DAFTAR SATUAN UPAH DAN BAHAN

PEMBANGUNAN TRIBUN LAPANGAN SEPAK BOLA

LOKASI : KRUENG GEUKUEH, ACEH UTARA


TAHUN : 2019

No. Uraian Kuantitas Satuan Harga Satuan (Rp)

UPAH PEKERJA
1 Pekerja 1.00 Jam 10,000.00
2 Kepala Tukang 1.00 Jam 15,000.00
3 Mandor 1.00 Jam 20,000.00
4 Tukang 1.00 Jam 7,000.00

HARGA BAHAN
1 Batu Bata 1.00 Bh 1,000.00
2 Batu Gunung 1.00 m³ 180,000.00
3 Besi Beton Polos 1.00 Kg 100,000.00
4 Besi Beton Ulir 1.00 Kg 150,000.00
5 Cat Dasar 1.00 Kg 100,000.00
6 Cat Meni 1.00 Kg 50,000.00
7 Cat Kayu Dasar 1.00 Kg 100,000.00
8 Cat Penutup 1.00 Kg 135,000.00
9 Cat Mengkilap 1.00 Kg 50,000.00
10 Kawat Beton 1.00 Kg 20,000.00
11 Kerikil Beton 1.00 m³ 150,000.00
12 Koral Beton 1.00 m³ 1,000,000.00
13 Pasir Beton 1.00 m³ 400,000.00
14 Pasir Pasang 1.00 m³ 350,000.00
15 Pasir Urug 1.00 m³ 150,000.00
16 Semen 1.00 kg 50,000.00
17 Air 1.00 Liter 2,500.00
18 Pintu 1.00 Bh 5,000,000.00
19 Bowplank 1.00 Ls 30,000.00
20 Papan Nama Proyek 1.00 Ls 500,000.00
21 Dokumentasi 1.00 Ls 10,000.00
22 Administrasi 1.00 Ls 5,000.00
DAFTAR ANALISA HARGA SATUAN
PEMBANGUNAN TRIBUN LAPANGAN SEPAK BOLA

LOKASI : KRUENG GEUKUEH, ACEH UTARA


TAHUN : 2019

Perkiraan
No. Uraian Satuan
Kuantitas
1.1 Pengukuran Dan Pemasangan Bowplank
1.1.1 Bowplank 1.00 Ls
Jumlah
1.2 Papan Nama Proyek, Administrasi Dan Dokumentasi
1.2.1 Papan Nama Proyek 1.00 Ls
1.2.2 Dokumentasi 1.00 Ls
1.2.3 Administrasi 1.00 Ls
Jumlah
2.1 Galian Tanah Pondasi Tapak
2.1.1 Pekerja 7.00 Jam
2.1.2 Mandor 7.00 Jam
Jumlah
2.2 Galian Tanah Pondasi Batu Gunung
2.2.1 Pekerja 7.00 Jam
2.2.2 Mandor 7.00 Jam
Jumlah
2.3 Urugan Kembali Bekas Galian
2.3.1 Pekerja 7.00 Jam
2.3.2 Mandor 7.00 Jam
Jumlah
3.1 Aanstamping Batu Gunung/Kali
3.1.1 Batu Gunung/Kali 100.00 m³
3.1.2 Pasir Urug 50.00 m³
3.1.3 Pekerja 7.00 Jam
3.1.4 Tukang 7.00 Jam
3.1.5 Kepala Tukang 7.00 Jam
3.1.6 Mandor 7.00 Jam
Jumlah
3.2 Pondasi Batu Gunung/Kali
3.2.1 Batu Gunung/Kali 150.00 m³
3.2.2 Semen 75.00 Kg
3.2.3 Pasir Pasang 75.00 m³
3.2.4 Pekerja 7.00 Jam
3.2.5 Tukang 7.00 Jam
3.2.6 Kepala Tukang 7.00 Jam
3.2.7 Mandor 7.00 Jam
Jumlah
3.3 Pasang Batu Bata
3.3.1 Batu Bata 3,000.00 Bh
3.3.2 Semen 75.00 Kg
3.3.3 Pasir Pasang 100.00 m³
3.3.4 Pekerja 7.00 Jam
3.3.5 Tukang 7.00 Jam
3.3.6 Kepala Tukang 7.00 Jam
3.3.7 Mandor 7.00 Jam
Jumlah
3.4 Plesteran Dinding Batu Bata
3.4.1 Semen 50.00 Kg
3.4.2 Pasir Pasang 100.00 m³
3.4.3 Pekerja 7.00 Jam
3.4.4 Tukang 7.00 Jam
3.4.5 Kepala Tukang 7.00 Jam
3.4.6 Mandor 7.00 Jam
Jumlah
4.1 Pondasi Tapak
4.1.1 Semen 100.00 Kg
4.1.2 Pasir Beton 50.00 m³
4.1.3 Koral Beton 40.00 m³
4.1.4 Pekerja 7.00 Jam
4.1.5 Tukang 7.00 Jam
4.1.6 Kepala Tukang 7.00 Jam
4.1.7 Mandor 7.00 Jam
Jumlah
4.2 Beton
4.2.1 Semen 100.00 Kg
4.2.2 Pasir Beton 50.00 m³
4.2.3 Kerikil Beton 50.00 m³
4.2.4 Air 15,000.00 Ltr
4.2.5 Pekerja 7.00 Jam
4.2.6 Tukang 7.00 Jam
4.2.7 Kepala Tukang 7.00 Jam
4.2.8 Mandor 7.00 Jam
Jumlah
4.3 Tulangan Besi
4.3.1 Besi Beton Polos 75.00 Kg
4.3.2 Kawat Beton 50.00 Kg
4.3.3 Besi Beton Ulir 125.00 Kg
4.3.4 Pekerja 7.00 Jam
4.3.5 Tukang 7.00 Jam
4.3.6 Kepala Tukang 7.00 Jam
4.3.7 Mandor 7.00 Jam
5.1 Cat Tembok Luar Dan Dalam
5.1.1 Cat Dasar 50.00 Kg
5.1.2 Cat Penutup 150.00 Kg
5.1.3 Cat Kayu Dasar 100.00 Kg
5.1.4 Cat Mengkilat 100.00 Kg
5.1.5 Cat Meni 75.00 Kg
5.1.6 Pekerja 7.00 Jam
5.1.7 Tukang 7.00 Jam
5.1.8 Kepala Tukang 7.00 Jam
5.1.9 Mandor 7.00 Jam
Jumlah

