BOJONEGORO
MINGGU KE : II (DUA)
S/D MINGGU KE : 30 Mei 2023
KEGIATAN :
PENYELENGARAAN JALAN KABUPATEN KOTA
PEKERJAAN :
BOJONEGORO
DATA PENDUKUNG
MUTUALING CONTROL AWAL ( MC 100% )
JENIS PEKERJAAN :
REHABILITASA JEMBATAN MENDALEM - SIMOREJO 2 ( MENDALEM - SIMOREJO ) KEC. KANOR
KONTRAKTOR PELAKSANA
1 2 3 4 5
I DIVISI 1. UMUM
1 Mobilisasi 1.00 Ls Rp 3,500,000.000 Rp 3,500,000.00 1.977
2 Kantor Lapangan dan Fasilitasnya 1.00 Ls Rp 1,000,000.000 Rp 1,000,000.00 0.565
TOTAL JUMLAH DIVISI 1. UMUM Rp. 4,500,000.00 2.542
1 2 3 4 5
VI DIVISI 8. STRUKTUR
1 Beton struktur, fc30 Mpa (2)- Lantai Kendaraan 25.37 m3 Rp 1,609,545.69 Rp 40,834,174.16 23.069
2 Beton strukur, fc20 MPa (1) Tembok penahan 26.16 m3 Rp 1,493,182.13 Rp 39,061,644.52 22.068
3 Beton strukur, fc20 MPa tampa begesting 1.68 m3 Rp 1263509.46 Rp 2122695.8928 1.199
4 Beton, fc10 Mpa 4.35 m3 Rp 1,228,698.55 Rp 5,344,838.69 3.020
3 Baja Tulangan Polos-BjTP 280 3440.499501 Kg Rp 17,705.77 Rp 60,916,692.85 34.414
4 pasangan batu 4.24 Kg Rp 830,599.08 Rp 3,521,740.10 1.990
5 sandaran (Railing) 48.63 M3 Rp 252,627.80 Rp 12,285,289.91 6.940
6 Papan Nama Jembatan 2 buah Rp 690,439.20 Rp 1,380,878.40 0.780
7 Pembongkaran beton 2.94 M3 Rp 516,225.43 Rp 1,517,702.76 0.857
TOTAL JUMLAH DIVISI 8. STRUKTUR Rp. 166,985,657.29 94.337
DIVISI 9. REHABILITASI
VII
JEMBATAN
Pengecatan Dekoratif pada elemen
1 48.63 M2 Rp 56,570.00 Rp 2,750,999.10 1.554
struktur beton, tebal 100 m DIVISI 9. REHABILITASI
TOTAL JUMLAH Rp. 2,750,999.10 1.554
JEMBATAN
SELISIH NILAI TOTAL ANTARA SPK ( KONTRAK ) DENGAN MUTUAL CONTROL AWAL ( MC 0%) SEBELUM PPN 11% =
Mengetahui : Mengetahui :
PEJABAT PEMBUAT KOMITMEN (PPK) PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK)
BIDANG JEMBATAN BIDANG JEMBATAN
6 7 8 9
6 7 8 9
Rp (119.38)
NO. JENIS PEKERJAAN SESUAI KONTRAK ( SPK ) SESUAI MC NOL ( MC 0% ) PEKERJAAN TAMBAH PEKERJAAN KURANG
P
I DIVISI 1. SISTEM
DIVISI 2. UMUM MANAJEMEN Rp 4,500,000.00 Rp 4,500,000.00 Rp - Rp -
II KESELAMATAN KONSTRUKSI
DIVISI 4. PEKERJAAN TANAH (SMKK) Rp 2,226,369.89 Rp 2,226,369.89 Rp - Rp -
III DAN GEOSINTETIK Rp 545,982.75 Rp 741,945.61 Rp 195,962.87 -Rp 195,962.87
VI DIVISI 8. REHABILITASI
DIVISI 9. STRUKTUR Rp 166,985,657.29 Rp 167,021,185.10 Rp 35,527.81 -Rp 35,527.81
VII JEMBATAN Rp 2,750,999.10 Rp 2,519,627.80 -Rp 231,371.30 Rp 231,371.30
TERBILANG : SERATUS SEMBILAN PULUH ENAM JUTA EMPAT RATUS DELAPAN PULUH RIBU RUPIAH
KETERANGAN :
KONTRAKTOR PELAKSANA TIDAK AKAN MENUNTUT TAMBAHAN BIAYA SEBESAR : Rp 119.38
###
TRI WAHYU INDRO PRASETYO ABDUL LATIF
Direktur Direktur
###
Mengetahui : Mengetahui :
PEJABAT PELAKSANATEKNIS KEGIATAN PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK)
BIDANG JEMBATAN BIDANG JEMBATAN
-
-
-
-
EDI DWI PURWANTO, ST., MM ADI TRI SETIYONO,ST
NIP. 19810909 200903 1 004 NIP . 19850423 201503 1 0001
MUTUAL CONTROL AKHIR ( MC 100% )
1 2 3 4 5 6 7
I DIVISI 1. UMUM
1 Mobilisasi 1.00 Ls Rp 3,500,000.00 Rp 3,500,000.00 1.98 1.00 Ls Rp
2 Kantor Lapangan dan Fasilitasnya 1.00 Ls Rp 1,000,000.00 Rp 1,000,000.00 0.56 1.00 Ls Rp
TOTAL JUMLAH PEKERJAAN PERSIAPAN DAN TANAH Rp. 4,500,000.00 2.54
VI DIVISI 8. STRUKTUR
1 Beton struktur, fc30 Mpa (2)- Lantai Kendaraan 25.21 m3 Rp 1,609,545.69 Rp 40,573,427.75 22.92 25.21 m3 Rp
2 Beton strukur, fc20 MPa (1) Tembok penahan 26.86 m3 Rp 1,493,182.13 Rp 40,106,872.01 22.66 26.86 m3 Rp
3 Beton strukur, fc20 MPa tampa begesting 1.68 m3 Rp 1,263,509.46 Rp 2,122,695.89 1.20 1.68 m3 Rp
4 Beton, fc10 Mpa 3.90 m3 Rp 1,228,698.55 Rp 4,791,924.35 2.71 3.90 m3 Rp
5 Baja Tulangan Polos-BjTP 280 3,487.78 Kg Rp 17,705.77 Rp 61,753,901.62 34.89 3,487.78 Kg Rp
6 pasangan batu 4.24 Kg Rp 830,599.08 Rp 3,521,740.10 1.99 4.24 Kg Rp
