PEMELIHARAAN RUTIN PLTG TELLO NO DOK :

WEEK-34 (21 - 25 AGUSTUS 2023) REV :

PIP UPDK TELLO

NO PM NUMBER WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

HME

1 GT02-PM-RTN-HME-MBJ-AV004 202313546 PM GT02 PENGECEKAN VISUAL FUEL FLEXIBLE HOSE HME 21/08/23 Asmar, Burhanudin 2 01:30 03:00
2 GT02-PM-RTN-HME-MBJ-AV001 202313545 PM GT02 PENGECEKAN MEKANIK DIESEL START HME 21/08/23 Asmar, Burhanudin 2 01:30 03:00
MAN HOUR REQUARED 24:00
MAN HOUR AVAILABLE 80
% UTILITY 30%

NO PM NUMBER WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

HKI & HLI

1 GT01-PM-RTN-HKI-MBN-BR034 202313585 PENGECEKAN INSTRUMENT DAN CONTROL FUEL VALVE VS1-1 HLI-GT 21/08/23 Ahmad, Rahmanda 2 01:00 02:00
2 GT01-PM-RTN-HKI-MBK-AU003 202313572 PM GT01 PENGECEKAN INSTRUMENT DAN CONTROL STARTING SOLENOID CS-1) HLI-GT 21/08/23 Ahmad, Rahmanda 2 01:00 02:00
3 GT02-PM-RTN-HLI-MBN-AP001 202313465 PM GT02 PENGECEKAN KELISTRIKAN MOTOR & SPACE HEATER FUEL FOWARDING PUMP 88FD
HLI-GT 21/08/23 Ahmad, Rahmanda 2 01:00 02:00
4 GT01-PM-RTN-HKI-MBN-BR019 202313584 PM GT01 PENGECEKAN INSTRUMENT DAN CONTROL SOLENOID VALVE FD HLI-GT 21/08/23 Ahmad, Rahmanda 2 01:00 02:00
MAN HOUR REQUARED 38:00
MAN HOUR AVAILABLE 80
% UTILITY 48%
PEMELIHARAAN RUTIN PLTD SELAYAR NO DOK :

WEEK-34 (21 - 25 AGUSTUS 2023) REV :