JUMLAH TOTAL
SATUAN
AN SEPAK BOLA

Harga Satuan (Rp) Jumlah Harga (Rp)

30,000.00 30,000.00
30,000.00

500,000.00 500,000.00
10,000.00 10,000.00
5,000.00 5,000.00
515,000.00

10,000.00 70,000.00
20,000.00 140,000.00
210,000.00

10,000.00 70,000.00
20,000.00 140,000.00
210,000.00

10,000.00 70,000.00
20,000.00 140,000.00
210,000.00

180,000.00 18,000,000.00
150,000.00 7,500,000.00
10,000.00 70,000.00
7,000.00 49,000.00
15,000.00 105,000.00
20,000.00 140,000.00
25,864,000.00

180,000.00 27,000,000.00
50,000.00 3,750,000.00
350,000.00 26,250,000.00
10,000.00 70,000.00
7,000.00 49,000.00
15,000.00 105,000.00
20,000.00 140,000.00
57,364,000.00

1,000.00 3,000,000.00
50,000.00 3,750,000.00
350,000.00 35,000,000.00
10,000.00 70,000.00
7,000.00 49,000.00
15,000.00 105,000.00
20,000.00 140,000.00
42,114,000.00

50,000.00 2,500,000.00
350,000.00 35,000,000.00
10,000.00 70,000.00
7,000.00 49,000.00
15,000.00 105,000.00
20,000.00 140,000.00
37,864,000.00

50,000.00 5,000,000.00
400,000.00 20,000,000.00
1,000,000.00 40,000,000.00
10,000.00 70,000.00
7,000.00 49,000.00
15,000.00 105,000.00
20,000.00 140,000.00
65,364,000.00

50,000.00 5,000,000.00
400,000.00 20,000,000.00
150,000.00 7,500,000.00
2,500.00 37,500,000.00
10,000.00 70,000.00
7,000.00 49,000.00
15,000.00 105,000.00
20,000.00 140,000.00
70,364,000.00

100,000.00 7,500,000.00
20,000.00 1,000,000.00
150,000.00 18,750,000.00
10,000.00 70,000.00
7,000.00 49,000.00
15,000.00 105,000.00
20,000.00 140,000.00
20,114,000.00

100,000.00 5,000,000.00
135,000.00 20,250,000.00
100,000.00 10,000,000.00
50,000.00 5,000,000.00
50,000.00 3,750,000.00
10,000.00 70,000.00
7,000.00 49,000.00
15,000.00 105,000.00
20,000.00 140,000.00
44,364,000.00

402,451,000.00
RENCANA ANGGARAN BIAYA
PEMBANGUNAN TRIBUN LAPANGAN SEPAK BOLA

LOKASI : KRUENG GEUKUEH, ACEH UTARA


TAHUN : 2019

Perkiraan
No. Uraian Pekerjaan Satuan
Kuantitas
1 PEKERJAAN PERSIAPAN
1.1 Pengukuran dan Pemasangan Bowplank 1.00 Ls
1.2 Papan Nama Proyek, Administrasi dan Dokumentasi 1.00 Ls
Jumlah
2 PEKERJAAN TANAH
2.1 Galian Tanah Pondasi Tapak 15.00 m³
2.2 Galian Tanah Pondasi Batu Gunung 50.00 m³
2.3 Urugan Kembali Bekas Galian 15.00 m³
Jumlah
3 PEKERJAAN PLESTERAN
3.1 Aanstamping Batu Gunung/Kali 10.00 m³
3.2 Pondasi Batu Gunung/Kali 20.00 m³
3.3 Pasang Batu Bata 100.00 m³
3.4 Plesteran Dinding Batu Bata 200.00 m²