7 sandaran (Railing) 44.54 M3 Rp 252,627.80 Rp 11,252,042.21 6.36 44.54 M3 Rp
8 Papan Nama Jembatan 2.00 buah Rp 690,439.20 Rp 1,380,878.40 0.78 2.00 buah Rp
9 Pembongkaran beton 2.94 M3 Rp 516,225.43 Rp 1,517,702.76 0.86 2.94 M3 Rp
TOTAL JUMLAH DIVISI 8. STRUKTUR Rp. 167,021,185.10 94.36
DIVISI 9. REHABILITASI
VII
JEMBATAN
Pengecatan Dekoratif pada elemen
1 44.54 M2 Rp 56,570.00 Rp 2,519,627.80 1.42 44.54 M2 Rp
struktur beton, tebal 100 m
TOTAL JUMLAH PEKERJAAN LANTAI Rp. 2,519,627.80 1.42
SELISIH NILAI TOTAL ANTARA MUTUAL CONTROL AWAL ( MC 0%) DENGAN MUTUAL CONTROL AKHIR ( MC 100%) SEBELUM PPN 10% = Rp -
7 8 9
Dibuat oleh :
Kontraktor Pelaksana
CV.DWI KARYA MUDA
ABDUL LATIF
Direktur
NO. URAIAN PEKERJAAN SA VOLUME HARGA SATUAN
TU
AN
I DIVISI 1. UMUM - - Rp
Mobilisasi Ls 1 Rp
Kantor Lapangan dan Fasilitasnya Ls 1 Rp
DIVISI 2. SISTEM MANAJEMEN
II
KESELAMATAN KONSTRUKSI (SMKK)
Penyiapan Dokumen Penerapan SMKK Unit 1 Rp
Alat Pelindung Kerja dan Alat Unit 1 Rp
Pelindung Diri
Asuransi dan perizinan terkait Unit 1 Rp
keselamatan konstruksi
Personel Keselamatan Konstruksi Unit 1 Rp
Fasilitas sarana, prasarana, dan alat Unit 1 Rp
kesehatan
Rambu dan Perlengkapan lalu lintas Unit 1 Rp
yang diperlukan atau manajemen lalu
III DIVISI 4. PEKERJAAN TANAH
DAN GEOSINTETIK
Galian Biasa M3 14.04 Rp
Timbunan Pilihan dari sumber galian M3 14.04 Rp
Limestone (Untuk Badan Jalan)
VI DIVISI 8. STRUKTUR
Beton struktur, fc30 Mpa (2)- Lantai Kendaraan 25.37 Rp
m3
- Rp -
3500000 Rp 3500000
1000000 Rp 1000000
300000 Rp 300000
470000 Rp 470000
166369.89 Rp 166369.89
1000000 Rp 1000000
150000 Rp 150000
140000 Rp 140000
17648.81 Rp 247789.29
21238.85 Rp 298193.45
1609545.69 Rp 40834174.1553
1493182.13 Rp 39061644.52
1263509.46 Rp 2122695.89
1228698.55 Rp 5344838.69
17705.77 Rp 60916692.85
830599.08 Rp 3521740.10
252627.8 Rp 12285289.91
690439.2 Rp 1380878.40
516225.43 Rp 1517702.76
56570 Rp 2750999.10
177009009.01
19470990.99
19572072.07
197500000
197500000
RENCANA ANGGARAN BIAYA (RAB)
1 2 3 4 5
IV PEKERJAAN PEMBESIAN
1 Beton Kolom K1 15/20 cm (Over Stek) 27.63 Kg Rp 14,267.00 Rp 394,197.21
2 Beton Kolom KP 13/17 cm (Over Stek) 17.28 Kg Rp 14,267.00 Rp 246,533.76
3 Beton Balok Gewel 15/20 cm 98.54 Kg Rp 14,267.00 Rp 1,405,870.18
4 Beton Ring Balok 15/20 cm 106.93 Kg Rp 14,267.00 Rp 1,525,570.31
5 Beton Balok Kuda-Kuda 15/20 cm 200.35 Kg Rp 14,267.00 Rp 2,858,393.45
6 Beton Balok Konsol 15/20 cm 147.25 Kg Rp 14,267.00 Rp 2,100,815.75
7 Beton Balok Tarik 15/30 cm 88.91 Kg Rp 14,267.00 Rp 1,268,478.97
TOTAL JUMLAH Rp. 9,799,859.63
V PEKERJAAN BEGESTING
1 Beton Kolom K1 15/20 cm (Over Stek) 2.68 m2 Rp 185,400.00 Rp 496,872.00
2 Beton Kolom KP 13/17 cm (Over Stek) 1.15 m2 Rp 185,400.00 Rp 213,210.00
3 Beton Balok Gewel 15/20 cm 4.04 m2 Rp 192,000.00 Rp 775,680.00
4 Beton Ring Balok 15/20 cm 5.85 m2 Rp 192,000.00 Rp 1,123,200.00
5 Beton Balok Kuda-Kuda 15/20 cm 15.08 m2 Rp 192,000.00 Rp 2,895,360.00
6 Beton Balok Konsol 15/20 cm 8.06 m2 Rp 192,000.00 Rp 1,547,520.00
7 Beton Balok Tarik 15/30 cm 4.17 m2 Rp 192,000.00 Rp 800,640.00
TOTAL JUMLAH Rp. 7,852,482.00
No. JENIS PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
1 2 3 4 5
VI PEKERJAAN PASANGAN
1 Pasang dinding bata merah 1Pc : 6Pp 48.96 m2 Rp 123,371.00 Rp 6,040,244.16
2 Plesteran Dinding 1Pc : 6Pp 73.94 m2 Rp 56,364.00 Rp 4,167,554.16
3 Benangan Sudut + Acian 40.20 m2 Rp 32,155.00 Rp 1,292,521.02
TOTAL JUMLAH Rp. 11,500,319.34
IX PEKERJAAN PLAFOND
1 Pasang Plafond Kalsiboard 40.86 m2 Rp 36,210.00 Rp 1,479,540.60
2 Pasang Rangka Plafond Galvalume 40.86 m2 Rp 128,080.00 Rp 5,233,348.80
TOTAL JUMLAH Rp. 6,712,889.40
I DIVISI
DIVISI 1.
