Anda di halaman 1dari 1

DAFTAR KUANTITAS & HARGA

HARGA SATUAN JUMLAH HARGA


No URAIAN PEKERJAAN VOLUME SATUAN TOTAL HARGA (Rp)
BAHAN UPAH BAHAN UPAH
1 2 3 4 6 7 8 9 10

I PEKERJAAN PENDAHULUAN
1 Pengukuran dan pemasangan Bouwplank 196.900 Ls 15,000.00 2,953,500.00 2,953,500.00
2 Mobilisasi dan Demobilisasi 1.000 Ls 6,000,000.00 6,000,000.00 6,000,000.00

II PEKERJAAN PAGAR DINDING BATU BATA Tinggi 2,50 Meter


SEPANJANG 196,90 Meter
A Pekerjaan Pondasi
Galian Tanah 2.400 m3 96,000.00 230,400.00 230,400.00
Cor Pondasi Beton 2.400 m3
a. Semen Portland 19.560 zak 58,000.00 1,134,480.00 1,134,480.00
b. Pasir Beton 1.303 m3 150,000.00 195,428.57 195,428.57
c. Batu Pecah 2 - 3cm 1.372 m3 450,000.00 617,400.00 617,400.00
B Kolom Praktis 15x15 cm (Tiang)
1 Beton Tiang 3.375 m3 250,000.00 843,750.00 843,750.00
a. Semen Portland 27.506 zak 58,000.00 1,595,362.50 1,595,362.50
b. Pasir Beton 1.832 m3 150,000.00 274,821.43 274,821.43
c. Batu Pecah 2 - 3cm 1.929 m3 450,000.00 868,218.75 868,218.75
2 Pembesian Tiang 461.125 kg 8,000.00 3,689,000.00 3,689,000.00
a. Tulangan Utama - Besi Dia. 10mm 50.000 Btg. 74,000.00 3,700,000.00 3,700,000.00
b. Tulangan Behel - Besi Dia. 6 mm jarak 20 Cm 33.750 Btg. 48,000.00 1,620,000.00 1,620,000.00
c. Kawat Beton 69.169 kg 27,000.00 1,867,556.25 1,867,556.25
3 Mall / Bekisting Tiang 10.000 m2 78,000.00 780,000.00 780,000.00
a. Papan 2/20 12.500 Btg. 80,000.00 1,000,000.00 1,000,000.00
b. Paku 7" s.d 2,5" 3.00 kg 20,000.00 60,000.00 60,000.00
C Sloof 20x25 cm
1 Galian Sloof 39.380 m3 96,000.00 3,780,480.00 3,780,480.00
2 Beton Sloof 10.000 m3 250,000.00 2,500,000.00 2,500,000.00
a. Semen Portland 81.500 zak 58,000.00 4,727,000.00 4,727,000.00
b. Pasir Beton 5.429 m3 150,000.00 814,285.71 814,285.71
c. Batu Pecah 2 - 3cm 5.717 m3 450,000.00 2,572,500.00 2,572,500.00
3 Pembesian Tiang 627.45 kg 8,000.00 5,019,637.33 5,019,637.33
a. Tulangan Utama - Besi Dia. 10mm 65.63 Btg. 74,000.00 4,856,866.67 4,856,866.67
b. Tulangan Behel - Besi Dia. 6 mm jarak 20 Cm 52.51 Btg. 48,000.00 2,520,320.00 2,520,320.00
c. Kawat Beton 94.12 kg 27,000.00 2,541,191.40 2,541,191.40
D Dinding Pasangan Batu Bata -
1 Dinding Pasangan Bata 367.500 m2 25,000.00 9,187,500.00 9,187,500.00
a. Bata merah 25,725.00 bh 550.00 14,148,750.00 14,148,750.00
b. Semen Portland 84.53 Kg 58,000.00 4,902,450.00 4,902,450.00
c. Pasir Beton 15.80 m3 150,000.00 2,370,375.00 2,370,375.00
2 Plesteran dan Acian ( 2 Sisi ) 735.00 m2 15,000.00 11,025,000.00 11,025,000.00
a. Semen Portland 150.29 Zak 58,000.00 8,716,982.40 8,716,982.40
b. Pasir Beton 14.70 m3 150,000.00 2,205,000.00 2,205,000.00

63,308,988.68 37,055,767.33 109,318,256.01

REKAPITULASI
I PEKERJAAN PENDAHULUAN 8,953,500.00
II Bahan 63,308,988.68
III Upah 37,055,767.33
IV Total Jumlah 109,318,256.01
V Dibulatkan 109,310,000.00
Terbilang : Seratus Tiga Puluh Dua Juta Empat Ratus Tiga Puluh Ribu Rupiah 555,154.90