ANALISA PEKERJAAN TERHADAP KEBUTUHAN WAKTU DAN ALAT

Jam Waktu Target Volume


Kap. Kap. Produksi 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 1-Aug 2-Aug 3-Aug 4-Aug 5-Aug 6-Aug 7-Aug 8-Aug 9-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug
No Urian Pekerjaan Volume Sat Kerja/Hari Penyelesai Waktu Bahan/
Produksi Harian
an/alat (hari) Alat
Kamis Jum'at Sabtu Minggu Senin Selasa Rabu Kamis Jum'at Sabtu Minggu Senin Selasa Rabu Kamis Jum'at Sabtu Minggu Senin Selasa Rabu Kamis Jum'at Sabtu Minggu Senin Selasa Rabu Kamis Jum'at Sabtu Minggu Senin Selasa Rabu Kamis Jum'at Sabtu Minggu Senin Selasa Rabu Kamis Jum'at Kamis Jum'at Sabtu Minggu Senin Selasa Rabu Kamis Jum'at Sabtu Minggu Senin Selasa Rabu Kamis Jum'at Sabtu Minggu Senin Selasa Rabu Kamis

1 Pekerjaan Service Road 6,160.00 m2


- Galian Tanah
- Excavator 3,696.00 51.84 m3/jam 12.00 622.08 5.94 6.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Dumptruck 3,696.00 11.16 m3/jam 12.00 133.87 27.61 6.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00

- Pemadatan Tanah Dasar


- Vibro Rooller 6,160.00 100.00 m2/jam 12.00 1,200.00 5.13 5.00 2.00 2.00 2.00 2.00 2.00 2.00
- Water Tank 6,160.00 100.00 m2/jam 12.00 1,200.00 5.13 5.00 2.00 2.00 2.00 2.00 2.00 2.00

- Timbunan Limestone 0.2 m


- Limestone 1,232.00 1,232 246.4 246.4 246.4 246.4 246.4
- Dumptruck 1,232.00 11.16 m3/jam 8.00 89.25 13.80 5.00 2.00 2.00 2.00 2.00 2.00 2.00
- Bull Dozer 1,232.00 100.00 m2/jam 12.00 1,200.00 1.03 2.00 1.00 1.00 1.00
- Vibro Rooller 1,232.00 100.00 m2/jam 12.00 1,200.00 1.03 2.00 1.00 1.00 1.00
- Water Tank 1,232.00 100.00 m2/jam 12.00 1,200.00 1.03 2.00 1.00 1.00 1.00

- Lean Concrete 0.15 m (PT.NB)


- Truck Mixer 924.00 21.00 m3/jam 12.00 252.00 3.67 6.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 - - - - - -
- Beton K 125 924.00 924 154 154 154 154 154 154
- Semen 217.14 217 36 36 36 36 36 36
- Pasir 518.60 519 86 86 86 86 86 86
- Split 635.71 636 106 106 106 106 106 106

- Rigid K 400 (PT.SCG)


- Truck Mixer 1,540.00 38.00 m3/jam 12.00 305.28 5.04 18.00 7.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
- Beton K 400 1,540.00 1,540.00 86 86 86 86 86 86 86 86 86 86 86 86 86 86 86 86 86 86
- Semen 634.48 634 106 106 106 106 106 106 106 106 106 106 106 106 106 106 106 106 106 106
- Pasir 789.25 789 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132
- Split 966.09 966 161 161 161 161 161 161 161 161 161 161 161 161 161 161 161 161 161 161

4 Pekerjaan Apron A,B,C,D


- Pengukuran 4.00
- Mobilisasi Alat 1.00
- Pembongkaran perkerasan apron
- Excavator Breaker 17,000.00 150.00 m2/jam 12.00 1,800.00 9.44 10.00 1.00 - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Dumptruck ( Buang jarak 1,5 km) 17,000.00 50.00 m2/jam 12.00 600.00 28.33 10.00 3.00 - 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00

- Galian Tanah
- Excavator 17,850.00 51.84 m3/jam 12.00 622.08 28.69 15.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00
- Dumptruck 17,850.00 11.16 m3/jam 12.00 133.87 133.34 15.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

- Pemadatan Tanah Dasar


- Vibro Rooller 17,000.00 100.00 m2/jam 12.00 1,200.00 14.17 14.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00
- Water Tank 17,000.00 100.00 m2/jam 12.00 1,200.00 14.17 14.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00