Jumlah
4 PEKERJAAN BETON
4.1 Pondasi Tapak 100.00 m³
4.2 Beton 5.00 m³
4.3 Tulangan Besi 200.00 Kg
Jumlah
5 PEKERJAAN PENGECATAN
5.1 Cat Tembok Luar Dan Dalam 600.00 m²
Jumlah
6 PEKERJAAN LAIN-LAIN
6.1 Pintu Depan 1.00 Ls
Jumlah

JUMLAH TOTAL
AN BIAYA
NGAN SEPAK BOLA

Harga Satuan (Rp) Jumlah Harga (Rp)

30,000.00 30,000.00
515,000.00 515,000.00
545,000.00

210,000.00 3,150,000.00
210,000.00 10,500,000.00
210,000.00 3,150,000.00
16,800,000.00

25,864,000.00 258,640,000.00
57,364,000.00 1,147,280,000.00
42,114,000.00 4,211,400,000.00
37,864,000.00 7,572,800,000.00

13,190,120,000.00

65,364,000.00 6,536,400,000.00
70,364,000.00 351,820,000.00
20,114,000.00 4,022,800,000.00
10,911,020,000.00

44,364,000.00 26,618,400,000.00
26,618,400,000.00

5,000,000.00 5,000,000.00
5,000,000.00

50,741,885,000.00
REKAPITULASI PEMBANGUNAN TRIBUN LAPANGAN SEPAK BOLA

LOKASI : KRUENG GEUKUEH, ACEH UTARA


TAHUN : 2019

No. Uraian Pekerjaan

1 Pekerjaan Persiapan
2 Pekerjaan Tanah
3 Pekerjaan Plesteran
4 Pekerjaan Beton
5 Pekerjaan Pengecatan
6 Pekerjaan Lain-Lain

JUMLAH TOTAL
AN TRIBUN LAPANGAN SEPAK BOLA

Jumlah Harga (Rp)

545,000.00
16,800,000.00
13,190,120,000.00
10,911,020,000.00
26,618,400,000.00
5,000,000.00

50,741,885,000.00
JADWAL PEMBANGUNAN TRIBUN LAPANGAN SEPAK BOLA

LOKASI : KRUENG GEUKUEH, ACEH UTARA


TAHUN : 2019

Perkiraan
No. Uraian Pekerjaan Satuan
Kuantitas
1 PEKERJAAN PERSIAPAN
1.1 Pengukuran dan Pemasangan Bowplank 1.00 Ls
1.2 Papan Nama Proyek, Administrasi dan Dokumentasi 1.00 Ls
Jumlah
2 PEKERJAAN TANAH
2.1 Galian Tanah Pondasi Tapak 15.00 m³
2.2 Galian Tanah Pondasi Batu Gunung 50.00 m³
2.3 Urugan Kembali Bekas Galian 15.00 m³
Jumlah
3 PEKERJAAN PLESTERAN
3.1 Aanstamping Batu Gunung/Kali 10.00 m³
3.2 Pondasi Batu Gunung/Kali 20.00 m³
3.3 Pasang Batu Bata 100.00 m³
3.4 Plesteran Dinding Batu Bata 200.00 m²

Jumlah
4 PEKERJAAN BETON
4.1 Pondasi Tapak 100.00 m³
4.2 Beton 5.00 m³
4.3 Tulangan Besi 200.00 Kg
Jumlah
5 PEKERJAAN PENGECATAN
5.1 Cat Tembok Luar Dan Dalam 600.00 m²
Jumlah
6 PEKERJAAN LAIN-LAIN
6.1 Pintu Depan 1.00 Ls
Jumlah

JUMLAH TOTAL
PANGAN SEPAK BOLA

, ACEH UTARA

Harga Satuan (Rp) Jumlah Harga (Rp)

30,000.00 30,000.00
515,000.00 515,000.00
545,000.00

210,000.00 3,150,000.00
210,000.00 10,500,000.00
210,000.00 3,150,000.00
16,800,000.00

25,864,000.00 258,640,000.00
57,364,000.00 1,147,280,000.00
42,114,000.00 4,211,400,000.00
37,864,000.00 7,572,800,000.00

13,190,120,000.00

65,364,000.00 6,536,400,000.00
70,364,000.00 351,820,000.00
20,114,000.00 4,022,800,000.00
10,911,020,000.00

44,364,000.00 26,618,400,000.00
26,618,400,000.00

5,000,000.00 5,000,000.00
5,000,000.00

50,741,885,000.00