 55 cm)
- Beton K-250 m3 62.62 0.52 - - - - - - - - -
- Bekesting m2 455.40 0.87 - - - - - - - - -
- Pembesian BJTD-32 kg 9,276.06 1.11 - - - - - - - - -
11 Pembuatan Beton Bertulang Tangga
- Beton K-250 m3 10.87 0.09 - - - - - - - - -
- Bekesting m2 90.56 0.14 - - - - - - - - -
- Pembesian BJTD-40 kg 1,881.18 0.22 - - - - - - - - -
12 Balok Kanopi (IWF 350.175.7.11)
- IWF 350.175.7.11 kg 2,678.40 0.64 - - - - - - - - -
- Baut M-20 bh 144.00 0.03 - - - - - - - - -
- Joint Plat dan Plat Buhul kg 76.32 0.02 - - - - - - - - -
13 Balok Kanopi (IWF 300.150.6,5.9)
- IWF 250.125.6.9.12 kg 249.56 0.06 - - - - - - - - -
- Baut M-20 bh 24.00 0.004 - - - - - - - - -
- Joint Plat dan Plat Buhul kg 12.72 0.003 - - - - - - - - -
14 Balok Kanopi (IWF 200.100.5,5.8)
- IWF 250.125.6.9.12 kg 383.40 0.09 - - - - - - - - -
- Baut M-20 bh 1,056.00 0.19 - - - - - - - - -
- Joint Plat dan Plat Buhul kg 559.68 0.13 - - - - - - - - -
15 Balok Kanopi (IWF 250.125.6.9.12)
- IWF 250.125.6.9.12 kg 2,296.96 0.55 - - - - - - - - -
- Baut M-20 bh 480.00 0.08 - - - - - - - - -
- Joint Plat dan Plat Buhul kg 254.40 0.06 - - - - - - - - -
16 Gording Kanopi (HLW 100.50.3)
- HLW 100.50.3 kg 5,819.35 1.38 - - - - - - - - -
E PEK. STRUKTUR LANTAI III ( Elev. + 9.50)
1 Balok B1 (35 cm x 65 cm)
- Beton K-250 m3 60.52 0.50 - - - - - - - - -
- Bekesting m2 375.06 0.73 - - - - - - - - -
- Pembesian BJTD-32 kg 13,679.00 1.63 - - - - - - - - -
2 Balok B2 (35 cm x 65 cm)
- Beton K-250 m3 54.46 0.45 - - - - - - - - -
- Bekesting m2 337.55 0.66 - - - - - - - - -
- Pembesian BJTD-32 kg 9,360.47 1.12 - - - - - - - - -
3 Balok B3 (25 cm x 50 cm)
- Beton K-250 m3 53.94 0.45 - - - - - - - - -
- Bekesting m2 435.87 0.85 - - - - - - - - -
- Pembesian BJTD-32 kg 11,463.00 1.37 - - - - - - - - -
4 Balok B4 (25 cm x 50 cm)
- Beton K-250 m3 0.86 0.01 - - - - - - - - -
- Bekesting m2 6.92 0.01 - - - - - - - - -
- Pembesian BJTD-32 kg 146.20 0.02 - - - - - - - - -
5 Balok B5 (25 cm x 50 cm)
- Beton K-250 m3 0.61 0.005 - - - - - - - - -
- Bekesting m2 6.45 0.01 - - - - - - - - -
- Pembesian BJTD-32 kg 69.04 0.01 - - - - - - - - -
6 Balok BK1 (35 cm x 65 cm)
- Beton K-250 m3 1.81 0.01 - - - - - - - - -
- Bekesting m2 13.39 0.03 - - - - - - - - -
- Pembesian BJTD-32 kg 303.88 0.04 - - - - - - - - -
7 Balok BK2 (35 cm x 65 cm) -
- Beton K-250 m3 6.65 0.05 - - - - - - - - -
- Bekesting m2 49.10 0.10 - - - - - - - - -
- Pembesian BJTD-32 kg 1,043.72 0.12 - - - - - - - - -
8 Pek. Beton bertulang lantai t. 12cm
- Beton K-250 m3 193.62 1.60 - - - - - - - - -
