Anda di halaman 1dari 3

PEMELIHARAAN RUTIN PLTG TELLO NO DOK :

WEEK-34 (21 - 25 AGUSTUS 2023) REV :

PIP UPDK TELLO

NO PM NUMBER WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

HME

7 GT02-PM-RTN-HME-MBK-AP001 202313551 PM GT02 PENGECEKAN MEKANIC HYDRAULIC MOTOR HR-1 HME 24/08/23 Asmar, Burhanudin 2 01:30 03:00
MAN HOUR REQUARED 24:00
MAN HOUR AVAILABLE 80
% UTILITY 30%

NO PM NUMBER WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

HKI & HLI

13 GT02-PM-RTN-HKI-MBH-GL007 202313603 PM GT02 PENGECEKAN INSTRUMENT DAN CONTROL TEMPERATURE TURBINE HEATERHLI-GT 24/08/23 Ahmad, Rahmanda 2 01:00 02:00
14 GT02-PM-RTN-HLI-MBV-AP006 202313468 PM GT02 PENGECEKAN KELISTRIKAN MOTOR OIL QE HLI-GT 24/08/23 Ahmad, Rahmanda 2 01:00 02:00
15 GT02-PM-RTN-HKI-MBH-GL001 202313601 PM GT02 PENGECEKAN INSTRUMENT DAN CONTROL TEMPERATURE HIGH ALARM HLI-GT 24/08/23 Ahmad, Rahmanda 2 01:00 02:00
16 GT02-PM-RTN-HKI-MBH-GL004 202313602 PM GT02 PENGECEKAN INSTRUMENT DAN CONTROL TEMPERATURE OFF BT HLI-GT 24/08/23 Ahmad, Rahmanda 2 01:00 02:00
MAN HOUR REQUARED 38:00
MAN HOUR AVAILABLE 80
% UTILITY 48%
PEMELIHARAAN RUTIN PLTD SELAYAR NO DOK :

WEEK-34 (21 - 25 AGUSTUS 2023) REV :

PIP UPDK TELLO

NO WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

PM PLTD SELAYAR

HME

48 SL10-PM-RTN-HME-MJV-AT001 PEMELIHARAAN P2 [MITSUBISHI 3] LUBE OIL FILTER & BYPASS HME 24 August 2023 Marwan, Khareum, Samsul 3 01:00 03:00
49 SL10-PM-RTN-HME-MJB-AN001 PEMELIHARAAN P1 [MITSUBISHI 3] MOTOR BLOWER 01-04 HME 24 August 2023 Marwan, Samsul, Agus 3 01:00 03:00
50 SL10-PM-RTN-HME-MJG-AN001 PEMELIHARAAN P1 [MITSUBISHI 3] MOTOR RADIATOR FAN 01-04 HME 24 August 2023 Marwan, Rizal, Ishaq 3 01:00 03:00
51 SL10-PM-RTN-HME-MJN-AT001 PEMELIHARAAN P1 [MITSUBISHI 3] FUEL FILTER, INJECTION PUMP 1-2, PIPING HME 24 August 2023 Marwan, Khareum, Samsul 3 01:00 03:00
52 SL10-PM-RTN-HME-MJP-AG001 PEMELIHARAAN P1 [MITSUBISHI 3] ALTERNATOR HME 24 August 2023 Marwan, Samsul, Rizal 3 01:00 03:00
53 SL10-PM-RTN-HME-MJV-AP001 PEMELIHARAAN P1 [MITSUBISHI 3] PRIMING PUMP HME 24 August 2023 Marwan, Rizal, Agus 3 01:00 03:00
MAN HOUR REQUARED 111:00
MAN HOUR AVAILABLE 200
% LOAD BALANCE 55,50%
HLI

25 SL10-PM-RTN-HLI-BBA-GS001 PEMELIHARAAN P2 [MITSUBISHI 3] SWITCHGEAR EQUIP. (VACUM CIRCUIT BREAKER) HLI 24 August 2023 Fachrul, Engga, Rizal D 3 01:00 03:00
26 SL10-PM-RTN-HLI-BAC-GS002 PEMELIHARAAN P1 [MITSUBISHI 3] VACUM CIRCUIT BREAKER HLI 24 August 2023 Fachrul, Engga, Rizal D 3 01:00 03:00
27 SL10-PM-RTN-HLI-BAT-AH001 HLI
PEMELIHARAAN P1 [MITSUBISHI 3] HEATING, STORAGE EQUIPMENT, TRANFORMER, ISOLATING LV & HV 24 August 2023 Fachrul, Engga, Rizal D 3 01:00 03:00
28 SL10-PM-RTN-HLI-BBT-GD001 HLI
PEMELIHARAAN P1 [MITSUBISHI 3] EQUPMENT 6,3 KV HV & LV, STATION SERVICE TRAFO 24 August 2023 Fachrul, Engga, Rizal D 3 01:00 03:00
29 SL10-PM-RTN-HLI-BTR-GR001 PEMELIHARAAN P1 [MITSUBISHI 3] 12 V BATTERY 220 AH SYSTEM HLI 24 August 2023 Fachrul, Engga, Rizal D 3 01:00 03:00
MAN HOUR REQUARED 69:00
MAN HOUR AVAILABLE 120
% UTILITY 58%
PEMELIHARAAN RUTIN PLTD TELLO NO DOK :

WEEK-34 (21 - 25 AGUSTUS 2023) REV :

