JADWAL PELAKSANAAN PEKERJAAN

ID Task Mode Uraian Pekerjaan Waktu Mulai Selesai Prodecessor


Pelaksanaan 2023 2024
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 JADWAL PELAKSANAAN PEKERJAAN ( 420 days? 20 Feb '23 15 Apr '24
RELOKASI GUNUNG PASIR )
2 SPMK 0 days 20 Feb '23 20 Feb '23 20 Feb '23
3 UMUM 420 days? 20 Feb '23 14 Apr '24
4 Mobilisasi 420 days 20 Feb '23 14 Apr '24
7 Pengamanan Lingkungan Hidup 385 days 13 Mar '23 31 Mar '24
60 Keselamatan dan Kesehatan Kerja 420 days? 20 Feb '23 14 Apr '24
106 Manajemen Mutu 420 days 20 Feb '23 14 Apr '24
108 DRAINASE 231 days? 24 Apr '23 10 Dec '23
109 Galian untuk Selokan Drainase dan Saluran Air 161 days 24 Apr '23 01 Oct '23
112 Pasangan Batu dengan Mortar 203 days 22 May '23 10 Dec '23
115 Gorong-gorong Kotak Beton Bertulang, ukuran 162 days? 24 Apr '23 02 Oct '23
dalam 150 cm x 150 cm
118 Gorong-gorong Kotak Beton Bertulang, ukuran 35 days 02 Oct '23 05 Nov '23 109
dalam 200 cm x 200 cm
119 Saluran berbentuk U Tipe DS 1 203 days 22 May '23 10 Dec '23
122 PEKERJAAN TANAH DAN GEOSINTETIK 322 days 13 Mar '23 28 Jan '24
123 Galian Biasa 252 days 13 Mar '23 19 Nov '23
126 Timbunan Pilihan dari galian 84 days 17 Jul '23 08 Oct '23
129 Matras Perkuatan Tipe III 161 days 21 Aug '23 28 Jan '24
132 Penanaman BIII Vegetasi dengan Teknik Mulsa 175 days 07 Aug '23 28 Jan '24
( mulching)
135 PERKERASAN BERBUTIR 147 days 17 Jul '23 10 Dec '23
136 Lapis Pondasi Agregat Kelas A 140 days 24 Jul '23 10 Dec '23
139 Lapis Pondasi Agregat Kelas B 133 days 17 Jul '23 26 Nov '23
142 PERKERASAN ASPAL 84 days 25 Dec '23 17 Mar '24
143 Lapis Resap Pengikat - Aspal Cair/Emulsi 84 days 25 Dec '23 17 Mar '24 152

144 Lataston Lapis Aus (HRS-WC) 84 days 25 Dec '23 17 Mar '24 143SS

145 Bahan anti pengelupasan 84 days 25 Dec '23 17 Mar '24 144SS

146 STRUKTUR 336 days 17 Apr '23 17 Mar '24


147 Beton struktur, fc’30 MPa 126 days 22 May '23 24 Sep '23
150 Beton strukur, fc’20 MPa 196 days 12 Jun '23 24 Dec '23
153 Beton , fc’15 Mpa 49 days 29 Jan '24 17 Mar '24 131;144FF

154 Beton, fc’10 Mpa 105 days 24 Apr '23 06 Aug '23
157 Baja Tulangan Sirip BjTS 420A 147 days 01 May '23 24 Sep '23
160 Tiang Bor Beton, diameter 300 mm (Strauss 112 days 17 Apr '23 06 Aug '23
Pile)
163 Pasangan Batu 189 days 19 Jun '23 24 Dec '23
166 PEKERJAAN HARIAN & PEKERJAAN 189 days 25 Sep '23 31 Mar '24
LAIN-LAIN
167 Marka Jalan Termoplastik 7 days 18 Mar '24 24 Mar '24 144

168 Rel Pengaman 91 days 25 Sep '23 24 Dec '23


171 Paku Jalan Memantul Bulat 7 days 25 Mar '24 31 Mar '24 167

172 PHO ( Provision Hand Over ) 0 days 15 Apr '24 15 Apr '24 6;105 15 Apr '24