- Bondeks m2 1,613.49 4.13 - - - - - - - - -
- Pembesian Wiremesh M8 kg 8,793.50 1.03 - - - - - - - - -
9 Kolom K1 (55 cm x 55 cm)
- Beton K-250 m3 81.67 0.67 - - - - - - - - -
- Bekesting m2 594.00 1.14 - - - - - - - - -
- Pembesian BJTD-32 kg 12,186.17 1.45 - - - - - - - - -
F PEK. STRUKTUR RINGBALK ( Elev. + 15.50)
1 Balok RB1 (35 cm x 65 cm) -
- Beton K-250 m3 61.65 0.51 - - - - - - - - -
- Bekesting m2 435.66 0.85 - - - - - - - - -
- Pembesian BJTD-32 kg 10,542.73 1.26 - - - - - - - - -
G PEKERJAAN KONSTRUKSI ATAP -
1 Kolom & Kuda-Kuda Atap Utama WF 250.125.6.9 kg 5,765.49 1.37 - - - - - - - - -
2 Pengaku (Stifiner) UNP 125.65.6.8 kg 10,059.65 2.39 - - - - - - - - -
3 Gording C Lips 100.50.20.3,2 kg 6,491.10 1.54 - - - - - - - - -
4 Base Plat t. 20 mm kg 847.80 0.20 - - - - - - - - -
5 Joint Plat dan Plat Buhul kg 1,459.12 0.34 - - - - - - - - -
6 Dudukan Gording L 75.75.7 kg 1,017.36 0.24 - - - - - - - - -
7 Baut M-20 bh 240.00 0.04 - - - - - - - - -
8 Cat Zincromate m2 1,582.50 0.18 - - - - - - - - -
9 Penutup atap ACP + Rangka Hollow Galvanis 40.40 m2 750.09 4.42 - - - - - - - - -
10 Penutup atap Spandek t. 0,35 mm m2 1,054.76 1.04 - - - - - - - - -
11 Listplank Panel ACP + Rangka Hollow Galvanis 40.40 m2 812.91 4.79 - - - - - - - - -
12 Tingkap Luar (Timpa Laja) - Panel ACP + Rangka Galv. 40.40 m2 526.29 3.10 - - - - - - - - -
H PEKERJAAN ARSITEKTUR
H.1 PEKERJAAN LANTAI 01
H.1.1 PEKERJAAN DINDING dan FASADE
1 Pek. Dinding Bata Adukan 1 : 4 m2 950.40 0.97 - - - - - - - - -
2 Pek. Plesteran 1 : 4 m2 1,900.80 0.92 - - - - - - - - -
3 Pek. Kolom dan Balok Praktis m3 14.89 0.85 - - - - - - - - -
H.1.2 PEKERJAAN KUSEN, PINTU, JENDELA ALUMINIUM
1 Pas. Pintu Jendela Type PJ1 - Kusen Aluminium (termasuk penggantung) unit 5.00 1.98 - - - - - - - - -
2 Pas. Pintu Jendela Type PJ2 - Kusen Aluminium (termasuk penggantung) unit 3.00 1.60 - - - - - - - - -
3 Pas. Pintu Jendela Type PJ3 - Kusen Aluminium (termasuk penggantung) unit 1.00 0.32 - - - - - - - - -
4 Pas. Pintu Jendela Type PJ4 - Kusen Aluminium (termasuk penggantung) unit 1.00 0.39 - - - - - - - - -
5 Pas. Pintu Jendela Type PJ5 - Kusen Aluminium (termasuk penggantung) unit 1.00 0.06 - - - - - - - - -
6 Pas. Pintu Jendela Type PJ6 - Kusen Aluminium (termasuk penggantung) unit 1.00 0.03 - - - - - - - - -
7 Pas. Pintu Jendela Type PJ7 - Kusen Aluminium (termasuk penggantung) unit 1.00 0.04 - - - - - - - - -
8 Pas. Pintu Type P1 - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 5.00 0.13 - - - - - - - -
9 Pas. Pintu Type P2 - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 4.00 0.10 - - - - - - - -