- Timbunan Limestone 0.2 m


- Dumptruck 3,400.00 11.16 m3/jam 8.00 89.25 38.10 4.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
- Bull Dozer 3,400.00 100.00 m2/jam 12.00 1,200.00 2.83 4.00 1.00 1.00 1.00 1.00 1.00
- Vibro Rooller 3,400.00 100.00 m2/jam 12.00 1,200.00 2.83 4.00 1.00 1.00 1.00 1.00 1.00
- Water Tank 3,400.00 100.00 m2/jam 12.00 1,200.00 2.83 4.00 1.00 1.00 1.00 1.00 1.00
- Limestone 3,400.00 3,400.00 243 243 243 243 243 243 243 243 243 243 243 243 243 243

- Basecourse 0.15 m
- Dumptruck 5,100.00 11.16 m3/jam 8.00 89.25 57.15 6.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
- Bull Dozer 5,100.00 100.00 m2/jam 12.00 1,200.00 4.25 6.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Vibro Rooller 5,100.00 100.00 m2/jam 12.00 1,200.00 4.25 6.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Water Tank 5,100.00 100.00 m2/jam 12.00 1,200.00 4.25 6.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Basecourse 5,100.00 5,100.00 243 243 243 243 243 243 243 243 243 243 243 243 243 243 243 243 243 243 243 243 243

- Pengecoran Lean Concrete tebal 12.5 cm (PT.NB) 2,125.00 21.00 m3/jam 12.00 252.00 8.43 30.00 3.00
- Beton K 125 2,125.00 2,125.00 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83 70.83
- Truck Mixer 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
- Semen 499.38 499 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65 16.65
- Pasir 1,192.66 1,193 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76 39.76
- Split 1,462.00 1,462 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73 48.73
- Tenaga Kerja 10.00 Org 10 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

- Pengecoran k400 tebal 53 cm (PT. SCG) 9,010.00 38.00 m3/jam 12.00 305.28 29.51 40.00 7.00
- Beton K 400 9,010.00 9,010 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286 286
- Truck Mixer 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00
- Semen 3,712.12 3,712 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116 116
- Pasir 4,617.63 4,618 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144 144
- Split 5,652.27 5,652 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177 177
- Bekisting 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00
- Tenaga Kerja 30.00 Org 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00

5 Pekerjaan Apron zona E


- Pengukuran 4.00
- Mobilisasi Alat 1.00

- Pemindahan WTP Eksisting


- Pemindahan System STP 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Pengurasan Bak Eksisting 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

- Pembongkaran perkerasan Bak WTP


- Excavator Breaker 9,000.00 150.00 m2/jam 8.00 1,200.00 7.50 8.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Dumptruck 9,000.00 11.16 m2/jam 12.00 133.87 67.23 8.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

- Pemadatan Tanah Dasar


- Vibro Rooller 9,000.00 100.00 m2/jam 12.00 1,200.00 7.50 8.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Water Tank 9,000.00 100.00 m2/jam 12.00 1,200.00 7.50 8.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

- Timbunan Limestone
- Dumptruck 4,500.00 11.16 m3/jam 8.00 89.25 50.42 4.00 13.00 13.00 13.00 13.00 13.00 13.00 13.00 13.00 13.00 13.00 13.00
- Moto Grader 4,500.00 100.00 m2/jam 12.00 1,200.00 3.75 4.00 1.00 1.00 1.00 1.00 1.00
- Vibro Rooller 4,500.00 100.00 m2/jam 12.00 1,200.00 3.75 4.00 1.00 1.00 1.00 1.00 1.00
- Water Tank 4,500.00 100.00 m2/jam 12.00 1,200.00 3.75 4.00 1.00 1.00 1.00 1.00 1.00
- Limestone 4,500.00 4,500.00 450 450 450 450 450 450 450 450 450 450

- Basecourse 0.15 m
- Dumptruck 1,350.00 11.16 m3/jam 8.00 89.25 15.13 3.00 6.00 6.00 6.00 6.00
- Moto Grader 1,350.00 100.00 m2/jam 12.00 1,200.00 1.13 3.00 1.00 1.00 1.00 1.00
- Vibro Rooller 1,350.00 100.00 m2/jam 12.00 1,200.00 1.13 3.00 1.00 1.00 1.00 1.00
- Water Tank 1,350.00 100.00 m2/jam 12.00 1,200.00 1.13 3.00 1.00 1.00 1.00 1.00
- Basecourse 1,350.00 1,350.00 450.00 450.00 450.00

- Pengecoran Lean Concrete tebal 12.5 cm (PT.NB) 1,125.00 21.00 m3/jam 8.00 168.00 6.70 10.00 3.00
- Beton K 125 1,125.00 1,125.00 113 113 113 113 113 113 113 113 113 113 113 113
- Truck Mixer 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
- Semen 264.38 264 26.44 26.44 26.44 26.44 26.44 26.44 26.44 26.44 26.44 26.44 26.44 26.44
- Pasir 631.41 631 63.14 63.14 63.14 63.14 63.14 63.14 63.14 63.14 63.14 63.14 63.14 63.14
- Split 774.00 774 77.40 77.40 77.40 77.40 77.40 77.40 77.40 77.40 77.40 77.40 77.40 77.40
- Tenaga Kerja 10.00 Orng 10 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