PIP UPDK TELLO

NO WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

PM PLTD SELAYAR

HME

23 SL05-PM-RTN-HME-MJA-AE001 PEMELIHARAAN P2 [DEUTZ 5] CRANKSHAFT HME 21 August 2023 Marwan, Nurwahidin 2 01:00 02:00
24 SL05-PM-RTN-HME-MJN-BN001 PEMELIHARAAN P2 [DEUTZ 5] INJECTION PUMP 01-02 HME 21 August 2023 Marwan, Wahab 2 01:00 02:00
25 SL05-PM-RTN-HME-MKY-GH001 PEMELIHARAAN P2 [DEUTZ 5] OVERSPEED AND EMERGENCY STOP HME 21 August 2023 Marwan, Ilyas 2 01:00 02:00
26 SL05-PM-RTN-HME-PCA-AC002 PEMELIHARAAN P2 [DEUTZ 5] ELEKTROMOTOR RADIATOR DEUTZ #5 HME 21 August 2023 Marwan, Mannimbangi 2 01:00 02:00
27 SL05-PM-RTN-HME-MJA-AV001 PEMELIHARAAN P1 [DEUTZ 5] CYLINDER HEAD 01-08 HME 21 August 2023 Marwan, Nurwahidin 2 01:00 02:00
28 SL05-PM-RTN-HME-MJG-AP001 PEMELIHARAAN P1 [DEUTZ 5] POMPA & MOTOR JACKET - INTERCOOLING WATER HME 21 August 2023 Marwan, Wahab 2 01:00 02:00
29 SL05-PM-RTN-HME-MJN-AT001 PEMELIHARAAN P1 [DEUTZ 5] FUEL DUPLEX HME 21 August 2023 Marwan, Ilyas 2 01:00 02:00
30 SL05-PM-RTN-HME-MJP-AA001 HME DUTCHWORK
PEMELIHARAAN P1 [DEUTZ 5] START MASTER VALVE, DISTRIBUTOR, COMPRESSED TANK, 21 August 2023 Marwan, Mannimbangi 2 01:00 02:00
31 SL05-PM-RTN-HME-MJV-AP001 PEMELIHARAAN P1 [DEUTZ 5] PRIMING PUMP & OIL FILTER HME 21 August 2023 Marwan, Nurwahidin 2 01:00 02:00
32 SL05-PM-RTN-HME-PCA-AC001 PEMELIHARAAN P1 [DEUTZ 5] ELEKTROMOTOR RADIATOR DEUTZ #5 HME 21 August 2023 Marwan, Wahab 2 01:00 02:00
39 SL07-PM-RTN-HME-MJG-AC001 PEMELIHARAAN P1 [CUMMINS 2] RADIATOR HME 21 August 2023 Marwan, Khareum 2 01:00 02:00
40 SL07-PM-RTN-HME-MJN-AT001 PEMELIHARAAN P1 [CUMMINS 2] FUEL FILTER & PIPING HME 21 August 2023 Marwan, Samsul 2 01:00 02:00
41 SL07-PM-RTN-HME-MJP-AG001 PEMELIHARAAN P1 [CUMMINS 2] ALTERNATOR HME 21 August 2023 Marwan, Rizal 2 01:00 02:00
42 SL07-PM-RTN-HME-MJQ-AZ001 PEMELIHARAAN P1 [CUMMINS 2] INTAKE MANIFOLD 01 HME 21 August 2023 Marwan, Ishaq 2 01:00 02:00
MAN HOUR REQUARED 111:00
MAN HOUR AVAILABLE 200
% LOAD BALANCE 55,50%
HLI

9 SL05-PM-RTN-HLI-BBA-GS001 PEMELIHARAAN P2 [DEUTZ 5] SWITCHGEAR EQUIP. (VACUM CIRCUIT BREAKER) HLI 21 August 2023 Fachrul, Engga 2 01:00 02:00
10 SL05-PM-RTN-HLI-BAC-GS002 PEMELIHARAAN P1 [DEUTZ 5] VACUM CIRCUIT BREAKER HLI 21 August 2023 Fachrul, Engga 2 01:00 02:00
11 SL05-PM-RTN-HLI-BAT-AH001 HLI LV & HV
PEMELIHARAAN P1 [DEUTZ 5] HEATING, STORAGE EQUIPMENT, TRANFORMER, ISOLATING 21 August 2023 Fachrul, Engga 2 01:00 02:00
12 SL05-PM-RTN-HLI-BBT-GD001 PEMELIHARAAN P1 [DEUTZ 5] EQUPMENT 6,3 KV HV & LV, STATION SERVICE TRAFO HLI 21 August 2023 Fachrul, Engga 2 01:00 02:00
18 SL07-PM-RTN-HLI-BAT-AH001 HLI
PEMELIHARAAN P1 [CUMMINS 2] HEATING, STORAGE EQUIPMENT, TRANFORMER, ISOLATING LV & HV 21 August 2023 Fachrul, Engga 2 01:00 02:00
19 SL07-PM-RTN-HLI-BBT-GD001 HLI
PEMELIHARAAN P1 [CUMMINS 2] EQUPMENT 6,3 KV HV & LV, STATION SERVICE TRAFO 21 August 2023 Fachrul, Engga, Rizal D 3 01:00 03:00
20 SL07-PM-RTN-HLI-BTR-GR001 PEMELIHARAAN P1 [CUMMINS 2] 12 V BATTERY 150 AH SYSTEM FOR CUMMINS #2 HLI 21 August 2023 Fachrul, Engga, Rizal D 3 01:00 03:00
MAN HOUR REQUARED 69:00
MAN HOUR AVAILABLE 120
% UTILITY 58%
PEMELIHARAAN RUTIN PLTD TELLO NO DOK :

WEEK-34 (21 - 25 AGUSTUS 2023) REV :