2. UMUM
SISTEM MANAJEMEN Rp 4,500,000.00 Rp 4,500,000.00 Rp - Rp -
II KESELAMATAN KONSTRUKSI
DIVISI 4. PEKERJAAN TANAH (SMKK) Rp 2,226,369.89 Rp 2,226,369.89 Rp - Rp -
III DAN GEOSINTETIK Rp 741,945.61 Rp 741,945.61 Rp - Rp -
IV DIVISI
DIVISI 8.
9. STRUKTUR
REHABILITASI Rp 167,021,185.10 Rp 167,021,185.10 Rp - Rp -
V JEMBATAN Rp 2,519,627.80 Rp 2,519,627.80 Rp - Rp -
TERBILANG : SERATUS SEMBILAN PULUH ENAM JUTA EMPAT RATUS DELAPAN PULUH RIBU RUPIAH
KETERANGAN :
KONTRAKTOR PELAKSANA TIDAK AKAN MENUNTUT TAMBAHAN BIAYA SEBESAR : Rp. -
-
-
EDI DWI PURWANTO, ST., MM ADI TRI SETIYONO,ST
NIP. 19810909 200903 1 004 NIP . 19850423 201503 1 0001
REKAPITULASI LAPORAN Minggu Ke : I ( SATU )
KEMAJUAN PEKERJAAN Tanggal : 30 Mei 2023 s/d 04 Juni 2023
TAHAP
BOBOT PENYELESAIAN
TAHAP
TERHADAP TIAP BAG.
NO. URAIAN PEKERJAAN PENYELESAIAN TIAP
SELURUH TERHADAP
BAGIAN PEKERJAAN
PEKERJAAN SELURUH
PEKERJAAN
TAHAP
BOBOT PENYELESAIAN
TAHAP
TERHADAP TIAP BAG.
NO. URAIAN PEKERJAAN PENYELESAIAN TIAP
SELURUH TERHADAP
BAGIAN PEKERJAAN
PEKERJAAN SELURUH
PEKERJAAN
TAHAP
BOBOT PENYELESAIAN
TAHAP
TERHADAP TIAP BAG.
NO. URAIAN PEKERJAAN PENYELESAIAN TIAP
SELURUH TERHADAP
BAGIAN PEKERJAAN
PEKERJAAN SELURUH
PEKERJAAN
TAHAP
BOBOT PENYELESAIAN
TAHAP
TERHADAP TIAP BAG.
NO. URAIAN PEKERJAAN PENYELESAIAN TIAP
SELURUH TERHADAP
BAGIAN PEKERJAAN
PEKERJAAN SELURUH
PEKERJAAN
TAHAP
BOBOT PENYELESAIAN
TAHAP
TERHADAP TIAP BAG.
NO. URAIAN PEKERJAAN PENYELESAIAN TIAP
SELURUH TERHADAP
BAGIAN PEKERJAAN
PEKERJAAN SELURUH
PEKERJAAN
TAHAP
BOBOT PENYELESAIAN
TAHAP
TERHADAP TIAP BAG.
NO. URAIAN PEKERJAAN PENYELESAIAN TIAP
SELURUH TERHADAP
BAGIAN PEKERJAAN
PEKERJAAN SELURUH
PEKERJAAN
TAHAP
BOBOT PENYELESAIAN
TAHAP
TERHADAP TIAP BAG.
NO. URAIAN PEKERJAAN PENYELESAIAN TIAP
SELURUH TERHADAP
BAGIAN PEKERJAAN
PEKERJAAN SELURUH
PEKERJAAN
TAHAP
BOBOT PENYELESAIAN
TAHAP
TERHADAP TIAP BAG.
NO. URAIAN PEKERJAAN PENYELESAIAN TIAP
SELURUH TERHADAP
BAGIAN PEKERJAAN
PEKERJAAN SELURUH
PEKERJAAN
MINGGU KE : I ( SATU )
I DIVISI 1. UMUM
1 Mobilisasi Ls 1.00 1.98% 0.00% 0.00% 1.98% 100.00% 1.98% 1.98% 100.00% 1.98%
2 Kantor Lapangan dan Fasilitasnya Ls 1.00 0.56% 0.00% 0.00% 0.56% 100.00% 0.56% 0.56% 100.00% 0.56%
TOTAL JUMLAH 2.54% 0.00% 2.54% 2.54% 12.84% 2.54%
VI DIVISI 8. STRUKTUR
1 Beton struktur, fc30 Mpa (2)- Lantai Kendaraan m3 25.21 22.92% 0.00% 0.00% 22.92% 0.00% 0.00% 22.92% 0.00% 0.00%
2 Beton strukur, fc20 MPa (1) Tembok penahan m3 26.86 22.66% 0.00% 0.00% 22.66% 0.00% 0.00% 22.66% 0.00% 0.00%
3 Beton strukur, fc20 MPa tampa begesting m3 1.68 1.20% 0.00% 0.00% 1.99% 0.00% 0.00% 1.99% 0.00% 0.00%
4 Beton, fc10 Mpa m3 3.90 2.71% 0.00% 0.00% 6.36% 0.00% 0.00% 6.36% 0.00% 0.00%
5 Baja Tulangan Polos-BjTP 280 Kg 3,487.78 34.89% 0.00% 0.00% 0.78% 0.00% 0.00% 0.78% 0.00% 0.00%
6 pasangan batu Kg 4.24 1.99% 0.00% 0.00% 0.86% 0.00% 0.00% 0.86% 0.00% 0.00%
7 sandaran (Railing) M3 44.54 6.36% 0.00% 0.00% 94.36% 0.00% 0.00% 94.36% 0.00% 0.00%
8 Papan Nama Jembatan buah 2.00 0.78% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Pembongkaran beton M3 2.94 0.86% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TOTAL JUMLAH 94.36% 0.00% 55.56% 0.00% 32.23% 0.00%
DIVISI 9. REHABILITASI
VII
JEMBATANDekoratif pada elemen
Pengecatan
1 M2 44.54 1.42% 0.00% 0.00% 1.42% 0.00% 0.00% 1.42% 0.00% 0.00%