10 Pas. Pintu Type P3 - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 2.00 0.03 - - - - - - - -
11 Pas. Pintu Type P4 - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 8.00 0.10 - - - - - - - -
12 Pas. Jendela Type J1 - Kusen Aluminium (termasuk penggantung) unit 1.00 0.07 - - - - - - - - -
13 Pas. Jendela Type J2 - Kusen Aluminium (termasuk penggantung) unit 1.00 0.04 - - - - - - - - -
14 Pas. Jendela Type J3 - Kusen Aluminium (termasuk penggantung) unit 1.00 0.03 - - - - - - - - -
15 Pas. Jendela Type J4 - Kusen Aluminium (termasuk penggantung) unit 2.00 0.04 - - - - - - - - -
L PEKERJAAN LANTAI 02
L.1 PEKERJAAN DINDING
1 Pek. Dinding Bata Adukan 1 : 4 m2 875.52 0.89 - - - - - - - - -
2 Pek. Plesteran 1 : 4 m2 1,751.04 0.85 - - - - - - - - -
3 Pek. Kolom dan Balok Praktis m3 14.33 0.81 - - - - - - - - -
L.2 PEKERJAAN KUSEN, PINTU, JENDELA ALUMINIUM -
1 Pas. Pintu Jendela Type PJ8 - Kusen Aluminium (termasuk penggantung) unit 3.00 0.17 - - - - - - - - -
2 Pas. Pintu Jendela Type PJ9 - Kusen Aluminium (termasuk penggantung) unit 4.00 0.18 - - - - - - - - -
3 Pas. Pintu Type P1 - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 3.00 0.08 - - - - - - - -
4 Pas. Pintu Type P1A - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 2.00 0.05 - - - - - - - -
5 Pas. Pintu Type P2 - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 2.00 0.05 - - - - - - - -
6 Pas. Pintu Type P3 - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 1.00 0.02 - - - - - - - -
7 Pas. Pintu Type P4 - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 4.00 0.05 - - - - - - - -
8 Pas. Pintu Type P5 - Kusen Aluminium, Daun Pintu Engineering (termasuk
-
penggantung) unit 4.00 0.10 - - - - - - - -
9 Pas. Jendela Type JB1 - Kusen Aluminium (termasuk penggantung) unit 18.00 3.51 - - - - - - - - -
10 Pas. Jendela Type JK1 - Kusen Aluminium (termasuk penggantung) unit 15.00 0.17 - - - - - - - - -
11 Pas. Jendela Type JK2 - Kusen Aluminium (termasuk penggantung) unit 4.00 0.05 - - - - - - - - -
M PEKERJAAN LANTAI 03
M.1 PEKERJAAN DINDING
1 Pek. Dinding Bata Adukan 1 : 4 m2 38.15 0.04 - - - - - - - - -
100 0.2 6.3 0.2 6.3

Kendari, 24 Mei 2021


Diketahui/disetujui Oleh; Diperiksa Oleh; Dibuat Oleh;
PEJABAT PEMBUAT KOMITMEN (PPK) PENGELOLA TEKNIS KONSULTAN PENGAWAS
BPTD WILAYAH XVIII PROV. SULTRA BPTD WILAYAH XVIII PROV. SULTRA PT. TRI ARTA CONSULINDO

ANDI FAIZHA ARSAL, ST.,M.Sc IWAN ASHARA ALI LA NGKURI, ST.,M.Sc


NIP. 19710527 199803 2 011 NIP. 19831130 201001 1 004 Site Engineer