- Pengecoran k400 tebal 53 cm (PT.SCG) 4,770.00 38.00 m3/jam 12.00 305.28 15.63 16.00 7.00
- Beton K 400 4,770.00 4,770 305.28 305 305 305 305 305 305 305 305 305 305 305 305 305 305 305
- Truck Mixer 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00
- Semen 1,965.24 1,965 123 123 123 123 123 123 123 123 123 123 123 123 123 123 123 123
- Pasir 2,444.63 2,445 152.79 153 153 153 153 153 153 153 153 153 153 153 153 153 153 153
- Split 2,992.38 2,992 187.02 187 187 187 187 187 187 187 187 187 187 187 187 187 187 187
- Bekisting 16.00 16 16.00 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16
- Tenaga Kerja 30.00 30 30.00 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30

6 Pekerjaan Apron zona F (window time)


- Pembongkaran perkerasan apron
- Excavator Breaker 3,654.00 150.00 m2/jam 6.00 900.00 4.06 6.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Dumptruck 3,654.00 50.00 m2/jam 6.00 300.00 12.18 6.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00

- Galian Tanah
- Excavator 3,654.00 51.84 m3/jam 6.00 311.04 11.75 12.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
- Dumptruck 3,654.00 11.16 m3/jam 6.00 66.93 54.59 12.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00

- Pemadatan Tanah Dasar


- Vibro Rooller 3,654.00 413.96 m2/jam 6.00 2,483.78 1.47 5.00 1.00 1.00 1.00 1.00 1.00 1.00
- Water Tank 3,654.00 413.96 m2/jam 6.00 2,483.78 1.47 5.00 1.00 1.00 1.00 1.00 1.00 1.00

- Timbunan Limestone 0.2 m


- Dumptruck 730.80 11.16 m3/jam 6.00 66.93 10.92 4.00 3.00 3.00 3.00 3.00 3.00 3.00
- Moto Grader 730.80 194.49 m3/jam 6.00 1,166.94 0.63 4.00 1.00 1.00 1.00 1.00 1.00
- Vibro Rooller 730.80 82.79 m3/jam 6.00 496.76 1.47 4.00 1.00 1.00 1.00 1.00 1.00
- Water Tank 730.80 82.79 m3/jam 6.00 496.76 1.47 4.00 1.00 1.00 1.00 1.00 1.00
- Limestone 730.80 730.80 183 183 183 183 183

- Basecourse 0.15 m
- Dumptruck 548.10 11.16 m3/jam 6.00 66.93 8.19 2.00 5.00 5.00 5.00 5.00
- Moto Grader 548.10 194.49 m3/jam 6.00 1,166.94 0.47 2.00 1.00 1.00 1.00
- Vibro Rooller 548.10 82.79 m3/jam 6.00 496.76 1.10 2.00 1.00 1.00 1.00
- Water Tank 548.10 82.79 m3/jam 6.00 496.76 1.10 2.00 1.00 1.00 1.00
- Basecourse 548.10 548.10 183 183 183

- Pengecoran Lean Concrete tebal 12.5 cm (PT.NB) 456.75 21.00 kg/jam 4.00 84.00 5.44 6.00 3.00
- Beton K 125 456.75 456.75 57.09 57.09 57.09 57.09 57.09 57.09 57.09 57.09
- Truck Mixer 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
- Semen 107.34 107 13.42 13.42 13.42 13.42 13.42 13.42 13.42 13.42
- Pasir 256.35 256 32.04 32.04 32.04 32.04 32.04 32.04 32.04 32.04
- Split 314.24 314 39.28 39.28 39.28 39.28 39.28 39.28 39.28 39.28
- Tenaga Kerja 10.00 10 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

- Pengecoran k400 tebal 53 cm (PT.HJB) 3,873.24 25.00 m3/jam 4.00 80.00 48.42 52.00 7.00
- Beton K 400 3,873.24 3,873 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32 76.32
- Truck Mixer 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00
- Semen 1,595.77 1,596 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69 30.69
- Pasir 1,985.04 1,985 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17 38.17
- Split 2,429.81 2,430 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73 46.73
- Bekisting 4.00 4 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00
- Tenaga Kerja 30.00 30 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00