struktur beton, tebal 100 m
TOTAL JUMLAH 1.42% 0.00% 1.42% 0.00% 0.34% 0.00%
JUMLAH TOTAL 100.00% 0.00% 108.38% 3.88% 100.00% 3.88%
MINGGU KE : II ( DUA )
I DIVISI 1. UMUM
1 Mobilisasi Ls 1.00 1.98% 100.00% 1.98% 1.98% 100.00% 1.98% 1.98% 100.00% 1.98%
2 Kantor Lapangan dan Fasilitasnya Ls 1.00 0.56% 100.00% 0.56% 0.56% 100.00% 0.56% 0.56% 100.00% 0.56%
TOTAL JUMLAH 2.54% 2.54% 2.54% 2.54% 2.54% 2.54%
VI DIVISI 8. STRUKTUR
1 Beton struktur, fc30 Mpa (2)- Lantai Kendaraan m3 25.21 22.92% 0.00% 0.00% 22.92% 0.00% 0.00% 22.92% 0.00% 0.00%
2 Beton strukur, fc20 MPa (1) Tembok penahan m3 26.86 22.66% 0.00% 0.00% 22.66% 0.00% 0.00% 22.66% 0.00% 0.00%
3 Beton strukur, fc20 MPa tampa begesting m3 1.68 1.20% 0.00% 0.00% 1.20% 0.00% 0.00% 1.20% 0.00% 0.00%
4 Beton, fc10 Mpa m3 3.90 2.71% 0.00% 0.00% 2.71% 0.00% 0.00% 2.71% 0.00% 0.00%
5 Baja Tulangan Polos-BjTP 280 Kg 3,487.78 34.89% 0.00% 0.00% 34.89% 0.00% 0.00% 34.89% 0.00% 0.00%
6 pasangan batu Kg 4.24 1.99% 0.00% 0.00% 1.99% 0.00% 0.00% 1.99% 0.00% 0.00%
7 sandaran (Railing) M3 44.54 6.36% 0.00% 0.00% 6.36% 0.00% 0.00% 6.36% 0.00% 0.00%
8 Papan Nama Jembatan buah 2.00 0.78% 0.00% 0.00% 0.78% 0.00% 0.00% 0.78% 0.00% 0.00%
9 Pembongkaran beton M3 2.94 0.86% 0.00% 0.00% 0.86% 0.00% 0.00% 0.86% 0.00% 0.00%
TOTAL JUMLAH 94.36% 0.00% 94.36% 0.00% 94.36% 0.00%
DIVISI 9. REHABILITASI
VII
JEMBATAN
Pengecatan Dekoratif pada elemen
1 M2 44.54 1.42% 0.00% 0.00% 1.42% 0.00% 0.00% 1.42% 0.00% 0.00%
struktur beton, tebal 100 m
TOTAL JUMLAH 1.42% 0.00% 1.42% 0.00% 1.42% 0.00%
JUMLAH TOTAL 100.00% 3.86% 100.00% 4.09% 100.00% 4.09%
0
Menyetujui, Dibuat oleh :
Konsultan Pengawas Kontraktor Pelaksana
CV. GRAMA ENGINEERING CV.DWI KARYA MUDA
I DIVISI 1. UMUM
1 Mobilisasi Ls 1.00 1.98% 100.00% 1.98% 1.98% 100.00% 1.98% 1.98% 100.00% 1.98%
2 Kantor Lapangan dan Fasilitasnya Ls 1.00 0.56% 100.00% 0.56% 0.56% 100.00% 0.56% 0.56% 100.00% 0.56%
TOTAL JUMLAH 2.54% 2.54% 2.54% 2.54% 2.54% 2.54%
VI DIVISI 8. STRUKTUR
1 Beton struktur, fc30 Mpa (2)- Lantai Kendaraan m3 25.21 22.92% 0.00% 0.00% 22.92% 0.00% 0.00% 22.92% 0.00% 0.00%
2 Beton strukur, fc20 MPa (1) Tembok penahan m3 26.86 22.66% 0.00% 0.00% 22.66% 0.00% 0.00% 22.66% 0.00% 0.00%
3 Beton strukur, fc20 MPa tampa begesting m3 1.68 1.20% 0.00% 0.00% 1.20% 0.00% 0.00% 1.20% 0.00% 0.00%
4 Beton, fc10 Mpa m3 3.90 2.71% 0.00% 0.00% 2.71% 0.00% 0.00% 2.71% 0.00% 0.00%
5 Baja Tulangan Polos-BjTP 280 Kg 3,487.78 34.89% 0.00% 0.00% 34.89% 32.00% 11.16% 34.89% 32.00% 11.16%
6 pasangan batu Kg 4.24 1.99% 0.00% 0.00% 1.99% 0.00% 0.00% 1.99% 0.00% 0.00%
7 sandaran (Railing) M3 44.54 6.36% 0.00% 0.00% 6.36% 0.00% 0.00% 6.36% 0.00% 0.00%
8 Papan Nama Jembatan buah 2.00 0.78% 0.00% 0.00% 0.78% 0.00% 0.00% 0.78% 0.00% 0.00%
9 Pembongkaran beton M3 2.94 0.86% 0.00% 0.00% 0.86% 0.00% 0.00% 0.86% 0.00% 0.00%
TOTAL JUMLAH 94.36% 0.00% 94.36% 11.16% 94.36% 11.16%
DIVISI 9. REHABILITASI
VII
JEMBATAN
Pengecatan Dekoratif pada elemen
1 M2 44.54 1.42% 0.00% 0.00% 1.42% 0.00% 0.00% 1.42% 0.00% 0.00%
struktur beton, tebal 100 m
TOTAL JUMLAH 1.42% 0.00% 1.42% 0.00% 1.42% 0.00%
JUMLAH TOTAL 100.00% 4.09% 100.00% 15.25% 100.00% 15.25%
0
Menyetujui, Dibuat oleh :
Konsultan Pengawas Kontraktor Pelaksana
CV. GRAMA ENGINEERING CV.DWI KARYA MUDA