PIP UPDK TELLO

NO WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL

HLI

18 DT01-PM-RTN-HLI-BBT-GH002 202313858 PEMELIHARAAN P1 PMT TRAFO PS MHI 1 MHI 1 HLI 21 August 2023 Kafrawi, Jabbar 2 00:45 01:30
19 DT01-PM-RTN-HLI-MJY-GH004 202313859 PEMELIHARAAN P1 OIL MIST DETECTOR MHI 1 MHI 1 HLI 21 August 2023 Kafrawi, Jabbar 2 00:45 01:30
20 DT01-PM-RTN-HLI-MJY-GH010 202313860 PEMELIHARAAN P1 PRESSURE TRANSMITTER MHI 1 MHI 1 HLI 21 August 2023 Kafrawi, Jabbar 2 00:45 01:30
29 DT01-PM-RTN-HLI-MJY-GH016 202313861 PEMELIHARAAN P1 ENGINE CONTROL PANEL MHI 1 MHI 1 HLI 21 August 2023 Kafrawi, Jabbar 2 00:45 01:30
30 DT01-PM-RTN-HLI-MJY-GH025 202313862 PEMELIHARAAN P1 PRESSURE SWITCH 1 SET MHI 1 MHI 1 HLI 21 August 2023 Kafrawi, Jabbar 2 00:45 01:30
31 DT01-PM-RTN-HLI-MJY-GH028 202313863 PEMELIHARAAN P1 TEMPERATURE SWITCH 1 SET MHI 1 MHI 1 HLI 21 August 2023 Kafrawi, Jabbar 2 00:45 01:30
32 DT01-PM-RTN-HLI-MKA-HA001 202313864 PEMELIHARAAN P1 FILTER UDARA GENERATOR MHI 1 MHI 1 HLI 21 August 2023 Kafrawi, Jabbar 2 00:45 01:30
MAN HOUR REQUARED 81:45
MAN HOUR AVAILABLE 120
% UTILITY 68%

HME

1 DT01-PM-RTN-HME-MJG-AH002 202313865 PEMELIHARAAN P1 SECONDARY COOLING WATER POND (BAK) MHI 1 MHI 1 HME 21 August 2023 Azwar, Ilham 2 01:00 02:00
2 DT01-PM-RTN-HME-MJG-AH024 202313866 PEMELIHARAAN P1 RADIATOR EQUIPMENT MHI 1 MHI 1 HME 21 August 2023 Azwar, Ilham 2 01:00 02:00
3 DT01-PM-RTN-HME-MJN-AP004 202313867 PEMELIHARAAN P1 HSD OIL TRANSFER PUMP MHI 1 MHI 1 HME 21 August 2023 Azwar, Ilham 2 01:00 02:00
4 DT01-PM-RTN-HME-MJN-AS002 202313868 PEMELIHARAAN P1 GOVERNOR MHI 1 MHI 1 HME 21 August 2023 Azwar, Ilham 2 01:00 02:00
5 DT01-PM-RTN-HME-MJV-AP001 202313869 PEMELIHARAAN P1 LUBE OIL PRIMMING PUMP MHI 1 MHI 1 HME 21 August 2023 Azwar, Ilham 2 01:00 02:00
6 DT01-PM-RTN-HME-MJY-GH019 202313870 PEMELIHARAAN P2 EXHAUST GAS THERMOCOUPLE MHI 1 MHI 1 HME 21 August 2023 Salvius, Azwar, Ilham 3 01:00 03:00
7 DT01-PM-RTN-HME-MJY-GH021 202313871 PEMELIHARAAN P2 TACHO GENERATOR MHI 1 MHI 1 HME 21 August 2023 Salvius, Azwar, Ilham 3 01:00 03:00
8 DT01-PM-RTN-HME-QEA-AN006 202313872 PEMELIHARAAN P1 AIR COMPRESOR TANABE 1 MHI 1 MHI 1 HME 21 August 2023 Azwar, Ilham 2 01:00 02:00
MAN HOUR REQUARED 80:00
MAN HOUR AVAILABLE 120
% UTILITY 67%