PIP UPDK TELLO

WORK ORDER
NO WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL
NUMBER

HLI

1 DT04-PM-RTN-HLI-BBT-GT002 202313909 PEMELIHARAAN P1 TRAFO PS SWD 2 SWD 2 HLI 24 August 2023 Kafrawi, Jabbar 2 00:45 01:30
2 DT04-PM-RTN-HLI-MJY-GH001 202313910 PEMELIHARAAN P1 ENGINE CONTROL PANEL SWD 2 SWD 2 HLI 24 August 2023 Kafrawi, Jabbar 2 00:45 01:30
3 DT04-PM-RTN-HLI-MJY-GH004 202313911 PEMELIHARAAN P2 TEMPERATURE TRANSMITTER (DCP) SWD 2 SWD 2 HLI 24 August 2023 Salvius, Kafrawi, Jabbar 3 00:45 02:15
4 DT04-PM-RTN-HLI-MJY-GH008 202313913 PEMELIHARAAN P2 MAIN BEARING TEMPERATURE CONTROLER SWD 2 SWD 2 HLI 24 August 2023 Salvius,, Kafrawi, Jabbar 3 00:45 02:15
5 DT04-PM-RTN-HLI-MJY-GH013 202313914 PEMELIHARAAN P2 EXHAUST GAS THERMOCOUPLE SWD 2 SWD 2 HLI 24 August 2023 Salvius,, Kafrawi, Jabbar 3 00:45 02:15
6 DT04-PM-RTN-HLI-MJY-GH021 202313917 PEMELIHARAAN P2 PRESSURE SWITCH 1 SET SWD 2 SWD 2 HLI 24 August 2023 Salvius,, Kafrawi, Jabbar 3 00:45 02:15
7 DT04-PM-RTN-HLI-MKA-HB001 202313919 PEMELIHARAAN P1 FRAME SWD 2 SWD 2 HLI 24 August 2023 Kafrawi, Jabbar 2 00:45 01:30
41 DT04-PM-RTN-HLI-BBT-GH002 202313908 PEMELIHARAAN P1 PMT TRAFO PS SWD 2 SWD 2 HLI 24 August 2023 Kafrawi, Jabbar 2 00:45 01:30
42 DT04-PM-RTN-HLI-MJY-GH015 202313915 PEMELIHARAAN P1 PICK UP SENSOR SWD 2 SWD 2 HLI 24 August 2023 Kafrawi, Jabbar 2 00:45 01:30
43 DT04-PM-RTN-HLI-MJY-GH018 202313916 PEMELIHARAAN P1 OIL MIST DETECTOR SWD 2 SWD 2 HLI 24 August 2023 Kafrawi, Jabbar 2 00:45 01:30
46 DT04-PM-RTN-HLI-MJY-GH006 202313912 PEMELIHARAAN P2 PRESSURE TRANSMITTER SWD 2 SWD 2 HLI 24 August 2023 Salvius,Kafrawi, Jabbar 3 00:45 02:15
47 DT04-PM-RTN-HLI-MJY-GH023 202313918 PEMELIHARAAN P2 TEMPERATURE SWITCH 1 SET SWD 2 SWD 2 HLI 24 August 2023 Salvius,Kafrawi, Jabbar 3 00:45 02:15
MAN HOUR REQUARED 81:45
MAN HOUR AVAILABLE 120
% UTILITY 68%

HME

24 DT04-PM-RTN-HME-MJG-AH001 202313921 PEMELIHARAAN P1 JAKET COOLING WATER RADIATOR SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
25 DT04-PM-RTN-HME-MJG-AH019 202313924 PEMELIHARAAN P1 JAKET COOLING FAN RADIATOR A SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
26 DT04-PM-RTN-HME-MJN-AP001 202313925 PEMELIHARAAN P1 HSD OIL TRANSFER PUMP SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
27 DT04-PM-RTN-HME-MJV-AC001 202313929 PEMELIHARAAN P1 LUBE OIL RADIATOR SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
28 DT04-PM-RTN-HME-MJV-AP002 202313930 PEMELIHARAAN P1 LUBE OIL PRIMMING PUMP A SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
29 DT04-PM-RTN-HME-MJV-AP008 202313931 PEMELIHARAAN P1 CVS LUBE OIL PUMP SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
30 DT04-PM-RTN-HME-MJA-HA002 202313920 PEMELIHARAAN P1 CYLINDER HEAD SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
31 DT04-PM-RTN-HME-MJG-AH013 202313922 PEMELIHARAAN P1 INJECTOR C.W. PUMP SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
32 DT04-PM-RTN-HME-MJG-AH016 202313923 PEMELIHARAAN P1 CHARGE AIR COOLING WATER RADIATOR SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
33 DT04-PM-RTN-HME-MJN-AS002 202313926 PEMELIHARAAN P1 GOVERNOR SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
34 DT04-PM-RTN-HME-MJN-BN002 202313927 PEMELIHARAAN P1 FUEL INJECTION SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
35 DT04-PM-RTN-HME-MJN-BN006 202313928 PEMELIHARAAN P1 PIPA SYSTEM BAHAN BAKAR SWD 2 SWD 2 HME 24 August 2023 Azwar, Ilham 2 01:00 02:00
36 DT04-PM-RTN-HME-MJV-AP014 202313932 PEMELIHARAAN P2 INDICATOR OIL FILTER S719 SWD 2 SWD 2 HME 24 August 2023 Salvius, Azwar, Ilham 3 01:00 03:00
37 DT04-PM-RTN-HME-MJV-AP016 202313933 PEMELIHARAAN P2 CVS LUBE OIL FILTER SWD 2 SWD 2 HME 24 August 2023 Salvius, Azwar, Ilham 3 01:00 03:00
MAN HOUR REQUARED 80:00
MAN HOUR AVAILABLE 120
% UTILITY 67%

Anda mungkin juga menyukai