MINGGU KE : IV ( EMPAT )
I DIVISI 1. UMUM
1 Mobilisasi Ls 1.00 1.98% 100.00% 1.98% 1.98% 100.00% 1.98% 1.98% 100.00% 1.98%
2 Kantor Lapangan dan Fasilitasnya Ls 1.00 0.56% 100.00% 0.56% 0.56% 100.00% 0.56% 0.56% 100.00% 0.56%
TOTAL JUMLAH 2.54% 2.54% 2.54% 2.54% 2.54% 2.54%
VI DIVISI 8. STRUKTUR
1 Beton struktur, fc30 Mpa (2)- Lantai Kendaraan m3 25.21 22.92% 0.00% 0.00% 22.92% 0.00% 0.00% 22.92% 0.00% 0.00%
2 Beton strukur, fc20 MPa (1) Tembok penahan m3 26.86 22.66% 0.00% 0.00% 22.66% 85.00% 19.26% 22.66% 85.00% 19.26%
3 Beton strukur, fc20 MPa tampa begesting m3 1.68 1.20% 0.00% 0.00% 1.20% 0.00% 0.00% 1.20% 0.00% 0.00%
4 Beton, fc10 Mpa m3 3.90 2.71% 0.00% 0.00% 2.71% 50.00% 1.35% 2.71% 50.00% 1.35%
5 Baja Tulangan Polos-BjTP 280 Kg 3,487.78 34.89% 32.00% 11.16% 34.89% 70.00% 24.42% 34.89% 70.00% 24.42%
6 pasangan batu Kg 4.24 1.99% 0.00% 0.00% 1.99% 25.00% 0.50% 1.99% 25.00% 0.50%
7 sandaran (Railing) M3 44.54 6.36% 0.00% 0.00% 6.36% 20.00% 1.27% 6.36% 20.00% 1.27%
8 Papan Nama Jembatan buah 2.00 0.78% 0.00% 0.00% 0.78% 0.00% 0.00% 0.78% 0.00% 0.00%
9 Pembongkaran beton M3 2.94 0.86% 0.00% 0.00% 0.86% 60.00% 0.51% 0.86% 60.00% 0.51%
TOTAL JUMLAH 94.36% 11.16% 94.36% 47.32% 94.36% 47.32%
DIVISI 9. REHABILITASI
VII
JEMBATAN
Pengecatan Dekoratif pada elemen
1 M2 44.54 1.42% 0.00% 0.00% 1.42% 0.00% 0.00% 1.42% 0.00% 0.00%
struktur beton, tebal 100 m
TOTAL JUMLAH 1.42% 0.00% 1.42% 0.00% 1.42% 0.00%
JUMLAH TOTAL 100.00% 15.25% 100.00% 51.40% 100.00% 51.40%
0
Menyetujui, Dibuat oleh :
Konsultan Pengawas Kontraktor Pelaksana
CV. GRAMA ENGINEERING CV.DWI KARYA MUDA
MINGGU KE : V ( LIMA )
I DIVISI 1. UMUM
1 Mobilisasi Ls 1.00 1.98% 100.00% 1.98% 1.98% 100.00% 1.98% 1.98% 100.00% 1.98%
2 Kantor Lapangan dan Fasilitasnya Ls 1.00 0.56% 100.00% 0.56% 0.56% 100.00% 0.56% 0.56% 100.00% 0.56%
TOTAL JUMLAH 2.54% 2.54% 2.54% 2.54% 2.54% 2.54%
VI DIVISI 8. STRUKTUR
1 Beton struktur, fc30 Mpa (2)- Lantai Kendaraan m3 25.21 22.92% 0.00% 0.00% 22.92% 50.00% 11.46% 22.92% 50.00% 11.46%
2 Beton strukur, fc20 MPa (1) Tembok penahan m3 26.86 22.66% 85.00% 19.26% 22.66% 100.00% 22.66% 22.66% 100.00% 22.66%
3 Beton strukur, fc20 MPa tampa begesting m3 1.68 1.20% 0.00% 0.00% 1.20% 0.00% 0.00% 1.20% 0.00% 0.00%
4 Beton, fc10 Mpa m3 3.90 2.71% 50.00% 1.35% 2.71% 50.00% 1.35% 2.71% 50.00% 1.35%
5 Baja Tulangan Polos-BjTP 280 Kg 3,487.78 34.89% 70.00% 24.42% 34.89% 81.00% 28.26% 34.89% 81.00% 28.26%
6 pasangan batu Kg 4.24 1.99% 25.00% 0.50% 1.99% 0.00% 0.00% 1.99% 0.00% 0.00%
7 sandaran (Railing) M3 44.54 6.36% 20.00% 1.27% 6.36% 50.00% 3.18% 6.36% 50.00% 3.18%
8 Papan Nama Jembatan buah 2.00 0.78% 0.00% 0.00% 0.78% 0.00% 0.00% 0.78% 0.00% 0.00%
9 Pembongkaran beton M3 2.94 0.86% 60.00% 0.51% 0.86% 80.00% 0.69% 0.86% 80.00% 0.69%
TOTAL JUMLAH 94.36% 47.32% 94.36% 67.60% 94.36% 67.60%
DIVISI 9. REHABILITASI
VII
JEMBATAN
Pengecatan Dekoratif pada elemen
1 M2 44.54 1.42% 0.00% 0.00% 1.42% 0.00% 0.00% 1.42% 0.00% 0.00%
struktur beton, tebal 100 m
TOTAL JUMLAH 1.42% 0.00% 1.42% 0.00% 1.42% 0.00%
JUMLAH TOTAL 100.00% 51.40% 100.00% 71.81% 100.00% 71.81%
0
Menyetujui, Dibuat oleh :
Konsultan Pengawas Kontraktor Pelaksana
CV. GRAMA ENGINEERING CV.DWI KARYA MUDA
MINGGU KE : VI ( ENAM )
I DIVISI 1. UMUM