PEKERJAAN ELEKTRIKAL
- Pekerjaan Apron Flood Light
- Pabrikasi Tiang Lampu dan Pengiriman 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
- Lampu LED merk ADB (Pengiriman) 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00
- Instal Lampu dan Tiang Lampu 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00

- Pekerjaan Apron Edge Light


- Lampu merk ADB (Pengiriman) 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00
- Instal Lampu 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

- Pekerjaan Spot Number Light


- Verifikasi Koordinat dan Nomor Parking Stand 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
- Pabrikasi SNL 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
- Instal SNL 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

REKAPITULASI BAHAN DAN ALAT

BAHAN
- Semen 8,995.84 - - - - - - 31 31 31 31 67 67 84 189 189 305 269 269 269 269 283 283 283 283 283 269 269 269 269 269 269 163 163 163 163 163 163 163 163 160 160 160 147 147 173 173 173 180 180 180 180 180 180 180 180 180 154 154 123 123 123 123 123 - -
- Pasir 12,435.54 - - - - - - 38 38 38 38 125 125 164 296 296 440 354 354 354 354 386 386 386 386 386 354 354 354 354 354 354 222 222 222 222 222 222 222 222 215 215 215 182 182 246 246 246 254 254 254 254 254 254 254 254 254 191 191 153 153 153 153 153 - -
- Split 15,226.52 - - - - - - 47 47 47 47 153 153 201 362 362 539 433 433 433 433 472 472 472 472 472 433 433 433 433 433 433 272 272 272 272 272 272 272 272 263 263 263 223 223 301 301 301 311 311 311 311 311 311 311 311 311 234 234 187 187 187 187 187 - -
- Limestone 9,862.80 - - - - - - - 246 489 489 489 489 243 243 243 426 426 426 426 426 243 243 - - - - - - - - - - - - - - - - - 450 450 450 450 450 450 450 450 450 450 - - - - - - - - - - - - - - - -
- Basecourse 6,998.10 - - - - - - - - - - 243 243 243 243 243 243 243 426 426 426 243 243 243 243 243 243 243 243 243 243 243 - - - - - - - - - - - - 450 - 450 - 450 - - - - - - - - - - - - - - - - -
- Beton K 125 4,630.75 - - - - - - - - - - 154 154 225 225 225 225 71 71 71 71 128 128 128 128 128 71 71 71 71 71 71 71 71 71 71 71 71 71 71 57 57 57 - - 113 113 113 113 113 113 113 113 113 113 113 113 - - - - - - - - -
- Beton K 400 19,193.24 - - - - - - 76 76 76 76 76 76 76 162 162 448 448 448 448 448 448 448 448 448 448 448 448 448 448 448 448 363 363 363 363 363 363 363 363 363 363 363 363 363 363 363 363 382 382 382 382 382 382 382 382 382 382 382 305 305 305 305 305 - -
- Bekisting 35.00 - - - - - - 4 4 4 4 4 4 4 4 4 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 20 20 20 20 20 20 20 20 20 20 20 16 16 16 16 16 - -

ALAT
- Dumptruck - - - - 17 22 22 24 34 34 36 36 34 34 34 37 37 37 37 28 20 20 10 10 10 10 10 10 10 10 19 9 9 9 9 9 9 9 - 13 13 13 13 19 13 19 13 19 13 - - - - - - - - - - - - - - - -
- Moto Grader - - - - - - - - - - - - - - - - 1 1 2 2 - - - - - - - - - - - - - - - - - - - 1 - - 1 - 1 1 1 - 2 - - - - - - - - - - - - - - - -
- Vibro Rooller - - - - - - 4 4 5 5 4 4 3 3 4 2 4 5 4 5 1 - 1 1 - - 1 - - - - 1 1 - 1 - 1 - 1 1 1 - 2 - 2 1 2 - 2 - - - - - - - - - - - - - - - -
- Water Tank - - - - - - 4 4 5 5 4 4 3 3 4 2 4 5 4 5 1 - 1 1 - - 1 - - - - 1 1 - 1 - 1 - 1 1 1 - 2 - 2 1 2 - 2 - - - - - - - - - - - - - - - -
- Excavator - - - - 3 4 4 4 4 4 3 3 3 3 3 3 3 2 2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- Excavator Breaker - 1 1 1 2 2 2 2 2 2 1 - - - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 1 1 - - - - - - - - - - - - - - - - - - - - - - - - - - -

TENAGA
- Tenaga Kerja - - - - - - 30 30 30 30 30 30 40 40 40 70 70 70 70 70 80 80 80 80 80 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 60 60 70 70 70 70 70 70 70 70 70 70 70 70 60 60 30 30 30 30 30 - -
26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 1-Sep

Jum'at Sabtu Minggu Senin Selasa Rabu Rabu


- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -

- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -

- - - - - - -