1 Mobilisasi Ls 1.00 1.98% 100.00% 1.98% 1.98% 100.00% 1.98% 1.98% 100.00% 1.98%
2 Kantor Lapangan dan Fasilitasnya Ls 1.00 0.56% 100.00% 0.56% 0.56% 100.00% 0.56% 0.56% 100.00% 0.56%
TOTAL JUMLAH 2.54% 2.54% 2.54% 2.54% 2.54% 2.54%
DIVISI 9. REHABILITASI
VII
JEMBATAN
Pengecatan Dekoratif pada elemen
1 M2 44.54 1.42% 0.00% 0.00% 1.42% 0.00% 0.00% 1.42% 0.00% 0.00%
struktur beton, tebal 100 m
TOTAL JUMLAH 1.42% 0.00% 1.42% 0.00% 1.42% 0.00%
JUMLAH TOTAL 100.00% 71.71% 100.00% 79.70% 100.00% 79.70%
0
Menyetujui, Dibuat oleh :
Konsultan Pengawas Kontraktor Pelaksana
CV. GRAMA ENGINEERING CV.DWI KARYA MUDA
I DIVISI 1. UMUM
1 Mobilisasi Ls 1.00 1.98% 100.00% 1.98% 1.98% 100.00% 1.98% 1.98% 100.00% 1.98%
2 Kantor Lapangan dan Fasilitasnya Ls 1.00 0.56% 100.00% 0.56% 0.56% 100.00% 0.56% 0.56% 100.00% 0.56%
TOTAL JUMLAH 2.54% 2.54% 2.54% 2.54% 2.54% 2.54%
VI DIVISI 8. STRUKTUR
1 Beton struktur, fc30 Mpa (2)- Lantai Kendaraan m3 25.21 22.92% 50.00% 11.46% 22.92% 100.00% 22.92% 22.92% 100.00% 22.92%
2 Beton strukur, fc20 MPa (1) Tembok penahan m3 26.86 22.66% 100.00% 22.66% 22.66% 100.00% 22.66% 22.66% 100.00% 22.66%
3 Beton strukur, fc20 MPa tampa begesting m3 1.68 1.20% 40.00% 0.48% 1.20% 100.00% 1.20% 1.20% 100.00% 1.20%
4 Beton, fc10 Mpa m3 3.90 2.71% 100.00% 2.71% 2.71% 100.00% 2.71% 2.71% 100.00% 2.71%
5 Baja Tulangan Polos-BjTP 280 Kg 3,487.78 34.89% 95.00% 33.14% 34.89% 100.00% 34.89% 34.89% 100.00% 34.89%
6 pasangan batu Kg 4.24 1.99% 50.00% 0.99% 1.99% 100.00% 1.99% 1.99% 100.00% 1.99%
7 sandaran (Railing) M3 44.54 6.36% 50.00% 3.18% 6.36% 100.00% 6.36% 6.36% 100.00% 6.36%
8 Papan Nama Jembatan buah 2.00 0.78% 0.00% 0.00% 0.78% 100.00% 0.78% 0.78% 100.00% 0.78%
9 Pembongkaran beton M3 2.94 0.86% 100.00% 0.86% 0.86% 100.00% 0.86% 0.86% 100.00% 0.86%
TOTAL JUMLAH 94.36% 75.48% 94.36% 94.36% 94.36% 94.36%
DIVISI 9. REHABILITASI
VII
JEMBATAN
Pengecatan Dekoratif pada elemen
1 M2 44.54 1.42% 0.00% 0.00% 1.42% 100.00% 1.42% 1.42% 100.00% 1.42%
struktur beton, tebal 100 m
TOTAL JUMLAH 1.42% 0.00% 1.42% 1.42% 1.42% 1.42%
JUMLAH TOTAL 100.00% 79.59% 100.00% 100.00% 100.00% 100.00%
0
Menyetujui, Dibuat oleh :
Konsultan Pengawas Kontraktor Pelaksana
CV. GRAMA ENGINEERING CV.DWI KARYA MUDA
I DIVISI 1. UMUM
1 Mobilisasi Ls 1.00 1.98% 100.00% 1.98% 1.98% 0.00% 0.00% 1.98% 100.00% 1.98%
2 Kantor Lapangan dan Fasilitasnya Ls 1.00 0.56% 100.00% 0.56% 0.56% 0.00% 0.00% 0.56% 100.00% 0.56%
0 TOTAL JUMLAH - - 2.54% 0.00% 0.00% 2.54% 0.00% 0.00% 2.54% 100.00% 2.54%
TOTAL JUMLAH 5.08% 2.54% 5.08% 0.00% 5.08% 5.08%
0 TOTAL JUMLAH
1 - - - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
TOTAL JUMLAH 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Beton strukur, fc20 MPa (1) Tembok penahan
1 Beton strukur, fc20 MPa tampa begesting m3 1.68 1.20% 100.00% 1.20% 1.20% 0.00% 0.00% 1.20% 100.00% 1.20%
2 Beton, fc10 Mpa m3 3.90 2.71% 100.00% 2.71% 2.71% 0.00% 0.00% 2.71% 100.00% 2.71%
3 Baja Tulangan Polos-BjTP 280 Kg 3,487.78 34.89% 100.00% 34.89% 34.89% 0.00% 0.00% 34.89% 100.00% 34.89%
TOTAL JUMLAH 38.79% 38.79% 38.79% 0.00% 38.79% 38.79%
### #REF!
1 #REF! #REF! #REF! #REF! #REF! #REF! #REF! 100.00% #REF! #REF! 100.00% #REF!
TOTAL JUMLAH #REF! #REF! #REF! #REF! #REF! #REF!
JUMLAH TOTAL #REF! #REF! #REF! #REF! #REF! #REF!
0
### #REF!
### #REF!
### #REF!
### #REF!
### #REF!
LAPORAN HARIAN
MINGGU KE : I ( SATU ) Hari : SELASA
Tanggal : 30 Mei 2023
1
1 Pelaksana Org - Mobilisasi
2 Mandor
1
Org L
3 Tukang Batu
2
Org E
4 Tukang Kayu
0
Org N
5 Tukang Besi
2
Org G
6 Tukang Cat
-
Org K
7 Tukang Listrik
-
Org A
8 Pekerja
6
Org P
0
9 Logistik Org
…................................. ….................................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : I ( SATU ) Hari : RABU
Tanggal : 31 Mei 2023
1
1 Pelaksana Org Besi Beton 498.00 kg - Mobilisasi
2 Mandor
1
Org Kawat Bendrat 8.00 kg L
3 Tukang
6
Org Semen 39.00 zak E
4 KepalaTukang
3
Org Pasir Beton 2.50 m3 N
5 Pekerja
6
Org Batu Pecah 3.60 m3 G
6 Logistik
1
Org Air 1,023.00 ltr K
A
P
…................................. ….................................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : I ( SATU ) Hari : KAMIS
Tanggal : 01 Juni 2023
1
1 Pelaksana Org - Kantor Lapangan dan Fasilitasnya
2 Mandor
1
Org L - Kantor Lapangan dan Fasilitasnya
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : I ( SATU ) Hari : JUM'AT
Tanggal : 02 Juni 2023
1
1 Pelaksana Org - Kantor Lapangan dan Fasilitasnya
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : I ( SATU ) Hari : SABTU
Tanggal : 03 Juni 2023
1
1 Pelaksana Org - Kantor Lapangan dan Fasilitasnya
Alat Pelindung Kerja dan Alat
2 Mandor
1
Org L - Pelindung Diri
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : I ( SATU ) Hari : MINGGU
Tanggal : 04 Juni 2023
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : II ( DUA ) Hari : SENIN
Tanggal : 05 Juni 2023
1
1 Pelaksana Org Alat Pelindung Diri - Pembersihan Lokasi Gorong Gorong
2 Mandor
1
Org Kegiatan Alat Yang terkait L - Pasang Bowplank Gorong Gorong
3 Tukang
6
Org Gorong Gorong Beton 7 E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : II ( DUA ) Hari : SELASA
Tanggal : 06 Juni 2023
1
1 Pelaksana Org - Pasang Gorong Gorong Beton
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : II ( DUA ) Hari : RABU
Tanggal : 07 Juni 2023
1
1 Pelaksana Org - Pasang Gorong Gorong Beton
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : II ( DUA ) Hari : KAMIS
Tanggal : 08 Juni 2023
1
1 Pelaksana Org - Pasang Gorong Gorong Beton
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : II ( DUA ) Hari : JUM'AT
Tanggal : 09 Juni 2023
1
1 Pelaksana Org - Galian Tanah
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : II ( DUA ) Hari : SABTU
Tanggal : 10 Juni 2023
1
1 Pelaksana Org - Galian Tanah
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : II ( DUA ) Hari : MINGGU
Tanggal : 11 Juni 2023
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : III ( TIGA ) Hari : SENIN
Tanggal : 12 Juni 2023
1
1 Pelaksana Org Kayu Kelas II 1.13 m3 - Galian Tanah Struktur
2 Mandor
1
Org Reng Kayu Jati 0.50 m3 L
3 Tukang
6
Org Paku 21.00 kg E
4 KepalaTukang
3
Org Genteng Bubungan 129.00 bh N
5 Pekerja
6
Org Semen 6.00 zak G
6 Logistik
1
Org Pasir Pasang 1.00 m3 K
Genteng Baru 500 bh A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : III ( TIGA ) Hari : SELASA
Tanggal : 13 Juni 2023
1
1 Pelaksana Org - Galian Tanah Struktur
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : III ( TIGA ) Hari : RABU
Tanggal : 14 Juni 2023
1
1 Pelaksana Org - Galian Tanah Struktur
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : III ( TIGA ) Hari : KAMIS
Tanggal : 15 Juni 2023
1
1 Pelaksana Org - Lantai Kendaraan
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : III ( TIGA ) Hari : JUM'AT
Tanggal : 16 Juni 2023
1
1 Pelaksana Org - Lantai Kendaraan
2 Mandor
1
Org L -
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : III ( TIGA ) Hari : SABTU
Tanggal : 17 Juni 2023
1
1 Pelaksana Org - Pemasangan Tembok Penahan
2 Mandor
1
Org L -
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : III ( TIGA ) Hari : MINGGU
Tanggal : 18 Juni 2023
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : IV ( EMPAT ) Hari : SENIN
Tanggal : 19 Juni 2023
1
1 Pelaksana Org Woodplank 82.00 m - Pemasangan Tembok Penahan
2 Mandor
1
Org Paku 7.50 kg L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
6 Logistik
1
Org K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : IV ( EMPAT ) Hari : SELASA
Tanggal : 20 Juni 2023
1
1 Pelaksana Org - Pemasangan Tembok Penahan
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : IV ( EMPAT ) Hari : RABU
Tanggal : 21 Juni 2023
1
1 Pelaksana Org - Pemasangan Tembok Penahan
2 Mandor
1
Org L -
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : IV ( EMPAT ) Hari : KAMIS
Tanggal : 22 Juni 2023
1
1 Pelaksana Org - Pemasangan Tembok Penahan
2 Mandor
1
Org L - Pengecora Beton fc 10 Mpa
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : IV ( EMPAT ) Hari : JUM'AT
Tanggal : 23 Juni 2023
1
1 Pelaksana Org - Pengecora Beton fc 10 Mpa
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : IV ( EMPAT ) Hari : SABTU
Tanggal : 24 Juni 2023
1
1 Pelaksana Org - Pemasangan Baja Tulangan Polos
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : IV ( EMPAT ) Hari : MINGGU
Tanggal : 25 Juni 2023
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : V ( LIMA ) Hari : SENIN
Tanggal : 26 Juni 2023
1
1 Pelaksana Org Hollow Galvalume Uk. 35x35mm 867.00 m - Pemasangan Baja Tulangan Polos
2 Mandor
1
Org Kalsiboard 93.00 lbr L
3 Tukang
6
Org Paku Kalsiboard 7.50 kg E
4 KepalaTukang
3
Org List Alumunium 290.00 m N
5 Pekerja
6
Org Paku Sekrup 1,376.00 bh G
6 Logistik
1
Org K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : V ( LIMA ) Hari : SELASA
Tanggal : 27 Juni 2023
1
1 Pelaksana Org - Pemasangan Baja Tulangan Polos
2 Mandor
1
Org L - Pemasangan Baja Tulangan Sirip
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : V ( LIMA ) Hari : RABU
Tanggal : 28 Juni 2023
1
1 Pelaksana Org - Pemasangan Baja Tulangan Sirip
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : V ( LIMA ) Hari : KAMIS
Tanggal : 29 Juni 2023
1
1 Pelaksana Org - Pemasangan Baja Tulangan Sirip
2 Mandor
1
Org L - Pemasangan Baja Tulangan Polos
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : V ( LIMA ) Hari : JUM'AT
Tanggal : 30 Juni 2023
1
1 Pelaksana Org - Pemasangan Baja Tulangan Sirip
2 Mandor
1
Org L - Pemasangan Baja Tulangan Polos
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : V ( LIMA ) Hari : SABTU
Tanggal : 01 Juli 2023
1
1 Pelaksana Org - Pembongkaran Batu
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : V ( LIMA ) Hari : MINGGU
Tanggal : 02 Juli 2023
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VI ( ENAM ) Hari : SENIN
Tanggal : 03 Juli 2023
1
1 Pelaksana Org Keramik 40 x 40 cm 1,373.00 bh - Pemasangan Batu
2 Mandor
1
Org Kermik Dinding 25 x 40 cm 318.00 bh L
3 Tukang
6
Org Semen 58.00 zak E
4 KepalaTukang
3
Org Pasir Pasang 10.00 m3 N
5 Pekerja
6
Org Lampu TL 20 Watt Err:509 bh G
6 Logistik
1
Org Lampu LED 12 Watt Err:509 bh K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VI ( ENAM ) Hari : SELASA
Tanggal : 04 Juli 2023
1
1 Pelaksana Org - Pemasangan Batu
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VI ( ENAM ) Hari : RABU
Tanggal : 05 Juli 2023
1
1 Pelaksana Org - Anyaman Kawat Las
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E - Pemasangan Lapis Perekat Aspal
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VI ( ENAM ) Hari : KAMIS
Tanggal : 06 Juli 2023
1
1 Pelaksana Org - Anyaman Kawat Las
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E - Pemasangan Lapis Perekat Aspal
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VI ( ENAM ) Hari : JUM'AT
Tanggal : 07 Juli 2023
1
1 Pelaksana Org - Anyaman Kawat Las
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E - Pemasangan Lapis Perekat Aspal
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VI ( ENAM ) Hari : SABTU
Tanggal : 08 Juli 2023
1
1 Pelaksana Org - Anyaman Kawat Las
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E - Pemasangan Lapis Perekat Aspal
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VI ( ENAM ) Hari : MINGGU
Tanggal : 09 Juli 2023
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VII ( TUJUH ) Hari : SENIN
Tanggal : 10 Juli 2023
1
1 Pelaksana Org - Anyaman Kawat Las
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E - Pemasangan Lapis Perekat Aspal
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VII ( TUJUH ) Hari : SELASA
Tanggal : 11 Juli 2023
1
1 Pelaksana Org - Pemasangan Lapis Perekat Aspal
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VII ( TUJUH ) Hari : RABU
Tanggal : 12 Juli 2023
1
1 Pelaksana Org - Pemasangan Ac-Wc Aspal Manual
2 Mandor
1
Org L - Pemasangan Lapis Perekat Aspal
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VII ( TUJUH ) Hari : KAMIS
Tanggal : 13 Juli 2023
1
1 Pelaksana Org - Pemasangan Lapis Perekat Aspal
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VII ( TUJUH ) Hari : JUM'AT
Tanggal : 14 Juli 2023
1
1 Pelaksana Org - Pemasangan Lapis Perekat Aspal
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VII ( TUJUH ) Hari : SABTU
Tanggal : 15 Juli 2023
1
1 Pelaksana Org - Pemasangan Lapis Perekat Aspal
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VII ( TUJUH ) Hari : MINGGU
Tanggal : 16 Juli 2023
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VIII ( DELAPAN ) Hari : SENIN
Tanggal : 17 Juli 2023
1
1 Pelaksana Org Kunci Pintu 3.00 bh - Pemasangan Lapis Perekat Aspal
2 Mandor
1
Org Plamir 65.00 kg L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org Cat Dasar 65.00 kg E
4 KepalaTukang
3
Org Cat Eksterior 36.00 kg N
5 Pekerja
6
Org Cat Interior 131.00 kg G
6 Logistik
1
Org K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VIII ( DELAPAN ) Hari : SELASA
Tanggal : 18 Juli 2023
1
1 Pelaksana Org - Pemasangan Lapis Perekat Aspal
2 Mandor
1
Org L - Pemasangan Ac-Wc Aspal Manual
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VIII ( DELAPAN ) Hari : RABU
Tanggal : 19 Juli 2023
1
1 Pelaksana Org - Pengectan Parapet
2 Mandor
1
Org L
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
LAPORAN HARIAN
MINGGU KE : VIII ( DELAPAN ) Hari : KAMIS
Tanggal : 20 Juli 2023
1
1 Pelaksana Org - fhinishing
2 Mandor
1
Org L -
3 Tukang
6
Org E
4 KepalaTukang
3
Org N
5 Pekerja
6
Org G
K
A
P
….................. …..................
Pengawas Pelaksana
DOKUMEN PELAKSANAAN
KEGIATAN :
PEKERJAAN :
ALAMAT :
2 0 2 3
TIME SCHEDULE
PROGAM : PROGRAM REHABILITASI JEMBATAN MINGGU KE : I ( SATU )
KEGIATAN : PENYELENGARAAN JALAN KABUPATEN KOTA
PEKERJAAN :
REHABILITASA JEMBATAN MENDALEM - SIMOREJO 2 ( MENDALEM - SIMOREJO ) KEC.
KANOR
Menyetujui,
Konsultan Pengawas
CV. GRAMA ENGINEERING
…..................
Pengawas
DAFTAR ISIAN
PENGGUNAAN HASIL PRODUKSI PERTAMBANGAN BAHAN
GALIAN GOLONGAN C
KABUPATEN BOJONEGORO DENGAN
SISTEM WAJIB PUNGUT ( WAPU )
1 Pasir 17.00 -
Bojonegoro, 2019
Dibuat oleh :
KONTRAKTOR PELAKSANA
CV.DWI KARYA MUDA
ABDUL LATIF
Direktur
DAFTAR ISIAN
PENGGUNAAN HASIL PRODUKSI PERTAMBANGAN BAHAN - GALIAN GOLONGAN
KABUPATEN BOJONEGORO DENGAN SISTEM WAJIB PUNGUT ( WAPU )
A. PERHITUNGAN MATERIAL
DATA RINCIAN (RAB) KOEFISIEN DALAM ANALISA SATUAN PEKERJAAN
NO. VOLUME PASIR PASIR TANAH
URAIAN PEKERJAAN SAT. PASIR COR
TOTAL PASANG URUG URUG
1 Pekerjaan Plesteran 1Pc : 6Pp (Tambal Sulam Yang Rusak) Err:509 m2 0.03
2 Benangan Sudut + Ornamen Err:509 m' 0.01
3 Pasang Keramik Lantai 40 x 40 cm 44.54 m2 0.05
4 Pasang Keramik Dinding 25 x 40 cm Err:509 m2 0.05
5 Pasang Genteng Bubungan Err:509 m' 0.03
6 Pek. Beton Mutu Fc' : 14,5 Mpa Err:509 m3 0.54
JUMLAH TOTAL
Mengetahui :
PEJABAT PEMBUAT KOMITMEN (PPK)
BIDANG JEMBATAN
EDI DWI PURWANTO, ST., MM
NIP. 19810909 200903 1 004
- GALIAN GOLONGAN C
PUNGUT ( WAPU )
ABDUL LATIF
Direktur